0% found this document useful (0 votes)
36 views

Inspection Report OTK-04

Uploaded by

wassimwalha2016
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views

Inspection Report OTK-04

Uploaded by

wassimwalha2016
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 61

INSPECTION REPORT

TK04
Inspection report
Tank no. TK04
Rev.001

CONTENTS INDEX

1- Inspection Report according to API 653, API 12B and API-RP 12R1.
2- Appendix A: reference photos.
3-Check-list
4- UT report.
Inspection report
tank TK04
Rev. 001

Contents

1 INTRODUCTION: ................................................................................................ 2
2- GENERAL REQUIREMENT .................................................................................. 2
2.1- Inspection Procedure ............................................................................................................... 2
2.2- Inspection Result...................................................................................................................... 3
2.3- Safety Precaution ..................................................................................................................... 4
2.4- Reference Document ............................................................................................................... 4
3- TANK DESCRIPTION ............................................................................................ 5
4- EXTENT AND INSPECTION METHOD ................................................................. 6
5- CONDITION OF THE TANK .................................................................................. 7
5.1- External Inspection ....................................................................................................................... 7
5.2- Internal Inspection....................................................................................................................... 11
6- DATA RECORDED AND NDT EVALUATION: ................................................... 12
6.1- Tank bottom ................................................................................................................................ 12
6.1.1- UT thickness measurement ................................................................................................. 13
6.1.2- Visual inspection of tank bottom .......................................................................................... 14
6.1.3- Evaluation of result. ............................................................................................................. 16
6.2- Tank shell ................................................................................................................................... 16
6.2.1- UT thickness measurement ................................................................................................. 16
6.2.2- Visual inspection .................................................................................................................. 17
6.2.3- Evaluation of result. ............................................................................................................. 18
6.3- Tank roof and structure ............................................................................................................... 19
6.3.1- UT thickness of tank roof ..................................................................................................... 19
6.3.2- Visual inspection .................................................................................................................. 19
6.3.3- Evaluation of result. ............................................................................................................. 19
6.4- Tank nozzles ............................................................................................................................... 19
7- DIMENSIONAL TOLERANCE CONTROL: ROUNDNESS ................................. 20
8- REPAIR METHODOLOGY .................................................................................. 20
8.1- Tank bottom repair ...................................................................................................................... 20
8.2- Tank shell repair ......................................................................................................................... 22
8.3- Tank nozzles repair..................................................................................................................... 22
9- TANK ROOF REPAIR.......................................................................................... 22
10- CONCLUSION, RECOMMENDATION. ............................................................. 22

Page | 1
Inspection report
tank TK04
Rev. 001

1 Introduction:
As a part of the inspection of tank TK04 in the MABRUK OIL OPERATION Field, a
thorough external and internal inspection (without sweep blasted) was carried out to assess any
deterioration or anomaly.
The inspection commenced on July 29th, 2024.

2- General Requirement
2.1- Inspection Procedure
The primary purpose of proper tank inspections is to assess the overall condition of storage tanks,
identify potential issues, and ensure compliance with relevant safety and environmental regulations. Tank
inspections should include evaluating the tank's structural integrity, checking for leaks or corrosion,
assessing the condition of tank components, and reviewing maintenance records. The frequency of
inspections will depend on factors such as tank material, age, use, and regulatory requirements.
Generally, most tanks should undergo routine visual inspections monthly or quarterly, while more in-depth
external inspections and comprehensive internal inspections, depending on the tank specifications and
usage.

-Visual inspection
Visual inspections are the most basic but critical step in a proper tank inspection process. Visual
inspections should focus on the overall condition of the storage tank, including:
 Assessment of the tank's exterior for signs of corrosion, cracks, or damage to the coatings, vents,
or piping systems
 Examination for any signs of leaks, such as disconsolation, staining, or wet spots around the tank
area.
 Inspecting ancillary components, such as valves, gauges, and bending, for any signs of wear or
damage hen conducting visual inspections, keep in mind that unexplained changes in tank levels,
persistent odors, or the presence of contaminants in nearby soil or water sources may indicate
an undetected leak.

- Structural Integrity Assessments


Maintaining the structural integrity of a storage tank is vital for preventing leaks, mechanical
failures, and environmental damage. Structural integrity assessments should include the following:
Inspection of tank shell, floors, and roofs for signs of corrosion or weakening Thickness testing using
ultrasonic testing (UT) or other non-destructive testing (NDT) techniques to identify areas of reduced
structural integrity due to corrosion or material degradation. Stress analyses to identify potential weak
points or overloaded areas within the tank's structure by regularly assessing the structural integrity of your
storage tanks, you can proactively address potential issues and ensure the tank's continued safe and
optimal operation.

- Evaluating Tank Components and Accessories

Page | 2
Inspection report
tank TK04
Rev. 001

A comprehensive tank inspection should also include a review of key components and
accessories associated with the storage tank, such as:
 Valves, Fittings, and Connections: Check for signs of wear, tears, or corrosion and ensure
proper functionality.
 Piping Systems: Inspect for signs of corrosion, leaks, or damage.
 Venting Systems: Examine for blockages, wear or corrosion and ensure proper operation to
prevent over or under- pressurization of the tank.
 Level Gauges, Pressure Gauges, and temperature sensors: Ensure accurate readings and
that they are in good working condition.
 Secondary Containment and Bunding Systems: Inspect for cracks, wear, or signs of
contamination and ensure efficient and adequate containment in case of a spill or leak
Regularly evaluating and maintaining these essential components can help prevent potential
issues, maintain compliance with regulations, and ensure the tank system's safe and effective
operation.

Proper documentation and record keeping are crucial for maintaining compliance with
regulations and showcasing a commitment to the safe, responsible management of storage tanks. Tank
inspection records should capture information such as inspection dates, findings, maintenance or repair
work conducted, and any identified issues or recommendations for additional actions. Additionally,
maintaining documentation of regulatory compliance inspections, internal assessments, and third-party
inspections can help streamline future audits, site investigations, or compliance checks.

Ensure that all inspection records are complete, accurate, and readily accessible. Implementing
a digital record-keeping system can increase efficiency and provide easy access to essential
documentation when required. By following these comprehensive guidelines for proper tank inspections,
you can confidently evaluate the condition of your storage tanks, address potential issues promptly, and
maintain compliance with relevant regulations. Regular inspections and proactive maintenance will
contribute to the overall safety and efficiency of your storage tank systems, protecting your valuable
resources and investments in the long term.

- Achieving Reliable Storage Tank Operations with Expert Inspections


Proper tank inspections are instrumental in ensuring the safety, efficiency, and compliance of
your storage assets. By thoroughly evaluating your tanks' structural integrity, detecting leaks, assessing
components and accessories, and maintaining comprehensive documentation.
Note: Before starting the scheduled inspection, no drawing is available for review.

2.2- Inspection Result


 Acceptance criteria that were applied in result interpretation are in accordance with applicable
code, standards…
 This report includes recommendations for repairs and monitoring necessary to restore the
integrity of the tank per standard and/or maintain integrity of the tank in-service.

Page | 3
Inspection report
tank TK04
Rev. 001

2.3- Safety Precaution


All specific work procedures were prepared and followed when conducting inspections that will assure
personnel safety and health and prevent property damage in the workplace according to pre-inspection
checklist.

2.4- Reference Document


The following references were used during the inspection:

Page | 4
Inspection report
tank TK04
Rev. 001

API 653: Tank Inspection, Repair, Alteration, and Reconstruction


API 575: Inspection Practices for Atmospheric and Low-Pressure Storage Tanks
API 650: Welded Tanks for Oil Storage
API RP 651: “Cathodic Protection of Aboveground Petroleum Storage Tank Bottoms”.
API RP 652: “Lining of Aboveground Petroleum Storage Tank Bottoms”.
ASME V: Non Destructive Examination - Requirements and Method.
ASME IX: welding, brazing and fusing qualifications.
API SPECIFICATION 12B: Specification for Bolted Tanks for Storage of Production Liquids
API-RP 12R1: Installation, Operation, Maintenance, Inspection, and Repair of Tanks in Production
Service.
Check-list: Inspection bolted tank check-list.
3- Tank Description
General Data
Tank No. OTK-04
Tank Type : Vertical
Desing Spec NP
As built Drawing available [Y/N] NP
Welded or bolted? Bolted
Construction date [Year] NP
Manufacturer : Geoservices
Nameplate present [Y/N] Yes (illigeble)

Dimension
Diameter: 11700 mm
Total height : 7300 mm
Capacity: 800 m3

Roof
Roof Type: Fixed
Material: Carbon steel (as per API RP 12B)
Construction Mode: Bolted
Nominal Thickness : 2.7

Stave
Material: Carbon steel (as per API RP 12B)
Construction Mode: Bolted
Nominal Thickness : 3.4, 3.4, 2.6

Page | 5
Inspection report
tank TK04
Rev. 001

Bottom segment
Material: Carbon steel (as per API RP 12B)
Construction Mode: Bolted
Nominal Thickness : 3.4

Operational
Product stored: Crude oil
Storage Temperature: Ambiante
Insulation: [Y/N] No
Earthing system: [Y/N] Yes

Fig N°1 : Representative illustration of the OTK-04 tank

4- Extent and Inspection Method

Performed Inspection on Tank:


Inspection Method Shell Bottom Roof
Visual Inspection   
Ultrasonic Measurement   
Others (Description) roundness survey

Page | 6
Inspection report
tank TK04
Rev. 001

Inspection Method Report N°:


External & Internal Visual Inspection
Wall Thickness Measurement (A-Scan Method)

5- Condition of the Tank


5.1- External Inspection

Element Condition Comments


Staves (Shell - Severe corrosion with holes presented on ring N°3; plates N°1, 5, 6, 7,
plates ) 8, 10, 11, 13, 15, 16, 17, 19, 20, 21, 23 & 24. (Photos N°21, 22, 23, 24,
65, 66, 67&68)
- The top plates of the third ring are severely corroded all around the
tank shell. (Photos N°21, 22, 23&24)
 The 3rd ring of shell plates shall be replaced.

- The shell plates are showing signs of atmospheric corrosion and painting
failure. (Photos N°29, 30, 31, 32, 33, 34, 35, 36, 41, 42, 43&44)
A1
 Perform surface preparation & touch-up painting of shell
plates according to approved painting procedure and under
supervision of certified painting inspector.
- The visual inspection of the shell plates has revealed the presence of
signs of a leak (more than 200 locations) in the vertical seam,
circumferential joint and bolts. (Photos N°25, 26, 27&28)
 The leak of tank shell caused by damaged of gasket; for
avoided the leak shall be replaced all shell gasket or
application a new sealant in vertical and horizontal seam &
around of the plastic encapsulated head from inside of the
tank.

Roof plates, - Severe corrosion with holes distributed on total roof plates; visually
venting, Manway detected from inside of the tank. (Photos 95&96)
A1  The tank roof shall be replaced.
 Roof nozzles, venting, flame arrestor and gauge hatch shall
be dismantled and inspected followed sweep blasting.

Page | 7
Inspection report
tank TK04
Rev. 001

External
Projection :Staves
segments &
bottom segments

 Staves segments
-The visual inspection of external projection has revealed a presence of
heavy corrosion in the bending of staves near clean out1, atmospheric
corrosion and painting failure of the rest of external projection. (Photos
N°7, 8, 11&12)
A1  Perform surface preparation & touch-up painting according
to approved painting procedure and under supervision of
painting inspector.
 Bottom segments:
- The removal of sand under the external projection near clean out1 shows
that the presence of heavy corrosion (hole) extends inside of the tank in
the plate N°26. (Photos N°9&10)
 The plate N°26 shall be replaced.
 Ensure then the rest of external projection (bottom
segments) is free from any severe corrosion.
 The critical area of shell plates (from inside of the tank) shall
be visually inspected after sweep blasted, any new defects
shall be assessment by API 653 Inspector.

Page | 8
Inspection report
tank TK04
Rev. 001

Clean out& - Corrosion was detected at the bolt-hole of the clean out1. (Photos
Nozzles N°47&48)
- Visual inspection of the nozzles revealed the presence of corrosion at
the fillet weld of the nozzle 1’’. (Photos N°53&54)
-Slight corrosion & painting failure in 6 O’clock of nozzle F2. (Photo 51)
B  Perform surface preparation & touch-up painting of shell
plates according to approved painting procedure and under
supervision of certified painting inspector.
-Faces flanges and inner side of nozzles (F1, F2, …, F5) visually in good
condition. (Photo N°50, 52, 55&56)
- The connection between the nozzles and the staves has shown signs
of leaks. (Photos 55&56)
-The clean out covers are in good condition.
 he nozzles strip gasket shall be replaced (all strip gaskets
between tank and nozzles).
-Staves bolts found in a secured condition. No sign of missing or
loosening. (Photos 45&46)
Bolting C
 10% randomly torque check of shell plates bolts shall be
done.
Concrete Foundation/ -Damaged and total deterioration of concrete foundation. (Photos 3&4)
Concrete Ringwall/  Due to the significant damage, it is recommended to perform
Concrete Slab/
A1 a tank settlement test.
Grade line
 The tank foundation shall be assessment by civil
engineering.
-Nameplate is uninstalled and illegible. (Photo 2)
 Nameplate shall be manufactured and installed in
Nameplate B
accordance with API specification 12B (Fig 12, Nameplate
format, API 12B)
- Damage/failure of coating and atmospheric corrosion noted at the shell
plates, shell nozzles, etc. (Photos N°29, 30, 31, 32, 33, 34, 35, 36, 41&51)
Coating B  Perform sweep blasting & painting according to approved
painting procedure of shell plates, firefighting piping and
handrail.
CP (Cathodic-
protection),
*** - There is no proof that there are CPs inside and outside of the tank.
Impressed
Current Systems

Page | 9
Inspection report
tank TK04
Rev. 001

-Structurally in good condition. The condition of the platform ladder


handrails was visually inspected and found safe for continuous use.
Access structure
C (Photos N°13, 14, 17&18)
(Varical ladder …)
 Perform sweep blasting & painting according to approved
painting procedure of handrails and firefighting piping.
-Unsatisfactory condition of tank liquid level. (Photos N°15&16)
Level indicator B
 The tank liquid level shall be repaired or replaced
-The gasket of tank nozzles has been damaged. (Photo 51)
Gasket A2  All strip gaskets of tank shell and nozzles shall be replaced
or applied a new sealant in internal of tank.
-The sealing between the tank concrete ring and annular ring projection
plate found damaged most of the way around the concrete ring. (Photos
Sealing system A2 N°7&8)
 For avoided water stagnation, a new sealant between
concrete ring and external projection shall be applied
- Damage/failure of coating and atmospheric corrosion noted at the
firefighting system. (Photos N°101&102)
 he firefighting system shall be dismantled, UT thickness
firefighting
B measurement examination and tested by hydrostatic testing.
piping,
 Perform sweep blasting & painting according to approved
painting procedure of firefighting piping followed visually
inspected.
- the Handrails was visually inspected and found safe for continuous use.
handrails (Photos N°17&18)
C
 Perform sweep blasting & painting of handrails.
-Earthing system is not connected. (Photos N°5&6)
Earthing system
A2
 The Earthing system shall be installed conformed to API 650
Tank Instruments
-Temperature sensor in unsatisfactory condition. (Photos N°59&60)
(Level Gauges,
Pressure Gauges, B
 The level gauges, pressure gauges, and temperature
and temperature
sensors shall be assessment by instrumentation engineer.
sensors)

Page | 10
Inspection report
tank TK04
Rev. 001

5.2- Internal Inspection


Element Condition Comments

-Internal shell found in good condition except the ring N°3 of the tank shell, visually
inspected without sandblasted. (Photos N°65, 66, 67&68)
 The 3rd ring of shell plates shall be replaced.
Shell Course A1
-Damaged of internal sealant visually detected. (Photos N°71&72)
 Either new sealant needs to be applied to the inside of the tank shell
or all shell strip gaskets shall be replaced.
-Presence of hole and scattered localized pits in the bottom plates with depth range
between 0.5 up to 3 mm. (Photos N°81, 82, 83, 83, 85, 86, 87, 88, 89, 90, 91&92)
 The holes in the bottom shall repaired by welded-on patch plate with
rounded corner.
Bottom  All pitting in the bottom plate with a depth up to 3mm shall be repaired
A1 by weld build-up repair.
 Settlement test of the tank bottom is recommended.
 The soil under tank bottom shall be assessed by civil engineer.
(Randomly removed plates as per choice of civil engineer)
Roof -Absolutely unacceptable condition of tank roof, as viewed from the inner side of
Plates A1 the tank. (Photos 95&96)
 The tank roof shall be replaced.
Rafters/ Jack - Severe corrosion of Rafters, Jack rafter connection and Rafter Bearing
Rafters Plate. Photos N°97, 98, 99&100)
Connection/ -The structurally sound is unsatisfactory.
Rafters Gusset/ A1
Rafters brace  Perform sweep blasting of rafters for further inspection.
angle / Rafters
brace Clip

C -The tank column found in satisfactory condition. (Photos N°93&94)


Tank column

Nozzles & -Internal tank nozzles are in good condition. (Photos N°77&78)
C
Man-way
-Tank shell bolts found in a secured condition, no sign of missing or loosening.
(Photos N°69&70)
-The plastic encapsulated head in good condition. (Photo N°74)
Bolts A2 -Missing of bolt in bottom plate; connection between plate N°10 & plate N°36.
(Photo N°90)
 The missing of bolt shall compensate.
 10% randomly torque check of bottom bolts shall be done.



Page | 11
Inspection report
tank TK04
Rev. 001

-The sealing of internal tank found damaged. (Photos N°71, 72, 75&76)
 New sealant shall be applied internal of the tank.(between shell and
Sealing
A2 annular plate, vertical seam, between shell courses, on bottom
system
plates and around of plastic encapsulated had)

- Damage/failure of coating and microbiological corrosion (MIC) are noted at the


bottom plates. (Photos N°81&82)
Coating B
 Perform sweep blasting of tank bottom according to approved
 procedure and under supervision of painting inspector.

Definition of the condition of the equipment

C – Nothing to report B – Minor defect A2 – Important defect A1 – Imminent danger

Equipment in good Rusted surface, or Higher corrosion, risk of General corrosion and / or
condition; no signs of surface corrosion less cracks adjacent to pin hole or other type of
damage or corrosion - than the corrosion welds - more damage crack. Significant damage
nothing to report allowance - damage than B but no risk of with risk of imminent danger
considered non- failure
hazardous

6- Data recorded and NDT evaluation:


6.1- Tank bottom
The tank's bottom is made up of 52 plates, with central one. They underwent UT thickness
measurements and were visually inspected before sandblasted. Inspection of the bottom (plates bolted
tanks) is stalled by dead zones, such as plate lapping, under bolts, and the bottom side of the plates.
Refer to the figures below for additional information on the plates' numbers and accessible zones.

Fig N°2:Bottom plates lapping

Page | 12
Inspection report
tank TK04
Rev. 001

6.1.1- UT thickness measurement


The tank bottom plates were inspected manually for UT-scanning. Figures N°3&4 show the
location of the reading (with 5 readings per plate). for more details, see UT thickness measurements
report.

Fig N°3:UT thickness measurement location in bottom plates

Page | 13
Inspection report
tank TK04
Rev. 001

Fig N°4: Measurement location in each plate

Referring to the thickness measurement report on tank bottom, the maximum and the minimum-recorded
thickness are respectively: 4.1 mm, 3.1 mm.
Note: The UT reading was recorded prior to sandblasting the tank bottom.

6.1.2- Visual inspection of tank bottom


The visual inspection of tank bottom has revealed a presence of heavy corrosion (hole & pitting) and
missing of bolt. the distributed of tank bottom defects are depicted in the figure below.

Page | 14
Inspection report
tank TK04
Rev. 001

Fig N°5:Metal loss location width symbol

The defects observed visually in top side of bottom plates are caused by damage/failure of painting
system. The defects (holes & pitting) are distributed randomly on all plates with different diameters.
The table below summarizes the defects found on the bottom plates.

Tab1: Plates summery


Plates N°1 to 26 Plates N°27 to 52 Center plates
N° of holes 28 8 1
N° of pitting (localized >80 40 6
corrosion)

* All holes & pitting have been marked in bottom plates


*Bottom plates bolts, found a missing of bolt located in junction seam between Plate N°36/10. The rest of
bolts are intact.
* The sealing of bottom tank (in edge of bottom plates) are damaged.
* The visual inspection of external projection has revealed a presence of heavy corrosion in the external
projection near clean out1 see fig N°6.

Page | 15
Inspection report
tank TK04
Rev. 001

Fig N°6 : Corrosion of external projection; bottom segments

6.1.3- Evaluation of result.


Maximum degradation of 3,4 mm (hole) was found in 25 plates after unspecified number of years
(historical data do not exist for the tank). The corrosion rate cannot be calculated (Long & short-term.
Critical zone: ‘3in(76.2mm) to shell plates’:
According to API-RP 12R1, the minimum required thickness on critical zone equals to 0.50*(5xCr) or an
absolute minimum of 0.062 in(1.57mm).
 Any metal loss with depth above to 3.4-1.57=1.83mm shall be repaired
Primary bottom thickness:
According to API-RP 12R1, the minimum required thickness is equal to 5 times the corrosion rate or an
absolute minimum of 0.05 in(1.27mm).
 Repaired of any degradation with depth above to 3.6-1.27=2.33mm
Central plate
According to API-RP 12R1, the minimum required thickness is equal to 5 times the corrosion rate or an
absolute minimum of 0.05 in(1.27mm).
 Any degradation with depth above to 3.6-1.27=2.33mm shall be repaired
6.2- Tank shell
6.2.1- UT thickness measurement
Manual UT A-scan were carried out on the tank shell course that have a nominal thickness of 3.4, 3.4,
2.6mm, scan width of each track is 200mm, for more details see UT thickness measurements Report N°
**/23).

Page | 16
Inspection report
tank TK04
Rev. 001

Fig7:Location of UT A-scan in each plate

The table below shows the maximum and minimum values of readings in different tracks.
Tab N°2: Minimum thickness of shell plates

Shell courses
Ring N°1 Ring N°2 Ring N°3
Max(mm) 3.6 3.9 3.3
Min(mm) 3.1 3.1 0

Note: The UT reading was recorded prior to sandblasting the tank shell, ring N°1 from external and ring
N°2&3 from Internal of the tank.
6.2.2- Visual inspection
Heavy corrosion (holes) located in the shell plates ring N°3 was observed during the visual inspection of
both the external and internal tank shell. The defects are dispersed throughout the plate surface and the
top of the plate (across of the bending) all around the tank. The defects locations of tank shell are
depicted in the figure below.

Page | 17
Inspection report
tank TK04
Rev. 001

Fig8:Location defect detail

Fig9:View from internal of the tank

- Ring N°3 has experienced severe localized corrosion with complete perforation of plates (holes) present
on plates N°1.5, 6, 7, 8, 10, 11, 13, 15, 16, 17, 19, 20, 21, 23, 24 & 25.
-The top plates of the third ring are severely corroded all around the tank shell. see Fig8: Location defect
detail
- The shell plates are showing signs of atmospheric corrosion and painting failure.
Shell plate bolts were found in a secure condition. No sign of missing or loosening bolts.
-Sign of leak caused by damaged of gasket.
6.2.3- Evaluation of result.
With reference to UT thickness measurement report the minimum thickness is 0mm in the 3rd ring.
Tab N°3: Evaluation of shell plates thickness

Course Number Nominal thickness Tmin required as per API 12R1 Minimum measured value Evaluation

Course N°1 3.4 mm 1.57mm 3.1 ✅

Course N°1 3.4 mm 1.57mm 3.1 ✅

Course N°3 2.6 mm 1.57mm 0 ✅

 The minimum thickness of 3rd ring of tank less than the minimum required.

Page | 18
Inspection report
tank TK04
Rev. 001

6.3- Tank roof and structure


The tank's roof is made up of 52 plates, with central one. The roof and rafters have been visually
inspected from internal of tank using scaffolding.

Fig N°10:Tank roof

6.3.1- UT thickness of tank roof


Due to severe corrosion, UT cannot scan the roof plates and only the tank rafters have been tested by
thickness measurement and hammer testing.
6.3.2- Visual inspection
The tank roof and rafters are in a catastrophic condition, as revealed by the visual inspection of the
bottom side of the tank roof.
6.3.3- Evaluation of result.
Referring to visual inspection on tank roof, the minimum-recorded thickness is 0mm (hole), in all of the
plates.
Tab N°4: Evaluation of roof plates thickness

Roof plate Nominal thickness Tmin required as per API 12R1 Minimum thickness value Evaluation

All plates 2.6 mm 1.27mm 0 ✅

 The minimum thickness roof plates less than the minimum required.
6.4- Tank nozzles
Manual UT thickness measurements were taken on the tank nozzles see UT report. the visual
inspection revealed the presence of corrosion at the fillet weld of the nozzle 1’’ see figure below.

Fig11:Fillet weld defect

Page | 19
Inspection report
tank TK04
Rev. 001

 The defect shall be repaired.

7- Dimensional tolerance control: Roundness


The survey of the tank roundness was performed at the level of one foot due that interfere with the laser
of laser-meter. Radius tolerances measured higher than one foot above the shell to bottom weld shall
not exceed three times the tolerances given in table 10.2 API 653.
Tab N°5: Roundness Measurements
Actual
Diameter
Angles Tank Diameter Differential (mm) Finding (1ft)
Dimension
(mm)

Within
0° 11700 11710 10
tolerance

Within
45° 11700 11692 8
tolerance

Within
90° 11700 11716 16
tolerance

Within
120° 11700 11702 02
tolerance

 The survey confirmed that the tank still within acceptable tolerances.

8- Repair methodology
Tank 04 of diameter over 9.17m (30 ft) shall be repaired in accordance with API Standard 653.
8.1- Tank bottom repair
The following repair will consist on returning the bottom fit for service. The defects of tank bottom severe
corrosion (holes & pitting) shall be repaired by placing patch plates and weld on build-up.
The figure (N°12) below resume the defects repair distribution:

Page | 20
Inspection report
tank TK04
Rev. 001

Fig N°12:Tank bottom repair distribution

*Replaced of full plate segment:


-All defects (hole) in critical zone or external projection (bottom segment) shall be repaired by replaced of
full plate segment, see internal inspection, see 5.2 internal inspection, bottom plates and external
projection.
*Patch plate:
- A patch plate with a rounded corner (minimum radius 2 inches) shall be used to repair the holes in the
bottom plate. Additional details about the patch can be found in the tables below.
Fig N°13:Patch plates design example

A patche-plates (fillet weld) are installed by a certified welder under the supervision of a welding
inspector in accordance with an approved procedure the groove and weld joints have been visual and
day penetrant testing.

Page | 21
Inspection report
tank TK04
Rev. 001

 In order to prevent residual stress and distortion, the following bellow shall be employed:
 Thickness of patch plate same to bottom plate.
 Pre-setting.
 Welding sequence.
*weld build-up or deposition of weld metal according to API 653.
- All pitting in the bottom plate with a depth range between 1 up to 3mm shall be repaired by weld build-
up repair, the welding shall be supervised by a welding inspector.
- All hot repair shall be examined by NDT method (before and after welding).
8.2- Tank shell repair
The ring N°3 of tank 04 shall be a replaced.
8.3- Tank nozzles repair
The welding defect shall be repaired by grinding and weld build-up, then dye penetrant testing.
9- Tank roof repair
The tank roof shall be a replaced.

10- Conclusion, recommendation.


The aboveground storage tank 04 has been subjected to a throughout inspection according API 653
Code requirements, and the following actions are recommended in order to ensure the tank integrity:
 Ensure repair of concrete foundation according to approved repair procedure under supervision
of the civil engineer.
 The tank roof and 3rd ring of shell plates shall be replaced.
 Perform sweep-blasting of tank bottom before welding repair, any new defects shall be
assessment by API 653 inspector.
 All defects in Tank bottom plates (localized corrosion, holes and pitting) shall be repaired or
replaced.
 Install a new Nameplate.
 All strip gaskets of tank shell nozzles shall be replaced
 Repaired or replaced of the level indicator.
 New sealant between concrete ring and external projection shall be applied to avoid any
seeping of water.
 10% randomly torque check of tank shell bolts and bottom bolts shall be done.
 Roof nozzles shall be dismantled and sandblasting for inspection.
 Tank Plumbness and settlement tests are recommended.
 Perform internal sweep-blasting and painting for tank according an approved painting procedure
under supervised of paint inspector.

Page | 22
Inspection report
tank TK04
Rev. 001

 Firefighting shall be dismantled, hydrostatic and UT testing.


 The PV/RV and flame arrestor shall be tested and the test certification provided by the client.
 All the hot repairs shall be performed according an approved repair procedure, PQR, WPS and
supervised by welding inspector.
 All welding repair shall be examined by NDT methods (DP, MT, vacuum box …)
 All repair activity shall be supervision by API 653 inspector.

API 653 Inspector


AKRMI Mohamed Salah
API 653 Certificate No: 105047

Page | 23
Appendix A
REFERENCE PHOTOS
Photo N°1: General view of tank TK04 Photo N°2: Name plate is uninstalled and illegible

Photos N°3&4: Damaged of concrete foundation

Photos N°5&6: Earthing system is not connected


Photos N°7&8: Slight corrosion & painting failure in external projection (shell elements)

Photos N°9&10: Severe corrosion with hole in external projection (bottom segment plate N°26 near cleanout1)

Photos N°11&12: Corrosion in external projection (shell plate N°1 near cleanout1)
Photo N°13: General view of vertical ladder Photo N°14: Vertical ladder in good condition

Photos N°15&16: Liquid level is damaged

Photos N°17&18: Handrail in satisfactory condition


Photos N°19&20: General view of staves(Shell plates)

Photos N°21&22: Severe corrosion with hole in stave ring N°3 & heavy corrosion in top of plates

Photos N°23&24: severe corrosion with hole in stave ring N°3


Photos N°25&26: Sign of leak in vertical seams

Photos N°27&28: Sign of leak in bolts of vertical seams

Photos N°29&30: Atmospheric corrosion & painting failure in lowest of shell plates ring N°1
Photo N°31: Corrosion in vertical seam bolts Photo N°32: Corrosion in staves 2sd ring

Photos N°33&34: Atmospheric corrosion and painting failure in 2sd ring

Photos N°35&36: Atmospheric corrosion and painting failure in 2sd ring


Photos N°37&38: damage of circumferential gasket (gasket between 1st & 2nd courses)

Photos N°39&40: Damaged of vertical gaskets

Photos N°41&42: Slight corrosion in top plates of ring N°1


Photo N°43: Slight corrosion & painting failure in shell plate N°3 Photo N°44: Slight corrosion & painting failure in shell plate N°3

Photos N°45&46: Close view of shell plate bolts ;no sing of missing or loosening

Photos N°47&48: Galvanic corrosion in bolt-hole of cleanout1


Photo N°49: General view of nozzle F2 Photo N°50: Face flange in good condition

Photo N°51: Slight corrosion & painting failure in 6 O’’ clock of Photo N°52: Inner side of nozzles in good condition
nozzle F2 and gasket damaged

Photos N°53&54: Slight corrosion inner side of nozzle 1’’


Photo N°55: General view of nozzle F3 Photo N°56: Sign of leak in the connection nozzle

Photos N°57&58: Nozzles in 3rd ring

Photos N°59&60: The temperature gauge is not functioning & corrosion in the connection bolts
Photos N°61&62: All cables of tank are uninstalled

Photos N°63&64: General view of internal shell plates

Photos N°65&66: Severe corrosion in staves; ring N°3


Photos N°67&68: Severe corrosion in staves; ring N°3

Photos N°69&70: Close view of vertical seam bolts; no sing of missing or loosening

Photos N°71&72: Deterioration of internal sealant


Photo N°73: Sealant of vertical seam Photo N°74: Plastic encapsulated head in good condition

Photos N°75&76: damaged of sealant between the shell and bottom

Photos N°77&78: Good condition of internal tank nozzles (inlet, outlet…)


Photos N°79&80: Unsatisfactory condition of tank liquid level

Photo N°81: General view of bottom plates Photo N°82: Visual inspection of tank bottom

Photo N°83: Severe corrosion with hole of diameter 43 mm in Photo N°84: Hole with diameter 72 mm in plate N°5
bottom plate N°3
Photo N°85: Hole in plate N°8 Photo N°86: Severe corrosion with holes near bottom plate bolts

Photo N°87: Severe corrosion in plate N°24 (hole with diameter Photo N°88: Severe corrosion in plate N°26 beginning from
140mm) external projection

Photo N°89: Hole in plate N° 36 Photo N°90: Missing of bolt in bottom plate (connection between
plate N°10 & plate N°36)
Photos N°91&92: Corrosion in bottom segments & damaged of bottom sealent.

Photos N°93&94:Tank column in satisfactory condition

Photos N°95&96: Severe corrosion in roof plates


Photos N°97&98: Severe corrosion in rafters

Photos N°99&100: Severe corrosion in rafters

Photos N°101&102: Slight corrosion in fire-fitting system


Checklists for bolted Tank Inspection
Tank Out-of-service Inspection Checklist (Bolted tank)

Completed
Item Comments

1 Overview

a- Check that tank has been cleaned, is gas free, and safe for entry.

b- Check that the tank is completely isolated from product lines, all electrical power, andsteam
lines.
c- Check that roof is adequately supported.
d- Check for presence of falling object hazards, such as corroded-through roof rafters,
asphalt stalactites, and trapped hydrocarbons in unopened or plugged equipment or
appurtenances, ledges, etc.

e- Inspect for slipping hazards on the bottom and roof plates.

f- Inspect structural bolted on access ways and clips.

g- Check surfaces needing inspection for a heavy-scale, check bolts and some areas needing
more cleaning, including blasting.

h- Review cathodic protection potential readings. ***

2 Tank Exterior

a- Inspect appurtenances opened during cleaning such as nozzle interiors (after removal of
valves).

b- Hammer test and ultrasonically test the roof and rafters

3 Bottom Interior Surface

a- Using a flashlight held close to and parallel to the bottom plates, and using the bottom plate
layout as a guide, visually inspect and hammer test the entire bottom.

b- Measure the depth of pitting and describe the pitting appearance (sharp edged, laketype,
dense, scattered, etc.)

c- Mark areas requiring repair or further inspection.

d- Mark locations for turning coupons for inspection. ***

e- Inspect all bottom bolts for corrosion and losing, particularly the shell-to-bottom junction
(external projection).
f- Inspect sketch plates for corrosion.

g- Check condition of internal sump, if applicable. Standing liquid should be removed from ***
the sump to allow for complete inspection and vacuum testing of weld seams as
appropriate.

h- Locate and mark voids under the bottom.

i- Record bottom data on a layout sketch using the existing bottom plates as a grid. List
the number and sizes of patches required.

j- Inspect of bottom plates gasket.

k- Hammer test or ultrasonically examine any slightly discolored spots or damp areas.

l- Check for reinforcing pads under all bottom attached clips, brackets, and supports.

m- Check the column bases of fixed roof supports for adequate pads and restraining clips.

n- Check area beneath swing line cable for indications of cable cutting or dragging.

o- Mark old oil and air test connection for removal and patching.

p- Identify and report low areas on the bottom that do not drain adequately.

q- Inspect coating for holes, dis-bonding, deterioration, and discoloration.

r- Spark test the interior surface reinforced lining. * in tank OTK-01


Tank Out-of-service Inspection Checklist (Bolted tank)

Completed
Item Comments

4 Shell Plate and bolts

a- On cone up bottoms, closely inspect and gauge the depth of metal loss on the lower2 in.
to 4 in. of the shell (area of standing water).

b- Measure the depth of pitting on each course.

c- Inspect and estimate the amount of metal loss on the heads of bolts and plastic
encapsulated head.
d- Inspect shell-to-bottom bolted lap joints (external projection).

e- Inspect existing protective coatings for damage, deterioration, and dis-bonding.

f- Visually inspect the shell plates, gaskets and bolts for indications of leakage.

g- Record the leak locations in shell plates, gasket, bolts and shell plates T-junctions.

h- Survey the shell to check for roundness and plumb.

5 Shell-mounted Overflows

a- Inspect overflow for corrosion and adequate screening.

b- Check location of overflow that it is not above any tank valves or equipment.

6 Roof Interior Surface

6.1 General

a- Visually inspect the underside surface of the roof plates for holes, scale buildup, andpitting.

b- Hammer test or ultrasonically examine to check for thin areas, particularly in at edge of roof on
cone roof tank.

c- Check all clips, brackets, braces, etc., welded to the roof deck plate for welded reinforcing
pads and see that they have not broken free.

d- If no pad is present, penetrant test for cracking of the weld or deck plate.

e- Inspect for protective coating for breaks, dis-bondment, and deterioration.

f- Spark test the interior surface coating if recoating is not planned. *

6.2 Fixed Roof Support Structure

a- Inspect the support columns for thinning in the upper 2 ft.

b- On API columns check for corrosion scale breaking the tack welds, unless the joint between
the channels is completely seal welded.

c- Check that the reinforcing pad on the bottom is seal-welded to the tank bottom with horizontal
movement restraining clips welded to the pad.

d- Determine if pipe column supports are concrete filled or open pipe. If open pipe, check for a
drain opening in the bottom of the pipe.

e- Inspect and gauge rafters for thinning, particularly near the center of the roof. Reportmetal loss.

f- Check for loose or twisted rafters.

g- Inspect girders for thinning and check that they are attached securely to the top of thecolumns.
Tank Out-of-service Inspection Checklist (Bolted tank)

Completed
Item Comments

h- Report if the columns have cross bracing in the area between the low pump out of thetop of
the shell (for future internal floating roof installation).

i- Inspect and report presence of any roof-mounted swing line bumpers.

j- Photograph the roof structure if no rafter layout drawing exists.

7 Fixed Roof Appurtenances

7.1 Inspection and Light Hatches

a- Inspect the hatches for corrosion, paint and coating failures, holes, and cover sealing.

b- On loose covers, check for a safety chain in good condition.

c- On light hatches over 30 in. across, check for safety rods.

d- Inspect the condition of the gaskets on bold or latched down hatch covers.

7.2 Staging Support Connection

Inspect the condition of the staging support for corrosion.

7.3 Breathers and Vents

a- Inspect and service the breather.

b- Inspect screens on vents and breathers.

7.4 Emergency P/V Hatches

a- Inspect and service pressure/vacuum hatches. (Setting should be high enough to pre- vent
chattering of breather during normal operation. See breather manufacturer’s guide.)

b- Inspect liquid seal hatches for corrosion and proper liquid level in the seal.

7.5 Sample Hatch

a- Inspect sample hatch for corrosion.

b- Check that the cover operates properly.

c- If the tank has no gauge well, check for a hold-off distance marker and check mea-surement.
Tank Out-of-service Inspection Checklist (Bolted tank)

Completed
Item Comments

8 Common Tank Appurtenances

8.1 Gauge Well

a- Inspect gate well pipe for thinning at about two-thirds distance above the bottom: lookfor
thinning at the edge of the slots.

b- Check for corrosion on the pipe joint. Check that sample cords, weights, thermometers, etc.,
have been removed from the pipe.

c- Check for cone at bottom end of pipe about one foot above the bottom.

d- Check condition of well washer pipe and that its flared end is directed at the near sideof the
hold off pad.

e- Check that supports for gauge well are welded to pad or to shell and not directly to bottom
plate.

f- Check operation of gauge well cover.

g- Check presence of a hold-off distance marker in well pipe and record hold-offdistance.
Hold-off distance.

h- Identify and report size and pipe schedule, and whether pipe is solid or slotted. Reportslot size.

i- Check that the hold-off distance plate is seal-welded to the bottom and that any gaugewell
supports are welded to the plate and not directly to the bottom.

j- Inspect vapor control float and cable.

k- Check for presence and condition of gauge well washer.

l- Check for bull plug or plate blind on gauge well washer valve.

m- Inspect gauge well guide in floating roof for pitting and thinning.

n- Inspect the guide rollers and sliding plates for freedom of movement.

o- Inspect condition of gauge well pipe seal system.

p- On black oil and diesel services: if gauge well is also used for sampling, check for presence of
a thief- and gauge-type hatch to avoid spillage.

q- Visually inspect inside of pipe for pipe weld protrusions which could catch or damagevapor
control float.

8.2 Sampling Systems: Roof Sample Hatches

a- Inspect roof-mounted sample hatches for reinforcing pads and cracking.

b- Inspect cover for operation.

c- For tanks complying with Air Quality Monitoring District rules, inspect sample hatchcovers for
adequate sealing.

d- Check horizontal alignment of internal roof sample hatches under fixed roof hatches.

e- Inspect the sealing system on the internal roof sample hatch cover.

f- Inspect floating roof sample hatch cover recoil reel and rope.

8.3 Shell Nozzles

a- Inspect shell nozzles for thinning and pitting.

b- Inspect hot tap nozzles for trimming of holes.


Tank Out-of-service Inspection Checklist (Bolted tank)

Item Completed
Comments

c- Identify type of shell nozzles.

d- Identify and describe internal piping, including elbow-up and elbow-down types.

8.4 For Nozzles Extended Into the Tank

a- Inspect pipe support pads welded to tank bottom.

b- Inspect to see that pipe is free to move along support without strain or tearing actionon
bottom plate.
c- Inspect nozzle valves for packing leaks and damaged flange faces.

d- Inspect heater stream nozzle flanges and valves for wire cutting.

e- Report which nozzles have thermal pressure relief bosses and valves.

f- In internal elbow-down fill line nozzles, inspect the wear plate on the tank bottom.

g- On elbow-up fill lines in floating roof tanks, check that opening is directed against underside
of roof, not against vapor space. Inspect impact are for erosion.
8.5 Diffusers and Air Rolling Systems

a- Inspect diffuser pipe for erosion and thinning.

b- Check holes in diffuser for excessive wear and enlargement.

c- Inspect diffuser supports for damage and corrosion.

d- Check that diffuser supports restrain, not anchor, longitudinal line movement.

e- Inspect air spiders on bottom of lube oil tanks for plugging and damaged or broken
threaded joints.
8.6 Swing Lines

a- Inspect flexible joint for cracks and leaks.

b- Scribe the flexible joint across the two moving faces and raise end of swing line to check the
joint’s freedom of movement, indicated by separation of scribe marks.
c- Check that flexible joints over 6 in. are supported.

d- Inspect the swing pipe for deep pitting and weld corrosion.

e- Loosen the vent plugs in the pontoons and listen for a vacuum. Lack of a vacuum indicates
a leaking pontoon.
f- Check the results of air test on pontoons during repairs.

g- Inspect the pontoons for pitting.

h- Inspect the pull-down cable connections to the swing.

i- Inspect the condition of the bottom-mounted support, fixed roof limiting bumper, or shell-
mounted limiting bumper for wood condition, weld and bolt corrosion, and sealwelding to
bottom or shell.
j- Inspect safety hold-down chain for corrosion and weak links.

k- Check that there is a welded reinforcing pad where the chain connects to the bottom.

l- If the floating swing in a floating or internal floating roof tank does not have a limiting
device preventing the swing from exceeding 60 degrees, measure and calculate the
maximum angle possible with the roof on overflow.
m- Inspect pull-down cable for fraying.
Tank Out-of-service Inspection Checklist (Bolted tank)

Completed
Item Comments

8.8 Mixer Wear Plates and Deflector Stands

a- Inspect bottom and shell plates and deflector stands.

b- Inspect for erosion and corrosion on the wear plates. Inspect for rigidity, structural soundness,
corrosion, and erosion of deck plates and reinforcing pads that are seal- welded to the bottom
under the deflector stand legs.

c- Measure for propeller clearance between the bottom of deflector stand and roof whenthe roof is
on low legs.

9 Access Structures

9.1 Handrails

a- Identify and report type (steel pipe, galvanized pipe, square tube, angle) and size of handrails.

b- Inspect for pitting and holes, paint failure.

c- Inspect attachment welds.

d- Identify cold joints and sharp edges. Inspect the handrails and midrails.

e- Inspect safety drop bar (or safety chain) for corrosion, functioning, and length.

f- Inspect the handrail between the rolling ladder and the gaging platform for a hazardous opening
when the floating roof is at its lowest level.

9.2 Platform Frame

a- Inspect frame for corrosion and paint failure.

b- Inspect the attachment of frame to supports and supports to tank for corrosion and weld failure.

c- Check reinforcing pads where supports are attached to shell or roof.

d- Inspect the surface that deck plate or grating rests on, for thinning and holes.

e- Check that flat-surface-to-flat-surface junctures are seal-welded.

9.3 Deck Plate and Grating

a- Inspect deck plate for corrosion-caused thinning or holes (not drain holes) and paintfailure.

b- Inspect plate-to-frame weld for rust scale buildup.

c- Inspect grating for corrosion-caused thinning of bars and failure of welds.


Tank Out-of-service Inspection Checklist (Bolted tank)

Completed
Item Comments

d- Check grating tie down clips. Where grating has been retrofitted to replace plate, measure
the rise of the step below and above the grating surface and compare withother risers on the
stairway.

9.4 Stairway Stringers

a- Inspect spiral stairway stringers for corrosion, paint failure, and weld failure. Inspect
attachment of stairway treads to stringer.

b- Inspect stairway supports to shell welds and reinforcing pads.

c- Inspect steel support attachment to concrete base for corrosion.

NOTES
Tank TK-04 Ultrasonic
thickness reading report

Client : SLB Line n° : **** DWG n°:NP Object n° : Tank TK-04

Plant : MOO Field NDT réf. code : API 653

Material: Carbon steel Surface Condition: Painted Nominal Thickness : NP

Calibration block: Step wedge Couplant: JELL

Equipment : USM go + Serial N°:12126205 Calibration due : 07/2024

Probe ref: MSEB 4 EN Serial N°:500068/61640

1. Introduction :

According to the API 653 Inspector scope of work, the thickness measurements
were carried out on the Export tank TK-04, which is implanted in MOO Field.
The UT thickness measurements were done in the selected and required areas.
2. Sketch and values:

TK04-General view

Page 1/10
Tank TK-04 Ultrasonic
thickness reading report

TK04-Bottom

Bottom plates:

From plate N°27 to plate N°52


From plate N°1 to plate N°26
Page 2/10
Tank TK-04 Ultrasonic
thickness reading report

 Tables of values :

Plate Nominal Mini. Plate Nom. Mini.


number thickness Reading number Thick. Reading
P 1/P1 3.42 3.9 P 9/P1 3.42 3.9
P 1/P2 3.42 3.5 P 9/P2 3.42 3.8
P 1/P3 3.42 3.6 P 9/P3 3.42 3.6
P 1/P4 3.42 3.8 P 9/P4 3.42 4.1
P 1/P5 3.42 3.8 P 9/P5 3.42 4.1
P 2/P1 3.42 4.0 P 10/P1 3.42 4.0
P 2/P2 3.42 3.4 P 10/P2 3.42 3.8
P 2/P3 3.42 3.9 P 10/P3 3.42 3.9
P 2/P4 3.42 3.6 P 10/P4 3.42 3.7
P 2/P5 3.42 3.8 P 10/P5 3.42 3.6
P 3/P1 3.42 3.5 P 11/P1 3.42 3.6
P 3/P2 3.42 3.7 P 11/P2 3.42 3.6
P 3/P3 3.42 4.0 P 11/P3 3.42 3.8
P 3/P4 3.42 4.1 P 11/P4 3.42 3.4
P 3/P5 3.42 3.5 P 11/P5 3.42 3.9
P 4/P1 3.42 3.9 P 12/P1 3.42 3.8
P 4/P2 3.42 3.4 P 12/P2 3.42 3.6
P 4/P3 3.42 3.6 P 12/P3 3.42 4.1
P 4/P4 3.42 3.8 P 12/P4 3.42 3.9
P 4/P5 3.42 4.1 P 12/P5 3.42 3.7
P 5/P1 3.42 3.9 P 13/P1 3.42 3.6
P 5/P2 3.42 3.7 P 13/P2 3.42 3.6
P 5/P3 3.42 3.6 P 13/P3 3.42 3.6
P 5/P4 3.42 3.6 P 13/P4 3.42 3.6
P 5/P5 3.42 3.6 P 13/P5 3.42 3.8
P 6/P1 3.42 3.8 P 14/P1 3.42 3.8
P 6/P2 3.42 3.4 P 14/P2 3.42 4.0
P 6/P3 3.42 3.9 P 14/P3 3.42 3.4
P 6/P4 3.42 3.8 P 14/P4 3.42 3.9
P 6/P5 3.42 3.6 P 14/P5 3.42 3.6
P 7/P1 3.42 4.1 P 15/P1 3.42 3.8
P 7/P2 3.42 4.1 P 15/P2 3.42 3.5
P 7/P3 3.42 4.0 P 15/P3 3.42 3.7
P 7/P4 3.42 3.8 P 15/P4 3.42 4.0
P 7/P5 3.42 3.4 P 15/P5 3.42 4.1
P 8/P1 3.42 3.9 P 16/P1 3.42 3.6
P 8/P2 3.42 3.4 P 16/P2 3.42 3.8
P 8/P3 3.42 3.5 P 16/P3 3.42 3.8
P 8/P4 3.42 3.5 P 16/P4 3.42 4.0
P 8/P5 3.42 3.8 P 16/P5 3.42 3.4
Page 3/10
Tank TK-04 Ultrasonic
thickness reading report

Plate Nominal Mini. Plate Nom. Mini.


number thickness Reading number Thick. Reading
P 17/P1 3.42 3.6 P 25/P1 3.42 3.6
P 17/P2 3.42 3.8 P 25/P2 3.42 4.1
P 17/P3 3.42 3.8 P 25/P3 3.42 4.1
P 17/P4 3.42 4.0 P 25/P4 3.42 4.0
P 17/P5 3.42 3.4 P 25/P5 3.42 3.8
P 18/P1 3.42 3.9 P 26/P1 3.42 3.4
P 18/P2 3.42 3.6 P 26/P2 3.42 3.6
P 18/P3 3.42 3.8 P 26/P3 3.42 3.8
P 18/P4 3.42 3.5 P 26/P4 3.42 3.8
P 18/P5 3.42 3.7 P 26/P5 3.42 4.0
P 19/P1 3.42 4.0 P 27/P1 3.42 3.4
P 19/P2 3.42 4.1 P 27/P2 3.42 3.9
P 19/P3 3.42 3.6 P 27/P3 3.42 3.6
P 19/P4 3.42 3.8 P 28/P1 3.42 3.9
P 19/P5 3.42 3.6 P 28/P2 3.42 3.8
P 20/P1 3.42 4.1 P 28/P3 3.42 3.6
P 20/P2 3.42 4.1 P 29/P1 3.42 4.1
P 20/P3 3.42 4.0 P 29/P2 3.42 4.1
P 20/P4 3.42 3.8 P 29/P3 3.42 4.0
P 20/P5 3.42 3.4 P 30/P1 3.42 3.8
P 21/P1 3.42 3.9 P 30/P2 3.42 3.4
P 21/P2 3.42 3.4 P 30/P3 3.42 3.9
P 21/P3 3.42 3.5 P 31/P1 3.42 3.4
P 21/P4 3.42 3.6 P 31/P2 3.42 3.5
P 21/P5 3.42 4.1 P 31/P3 3.42 3.5
P 22/P1 3.42 4.1 P 32/P1 3.42 3.8
P 22/P2 3.42 4.0 P 32/P2 3.42 3.9
P 22/P3 3.42 3.8 P 32/P3 3.42 3.8
P 22/P4 3.42 3.4 P 33/P1 3.42 3.6
P 22/P5 3.42 3.9 P 33/P2 3.42 4.1
P 23/P1 3.42 3.6 P 33/P3 3.42 4.1
P 23/P2 3.42 3.8 P 34/P1 3.42 4.0
P 23/P3 3.42 3.5 P 34/P2 3.42 3.8
P 23/P4 3.42 3.7 P 34/P3 3.42 3.3
P 23/P5 3.42 4.0 P 35/P1 3.42 3.6
P 24/P1 3.42 4.1 P 35/P2 3.42 3.8
P 24/P2 3.42 3.6 P 35/P3 3.42 3.8
P 24/P3 3.42 3.3 P 36/P1 3.42 4.0
P 24/P4 3.42 3.6 P 36/P2 3.42 3.4
P 24/P5 3.42 3.8 P 36/P3 3.42 3.9

Page 4/10
Tank TK-04 Ultrasonic
thickness reading report

Plate Nominal Mini. Plate Nom. Mini.


number thickness Reading number Thick. Reading
P 37/P1 3.42 4.1 P 45/P1 3.42 3.1
P 37/P2 3.42 3.5 P 45/P2 3.42 3.9
P 37/P3 3.42 3.4 P 45/P3 3.42 3.8
P 38/P1 3.42 3.6 P 46/P1 3.42 3.4
P 38/P2 3.42 3.8 P 46/P2 3.42 3.6
P 38/P3 3.42 3.8 P 46/P3 3.42 3.5
P 39/P1 3.42 4.0 P 47/P1 3.42 3.9
P 39/P2 3.42 3.4 P 47/P2 3.42 3.5
P 39/P3 3.42 3.9 P 47/P3 3.42 3.5
P 40/P1 3.42 3.6 P 48/P1 3.42 3.7
P 40/P2 3.42 3.8 P 48/P2 3.42 3.9
P 40/P3 3.42 3.5 P 48/P3 3.42 3.6
P 41/P1 3.42 3.7 P 49/P1 3.42 3.6
P 41/P2 3.42 4.0 P 49/P2 3.42 3.8
P 41/P3 3.42 3.8 P 49/P3 3.42 3.8
P 42/P1 3.42 3.6 P 50/P1 3.42 4.0
P 42/P2 3.42 3.7 P 50/P2 3.42 3.4
P 42/P3 3.42 3.4 P 50/P3 3.42 3.9
P 43/P1 3.42 3.9 P 51/P1 3.42 3.6
P 43/P2 3.42 3.9 P 51/P2 3.42 3.8
P 43/P3 3.42 4.0 P 51/P3 3.42 3.5
P 44/P1 3.42 3.6 P 52/P1 3.42 3.7
P 44/P2 3.42 3.5 P 52/P2 3.42 4.0
P 44/P3 3.42 3.7 P 52/P3 3.42 4.1

Bottom- Central plate :

Nominal thickness Minimum


Reading
0° 3.42 3.5
90° 3.42 3.7
270° 3.42 4.0
360° 3.42 4.1

Page 5/10
Tank TK-04 Ultrasonic
thickness reading report

COLUMN:

Nominal Reading / Clock Position


Area N° Diameter
thickness N E S W
A1 6" 7.1 7.7 7.3 7.5 7.5
A2 6" 7.1 7.5 7.6 7.8 7.6
A3 6" 7.1 7.6 7.6 7.4 7.1
A4 6" 7.1 7.2 7.2 7.5 7.6
A5 6" 7.1 7.6 7.5 7.5 7.2
A6 6" 7.1 7.5 7.6 7.4 7.5
A7 6" 7.1 7.8 7.7 7.6 7.5
A8 6" 7.1 7.4 7.3 7.7 7.6

Shell plate and nozzles:

Page 6/10
Tank TK-04 Ultrasonic
thickness reading report

 Tables of values :

Course number Plate Nominal thickness Minimum reading


number
Course N°1 P1 3.42 3.38
Course N°1 P2 3.42 3.26
Course N°1 P3 3.42 3.20
Course N°1 P4 3.42 3.11
Course N°1 P5 3.42 3.25
Course N°1 P6 3.42 3.65
Course N°1 P7 3.42 3.14
Course N°1 P8 3.42 3.29
Course N°1 P9 3.42 3.45
Course N°1 P 10 3.42 3.26
Course N°1 P 11 3.42 3.66
Course N°1 P 12 3.42 3.25
Course N°1 P 13 3.42 3.54
Course N°1 P 14 3.42 3.52
Course N°1 P 15 3.42 3.31
Course N°1 P 16 3.42 3.20
Course N°1 P 17 3.42 3.33
Course N°1 P 18 3.42 3.28
Course N°1 P 19 3.42 3.20
Course N°1 P 20 3.42 3.26
Course N°1 P 21 3.42 3.36
Course N°1 P 22 3.42 3.18
Course N°1 P 23 3.42 3.45
Page 7/10
Tank TK-04 Ultrasonic
thickness reading report

Course number Plate Nominal thickness Minimum reading


number
Course N°1 P 24 3.42 3.23
Course N°1 P 25 3.42 3.24
Course N°1 P 26 3.42 3.19
Course N°2 P1 3.42 3.4
Course N°2 P2 3.42 3.6
Course N°2 P3 3.42 3.8
Course N°2 P4 3.42 3.7
Course N°2 P5 3.42 3.2
Course N°2 P6 3.42 3.5
Course N°2 P7 3.42 3.6
Course N°2 P8 3.42 3.4
Course N°2 P9 3.42 3.1
Course N°2 P 10 3.42 3.5
Course N°2 P 11 3.42 3.9
Course N°2 P 12 3.42 3.4
Course N°2 P 13 3.42 3.6
Course N°2 P 14 3.42 3.4
Course N°2 P 15 3.42 3.8
Course N°2 P 16 3.42 3.7
Course N°2 P 17 3.42 3.5
Course N°2 P 18 3.42 3.6
Course N°2 P 19 3.42 3.4
Course N°2 P 20 3.42 3.9
Course N°2 P 21 3.42 3.1
Course N°2 P 22 3.42 3.6
Course N°2 P 23 3.42 3.4
Course N°2 P 24 3.42 3.2
Course N°2 P 25 3.42 3.1
Course N°2 P 26 3.42 3.3
Course N°3 P1 2.7 3..1
Course N°3 P2 2.7 3.0
Course N°3 P3 2.7 2.9
Course N°3 P4 2.7 3.0
Course N°3 P5 2.7 3.1
Course N°3 P6 2.7 3.2
Course N°3 P7 2.7 3.0
Course N°3 P8 2.7 3.3
Course N°3 P9 2.7 2.9
Course N°3 P 10 2.7 2.9
Course N°3 P 11 2.7 3.1
Course N°3 P 12 2.7 3.0
Course N°3 P 13 2.7 3.2
Course N°3 P 14 2.7 3.0
Course N°3 P 15 2.7 3.2
Page 8/10
Tank TK-04 Ultrasonic
thickness reading report

Course number Plate Nominal thickness Minimum reading


number
Course N°3 P 16 2.7 3.2
Course N°3 P 17 2.7 3.1
Course N°3 P 18 2.7 3.2
Course N°3 P 19 2.7 3.1
Course N°3 P 20 2.7 3.2
Course N°3 P 21 2.7 3.0
Course N°3 P 22 2.7 3.2
Course N°3 P 23 2.7 3.2
Course N°3 P 24 2.7 3.2
Course N°3 P 25 2.7 3.1
Course N°3 P 26 2.7 3.2

Nozzles

 Tables of values :

Nozzles Nominal Reading / O’Clock Position


Diameter
ID thickness 12 3 6 9
N1 10" - 9.42 9.27 9.14 9.23
N2 6" - 7.86 7.39 7.74 7.49
N3 3" - 5.93 5.36 5.52 5.63
N4 1" - - - - -
N5 1" - - - - -
N6
N7 Inaccessible

Page 9/10
Tank TK-04 Ultrasonic
thickness reading report

Roof plate

All roof plates and their rafters suffer from sever localized corrosion and
perforated

NOTE:
- All ultrasonic readings are in mm

Prepared by AOS inspector Checked by AOS QC/QC Approved SLB


Name Azmi Hasan
Position UT Level II
signature
date 03/08/2024

Page
10/10

You might also like