Annex Construction Annex Construction: Annex.1 Initial Construction Phase Annex.1 Initial Construction Phase

Sample Work Breakdown Structure using Primavera Software

Uploaded by

Yashica
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views

Annex Construction Annex Construction: Annex.1 Initial Construction Phase Annex.1 Initial Construction Phase

Sample Work Breakdown Structure using Primavera Software

Uploaded by

Yashica
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CONSTRUCTION Activities/Activity Usage Spreadsheet 11-Nov-24 06:12

# Activity ID Activity Name Start Finish Resources

1 ANNEX CONSTRUCTION 02-Nov-24 30-Jan-26

2 ANNEX.1 INITIAL CONSTRUCTION PHASE 04-Nov-24 30-Dec-25

3 ANNEX.1.1 Site Preparation 04-Nov-24 26-Nov-24


4 A1030 Temporary Utilities Installation 11-Nov-24* 12-Nov-24
5 A1020 Excavation & Grading 13-Nov-24* 26-Nov-24
6 A1010 Site Clearing 06-Nov-24* 12-Nov-24
7 A1000 Mobillization 04-Nov-24* 08-Nov-24
8 ANNEX.1.2 Foundation 27-Nov-24 07-Jan-25
9 A1070 Backfilling & Compaction 03-Jan-25* 07-Jan-25
10 A1060 Concrete Pouring & Curing 13-Dec-24* 02-Jan-25
11 A1050 Reinforcement & Formwork 06-Dec-24* 12-Dec-24
12 A1040 Foundation Excavation 27-Nov-24* 05-Dec-24
13 ANNEX.1.3 Structural Construction 08-Jan-25 24-Jun-25
14 A1110 Roof Installation 28-May-25* 24-Jun-25
15 A1100 Formwork Setup & Concrete 02-Apr-25* 27-May-25
16 A1090 Reinforcement Installation 05-Mar-25* 01-Apr-25
17 A1080 Columns, Beams, and Slabs 08-Jan-25* 04-Mar-25
18 ANNEX.1.4 Elevator Shaft and Stairs Construction 25-Jun-25 05-Aug-25
19 A1140 Staircase Construction 09-Jul-25* 05-Aug-25
20 A1130 Shaft Construction 25-Jun-25* 08-Jul-25
21 A1120 Pit Excavation & Foundation 25-Jun-25* 08-Jul-25
22 ANNEX.1.5 Installation of MEPF Systems 06-Aug-25 23-Sep-25
23 A1180 Fire Safety Systems 27-Aug-25* 09-Sep-25
24 A1170 Plumbing Pipes & Fixtures 27-Aug-25* 16-Sep-25
25 A1160 Electrical Wiring & Conduits 27-Aug-25* 23-Sep-25
26 A1150 HVAC Ducting 06-Aug-25* 26-Aug-25
27 ANNEX.1.6 Interior Finishing 24-Sep-25 09-Dec-25
28 A1220 Fixtures & Fittings 12-Nov-25* 09-Dec-25
29 A1210 Doors, Windows, & Handrails Installation 12-Nov-25* 25-Nov-25
30 A1200 Flooring Installation 24-Sep-25* 14-Oct-25
31 A1190 Wall Plastering & Painting 15-Oct-25* 11-Nov-25
32 ANNEX.1.7 Commissioning 10-Dec-25 30-Dec-25
33 A1250 Final Inspections 24-Dec-25* 30-Dec-25
34 A1240 Elevator Testing 10-Dec-25* 16-Dec-25
35 A1230 System Testing 10-Dec-25* 23-Dec-25
36 ANNEX.2 OPERATIONAL PHASE 04-Nov-24 30-Jan-26

37 ANNEX.2.1 Utilities 05-Jan-26 09-Jan-26


38 A1260 Utility Management 05-Jan-26* 09-Jan-26
39 ANNEX.2.2 Cleaning and Custodial Services 19-Jan-26 30-Jan-26
40 A1280 Waste Collection & Disposal 26-Jan-26* 30-Jan-26
41 A1270 Daily Cleaning 19-Jan-26* 23-Jan-26
42 ANNEX.2.3 Elevator Operation 04-Nov-24 04-Nov-24
43 A1290 Elevator Operation 04-Nov-24 04-Nov-24
44 ANNEX.3 MAINTENANCE PHASE 02-Nov-24 08-Nov-24

45 ANNEX.3.1 Routine Inspections 04-Nov-24 06-Nov-24


46 A1310 Quarterly System Testing 04-Nov-24 06-Nov-24

Page 1 of 2 TASK filter: All Activities


© Oracle Corporation
CONSTRUCTION Activities/Activity Usage Spreadsheet 11-Nov-24 06:12
# Activity ID Activity Name Start Finish Resources

47 A1300 Monthly Visual Inspections 04-Nov-24 04-Nov-24


48 ANNEX.3.2 HVAC System Maintenance 02-Nov-24 08-Nov-24
49 A1340 Cooling/Heating Maintenance 02-Nov-24 08-Nov-24
50 A1330 Duct Cleaning 02-Nov-24 08-Nov-24
51 A1320 Filter Replacement 02-Nov-24 08-Nov-24
52 ANNEX.3.3 Elevator Maintenance 02-Nov-24 08-Nov-24
53 A1370 Component Lubrication 02-Nov-24 08-Nov-24
54 A1360 Annual Inspection 02-Nov-24 08-Nov-24
55 A1350 Monthly Safety Checks 02-Nov-24 08-Nov-24
56 ANNEX.3.4 Plumbing and Electrical Maintenance 02-Nov-24 08-Nov-24
57 A1400 Lighting Replacement 02-Nov-24 08-Nov-24
58 A1390 Electrical Panel Maintenance 02-Nov-24 08-Nov-24
59 A1380 Pipe Inspections 02-Nov-24 08-Nov-24
60 ANNEX.4 REPAIR & REPLACEMENT PHASE 02-Nov-24 22-Nov-24

61 ANNEX.4.1 Major Repairs 04-Nov-24 22-Nov-24


62 A1420 Facade Repairs 04-Nov-24 22-Nov-24
63 A1410 Roof Repair/Replacements 04-Nov-24 22-Nov-24
64 ANNEX.4.2 System Replacements 02-Nov-24 22-Nov-24
65 A1450 Electrical & Plumbing Upgrade 02-Nov-24 08-Nov-24
66 A1440 HVAC System Replacement 04-Nov-24 15-Nov-24
67 A1430 Elevator System Replacement 04-Nov-24 22-Nov-24
68 ANNEX.4.3 Interior Refurbishments 04-Nov-24 15-Nov-24
69 A1470 Interior Painting 04-Nov-24 15-Nov-24
70 A1460 Flooring Replacement 04-Nov-24 15-Nov-24
71 ANNEX.5 END-OF-LIFE (DISPOSAL) PHASE 02-Nov-24 22-Nov-24

72 ANNEX.5.1 Demolition & Site Clearing 02-Nov-24 22-Nov-24


73 A1490 Structural Demolition 04-Nov-24 22-Nov-24
74 A1480 Pre-Demolition Inspection 02-Nov-24 08-Nov-24
75 ANNEX.5.2 Salvage or Recycling 04-Nov-24 12-Nov-24
76 A1500 Material Sorting & Salvage 04-Nov-24 12-Nov-24
77 ANNEX.5.3 Site Restoration 02-Nov-24 08-Nov-24
78 A1510 Site Cleanup & Restoration 02-Nov-24 08-Nov-24

Page 2 of 2 TASK filter: All Activities