Procedure For Sanction and Release of Load
Procedure For Sanction and Release of Load
1.0 All the prospective consumers have to enter into an agreement with the HPSEB Ltd., on the
standard Application and Agreement Form C.S-1(a) obtainable free of cost from the local/
designated office of the HPSEBL. The Application & Agreement form can also be downloaded
from HPSEBL website i.e. www.hpseb.com/. The Application duly completed by the
prospective consumer accompanying requisite documents should be presented in the local
office of HPSEB Ltd. provided that in case where the contract demand for new or
additional load exceeds 100 kVA the consumer shall apply for PAC (Power
Availability Certificate) before applying for electricity connection. The Consumer
shall submit the PAC along with A&A form for sanction of load. The procedure for
issuance of PAC has been separately described. The consumer may also apply online
through HPSEBL website www.hpseb.com or portal.hpseb.in and deliver the hard copy of
original application and agreement form, alongwith the other requisite documents in the local
office of HPSEB Ltd.
2.0 The checklist of documents to be enclosed with the load sanction application is as under:-
Checklist for Other than Domestic Consumers/Applicants[CS-1(b)]
B) General
i) Application and Agreement Form (A&A Form) duly completed and signed by
the applicant.
ii) Test Report duly filled and signed by licensed Electrical Contractor.
iii) Crossed Non-Judicial Stamp paper of Rs.10/- attached with A&A form
iv) Undertaking on Appendix-I on plain paper (where “NOC is not available
with consumer)
B) Identity/Ownership
i) Identity Proof ( any one of the documents given below)
PAN
Adhaar Card
Driving License
Passport
Voter ID Card
ii) Proof of Ownership/Occupancy( any one of the documents given
below)
Revenue Papers for Land/Building/premises
Sale Deed
Lease Deed
Any other proof of ownership/occupancy given by Statutory
Authority.
C) Charges to be deposited[Ref. HPERC Regulations 419/2012,HPERC Security
Deposit Regulations,2005] and their amendments from time to time.
iv) Initial Security
v) Normative IDC*
vi) Cost of Service Line or Departmental Charges as the case may be.
* Those consumers who are covered under Regulation-6, 5(3) & 5(9) of
HPERC(Recovery of Expenditure for supply of Electricity),Regulations,2012
as amended from time to time shall have to bear the cost accordingly.
Page 3 of 15
3.0 As soon as an application on the standard form from a prospective consumer is received, it
will be scrutinized by the authorized HPSEBL official and any shortcoming noticed therein,
should be immediately got rectified from the applicant. The receiving clerk should see that all
the columns mentioned in the application are properly filled in and the items which are not
applicable are scored out to avoid confusion. Following precautions shall be taken while
signing/scrutiny of the Application and agreement Form:-
1) A&A form should be filled in and signed by the authorized signatory of both the parties.
2) There shall be no-overwriting or cutting in the A&A form. Corrections, if any, should be
signed/ authenticated by the executants.
3) Each page of the A&A form shall be signed /stamped by the executants.
4) Authorized Signatory signing agreement shall arrange his/her identity proof as mentioned
in the A&A form/Checklist.
5) A&A form must be signed by the prospective consumer in the presence of AE/AEE/SDC in
the sub-division and AAE Incharge in the Sub-Office. The aforesaid official shall ensure
that A&A form has been filled in correctly and no ambiguity exists
6) The minor applicant is not eligible to sign the agreement. However, he/she can avail the
connection through his/her lawful/natural guardian.
7) The A&A form is also required to be signed by the witness as an essential formality before
it is accepted. The witness shall always be one of the HPSEBL’s consumer by filling the
requisite details as provided in the A&A form.
4.0 It would be advisable to obtain a self-certified copy of the partnership deed along with a letter
of attorney signed by all the partners in the name of person executing the agreement and
signing other allied documents on behalf of a “Partnership Firm”. If, however, the firm is
registered one, no letter of attorney is required, if the agreement is signed by one of the
partners, but if the signatory is other than the partner letter of attorney should be obtained.
(i) The above procedure shall also be applicable for temporary metered supply
connections.
(ii) In case of conditional NOC or NOC given for a specific period by the competent
authority, it shall be the sole responsibility of the consumer to keep the NOC updated.
And in case brought to the notice of the concerned field units by the issuing authority,
the connection is liable to be disconnected without any notice to the consumer.
5.0 After verification of the documents submitted by the applicant as detailed above, the applicant
shall be issued acknowledgement of receipt of load sanction case on the format available with
A&A form. In case the load sanction is within the competency of Sub-Division, the same may
be sanctioned by AE/AEE concerned and in case it falls in the competency of higher officers in
the hierarchy, the same be forwarded to the quarter concerned.
of material for preparation of inventory for the material required for each service
connection. It should be ensured that the entries of the load in the application for
supply of electricity are based on the actual requirement and in case of discrepancy
necessary corrections should be made. In determining the actual load requirements,
the following guidelines shall be kept in view.
6.2 It should be ensured that the entries of the load in the relevant columns of the
application form are based on actual rating of device/apparatus connected to the
wiring. If, however, the actual rating of any of the energy consuming apparatus
connected with the system is not known/ or not visible, the load may be assessed on
the following standard wattages for Domestic and general load of other categories of
consumers:-
Description Domestic Commercial & General load of
Supply NDNC other categories
Supply
Light Point 60 Watts each 80 Watts each 80 Watts each
Fan Point 80 Watts each 100 Watts each 100 Watts each
Radiator 1000 Watts 1000 Watts each 1000 Watts each
(Small) each
Radiator(large) 2000 Watts 2000 Watts each 2000 Watts each
each
All sockets for 60 Watts each 80 Watts each 80 Watts each
light and
Fan(5A)
Power 1000 Watts 1000 Watts each 2000 Watts each
Sockets(15 A) each
Air Conditioner 2500 Watts As per rating As per rating mentioned in
each mentioned in name plate
name plate
6.3
i) In case single switch is used for controlling more than one lamp/appliance, the
sum of all the lamps/appliances shall be taken into account for connected load
purposes.
i) In case the rating of windows/split air conditioner is not mentioned, the same
may be taken as 2.5 kW. In case of domestic and NRS consumers, the air
conditioners shall be permanently wired through miniature circuit breakers and
isolators which are not controlled through power sockets. In case of existing
domestic and NRS consumers, the excess load of AC’s may be regularized with
revised A&A form and after obtaining additional security and recovery of
expenditure as per HPERC(Recovery of Expenditure for Supply of Electricity)
Regulations, 2012 as amended from time to time .
ii) The actual load of the Geysers installed through power plug shall be taken and
in absence of rating, the connected load may be taken as 2 kW in case of
storage type Geysers and 3 kW in case of instant Water Heater.
6.4 Where the consumer has installed rectifier transformer for electrolysis, the connected
load of the rectifier transformer shall be taken as a sum of ratings of
motors/equipments on output side. Capacity of the rectifier transformer shall not
exceed connected load by 20%.
Page 5 of 15
6.5 The connected load of arc-furnace/ induction furnace shall be kVA/kW rating of the
furnace transformer feeding the furnace exclusively
6.6 Where welding sets are found/used in the premises of industrial units like rice shellers,
spinning mills, cold storage, ice factories, atta-chakkies, flour mills, cotton spinning
mills, oil mills etc. and where these are used for carrying out minor repairs to the
machinery installed and where no job order or outside welding work is carried out, load
of one welding set shall not be counted while working out the connected load. In case,
more than one welding sets are existing/ installed in such factories, the welding set of
lowest rating shall not be counted towards connected load and other welding sets shall
be considered towards connected load.
6.7 Installation of three phase power sockets by NRS and Industrial consumers will not be
allowed. In case found at site during inspection, the rating should be taken as 6 kW for
the purpose of assessing un-authorised use/Theft.
6.8 In case of computer centres, the computer systems connected through UPS, the rating
of UPS indicated in kVA will be converted into kW by multiplying with a power factor of
0.9. However, the sockets installed on output side of UPS will not be taken into
account.
7.1 The consumer is required to apply for sanction of load on the A&A form with deposit of
requisite charges as detailed above in Instruction No.1 to 5. The concerned Sub-Division shall
process the case with detailed feasibility of feeding the load, voltage regulation calculations of
the feeder from where the supply is to be released and sanction the load in case in the
competency of Sub-Division and submit the case to the concerned Division. The concerned
Division shall check the documents and verify the feasibility report. In case the feeding sub-
station is under control of Electrical System Wing or the supply voltage of the proposed load is
66 kV or above, the feasibility report shall be forwarded to Electrical System Division for
verification and recommendations.
As in some of the cases the authorities competent to sanction the load and the estimate may
be different, steps should, therefore, be taken to get the estimate sanctioned in advance
specifically in case the service line is a dedicated feeder or the connection is to be released at
11 kV and above, after issuance of PAC to the consumers. The consumer shall apply for
sanction of load after the installation of plant and machinery including the electrical
installation and wiring is almost complete and the details of load of plant and machinery can
be verified at site.
Page 6 of 15
7.2 The various officers are competent to accept the A&A form and sanction of loads at standard
supply voltage for all categories of consumers whether permanent or temporary up to the
following extent:--
Sr. Designation D.O.P. for sanction of load
No. Connected load Contract Demand
1. Engineer Incharge of <=50 kW <=50 kVA
Operation Sub- Division (at LT Supply)
(AE, AEE, Ex.Engg.)
2. Sr. E.E./ Addl.S.E. >50 kW to <=1000 kW >50 kVA to <=1000 kVA
Incharge of Operation ( up to 11 kV & 22 kV)
Division
3. Dy. Chief Engineer >1000 kW at 11 kV or 33 >1000 kVA
(Op.)/SE(Op), Circle. kV or 66 kV or 132 kV or
220 kV
All electric furnaces(S) load of 100 kW and above with
contract demand of 100 kVA and above.
All loads containing steel rolling mills and rolling / re-
rolling mills.
All loads at 33 kV and above.
Note: In cases of extension of load the above limits shall apply for total load i.e. sanctioned
existing load and additional load. The competent authorities to sanction such load in
such cases shall be the same as for the total connected load after inclusion of
additional load as indicated above.
7.3 The indicative terms and conditions to be intimated to the domestic consumer at the time of
sanction of load shall be as below:-
The details of sanction of load such as Name of the Applicant, Location of the premises for
which load is sanctioned, purpose for which load is sanctioned, the connected load (kW)
sanctioned ( in case of additional connected load, the existing load(kW) and additional
load(kW) may also be entered) , supply voltage at which load is sanctioned and the feeding
sub-station from where power shall be made available shall be mentioned in the starting
paragraph of the sanction of load.
1) The consumer has to submit proof of ownership /occupancy of the premises for which
electricity connection is being applied for
3) In case of applications for electric connections falling under Planning areas, Municipal
Corporations, Nagar Panchayats and other local bodies where TCP Act, 1977 is applicable,
the connection shall be released to the consumer as per Sales Circular No. 28/2019
circulated vide letter No. HPSEBL/CE(Comm.)/S-4/Vol-IV/2019-17840-18178 dated
16.02.2019 in compliance to amendment in Supply Code.
4) The power will be made available on the basis of self- certified declaration/ undertaking
given by the consumer at the time of sanction of load. In case of non-fulfillment of statutory
provisions/ approvals/ clearances from Govt. (Central/ State) Departments and other
Page 7 of 15
statutory bodies, the connection shall be disconnected with intimation, as agreed in the
declaration/ undertaking.
5) The consumer has deposited security amounting to Rs. [ Rs. _______in cash + BG
amounting to Rs.__________] as per HPERC (Security Deposit Regulations),2005 for the
contract demand as per billing cycle with the concerned Sub Divisional Officer. The amount
payable towards Security Deposit shall be in the form of Cash/ Demand Draft (D.D.) drawn
in favour of the concerned Sub-Divisional Officer.
6) The consumer shall deposit cost towards Expenditure for Supply of Electricity as per HPERC
(Recovery of Expenditure for Supply of Electricity) Regulations,2012 and amendments. The
amount deposited must be entered in the A&A form in the space provided for the purpose.
7) The cost of service line and associated equipment at both ends, as the case may be, will
have to be borne by the consumer as per HPERC (Recovery of Expenditure for Supply of
Electricity) Regulations,2012 and amendments.
8) The metering of the consumer shall be done as per Central Electricity Authority
(Installation and Operation of Meters) Regulations, 2006 as amended from time to time.
9) During winter months i.e. from November to March, in case there is shortage of power,
which otherwise is not a general phenomenon, the release of power will depend upon
its availability and HPSEBL reserves the right to impose any restrictions.
10) The consumer shall abide by the provisions of Electricity Act,2003, all applicable laws,
conditions of supply, General Conditions of Tariff and Schedule of Tariff, Supply Code, rules,
regulations, orders, Directives, Notifications issued and enforced under applicable laws by
HPERC/CEA/Govt. of India/Govt. of H.P. and any other instructions/circulars issued by
HPSEB Ltd. from time to time, and as amended from time to time, for equitable and efficient
distribution of electric energy.
11) The HPSEBL reserves the right to impose any restrictions depending upon the loading
conditions of the feeding substation and availability of power as may deem fit to regulate
the supply in the most efficient manner.
12) HPSEBL will not be held responsible for any loss to the consumer as a result of any
breakdown, shutdown (whether planned or emergency) or restriction power etc.
13) The consumer will have to abide by the CEA (Measures relating to safety and electric
supply) regulation 2010 and its amendments.
7.4 The indicative terms and conditions to be intimated to the other than domestic consumers at the
time of sanction of load shall be as below:
The details of sanction of load such as Name of the Applicant, Location of the premises for which
load is sanctioned, purpose for which load is sanctioned, the connected load (kW) and Contract
demand (kVA) sanctioned ( in case of additional connected load and/or Contract demand, the
existing load(kW) and additional load(kW) with existing Contract demand(kVA) and additional
Contract demand (kVA) may also be entered) , supply voltage at which load is sanctioned and the
Page 8 of 15
feeding sub-station from where power shall be made available shall be mentioned in the starting
paragraph of the sanction of load. The condition of construction of new sub-station or augmentation
of existing sub-station for release of the load shall also be mentioned in case applicable.
1) In case of drawl of Contract demand in excess of the Contract demand sanctioned, the firm
will be liable to pay penalty for over drawl as notified from time to time.
2) The supply during peak load hours (6:30 PM to 10 PM) shall be governed by the additional
conditions as specified in the H.P. Electricity Supply Code & Schedule of Tariff and
Schedule of General & Service Charges approved by HPERC. The prior intimation of 30
days of his intention of using the load during peak load hours has to be intimated to
HPSEBL.
3) The consumer has to submit proof of ownership /occupancy of the premises for which
electricity connection is being applied for.
5) In case of applications for electric connections falling under Planning areas, Municipal
Corporations, Nagar Panchayats and other local bodies where TCP Act, 1977 is applicable,
the connection shall be released to the consumer as per Sales Circular No. 28/2019
circulated vide letter No. HPSEBL/CE(Comm.)/S-4/Vol-IV/2019-17840-18178 dated
16.02.2019 in compliance to amendment in Supply Code.
6) The power will be made available on the basis of self- certified declaration/ undertaking
given by the consumer at the time of sanction of load. In case of non-fulfillment of statutory
provisions/ approvals/ clearances from Govt. (Central/ State) Departments and other
statutory bodies, the connection shall be disconnected with intimation, as agreed in the
declaration/ undertaking.
7) The consumer has deposited security amounting to Rs. [ Rs. _______in cash + BG
amounting to Rs.__________] as per HPERC (Security Deposit Regulations),2005 for the
contract demand as per billing cycle with the concerned Sub Divisional Officer. The amount
payable towards Security Deposit shall be in the form of Cash/ Demand Draft (D.D.) drawn
in favour of the concerned Sub-Divisional Officer. The firm may opt to furnish the security in
the form of Bank Guarantee in place of cash deposit where the amount payable towards
security deposit exceeds Rs.10.00 lac and the same shall remain valid during the period the
agreement for supply of energy remains in force. The validity of BG in no case should be
less than 3 years. The entry of security deposited by the consumer may be made in the A&A
form in the space provided for the purpose.
8) The consumer shall deposit cost towards Expenditure for Supply of Electricity as per HPERC
(Recovery of Expenditure for Supply of Electricity) Regulations,2012 and amendments. The
amount deposited must be entered in the A&A form in the space provided for the purpose.
Page 9 of 15
9) The cost of ____ kV dedicated feeder /joint dedicated feeder along with bay and associated
equipment at both ends, as the case may be, will have to be borne by the consumer as per
HPERC (Recovery of Expenditure for Supply of Electricity) Regulations, 2012 and
amendments. The cost of all these components will be intimated to the consumer by the
Chief Engineer (Op.), concerned / Chief Engineer (ES), HPSEBL, Hamirpur, as the case may
be. The entry of amount deposited by the consumer on this account shall be made in the
A&A form in the space provided.
10) The cost of the whole or part of the service line/equipment paid by the consumer and
maintained by the HPSEBL/consumer as per HPERC Regulations, shall remain the property
of HPSEBL and HPSEBL shall have the right to make use of the service line/equipment for
extending power supply to other consumer(s) in the vicinity or for any other purpose.
11) The consumer will have to build up the load to the extent of load sanctioned /contract
demand within a period of two months of readiness of HPSEBL failing which the
demand charges will be levied as per provision of H.P. Electricity Supply Code (First
Amendment) Regulations, 2014.
12) The metering of the consumer shall be done as per Central Electricity Authority
(Installation and Operation of Meters) Regulations, 2006 as amended from time to time.
13) No new supply to LT installations with induction motor(s) of capacity above 3 HP and
/or welding transformers above 2 kVA shall be given unless shunt capacitors of
appropriate ratings are installed to the entire satisfaction of the HPSEBL
14) The consumer shall comply with the harmonics standards as specified by the Authority and
for voltage levels for which harmonics standards have not been specified by the Authority,
the user shall comply with the standards specified in the relevant International Electrical and
Electronic Engineers regulations. In case of failure to comply the specified standards, action
shall be taken as per Clause No. 2.1.9 of H.P. Electricity Supply Code, 2009.
15) The consumer shall abide by the provisions of Electricity Act,2003, all applicable laws,
conditions of supply, General Conditions of Tariff and Schedule of Tariff, Supply Code, rules,
regulations, orders, Directives, Notifications issued and enforced under applicable laws by
HPERC/CEA/Govt. of India/Govt. of H.P. and any other instructions/circulars issued by
HPSEB Ltd. from time to time, and as amended from time to time, for equitable and efficient
distribution of electric energy.
16) The HPSEBL reserves the right to impose any restrictions depending upon the loading
conditions of the feeding substation and availability of power as may deem fit to regulate
the supply in the most efficient manner.
17) The supply of electricity shall not be commenced by HPSEBL for HT and EHT supply voltage
unless the permission from Electrical Inspector is obtained by the consumer to commence or
recommence the supply after an installation has been disconnected for six months. The
consumer will have to abode by the CEA (Measures relating to safety and electric supply)
regulation 2010 and its amendments.
Page 10 of 15
18) It is mandatory for the consumer to use BEE star labeled (with minimum 4 star rating)
Motor pump sets, and ISI/BIS marked power capacitors, foot/reflex valves etc. as per
Govt. of H.P., MPP & Power Deptt. Order No. Vidyut-C(7)-1/2008 dated 5.12.2009 and
its amendment dated 28.12.2016.
The details of sanction of permanent reduction of contract demand such as Name of the
Applicant, Location of the premises for which load is sanctioned, existing contract demand
before reduction and contract demand after reduction and supply voltage shall be mentioned.
The effective date of permanent reduction of contract demand shall be the date on which the
reduction of contract demand has been sanctioned or 30 days ( timeframe as per
HPERC(Distribution Standards Performance) Regualtions,2010) from receipt of application in
the sub-division with processing fee, whichever, is earlier.
The details of processing fee deposited at the time of application on the changed quantum of
contract demand as per Schedule of Tariff and Schedule of General and Service Charges shall
be mentioned in the order.
The enhancement of contract demand, if any, required in future shall be regulated as per
Clause No. 3.2 of H.P. Electricity Supply Code (First Amendment) Regulations, 2014 and
recovery of expenditure shall be made as per regulation 7(2) of HPERC(Recovery of
Expenditure for supply of Electricity) Regulations,2012 and its amendments.
The other terms and conditions of original load sanction shall remain unchanged.
8.1 After the load applied for by the prospective consumer and the estimate for service line as per
Regulation 4 of HPERC (Recovery of Expenditure for supply of Electricity) Regualtions,2012
and its amendments and as per Sub-Regulation 3 and 9 of Regulation 5 of HPERC(Recovery
of Expenditure for supply of Electricity) Regulations, 2012 ,wherever applicable have been got
sanctioned from the competent authority, suitable entry should be made in the service
register. The consumer shall be intimated about the acceptance of his application and demand
notice shall be issued. The demand notice to the consumer should comprises of the
following:-
a) The initial security deposit for new/additional load/Contract demand, as applicable, as per
HPERC(Security Deposits) Regulations,2005 as amended from time to time.
c) The cost of service line estimate as per Regulation 4 of HPERC (Recovery of Expenditure
for Supply of Electricity) Regulations 2012.
Page 11 of 15
e) The entire cost of works in the areas where no infrastructure is available or no growth is
foreseen in immediate future including the sites where locations of the loads depend upon the
geographic factors and availability of basic raw material such as cement factories and
construction power for Hydel projects etc as per Regulation 5(3) of HPERC (Recovery of
Expenditure for Supply of Electricity) Regulations 2012 and sub-regulation 9 of
Regulation 5 of HPERC(Recovery of Expenditure for supply of Electricity) Regulations,2012 for
exclusive works , as the case may be.
8.2 The demand notice (in duplicate) should immediately be issued within the time period
specified under clause 3 of HPERC (Licensee’s Duty for Supply of Electricity on request)
regulations 2004 against proper receipt or by registered/ speed post to the prospective
consumer on form CS -5 (a) in case of LT Consumers and on form – CS 5(b) in case of
HT/EHT consumers for its compliance by the consumer.
ii) Necessity to furnish the test report from the approved wiring contractor in case not
submitted at the time of application for connection. It some minor installation & testing
by the electrical contractor at the premises of applicant is left, the consumer may be
allowed to submit the Test Report after sanction of load by the competent field
officers. However, the test report on parameters related to safety and protection of the
installation should be submitted at the time of submission of initial test report along
with A&A form only.
iii) The deposit of charges as per regulations notified by HPERC as indicated above.
8.3.1 In the demand notice the period for which the offer will remain valid is also required to
be intimated to the applicant. The normal validity period to comply with the demand
notice is 90 days which can further be extended at the request of the consumer on
valid grounds up to a period limited to six months.
8.3.2 In case of non-compliance of the demand notice within the period mentioned in such
notice or within such period as may be mutually agreed between the licensee(HPSEBL)
and the applicant which in not more than six months, the application, against which
the demand notice had been issued, shall be treated as withdrawn and the matter
shall be further dealt with in accordance with relevant governing Regulations and
Codes of the Commission.
Page 12 of 15
It may, however, be pointed out here that the period specified above is the maximum
and that normally it should be possible to verify the test reports in much shorter
period.
Note: -
(i) In case the electrical installation of the consumer does not conform the
relevant provisions of the CEA (Measures relating to Safety & Electric
Page 13 of 15
11.1 After the load has been sanctioned, the HPSEB Ltd. shall carry out all the necessary
codal formalities and execution of works for supply of power in line with the HPERC
(Licensee’s Duty for Supply of Electricity on Request) Regulations 2004. As soon as
HPSEB Ltd. completes all works required for releasing the connection to the
prospective/ existing consumer, concerned Sr. executive Engineer, Electrical Division
shall intimate prospective/ existing consumer in writing the readiness of HPSEBL to
release the load and shall request the prospective/ existing consumer to avail the load
with in specified period of two months. The prospective/ existing consumer shall carry
out all the inspection and testing work of his installation done within the period of two
months.
11.2 In case the prospective/ existing consumer, either delays to receive supply of
electricity or does not avail the full contract demand within two months, demand
charges in respect of consumers to whom two part tariff is applicable, on the
sanctioned contract demand shall be charged on the sanctioned contract demand at
the rates as per the relevant Schedule of Tariff subject to following limits in line with
clause 3.9 of the Supply code:
S.No. Description Minimum Limit
i For initial twelve months Maximum demand actually availed if any.
from the expiry of notice
period or date of release of
connection, whichever is
earlier;
ii For next six months; Maximum demand actually availed, if any, or
30% of the total sanctioned contract demand,
whichever is higher
iii After expiry of the period Maximum demand actually availed, if any, or
provided in item (ii) above 50% of the total sanctioned contract demand,
whichever is higher
Provided that the minimum limits, as given, in (ii) and (iii) above, shall not be further
decreased on the account of tariff provisions relating to charging of demand charges
for lesser quantum of demand due to non utilization or temporary reduction of
contract demand.
Note:- The procedure has been described for the general awareness of public and the
clauses of this procedure should not be quoted while sanctioning/releasing the
electricity connection connections to the consumers. For that purpose, the clauses of
Supply Code, regulations and sales manual may only be refereed.