BMT 13 - Cpa (Tasks) Answers v3.5
BMT 13 - Cpa (Tasks) Answers v3.5
6
2
A 6 C
6 2
0 8 E 12 F 14
1 4 5 6
0 8 4 12 2 14
B D
2 2 3
3
5
B E
2 3
0 4 7 11 F 16 H 21
A D
1 2 3 4 5 6
0 4 4 7 4 11 2 16 5 21
C G
3 5
8
3
B D
10
4 2
0 A 4 12 F 15 G 17
1 2 5 6 7
0 4 4 12 3 15 2 17
C E
2 6 6
4
6
6 C 9
A 2 4
10 3 13 E
6 2
0 15 G 18
1 6 7
0 15 3 18
B F
6 D 10
6 3 5 5
6 4 10
A 8 D 10 F
2 4
8 8 2 10 9
0 B 10 E 16 G 19 H 22
1 3 5 6 7
0 5 10 6 16 3 19 3 22
C
3
Project duration = 22 days Critical path = A, D, F, H