Ch4 LPModellingExamples 2
Ch4 LPModellingExamples 2
Shipping costs
Mills Grain
Grain Elevators Chicago St. Louis Cincinnati Supply Shipped Grain Elevators
Kansas City 25 0 125 150 150 Kansas City
Omaha 0 0 175 175 175 Omaha
Des Moines 175 100 0 275 275 Des Moines
Demand 200 100 300 600
Grain Shipped 200 100 300
Cost = 4525
Mills
Chicago St. Louis Cincinnati
6 8 10
7 11 11
4 5 12
Construction Site Example
Shipping costs
Construction Site Concrete
Plants A B C Supply Shipped Plants
1 70 50 0 120 120 1
2 80 0 0 80 80 2
3 0 0 80 80 80 3
Demand 150 70 100 280
Concrete Shipped 150 50 80
Cost = 2810
Construction Sites
A B C
8 5 6
15 10 12
3 9 10