Saraswati Construction Company: Engineers & Contractor (M) 9310858518
Saraswati Construction Company: Engineers & Contractor (M) 9310858518
ABSTRACT
Item Previous Bill This Bill Total
Item Description Unit Rate Previous Bill Amount This Bill Amount Total Amount
code Quantity Quantity Quantity
1 EXCAVATION AND REFILLING WORK
1(a) Earth work in excavation in trench. Footing etc not exceeding in
depth 3.0 mtrs. Including disposal of excavated earth lead up to cum 554.399 554.40 200.00 110,879.82 110,879.82
30.00mtrs.
2 (b) Refilling of excavated earth or earth supplied by client, Spreading
in trench in layers not exceeding 300mm in depth, consoliddating cum 636.139 636.14 110.00 69,975.24 69,975.24
Providing and laying first class Brick Masonry in CM 1:5 in Super Structure (above FFL)
level using approved quality Chamber bricks or locally available good quality burnt stock
5 (a) bricks having Min. Compressive Strength of 5 N/Sqmm or 50 Kg /sqcm and as approved cum 121.574 121.57 7500.00 911,802.05 911,802.05
by Consultant / Client including raking the joints, curing, scaffolding etc. complete.
(excluding cement)
6 Plaster work - - -
Prepare the surfaces of all internal & External walls at all heights and plaster in cm 1:4,
15mm thick, finished smooth with trowel and sponge and providing 6 mm x 6mm
6 (a) recessed grooves at the junction of all RCC surfaces and brickwork including and sqm 1,343.085 1,343.08 550.00 738,696.72 738,696.72
scaffolding, curing, etc complete. (excluding cement)
RCC in Footing
Grid A, B/1-7, 1,7/A-D cum 17 -1 3.000 3.000 0.300 -45.900
Tapper part cum 17 -1 3.583 0.550 -33.504
Column up to Plinth cum 17 -1 0.400 0.400 0.825 -2.244
Grid 1A/B,C,D cum 3 -1 1.500 1.500 0.300 -2.025
Lift Raft cum 1 -1 4.280 2.760 0.300 -3.544
cum 1 -1 0.400 0.400 1.375 -0.220
Column up to Plinth cum 3 -1 0.300 0.300 1.375 -0.371
Lift RCC Long wall up to Plinth Top cum 2 -1 2.300 0.230 1.375 -1.455
outer side RCC Wall of Lift up to Plinth Top cum 1 -1 1.800 0.230 1.375 -0.569
Inner side RCC Wall of Lift up to Plinth Top cum 1 -1 1.860 0.230 1.375 -0.588
Inner side Lift cum -1 1 2.070 1.800 1.375 -5.123
Back Filling above NGL to Plinth Beam cum 1 1 24.496 12.217 0.700 209.487
cum 1 1 8.217 3.100 0.700 17.831
Plinth Beam
Grid A, B/1-7, cum 2 -1 24.496 0.400 0.400 -7.839
Grid 1,7/A-D cum 2 -1 11.417 0.400 0.400 -3.653
Staircase Beam cum 1 -1 8.217 0.300 0.400 -0.986
Staircase Beam D, B/1A-1 cum 2 -1 2.800 0.300 0.400 -0.672
TOTAL Qty 636.139
2 CEMENT CONCRETE WORK
Providing and laying in position cement concrete
2 (a) 1:4:8(PCC), Excluding cost of shuttering
(stoneaggregate 40mm nominal size)
PCC Below Footing
Grid A,D/1-7 cum 2 1 27.996 3.000 0.125 20.997
Grid 1,7/A-D cum 2 1 9.500 3.000 0.125 7.125
Staircase 1A/B-D cum 1 1 10.817 3.000 0.125 4.056
Lift area offset cum 1 1 1.800 4.260 0.125 0.958
Grid A, B/1-7, cum 2 1 21.696 0.500 0.100 2.170
Grid 1,7/A-D cum 2 1 10.617 0.500 0.100 1.062
Page No. 3 of 14 MB
Detail of Measurment and Calculated of Quantities
Item L B D
Item Description Unit No. No. Quantity Remark
code (meter) (meter) (meter)
Staircase Beam cum 1 1 7.317 0.400 0.100 0.293
Staircase Beam D, B/1A-1 cum 2 1 2.800 0.400 0.100 0.224
TOTAL
36.885
Qty
2b Floor PCC
Grid 1-7/A-D cum 1 1 24.036 11.757 0.100 28.259
staircase area cum 1 1 7.297 2.87 0.100 2.094
TOTAL
30.353
Qty
2 RCC
2 (b) Providing and laying in position reinforcement
cement concrete 1:1:2 (M25) in footing, Retaing
wall, lintel beam, slab , stair cases, shelves,
Fascia, louvers etc complet using 20mm stone
aggrigate and down size ( the above excludes
shuttering , Reinforce ment )
RCC in Footing
Grid A, B/1-7, 1,7/A-D cum 17 1 3.000 3.000 0.300 45.900
Tapper part cum 17 1 3.583 0.550 33.504
Column up to Plinth cum 17 1 0.400 0.400 1.225 3.332
Grid 1A/B,C,D cum 3 1 1.500 1.500 0.300 2.025
Lift Raft cum 1 1 4.280 2.760 0.300 3.544
cum 1 1 0.400 0.400 2.175 0.348
Column up to Plinth cum 3 1 0.300 0.300 2.175 0.587
Lift RCC Long wall up to Plinth Top cum 2 1 2.300 0.230 2.175 2.301
outer side RCC Wall of Lift up to Plinth Top cum 1 1 1.800 0.230 2.175 0.900
Inner side RCC Wall of Lift up to Plinth Top cum 1 1 1.860 0.230 2.175 0.930
Plinth Beam
Grid A, B/1-7, cum 2 1 24.496 0.400 0.400 7.839
Grid 1,7/A-D cum 2 1 11.417 0.400 0.400 3.653
Staircase Beam cum 1 1 8.217 0.300 0.400 0.986
Staircase Beam D, B/1A-1 cum 2 1 2.800 0.300 0.400 0.672
Column from Plinth Beam to GF cum 14 1 0.400 0.400 4.600 10.304
cum 3 1 0.300 0.300 4.600 1.242
Staircase Beam 1st Landing level cum 1 1 7.317 0.230 0.300 0.505
cum 2 1 2.800 0.230 0.300 0.386
Lintel Beam
Grid A, B/1-7, cum 8 1 3.616 0.230 0.300 1.996
Lift Column up to Slab cum 2 1 0.230 0.230 4.600 0.487
Staircse waist slab up to 1st landing cum 1 1 4.430 1.500 0.125 0.831
1st Landing cum 1 1 3.100 1.800 0.125 0.698
1st Landing to 2nd Landing cum 1 1 4.430 1.500 0.125 0.831
2nd Landing cum 1 1 3.100 1.800 0.125 0.698
First Floor 0.000
Column up to slab cum 14 1 0.400 0.400 3.600 8.064
cum 3 1 0.300 0.300 3.750 1.013
Lift Column up to 2nd Floor level cum 2 1 0.230 0.230 3.750 0.397
RMC Concrete in Slab
Ground Floor
Beam Grid A, D/1-7 cum 2 1 21.696 0.300 0.450 5.858
Beam Grid 1,7/A-D cum 2 1 10.617 0.300 0.450 2.867
Beam Grid B,C/1-7 cum 2 1 23.696 0.300 0.450 6.398
Beam Grid 2,3,4,5,6/A-D cum 5 1 11.417 0.300 0.450 7.706
Lift Beam cum 2 1 2.300 0.230 0.230 0.243
cum 1 1 1.800 0.230 0.230 0.095
slab Grid 1-7/A-D cum 1 1 24.496 14.217 0.150 52.239
First Floor
Beam Grid A, D/1-7 cum 2 1 21.696 0.300 0.450 5.858
Beam Grid 1,7/A-D cum 2 1 10.617 0.300 0.450 2.867
Beam Grid B,C/1-7 cum 2 1 23.696 0.300 0.450 6.398
Beam Grid 2,3,4,5,6/A-D cum 5 1 11.417 0.300 0.450 7.706
Lift Beam cum 2 1 2.300 0.230 0.230 0.243
cum 1 1 1.800 0.230 0.230 0.095
slab Grid 1-7/A-D cum 1 1 24.496 14.217 0.150 52.239
TOTAL Qty 284.785
2 (c ) DPC Work
Grid A, B/1-7, sqm 2 1 24.496 0.230 11.268
Page No. 4 of 14 MB
Detail of Measurment and Calculated of Quantities
Item L B D
Item Description Unit No. No. Quantity Remark
code (meter) (meter) (meter)
Grid 1,7/A-D sqm 2 1 11.417 0.230 5.252
Staircase Beam sqm 1 1 8.217 0.230 1.890
Staircase Beam D, B/1A-1 sqm 2 1 2.800 0.230 1.288
TOTAL 19.698
Page No. 5 of 14 MB
Detail of Measurment and Calculated of Quantities
Item L B D
Item Description Unit No. No. Quantity Remark
code (meter) (meter) (meter)
slab Grid 1-7/A-D, Bootom sqm 1 1 24.496 14.217 348.260
sqm 1 2 24.496 0.150 7.349
sqm 1 2 14.217 0.150 4.265
sqm TOTAL 1580.614
4 Reinforcement
5 Brick Work
Ground Floor
Brick work Below DPC
Grid A, B/1-7, cum 2 1 21.696 0.230 0.400 3.992
Grid 1,/A-D cum 2 1 10.617 0.230 0.400 1.954
Staircase Brick work cum 1 1 8.217 0.230 0.400 0.756
Staircase Beam D, B/1A-1 cum 2 1 2.800 0.230 0.400 0.515
Brick work above Floor cum
Grid A, B/1-7, cum 2 1 21.696 0.230 4.150 41.418
Grid 1,/A-D cum 1 1 10.617 0.230 4.150 10.134
Staircase wall cum 1 1 7.317 0.230 4.300 7.237
Lift wall cum 1 2 2.070 0.230 4.600 4.380
cum 1 1 1.800 0.230 4.600 1.904
Deduction Lift Opening wall cum -1 1 1.630 0.230 4.150 -1.556
Staircase Door cum -1 1 1.500 0.230 2.100 -0.725
First Floor
Grid A, B/1-7, cum 2 1 21.696 0.230 3.150 31.438
Grid 1,/A-D cum 1 1 10.617 0.230 3.150 7.692
Staircase wall cum 1 1 7.317 0.230 3.300 5.554
Lift wall cum 1 2 2.070 0.230 3.300 3.142
cum 1 1 1.800 0.230 3.300 1.366
Deduction Lift Opening wall cum -1 1 1.630 0.230 3.150 -1.181
Staircase Door cum -1 1 1.500 0.230 2.100 -0.725
Deduction Door for Chajja cum -2 1 0.750 0.230 2.100 -0.725
Parapit wall cum 2 1 24.496 0.230 0.300 3.380
cum 2 1 11.757 0.230 0.300 1.622
sqm TOTAL 121.574
6 Plaster Work
Prepare the surfaces of all internal & External walls at all heights
and plaster in cm 1:4, 15mm thick, finished smooth with trowel
6 (a) and sponge and providing 6 mm x 6mm recessed grooves at the
junction of all RCC surfaces and brickwork including and
scaffolding, curing, etc complete. (excluding cement)
Ground Floor
Plaster work (Internal )
Grid A, B/1-7, , Long wall sqm 2 1 24.036 4.600 221.131
Grid 1,/A-D, short wall sqm 1 1 11.757 4.600 54.082
Column offset sqm 2 12 0.170 4.600 18.768
Beam offset, Long Beam sqm 2 1 24.036 0.070 3.365
Beam offset, Short Beam sqm 1 1 11.757 0.070 0.823
Deduction staircase Door sqm 1 -1 1.500 2.100 -3.150
Door for wall opening for Toilet sqm 1 -1 0.750 2.100 -1.575
Deduction Lift Door sqm 1 -1 1.630 4.150 -6.765
Plaster Lift area sqm 1 2 2.300 4.750 21.850
sqm 1 2 1.800 4.750 17.100
Plaster work (External)
Grid A, B/1-7, , Long wall sqm 2 1 24.496 4.750 232.712
Grid 1,/A-D, short wall sqm 1 1 12.217 4.750 58.031
staircase wall sqm 1 2 8.217 4.750 78.062
side sqm 1 2 0.300 4.750 2.850
Lift wall side sqm 1 2 2.300 4.750 21.850
Page No. 6 of 14 MB
Detail of Measurment and Calculated of Quantities
Item L B D
Item Description Unit No. No. Quantity Remark
code (meter) (meter) (meter)
First Floor
Plaster work (Internal )
Grid A, B/1-7, , Long wall sqm 2 1 24.036 3.600 173.059
Grid 1,/A-D, short wall sqm 1 1 11.757 3.600 42.325
Column offset sqm 2 12 0.170 3.600 14.688
Beam offset, Long Beam sqm 2 1 24.036 0.070 3.365
Beam offset, Short Beam sqm 1 1 11.757 0.070 0.823
Deduction staircase Door sqm 1 -1 1.500 2.100 -3.150
Deduction Door for chajja sqm 1 -2 0.750 2.100 -3.150
Deduction Lift Door sqm 1 -1 1.630 3.150 -5.135
Plaster Lift area sqm 1 2 2.300 3.600 16.560
sqm 1 2 1.800 3.600 12.960
Plaster work (External)
Grid A, B/1-7, , Long wall sqm 2 1 24.496 3.750 183.720
Grid 1,/A-D, short wall sqm 1 1 12.217 3.750 45.814
staircase wall sqm 1 2 8.217 3.750 61.628
side sqm 1 2 0.300 3.750 2.250
Lift wall side sqm 1 2 2.300 3.750 17.250
Parapit wall 0.000
Long wall sqm 2 1 24.496 0.830 40.663
short wall sqm 2 1 12.217 0.830 20.280
TOTAL 1343.085
Page No. 7 of 14 MB
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF LOCATION :
Foundation
Footing (3000x3000x850) 18
Nos.
Main Bars Bottom Long 10 100 c/c 28 18 504 0.150 2.900 0.150 3.200 1612.8
Distribution Bars 10 100 c/c 28 18 504 0.150 2.900 0.150 3.200 1612.8
Footing (1500x1500x300),
3 Nos.
Main Bars Bottom Long 10 100 c/c 14 3 42 0.150 1.400 0.150 1.700 71.4
Distribution Bars 10 100 c/c 14 3 42 0.150 1.400 0.150 1.700 71.4
Lift Raft
(4280x2760x300),
Main Bars Bottom & Top 10 100 c/c 41 2 82 0.150 2.660 0.150 2.960 242.7
Distribution Bars 8 100 c/c 26 2 52 0.150 4.180 0.150 4.480 232.96
Chair bars 10 10 1 10 0.300 0.172 0.600 0.172 0.300 1.544 15.4
Retaining wall Main Bars 10 150 c/c 55 2 110 0.300 2.600 2.900 319.0
Binder Long wall 8 150 c/c 14 2 28 0.300 2.450 0.300 3.050 85.4
8 150 c/c 14 2 28 0.300 2.180 0.300 2.780 77.84
U Bars 10 24 1 24 0.300 0.130 0.300 0.730 17.5
Column from foundation
to GF
C1 (400x400) 18 nos. 0.000
Main Bars 20 12 18 216 0.300 7.175 1.000 8.475 1830.6
Stirrups Bars 8 150 c/c 47 18 846 0.320 0.320 0.320 0.320 0.160 1.440 1218.24
Stirrups Bars 8 150 c/c 94 18 1692 0.180 0.320 0.180 0.320 0.160 1.160 1962.72
C2 (300x300) 3 nos. 0.000
Main Bars 16 6 3 18 0.300 7.175 1.000 8.475 152.55
Stirrups Bars 8 150 c/c 47 3 141 0.220 0.220 0.220 0.220 0.160 1.040 146.64
Column (230x230) 2 Nos.
Main Bars 16 6 2 12 0.300 7.175 1.000 8.475 101.7
Stirrups Bars 8 150c/c 47 2 94 0.150 0.150 0.150 0.150 0.160 0.760 71.44
Plinth Beam 0.000
Grid A,D/1-7 0.000
Main Bars Bottom 20 4 2 8 0.300 24.446 0.300 2.000 27.046 216.368
Main Bars Top 20 4 2 8 0.300 24.446 0.300 2.000 27.046 216.368
Stirrups Bars 8 150 c/c 144 2 288 0.350 0.350 0.350 0.350 0.160 1.560 449.28
Grid 1,7/A-D 0.000
Main Bars Bottom 20 4 2 8 0.300 12.167 0.300 1.000 13.767 110.136
Main Bars Top 20 4 2 8 0.300 12.167 0.300 1.000 13.767 110.136
Page 8 of 14
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF LOCATION :
Page 9 of 14
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF LOCATION :
Page 10 of 14
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF LOCATION :
Page 11 of 14
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF LOCATION :
Page 12 of 14
SARASWATI CONSTRUCTION COMPANY
PROJECT :
CLIENT :
CONTRACTOR:- Saraswati Construction Company
Cement Consumption
Sr. No Material Description Unit Quantity Per Bags Cement Cement Qty. Remark
A CEMENT :
2 Cement Consumption in RCC - M25 Grade Cum 134.785 7.000 943.49 Bags
kg /cum 350kg