0% found this document useful (0 votes)
46 views

MS .SVG

Uploaded by

Fathy Selim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views

MS .SVG

Uploaded by

Fathy Selim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

500MW Kom Ombo Solar Photovoltaic Power Plant

MS for SVG Installa�on and Termina�on

Client

EPC

Consultant

Subcontractor
QAR ASPC-QD-PVS-EL-MS- Issued Construction team
PTRF-001-00

REV 0 Review Quality Team


DATE 13-05-2024 Verifying

1. Introduction:
This method statement outlines the procedure for the installation of
four SVGs in the AIS substation. The SVGs will be used to regulate
voltage and control reactive power, enhancing the power transmission
and distribution system's performance and stability.
2. Equipment and Materials:
• Four SVG units
• Mounting brackets and hardware
• Electrical cables and connectors
• Cable trays and supports
• Tools (e.g., wrenches, screwdrivers, cable cutters, etc.)
• Personal protective equipment (PPE)
3. Pre-Installation Activities:
a. Conduct a site survey to determine the optimal location for the SVG
installation, considering factors such as accessibility, clearance
requirements, and proximity to the equipment it will interact with.
b. Ensure that all necessary permits and approvals are obtained.
c. Prepare the AIS substation by ensuring the availability of power
supply, proper grounding, and a safe working environment.
d. Verify that the SVG units are in good condition and all required
accessories are available.
4. Installation Procedure:
a. Install the mounting brackets for each SVG unit at the predetermined
locations, following the manufacturer's guidelines and considering
structural integrity.
b. Mount the SVG units onto the brackets securely, ensuring proper
alignment and clearance requirements.
c. Connect the electrical cables to the input and output terminals of
each SVG unit, following the manufacturer's instructions and adhering to
electrical codes and standards.
d. Route the cables neatly and secure them using cable trays, supports,
and appropriate fasteners to maintain a safe and organized
environment.
e. Terminate the cables at the designated connection points within the
AIS substation, ensuring proper insulation, tight connections, and
adherence to electrical safety practices.
f. Perform a thorough inspection of the installed SVG units, brackets,
and cable connections to verify their integrity and compliance with
specifications.
5. Post-Installation Activities:
a. Conduct a comprehensive check of all installed SVG units to ensure
they are properly installed and functioning correctly.
b. Carry out necessary testing and commissioning activities as per the
manufacturer's recommendations and project requirements.
c. Record all relevant information, including SVG unit details, installation
dates, test results, and any observations or deviations encountered
during the installation process.
d. Provide appropriate training to the relevant personnel regarding the
operation, maintenance, and safety considerations associated with the
SVG units.
6. Safety Considerations:
a. Follow all applicable safety regulations and guidelines during the
installation process.
b. Ensure the use of appropriate PPE, such as safety glasses, gloves, and
safety shoes, to protect against potential hazards.
c. Take necessary precautions to prevent electrical shock, such as de-
energizing the equipment and following proper lockout/tagout
procedures.
d. Adhere to safe working practices, including proper lifting techniques
and the use of equipment and tools in a responsible manner.
Installation of Static Var Generator (SVG)

1. Project Information:

- Project Name: [Project Name]

- Location: [Location]

- Client: [Client Name]

- Reference Number: [Reference Number]

2. Scope of Work:

The scope of work includes the installation of a Static Var Generator (SVG) for power factor
correction and voltage regulation. This involves the following activities:

- Mobilization of equipment and personnel

- Preparation of the installation area

- Mounting and connection of the SVG equipment

- Installation of control and protection devices

- Connection of electrical cables and accessories

- Testing and commissioning of the SVG system

3. Materials and Equipment:

- Static Var Generator (SVG) equipment

- Mounting brackets and supports

- Control and protection devices (e.g., controllers, relays)

- Electrical cables, connectors, and accessories


- Testing equipment (e.g., multimeters, power quality analyzers)

- Personal protective equipment (PPE)

- Tools and consumables (e.g., wrenches, bolts, insulation tape)

4. Work Procedures:

a. Mobilization of Equipment and Personnel:

- Identify and allocate required resources, including personnel and equipment.

- Conduct a pre-mobilization meeting to communicate the objectives, roles, and


responsibilities.

b. Preparation of the Installation Area:

- Clear the installation area of any obstructions and debris.

- Ensure that the foundation or mounting surface is prepared according to the SVG equipment
specifications.

- Verify the availability and adequacy of electrical connections and grounding points.

c. Mounting and Connection of SVG Equipment:

- Inspect the SVG equipment for any visible damages or defects before installation.

- Follow the manufacturer's instructions for proper mounting and connection of the SVG
equipment.

- Install the SVG equipment securely using suitable mounting brackets or supports.

- Connect the electrical cables to the SVG equipment, ensuring proper insulation and
termination.

d. Installation of Control and Protection Devices:

- Identify and mark the locations for control and protection devices.
- Install the control and protection devices according to the approved layout and design.

- Connect control and communication cables to the SVG equipment and control devices.

- Program and configure the control devices according to the system requirements.

e. Connection of Electrical Cables and Accessories:

- Identify and verify the correct cable routing based on electrical diagrams and specifications.

- Install and connect the required electrical cables, ensuring proper insulation and
termination.

- Follow recommended torque values for tightening cable connectors.

- Perform insulation resistance tests and continuity checks to ensure proper electrical
connections.

f. Testing and Commissioning of SVG System:

- Coordinate with the electrical testing team to conduct tests such as power factor correction,
voltage regulation, and harmonic analysis.

- Verify the functionality of control and protection devices, including settings and alarms.

- Document test results and ensure compliance with applicable standards and specifications.

- Obtain necessary approvals and clearances before energizing the SVG system.

5. Safety Considerations:

- Conduct a thorough risk assessment before starting the installation.

- Ensure all personnel involved in the installation wear appropriate PPE, including helmets,
safety shoes, gloves, and high-visibility vests.

- Adhere to electrical safety protocols and isolation procedures.

- Implement proper barricades and warning signs to prevent unauthorized access to the
installation area.
- Establish emergency procedures, including fire safety and evacuation plans.

6. Quality Control:

- Inspect the SVG equipment and control devices for any damages or defects before installation.

- Verify the accuracy and completeness of documentation, including drawings, specifications,


and test reports.

- Conduct quality checks during each installation phase to ensure compliance with standards
and specifications.

- Perform final inspections and tests to confirm proper installation and functionality of the SVG
system.

7. Environmental Considerations:

- Implement measures to prevent oil spills or leakages during the installation if applicable.

- Properly handle and dispose of any waste materials generated during the installation.

- Comply with environmental regulations and guidelines related to noise, emissions, and waste
management.

8. References:

- Electrical drawings and specifications for the SVG installation

- Applicable standards and regulations, such as IEC, ANSI, and local electrical codes

Note: This Method of Statement is a general outline and should be adapted and expanded based
on the specific requirements, site conditions, and applicable regulations of the project.

You might also like