APPENDIX B
lf there are repair or rework processes, are they included on this contrai plan or on
10
a separata control plan linked to this contrai plan?
11 Have repair and rework processes been approved by customer?
12 Are engineering performance testing and dimensional requirements identified?
13
Are all error-proofing devices listed on the control plan, with method and frequency
GATED MANAGEMENT
to confirm effectiveness or proper functioning?
Does the frequency to confirm effectiveness or proper functioning of error-proofing
14 devices enable effective containment of product produced since the last good
verification check?
Are sample sizes based upon industry standards, statistical sampling plan tables, or
15
other statistical process control methods or techniques?
lf sampling frequency is not 100%, is the frequency based upon volume produced to
16
support effective containment?
17 Are gages and test equipment available as required by the control plan?
Are the gage methodology and compatibility appropriate to meet customer
18
requirements?
Have measurement systems analysis been completed in accordance with customer
19
reqlirements?
20 lf required, has the customer approved the control plan?
21 Have lessons learned and "Read Across" actions been implemented?