Minigrids and Access To Electricity in SAARC 2021
Minigrids and Access To Electricity in SAARC 2021
2021
ACKNOWLEDGEMENTS
This report is based on study carried out by SAARC Energy Centre (SEC), Islamabad. The study was
commissioned and supervised by Mr. Ahmad Talha (Research Fellow – Technology Transfer). The
internal review of the study was conducted by Dr. Tanvir Ahmad (Programme Leader – Technology
Transfer).
SAARC Energy Centre, Islamabad would like to thank Lead Authors of this study; IT Power Pvt. Ltd.,
India for undertaking this study in professional manner. Moreover, SEC acknowledges the valuable
contributions made by key stakeholders (government officials, utility companies, academicians,
researchers, technology providers) for their inputs and feedback on this study, including provision of
data.
STUDY COORDINATOR
Mr. Ahmad Talha (Research Fellow – Technology Transfer)
LEAD REVIEWER
Dr. Tanvir Ahmad (Programme Leader – Technology Transfer)
ATTRIBUTION
Please cite the work as follows: Minigrids and Access to Electricity in SAARC, 2022, SAARC Energy
Centre, Islamabad.
DISCLAIMER
The findings, interpretations and conclusions expressed in this work do not necessarily reflect the
views of the SAARC Energy Centre or SAARC and the governments they represent. All efforts have
been made to ensure data integrity in this report. However, SAARC Energy Centre does not,
guarantee the accuracy, completeness or usefulness of information in this report, and cannot be held
responsible for any errors, omissions, or losses, which emerge from its use.
FOREWORD
Access to modern energy, and electricity in particular, is an indispensable ingredient of socio-
economic progress and well-being. However, this is a challenging task, demanding adequate
technical, financial, social and regulatory support. Minigrids can be a key enabler for achieving almost
all the SDGs, including the eradication of poverty, health, education, clean water and combating
climate change. The SAARC Region has very diverse type of climates in different areas, hence
different sources of renewable energy generation such as wind, solar and small hydel etc., are
available, which can be combined to form a minigrid. Utilizing these renewable energy sources can
electrify many energy-poor rural communities in the SAARC Member States resulting in socio-
economic uplift of the people.
This study covers the most pressing technical and non-technical aspects and details of mini grids.
Case studies from the Member States have been detailed in the study report to show the importance
of the mini grids for energy access in the SAARC region. The policy aspects and cost competitiveness
of energy access through mini grids make an integral part of the study. Additionally, the study
comprises of realistic technological innovation based on the modern Information and
Communication Technologies (ICT).
i
ii
Table of Contents
FOREWORD ................................................................................................................................ I
LIST OF TABLES........................................................................................................................... V
LIST OF FIGURES ......................................................................................................................... V
LIST OF ACRONYMS .................................................................................................................. VII
EXECUTIVE SUMMARY ............................................................................................................. XII
1 INTRODUCTION .................................................................................................................. 1
1.1 Background ........................................................................................................................... 2
1.2 Objective of the study ........................................................................................................... 2
1.3 Scope of the study ................................................................................................................ 3
1.4 Limitations of the study ........................................................................................................ 3
1.5 Challenges faced and ways to overcome .............................................................................. 3
1.6 Structure of the report.......................................................................................................... 4
2 OVERVIEW OF MINIGRIDS ................................................................................................... 5
2.1 Global overview of minigrid sector ....................................................................................... 6
2.2 Technical features ................................................................................................................. 7
2.3 Conventional and renewable energy technologies for minigrids ....................................... 11
2.4 Cost of minigrids ................................................................................................................. 14
2.5 Service delivery models ...................................................................................................... 18
2.6 Operation and management............................................................................................... 22
2.7 Integration of minigrid with the centralized grid................................................................ 23
2.8 Latest innovation and improvements ................................................................................. 24
2.9 Impacts of minigrid ............................................................................................................. 28
2.10 Barriers to minigrid development....................................................................................... 30
3 STATUS OF MINIGRIDS IN SAARC MEMBER STATES ............................................................ 32
3.1 Framework for assessing minigrids status .......................................................................... 33
3.2 Afghanistan ......................................................................................................................... 34
3.3 Bangladesh .......................................................................................................................... 40
3.4 Bhutan ................................................................................................................................. 45
3.5 India .................................................................................................................................... 49
3.6 Maldives .............................................................................................................................. 56
3.7 Nepal ................................................................................................................................... 60
3.8 Pakistan ............................................................................................................................... 65
iii
3.9 Sri Lanka .............................................................................................................................. 69
4 CASE STUDIES ................................................................................................................... 75
4.1 Introduction ........................................................................................................................ 76
4.2 Bamiyan solar PV minigrid, Afghanistan ............................................................................. 77
4.3 Microgrids with interconnected solar home systems, Bangladesh .................................... 81
4.4 Solar PV minigrid in Bheldi, Saran District, Bihar, India ...................................................... 85
4.5 Baglung minigrid, Nepal ...................................................................................................... 89
4.6 Solar hybrid minigrid, Tokelau ............................................................................................ 92
4.7 Bambadinca PV minigrid, Guinea Bissau ............................................................................ 95
4.8 MHP project in Sar Kalay village, Khyber Pakhtunkhwa Province, Pakistan ....................... 98
4.9 Key lessons ........................................................................................................................ 101
5 CONCLUSION AND RECOMMENDATIONS......................................................................... 104
5.1 Country wise summary and recommendations ................................................................ 105
5.2 Overall recommendations ................................................................................................ 117
6 BIBLIOGRAPHY ............................................................................................................... 121
7 ANNEXURE ..................................................................................................................... 132
7.1 Annexure 1: List of stakeholders and experts consulted for the study ............................ 133
7.2 Annexure 2: Solar GHI maps of SAARC Member States.................................................... 134
iv
LIST OF TABLES
LIST OF FIGURES
vi
LIST OF ACRONYMS
vii
DBFOOT Design, Build, Finance, Own, Operate and Transfer
DC Direct Current
DDG Decentralized Distributed Generation
DDUGJY Deendayal Upadhyaya Gram Jyoti Yojana (India)
DESI Decentralised Energy Systems of India
DFID Department for International Development
DG Diesel Generators
DGPC Druk Green Power Corporation Limited (Bhutan)
DISCOM Distribution Company
DoRE Department of Renewable Energy (Bhutan)
DRE Decentralized Renewable Energy
DSM Demand Side Management
ECREEE ECOWAS Centre for Renewable Energy and Energy Efficiency
ECS Electricity Consumer Society (Sri Lanka)
EESL Energy Efficiency Services Limited (India)
EFA Energy for Access
EMS Energy Management System
EPC Engineering, Procurement and Construction
ESCO Energy Service Company
ESMAP Energy Assistance Management Program
ETFC Electricity Tariff Fixation Commission (Nepal)
FiT Feed in Tariff
FY Fiscal Year
GCF Green Climate Fund
GDP Gross Domestic Product
GEF Global Environment Facility
GHG Greenhouse Gas
GoB Government of Bangladesh
GOGLA Global Off- Grid Lighting Association
GoIRA Government of Islamic Republic Afghanistan
GoM Government of Maldives
GoN Government of Nepal
GoSL Government of Sri Lanka
HH Household
HOMER Hybrid Optimization of Multiple Energy Resources
HSU Humboldt State University
HRE Hydropower and Renewable Energy Project (Pakistan)
IDCOL Infrastructure Development Company Limited (Bangladesh)
IEA International Energy Agency
IFC International Finance Corporation
INDC Intended Nationally Determined Contribution
IoT Internet of Things
IPDS Integrated Power Development Scheme (India)
IPP Independent Power Project
IRENA International Renewable Energy Agency
KII Key Informant Interview
viii
KTOE Kilo Tonne of Oil Equivalent
kW Kilo Watt
kWh Kilo Watt Hour
LCOE Levelized Costs of Energy
LECO Lanka Electricity Company (Private) Limited (Sri Lanka)
LEDS Low Emission Development Strategy
LES Localized Energy Systems
LFI Local Financial Institutions
LTGEP Long Term Generation Expansion Plan (Sri Lanka)
MFI Microfinance Institutions
MGs Minigrids
MGEAP Minigrid Energy Access Project (Nepal)
MGP Mera Gao Power (India)
MHDF Micro Hydro Debt Fund (Nepal)
MHP Micro Hydro Power
ML Machine Learning
MNRE Ministry of New and Renewable Energy (India)
MoAF Ministry Of Agriculture and Forests (Bhutan)
MoEA Ministry Of Economic Affairs (Bhutan)
MoEWRI Ministry of Energy, Water, Resources, and Irrigation (Nepal)
MPEMR Ministry of Power, Energy and Mineral Resources (Bangladesh)
MPPT Maximum Power Point Tracking
MPRE Ministry of Power and Renewable Energy (Sri Lanka)
MRRD Ministry of Rural Rehabilitation and Development (Afghanistan)
MW Mega Watt
NABDP National Area Based Development Programme (Afghanistan)
NDC Nationally Determined Contribution
NEA Nepal Electricity Authority
NEPRA National Electric Power Regulatory Authority (Pakistan)
NEPS National Energy Policy and Strategies (Sri Lanka)
NGO Non-Governmental Organization
NIWE National institute of Wind Energy (India)
NPA Non-Performing Assets
NPP National Priority Programme (Afghanistan)
NREP Nepal Renewable Energy Programme
NRSP National Rural Support Programme (Pakistan)
NSP National Solidarity Programme (Afghanistan)
NWP Numerical Weather Prediction
NZD New Zealand Dollar
NZMFAT New Zealand Ministry of Foreign Affairs and Trade
O&M Operation and Management
P2P Peer to Peer
PAYG Pay-As-You-Go
PDD Power Development Department (Ladakh, India)
PLF Plant Load Factor
POISED Preparing Outer Islands for Sustainable Energy Development (Maldives)
ix
PPA Power Purchase Agreement
PPAF Pakistan Poverty Alleviation Fund
PPP Public Private Partnership
PV Photovoltaic
RAPSS Remote Area Power Supply System (Bangladesh)
RE Renewable Energy
REB Rural Electrification Board (Bangladesh)
REDF Renewable Energy Development Fund (Bhutan)
REP Rural Energy Policy 2006 (Nepal)
RER2032 Renewable Energy Roadmap for Afghanistan 2032
RERED Renewable Energy for Rural Economic Development (Sri Lanka)
RERL Renewable Energy for Rural Livelihood (Nepal)
RESCO Renewable Energy Service Companies
RET Renewable Energy Technology
RGoB Royal Government of Bhutan
ROR Run of River
RVEP Remote Village Electrification Programme (India)
SAARC South Asian Association of Regional Cooperation
SAP Strategic Action Plan (Maldives)
SASEC South Asia Sub-Regional Economic Cooperation
SDG Sustainable Development Goal
SEC SAARC Energy Centre
SECF Sustainable Energy Challenge Fund (Nepal)
SEforAll Sustainable Energy for All
SESI Sustainable Energy Systems International
SHS Solar Home System
SIDS Small Island Developing States
SME Small and Medium Enterprises
SMS SAARC Member States
SPEED Smart Power for Environmentally sound Economic Development (India)
SPI Smart Power India
SPP Small Power Producers
SREDA Sustainable And Renewable Energy Development Authority (Bangladesh)
SRSP Sarhad Rural Support Programme (Pakistan)
T&D Transmission & Distribution
TANESCO Tanzania Electric Supply Company Limited
ToU Time of Use
TPRM TP Renewable Microgrid (India)
TREP Tokelau Renewable Energy Project
UNCDF United Nations Capital Development Fund
UNDESA United Nations Department of Economic and Social Affairs
UNDP United Nations Development Programme
UNHCR United Nations High Commissioner for Refugees
UNIDO United Nations Industrial Development Organization
USAID U.S. Agency For International Development
USD United States Dollar
x
UT Union Territory
VAT Value Added Tax
VDC Village Development Council
VESP Village Energy Security Programme (India)
VGF Viability Gap Funding
W Watt
WB World Bank
WBREDA West Bengal Renewable Energy Development Agency (India)
XOF West African CFA franc
xi
EXECUTIVE SUMMARY
SAARC Energy Centre (SEC) commenced this study “Minigrids and Access to Electricity in SAARC” to
enhance the deployment of minigrid systems in each of the SAARC Member State(s) (SMS). The study
seeks to present the up-to date information and analysis of the minigrid status, challenges and trends
in the sector and proposes recommendations to overcome the barriers.
The specific scope of the study included research and analysis on the status of minigrid systems
exploring technical, policy, financial and socio-economic aspects in each of the SAARC Member States
and identifying country-specific conditions that shall ensure sustainability of minigrid systems. The
scope also included analysis of actual case studies to depict their broad success factors.
The outcome of the study is limited to secondary sources and discussions with key stakeholders in
each SMS. The analysis and data collection are based on public sources of information such as
industry studies, journals, publications, and various research databases.
The study begins with a general overview of minigrid systems detailing the global status of minigrids;
technical and operational aspects of a minigrid system; use of conventional and renewable energy
technologies; cost trends; business models; and latest innovations in the minigrid sector. Technical
aspects detail the structure of a minigrid, technical configurations used and key steps in design of
minigrid systems. Innovations including Artificial Intelligence (AI), smart meters, Demand Side
Management (DSM) and Internet of Things (IoT) devices used to improve power management,
integration, and system efficiency of the minigrid have been discussed. The chapter also discusses
the operational issues related to minigrid projects and integration of minigrid with the centralised
national grid.
Further, assessment of the status of minigrids’ deployment in each of the SAARC Member States has
been conducted based on the multi-dimensional framework comprising of nine parameters. These
include overall status, national strategy for electrification, policies and regulations, technical aspects,
business models, minigrid tariffs, financing, opportunities, and barriers. Secondary data as well as
information collected through discussions with stakeholders in each country has been used to carry
out the assessment. The assessment provides a comparative analysis on minigrids development in
each country and provides cross-learning potential that could be exploited in the SAARC Member
States for scaling up minigrids’ deployment.
The study later discusses seven specific case studies, with a view to deep dive into several key aspects
of minigrid including key factors for minigrid development and associated barriers. Following cases
have been drawn across the SAARC Member States and globally with each showcasing a unique
feature:
1. Bamiyan solar Photovoltaic (PV) minigrid, Afghanistan: first-of-its-kind 1 MW solar PV-
diesel-battery minigrid system in Afghanistan using state of the art technologies and
concepts
2. Microgrids with interconnected Solar Home Systems (SHSs), Bangladesh: a new approach
to interconnect SHSs into smart peer to peer (P2P) microgrids, monetizing excess solar
energy with mobile money in real time
xii
3. Solar PV minigrid set up under Smart Power for Environmentally sound Economic
Development (SPEED) project, India: a 30-kW solar PV-battery system with load limiters and
prepayment facilities used for the first-time and innovative structuring of the business model
to de-risk project proponents
4. Baglung minigrid, Nepal: Six Micro Hydro Power plants (MHPs) ranging from capacity of 9
kW to 26 kW interconnected to form minigrid to provide reliable electricity to households
5. Solar PV hybrid minigrid, Tokelau: One MW solar PV with battery storage to provide at least
90% of this pacific islands’ electricity needs in a year from solar power and reduce diesel
consumption
6. Bambadinca PV Minigrid, Guinea Bissau: A project of the size 312 kW solar PV with battery
& Diesel Generator (DG) set installed under public-community partnership model to increase
access to electricity
7. MHP minigrid, Khyber Pakhtunkhwa Province, Pakistan: A 36-kW MHP installed by Pakistan
Poverty Alleviation Fund (PPAF) with support of German Development Cooperation in a
remote and off-grid area to provide electricity to 580 people.
Above case studies highlight lessons as well as barriers for successful minigrid development. Access
to and demand for electricity is the prime driver for minigrid development while enterprise load
enables a minigrid to support its operation over time covering operating expenses. Innovations in
technical design and business models as well as active engagement of community have proved to be
instrumental in improving viability and increasing consumers adoption. Other challenges related to
minigrid sector include absence of technical and project management skills, risk perceptions among
financiers towards introduction of new technologies and low adoption rate of consumers.
Based on the outcome of the above research, the study concludes with summarising key prospects,
drivers, and barriers, with specific recommendations for accelerating deployment of minigrids in
xiii
each SMS.
Figure 1 below provides this summary. The study has also suggested the following specific overall
recommendations/ action plan to foster cooperation in the region to achieve the above:
1. Regional minigrid cooperation mechanism: a platform to facilitate coordination and
exchange of good practices and learnings among the SAARC Member states. The mechanism
could operate through a task force consisting of officials from each SMS and will allow
interaction and discussions on regular basis as well as provision of technical assistance.
2. Specialized course on design and operation of minigrids: short term specialized course on
minigrid design and operational aspects that can be offered to relevant stakeholders of
minigrid sector in the SMS for their capacity building. The course would build on
xiv
contemporary thinking and technologies available and used in the minigrid sector. The
course may be offered by recognized technical institutions in the SAARC Member States.
3. Finance facilitation desk/ unit: an online e-platform to connect minigrid project developers,
services providers, and financiers/investors. The facilitation desk would support the
deployment of minigrid projects by helping project developers secure financing more
efficiently and supporting investors and lenders to build stronger project portfolios.
xv
SAARC Countries Drivers/ Opportunities Barriers Recommendations
▪ Minigrids for remote off- ▪ No specific minigrid policy/ ▪ Policy for minigrids in
Bangladesh grid islands strategy remote areas
▪ National target of 10% RE ▪ High minigrid tariff ▪ Upgrade, connect existing
in the mix ▪ Land availability minigrids and buy electricity
xvi
SAARC Countries Drivers/ Opportunities Barriers Recommendations
xvii
1 INTRODUCTION
1
1.1 Background
Access to electricity rose consistently from 71% of global population in 1990 to 83% of population in
2010 and to 90% in 2019, shrinking the number of those without electricity access from 1.5 billion in
1990 to 1.2 billion in 2010, and to 759 million in 2019. Expansion of grid infrastructure and deployment
of off-grid solar including minigrids are the key reasons for this progress (IEA, Tracking SDG7: The
energy progress report, 2021).
Minigrids are described as electric systems, consisting of power generation and distribution network,
providing electricity to households, businesses, public institutions, productive and anchor loads (such
as telecom towers) in remote settlement or in a town or city. Minigrids can be fully detached from the
main grid or connected to it with a provision to isolate themselves from the grid.
Globally, at least 19,000 minigrids are installed in 134 countries and territories, representing a total
investment of USD 28 billion, providing electricity to around 47 million people. In the South Asia
region, there are around 9,300 minigrids installed, with majority of them based in Afghanistan, India,
and Nepal (ESMAP, 2019). However, there is still a strongly felt need for last-mile energy connectivity
that is cost-effective and reliable. Often, centralised electricity supply fails to deliver reliable and
affordable electricity in the remote rural areas. This impedes energy access in under-served and
unserved areas, and hence seriously affects quality of life, livelihoods as well as health and education.
Minigrids have been found to be the cost-effective option for rural electrification when the lower
Levelized Cost of Energy (LCOE) of minigrid electricity supply outweighs the high fixed cost of
extending the national grid (ESMAP, 2017). In unserved and/or under-served rural areas, minigrids
have the potential to provide high quality energy for productive uses to communities.
Such systems score strongly on their potential to promote environment-friendly economic progress,
and contribute to realisation of Sustainable Development Goals (SDGs) by reducing poverty (SDG1),
improving access to energy (SDG7) and on social indicators such as health (SDG3) and education
(SDG4). Minigrids also provide clean electricity services for irrigation and other agricultural activities.
Although there have been success stories of minigrids globally as well as in the SAARC region in the
form of enabling policies, business models and innovative project designs, there is a need for a
systemic analysis of lessons and experiences to enable informed decision making on scaling up the
deployment of minigrids in the SAARC Member States, which has necessitated the present study.
2
1.3 Scope of the study
The scope of study includes the following aspects:
A. Research and analysis on the status of minigrid systems and to explore their efficacy as
decentralized means of energy access, powering livelihoods, building climate resilience, and
furthering realization of SDGs.
B. Detailing the technical and operational structure of a minigrid and potential opportunities in
the SMS.
C. Establish, through a country-level analysis, the key drivers, and barriers for minigrids, i.e., social,
economic, technological, and financial etc.
D. Explore cost competitiveness and socio-economic benefits of electricity access through
minigrids.
E. Analyse various business models that are in operation in the SMS including business models
anchored by community, Renewable Energy Service Companies (RESCO) and/or a lease-to-own
asset ownership and an analysis of financial models funded by donors, government, etc.
F. Evaluate potential of minigrid projects to encourage enterprise and entrepreneurship, i.e.
enabling consumers who can utilize minigrid electricity to set up their own enterprises.
G. Identify country-specific conditions that shall ensure sustainability of minigrid systems.
H. Finally, provide insights on actual case studies to depict their broad success factors including
their role to support growth in the SAARC Member States.
3
A second challenge was in the way of engaging with stakeholders. Due to Covid-19 restrictions during
the assignment, extensive field surveys were ruled out. However, the team conducted online
engagement with stakeholders to overcome this handicap.
4
2 OVERVIEW OF MINIGRIDS
5
2.1 Global overview of minigrid sector
Minigrid market has grown from very few numbers of projects installed globally in 2010 to 19,000
minigrids in 2019. Most of these minigrids are hydro and diesel powered installed in 134 countries.
There are around 7,500 minigrids (mostly solar hybrid) that are planned. As seen in Figure 2, Asia has
the most minigrids installed, and Africa has the most minigrids planned. South Asia has a combined
total of 9,300 installed minigrids and 2,200 planned minigrids (ESMAP, 2019).
Approximately half of installed capacity of minigrids is from diesel and other fossil fuel powered
generators, with hydro and solar accounting for an additional 20% and 13%, respectively. Planned
minigrids are expected to utilize energy from renewable sources, with hydro and solar accounting for
46% and 40% of planned capacity, respectively. To reach universal access to electricity by 2030, more
than 210,000 minigrids need to be developed and operated globally.
10
Number of minigrids
8
(Thousands)
6
4
Installed
2
Planned
0
Africa East Asia and OECD and South Asia Other
Pacific Central Asia
Region
Recent stabilisation and lowering of capital costs for minigrid projects, and improvement in quality of
service have made minigrids an attractive option to connect un-served and under-served
communities, complementing grid extension and standalone home electricity systems to catalyse
progress towards universal access to electricity by 2030. In 2019, while the share of population with
electricity access grew to an estimated 90%, 759 million people are still without access to electricity.
The population without electricity access most likely grew in 2020 in Sub-Saharan Africa. So,
considering the current and planned policies and further affected by the Covid-19 crisis around the
globe, the 2021 Tracking SDG7 Report estimates 660 million people would still lack electricity access
in 2030 (IEA, 2021).
While the potential for minigrids is large, their deployment is rather low as discussed above. The
challenges faced by minigrid are not technical in nature but often due to uncertain or underdeveloped
policies, financing, or regulatory issues. Therefore, stable policies and favourable economic condition
are needed for growth of minigrids. Several policy elements that have been successful in creating an
enabling environment for deployment of minigrids globally are depicted in Figure 3.
1 (ESMAP, 2019)
6
Guides public, private and
Ensures availability of donor agencies to collaborate,
expertise to design, install, and National mobilize, and direct resources
operate minigrids Capacity energy/RE
building policy
programs highlighting
role of minigrid
Interconnection
Tariff standards and
Helps in ensuring affordability regulations grid arrival Interconnection standards and
of service for consumers and rules compensation mechanisms for grid
cost-recovery for private
arrival allay associated risks, and
minigrid operators
increase attractiveness of sector
The basic technical structure of a minigrid includes components that are grouped mainly under three
categories - production, distribution, and end-user (see Figure 4). Each system includes various
components, which are based on available resources, desired services, and user features (USAID,
2018).
Production: The production system comprises of power generation technologies, inverters, charge
controller, energy management system, remote monitoring, and energy storage. The production
system determines minigrid’s overall capacity to provide electricity to end users. Power generation
technologies in a minigrid may include a single renewable or non-renewable energy source or
2 (USAID, 2018)
7
combination of energy sources (hybrid). Renewable energy sources such as solar and wind are
intermittent sources. Therefore, to provide end users with power on demand facility, minigrid must
include energy storage (such as batteries). Storage system stores energy at time of low demand and
supplies it when resources are not available, or demand is higher than the resource available. Energy
storage also adds stability to the system by storing energy for peak consumption.
Distribution: The distribution system transfers power from the production system to end users. It
includes distribution lines, transformers, may include transmission lines, and the infrastructure such
as electric poles or underground cables to support the electricity distribution network. The distribution
system can be either Alternating Current (AC), having either single- or three-phase power, or Direct
Current (DC) based network. Different components in a distribution system have different efficiencies,
and therefore, the choice of voltage, current and transformers impacts energy losses. However, there
are factors such as quality of power, size of the minigrid and user tariff, that usually dictate the option
chosen by project developers.
End User Systems: End-user systems are an interface for end users to access, use and monitor
electricity from the minigrid. It comprises of electrical connections from the distribution network,
remote monitoring component, protection systems to prevent electrical shocks and power
consumption metering. The design of end-user systems should always consider consumers’ needs and
energy uses. However, in a minigrid architecture, the narrative is more complex due to supply
constraints: minigrids power stations may not be continuously generating, as a result there is a
demand-supply mismatch that often calls for user rationing. Thus, users need to be monitored for
excess consumption. At the same time, often usage of electricity is bound to a Pay-As-You-Go (PAYG)
system, asking for prepayments. These realities often govern consumer behaviour, as well as business
and revenue models.
8
Figure 5: Technical Features of Third Generation Minigrid3
Assessment of
Sizing of the Selection of system Designing the
Site selection available energy Load assessment
system configuration distribution system
resources
Site selection: Various studies have analysed the key parameters required to select a minigrid site.
The key parameters for site selection are geographical suitability, energy resource potential, existing
economic activity and availability of target customers, population density, power demand, security
situation, as well as distance of main grid and risk of main grid arrival (IFC, 2017). The Alliance for Rural
Electrification (ARE) study has analysed 11 case studies in South and South-East Asia and reported that
two main criteria have emerged for selecting minigrid sites, which are (ARE, 2019): the local economic
activity (including the potential for productive uses); and proximity to the main grid or remoteness of
the site.
Assessment of available resources: After defining the geographic scope of the project, developers
need to assess local energy resources, including their availability, potential, cost, sustainability, and
potential conflicting uses. The choice of generation source generally depends on resource availability
and cost of technology. During the assessment process, it is essential that project developers interact
3 (ESMAP, 2019)
9
closely with local communities to understand valuable information about availability and potential
conflicting uses.
Load assessment: A minigrid’s size or capacity determines the maximum power output available from
the system to meet the consumer loads. Therefore, it is essential to correctly estimate the present
and future load requirements of the consumers before designing the systems. The present load
requirements are estimated by undertaking a survey of households, businesses, institutions in the
village to collect data from potential customers. The data on electrical devices present, their power
rating and duration of use is analysed to assess the present power demand in the region. In case, the
village does not have any kind of electrical appliances, then the power demand is determined based
on the aspirational need of the potential users.
In design and development of minigrids, the ability of the project developer to correctly estimate the
future energy demand profile of a user community (such as a village) is one of the key success factors.
Incorrect estimation may lead to oversizing of the generation system, leading to lower capacity
utilisation and weak cost recovery, making the unit less viable. On the other hand, under-sizing could
lead to users not receiving as much electricity as needed, leading to rationing of electricity, dissatisfied
customers, and a way for other providers to step in (such as a local diesel minigrid). These
developments create potential conflict issues that often destabilise operations of the unit.
Sizing of the system: Developers and planners often use tool such as Hybrid Optimization of Multiple
Energy Resources (HOMER) software to model and define system’s expected loads, available
resources, technical specification, cost to identify the most optimal size of the system. A minigrid that
can meet increased demand over time is more financially sustainable. The best size for a minigrid also
depends on whether it is likely to connect to the national grid in the future.
Selection of system configuration: Different energy generation technologies favour different
configurations. Hydropower, geothermal energy, diesel power and biomass-based power generate
AC, so they generally use AC configurations. Solar PV systems produce DC, and wind turbines can be
configured to produce either AC or DC. Cost, expected usage, type of end user loads, and plans to
eventually integrate into a larger (typically AC) network are factors that influence decision making. DC
configurations are typically used for shorter distances, lower voltages and systems generating less
power (W rather than kW). AC configurations, which transmit power more efficiently, are more
commonly used for longer distances, higher distribution voltages and systems generating more power.
DC systems are generally less expensive than AC because AC requires power conditioning equipment.
However, the choice of technology mainly depends on the availability of appliances at consumer end.
Today, vast majority of consumer appliances require AC supply and also considering minigrid
integration into the national grid with minimal system or component replacements, which would not
be possible in a DC-based network.
Designing the distribution and control system: Minigrid distribution systems are often more complex
than those of standard grids as they may have bidirectional power flows and multiple energy sources.
This operational complexity requires extra controls and software. In hybrid systems, each power
source requires separate controllers, and the minigrid must have an overall management control to
integrate the different power sources. The design of distribution systems should also comply with local
codes and standards if it is likely to be interconnected with national grid.
10
2.3 Conventional and renewable energy technologies for minigrids
Minigrids can be powered with conventional as well as renewable energy technologies or a
combination of both. They may use fossil fuel-based generation sources such as DG or Renewable
Energy Technologies (RET) such as solar, hydro, biomass, or wind. Minigrids can also be coupled with
energy storage systems such as batteries. Diesel Generators are still very popular due to their reduced
up-front costs. However, some of the RET such as wind and solar are already competitive with diesel
generators in terms of levelized costs of energy (ADB, 2017). The LCOE of solar and wind systems is
estimated to be around USD 0.057/ kWh and USD 0.039/ kWh respectively (IRENA, Renewable Power
Generation Costs in 2020, 2021). Whereas the cost of diesel systems has been found to range around
USD 0.3 to 0.5 per kWh considering subsidized diesel prices (Solano-Peralta, Moner-Girona, van Sark,
& Vallve, 2009). The technology-wise share of installed and planned minigrids worldwide is depicted
in Figure 6. The description of different power generation technologies in minigrids are discussed
below in this section.
5 (ADB, 2017)
12
2.3.3 Biomass and biogas-based systems
Organic materials, such as wood, rice husk, coconut shell, bark, etc. are used to generate electricity
from biomass-based power generation systems. Energy from biomass is reliable as it is free of
fluctuation and does not need storage to firm up the capacity or compensate for the intermittency
unlike wind or solar power . However, energy generation utilizing biomass resource is challenging
because of issues of biomass supply chain. Biomass from agriculture is available only after harvesting
period, so there is a need to procure, transport and then store required quantity of biomass within
the stipulated time. The agri-residues and other biomass stocks have alternate uses as well such as
fodder, cooking fuel, etc. and thus, there is limited availability of biomass for energy recovery, and the
prices of residues are also high. Biomass projects generate solid, liquid, and gaseous waste that, if not
controlled, can harm the environment. Thus, appropriate measures should be taken to minimize
harmful emissions and comply with environmental regulations, which include proper operational
procedures and emission control systems.
Biogas is a renewable fuel produced by the breakdown of organic matter such as food scraps and
animal waste by microorganisms in the absence of oxygen. After biogas is captured, it can produce
heat and electricity for use in engines, microturbines, and fuel cells. Stored biogas can provide a clean,
renewable, and reliable source of baseload power in place of coal or natural gas. Similar to natural
gas, biogas can also be used as a source of peak power that can be rapidly ramped up. The supply
chain issues such as poor collection, improper segregation, and transportation of waste are barriers
for utilising waste in biogas production.
13
run enterprises, since diesel is taxed in the SAARC Member States. Finally, gensets are noisy and
polluting, and have severe health impacts. Each litre of diesel fuel consumption produces, on average,
2,664 g of CO2. (Aaron Zvi, n.d.).
To provide reliable quality of service, RE minigrids need to have larger generation capacity in
comparison to fossil fuel or hybrid systems, which will increase energy price. Thus, depending on the
load profile, installing diesel generators along with RE is an effective way to decrease costs, reduce
emissions and provide high-quality energy services. Renewable energy minigrids, in future, will
increasingly use hybridisation of multiple sources such as solar/wind, solar/hydro and others, which
are the least-cost long-term energy solutions capable of delivering the best services. Figure 8 provides
a typical layout of hybrid minigrid system.
6 (ADB, 2017)
14
2.4.1 Capital cost of minigrid
The capital costs of minigrids include cost of project development, generation and distribution assets
and logistics. In developing countries, the total cost of installing a solar-diesel-battery hybrid minigrid
in an off-grid setup is extremely high for many rural customers. The capital cost for solar hybrid
minigrids is in the range of USD 1,420/kW to USD 22,689/kW, with the average and median costs as
USD 6,193 and USD 4,849, respectively (BNEF & SEforAll, 2020). Figure 9 provides the breakup of
capital cost for a solar-diesel-hybrid minigrid system.
The generating components of the minigrid system accounted for 54% of total capital costs. The
components with the largest share of overall cost were batteries (15%), distribution system (14%), PV
modules (11%), inverters (5–9%), powerhouses (7%), and meters (4%). The variations in taxes and
duties, wholesalers and distributors margins, and other costs incurred in setting up minigrid across
countries explains much of the variation in minigrid component costs.
The costs of key minigrid components have fallen by 62–85% between 2010 and 2018, partly because
of economies of scale outside the minigrid sector. For solar PV, the deployment of utility-scale solar
PV parks and rooftop solar home systems drove cost reductions of 85%. The cost of lithium-ion
batteries also fell by 85%, which was mainly driven by the increased use in electric vehicles and utility-
scale storage projects (ESMAP, 2019). Figure 10 provides the trends in solar PV cost from 2011 to 2019.
ESMAP has analysed selected solar and solar hybrid minigrids in Africa and Asia to study the LCOE of
minigrid electricity under different scenarios. As per ESMAP study, the LCOE for minigrids ranges from
USD 0.55 to 0.85 per kWh. Bloomberg New Energy Finance (BNEF)/ Sustainable Energy for All (SEforAll)
study has also analysed the LCOE for various types of minigrids currently in operation across the six
case study countries. The study shows that LCOE of solar hybrid minigrid operating in isolated areas
and serving productive loads ranges from USD 0.49 – 0.68/ kWh.
LCOEs have been found to be consistently lower for minigrids that serve productive-use customers
than for those that serve residential customers. This is because productive-use customers such as
agricultural processing facilities and enterprises tend to use daytime electricity, which correlates
better with the generation profiles of PV systems, increasing the utilization rate of the minigrid and
leading to a lower LCOE. It was found that when a 40% load factor was achieved through significant
daytime consumption by local enterprises and commercial setups, the LCOE fell by 25% compared
with the base case (see Figure 11) (Chris Greacen, 2019).
Increasing productive uses of minigrid electricity creates a win-win-win-win scenario for minigrid
developers, rural entrepreneurs, communities, and national utilities over time. It reduces the LCOE,
which increases the minigrid developer’s margins and therefore financial viability. Entrepreneurs and
communities benefit from affordable minigrid electricity, creation of new jobs and increased
economic activity. Although electricity generation from renewable energy usually entails high fixed
costs and related risks, renewables can play an important role in minigrids as prices have decreased
considerably within the last few years. Figure 12 depicts the unsubsidized costs of 100% renewable
energy minigrids from 2005 to 2035. The 100% renewable energy minigrids are a cost-competitive
solution in comparison with small gasoline and diesel generators.
9 (ESMAP, 2019)
17
Figure 12: Unsubsidised Cost Ranges for Renewable Minigrids from 2005 To 2035 10
For small scale remote projects, being usually not profitable, involving private sector in minigrid can
be challenging. However, creative approaches such as anchor load approach, community clustering
approach and private-private partnership can make minigrid investment financially attractive.
12 (ARE, 2019)
20
2.5.3 Utility based model
National utilities operate minigrids in similar manner as the national grid but on a smaller scale. The
utility sometimes contracts the local energy service companies to supply and install minigrids. In this
model, subsidies are often used to keep tariffs affordable in remote areas. Usually, tariffs are set equal
to that of national grid although cost of minigrid is higher.
This model is efficient when government supports minigrid development as part of its national
electrification strategy. Traditional national utilities without a minigrid strategy tend to prioritize grid
extension. Figure 16 provides the schematic diagram of utility-based business model.
Da Afghanistan Breshna Sherkat (DABS) in Afghanistan has implemented a 1 MW solar-diesel minigrid
in Bamyan province that utilizes pay-for power mechanism, which could be run by local utilities (CIF,
2014).In Sri Lanka, Electricity Consumer Society (ECS) supplied electricity to rural households in villages
that had not yet been connected to the main grid of the national utility (the Ceylon Electricity Board
[CEB]). With the arrival of CEB grid, more than 100 of the isolated minigrids went out of existence,
while three ECSs converted their minigrids into main grid connected Small Power Producers (SPP)
(ESMAP, 2018).
In Bihar, a state of India, two electricity distribution companies - North Bihar Power Distribution
Company Limited (NBPDCL) & South Bihar Power Distribution Company Limited (SBPDCL) are
collectively running around 373 microgrids. The average size of each microgrid is around 10-20 kW.
The microgrids have been developed and are being maintained by L&T Construction, a private project
developer. The project has electrified around 44,000 households, spread across 240 villages. The
monthly fee for households has been kept at INR 60 (USD 0.7813) and for poor households, the monthly
fee has been reduced to INR 30 (USD 0.39) (M Ramesh, 2019).
Tanzania Electric Supply Company Limited (TANESCO) has implemented successful utility based
minigrid model that uses cross subsidization and contracts with local energy service companies.
13
1 INR = 0.013 USD as on 27th October 2021
21
TANESCO charges a uniform tariff throughout the country to subsidize minigrid operations (USAID,
2018).
In another hybrid model, private company generates and sells power to the utility through Power
Purchase Agreement (PPA) and the utility distributes the electricity. Utility can also generate and sell
power to local utilities for distribution to customers. Mwenga Hydro Ltd. in Tanzania generates the
power and sells it to the rural power development company which distributes the electricity (USAID,
2018).
• In-country or provincial regulations that allow minigrid to merge with central grid, has
supported the coexistence of minigrid and central grid. An excellent case in point is the minigrid
policy of Uttar Pradesh in India in which two exit routes have been identified at the advent of
central grid arrival that is, the developer can either feed power to the grid or can sell the project
to the discom after grid arrival. However, the tariff at which minigrid developers will sell power
to the grid will be determined at the time of exit/integration with the grid, but the calculation
methodology has not been specified in the policy. Therefore, the developers have opted to stay
away from this policy because of the uncertainty over commercial terms of agreement
(Priyavrat Bhati & Mandvi Singh, 2018).
• Sri Lanka has developed procedures to acquire existent minigrids and integrate them with the
national grid as last mile connectivity. As a result, majority of erstwhile minigrids are now
wheeling power to the central grid, or the asset has been fully integrated with the central grid
(ADB, Sri Lanka Energy Sector Assessment, Strategy, and Roadmap, 2019).
• In Bhutan, minigrids that have lower cost of power (compared to a threshold value of BTN 5.81
(USD 0.077)14 /kWh) are allowed to sell power to the centralised grid (IRENA, 2019)
Technical requirements for interconnecting minigrids with central grid can be of theoretical as well as
practical relevance for minigrid design and operations. While in certain instances the two can be
allowed to operate in parallel (especially in regions where the centralised grid is inexpensive but
sporadic), there needs to be precautions (such as islanding) in design of minigrid architecture
protecting the local minigrid in the event of a load shedding or brown out in the main grid. Other
options (such as in Sri Lanka) are to generate and wheel the minigrid power to the central grid and
connect the minigrid’s distribution network with the nearest sub-station or create a bus bar for local
distribution using the minigrid network.
14 1 BTN = 0.013 USD as on 27th October 2021, same exchange rate has been used to convert BTN to USD in this report
23
2.8 Latest innovation and improvements
Minigrids normally involve hybridized systems with a considerable share of renewable energy supply
for electricity generation. However, renewable energy technologies are characterised by their
intermittency that is difficult to predict. These conditions involve a challenge in terms of plant
operation and management because of the required flexibility to maintain a regular system operation
and stability. The minigrid faces further challenges in terms of rising energy demand, demand patterns
and a lack of actual data analytics for the optimised operation and management of the system.
For these reasons, the minigrid energy sector is starting to innovate new solutions that include
amongst others: Artificial Intelligence, smart grids, smart meters, and Internet of Things devices. These
solutions aim to improve power management, integration, and system efficiency of the minigrid.
Furthermore, DSM is another innovation that is being considered by minigrid developers to implement
the strategies of actively influencing electricity demand to match electricity generation.
Smart grids are developing solutions that allow, for example, to trade electricity with the consumers
in minigrid applications with the utilisation of demand-supply matching algorithms. Artificial
Intelligence or Machine Learning power controls come into play to undertake the matching process,
so that the minigrid systems are able to perform as an integrated system. Obviously, a critical point to
consider for the application of these type of innovations, especially in rural environments, are internet
connectivity constraints which may hamper the viability of such solutions.
24
Figure 18: Example of IoT Smart Metering Platform15
This intermittency is challenging not only from the energy dispatching point of view but also in terms
of its O&M and actual system regulation. Several techniques are currently being developed for wind
and solar forecasting that include Numerical Weather Prediction (NWP) and Machine Learning (ML)
techniques such as Artificial Neural Networks (ANNs) etc.
The NWP prediction models are normally operated by weather service companies that basically collect
measured weather data, which they utilised to predict solar irradiation, wind speeds, ambient
temperature, etc. This data allows then to estimate the power output with physical equations or
15 (SteamaCo, 2020)
16 (energymeteo, 2020)
25
statistical tools such as ANNs. Some of the power forecast providers are Meteologica S.A., Meteogrid,
Entec Solutions, and Vaisala.
The AI allows to assess large volumes of data from diverse real-time sensors where a prediction of the
power to be generated in a minute timeframe would be forecasted. This estimate would then be
compared against the actual power generation by the renewable energy plant. If a large discrepancy
is tracked by the AI, the system will send an alert signal to the operators to perform preventative
maintenance. This will not only avoid potential system component breakdowns but also minimize
potential underperformance losses and labour cost reduction.
17 (MOXA, 2019)
26
demand periods that would help to reduce electricity costs. This would avoid the need of system
capacity upgrade and at the same time have a more levelled demand over the day. Other DSM option
in the minigrid context could involve charges when inefficient equipment is utilized. This would favour
the customer utilizing energy efficient equipment. The DSM load management technique can be
classified as:
i. Load levelling
It optimizes the electricity demand so that reserve capacity is minimized over periods of high demand.
This can be undertaken through following levelling methods (see Figure 21):
• Peak clipping: This basically involves the reduction of the consumption during peak demand
periods
• Valley filling: For low demand periods the “filling” with consumptions that are displaced to that
period. For example, mobile charging equipment
• Load shifting: This option involves the displacement of the loads from peak to valley times
• Load conservation: This would involve the application of efficiency measures to reduce the
customer electricity demand
18 IEEE FOUNDATION
27
Mini-grid Solar PV / Wind / Battery
Electricity Tariffs Performance Signal
Other Signals
Information
Control signal
Consumer Load
Usually, there is an interruptible load contract between the user and retailer with some incentives or
compensation in return. Normally the retailer does not physically interrupt the electricity supply for
the customer, instead it provides the user with an advance notice requesting the load curtailment.
Under the scenario of not complying with request this would potentially lead to penalties or even
customer load interruption. The current load control technologies do allow the switching of the loads
to be undertaken:
• Automatically: the switching responds in an automatic manner to a specific signal
• Manually: the switching is undertaken in response to a specific event or information
The switching may be undertaken locally or in a remote manner by a program triggered by a given
signal. The actual switching of the loads may involve:
• Load Cycling: the loads are switched on and off based on a timing schedule
• Load Reduction: the loads are reduced to defined pre-set values
• Load switching: basically, switching off the load
The key demand management strategies and technologies have been summarized in Figure 23 below.
28
Electricity access: Around 47 million people have been provided access to electricity through 19,000
minigrids installed across 134 countries globally (ESMAP, 2019).
Reliable and quality electricity: Today, minigrid developers are designing systems that can provide
24/7 electricity. Use of remote monitoring systems, smart meters, load limiters have led to increase
in the quality and the reliability of minigrids. For example, it has been observed that the average
uptime of minigrids owned and operated by Africa Minigrid Developers Association (AMDA) members
have exceeded 97% (ESMAP, 2019).
Economic development: Modern minigrids are designed such that the payback periods are less than
12 months for more than 30 income-generating machines and other equipment. As a result, it
improves financial viability of developers as well as create jobs and enhance livelihoods in
communities (ESMAP, 2019). As per Global Off-Grid Lighting Association (GOGLA) data, USD 4.9 billion
has been generated as additional income because of off-grid solar projects (BNEF & SEforAll, 2020). In
another example, an African minigrid project developer, RVE.Sol has set up Kudura minigrids in East
Africa to provide electricity as well as drinking water to populations whose mean per capita income is
just about USD 3 per day. The project has positively impacted 2,100 Kenyans directly. The fee-based
PAYG model has reduced energy costs in these households by almost 75%, as reported by one of the
investing entities in the company (Acumen, 2021).
Cleaner environment: A renewable energy powered minigrid avoids noise and air pollution caused by
diesel-based generators, thereby contributing to a cleaner local environment. ESMAP has estimated
by 2030, 10–15 GW of solar PV could be installed using 50–110 GWh of mostly lithium-ion batteries
and energy efficient appliances, which is expected to result in 1.5 billion tons of carbon dioxide
emissions avoided (ESMAP, 2019). However, there are hazards and pollution associated with disposing
of these batteries which needs to be addressed.
Improved health and education: Use of minigrids has resulted in improved health indicators for women
and children from the replacement of polluting energy sources such as kerosene lamps. Further, in
the current context of the Covid pandemic, minigrids energising rural health clinics has paved way for
a functional clinic capable of storing Covid vaccines and other medicines. Minigrids have also resulted
19 Figure recreated by the Consultant based on Figure 88 given in (BNEF & SEforAll, 2020)
29
in improved education indicators through access to reliable household lighting and school power
supply.
Benefit to national utilities: Modern minigrids are typically designed as grid ready as well as promote
productive uses of electricity and create local economic development. Thus, when the main grid
arrives at the site, there is already significant demand for electricity and consumers have greater
ability to pay, hence increasing the economic viability of the main grid’s extension.
Private sector participation: Private-sector participation in the minigrid market has increased as the
economics of minigrids are becoming more attractive. Several industry associations across countries
and regions have been initiated such as AMDA which comprises of 27 minigrid developers (each
operating a portfolio of commercially viable minigrids) in Sub-Saharan Africa, CLEAN network in India
is a network of 200+ members across India and is considered as the industry body for the DRE space.
30
Technical Barriers: Minigrids are unique and require custom installations specific to the site. There
are also limitations related to technical expertise available among the human resource to deploy
minigrid. Intermittency of the renewable resources also adds to the complexity in technical design of
RE minigrids. Minigrid system should be designed as grid ready to avoid redundancy of the project
after the arrival of the grid, but many countries have not yet issued the interconnection requirements
for connecting to main grid.
Economic Barriers: Remote areas or off grid areas have low or unpredictable demand to electricity as
well as low-income sources as many rely on agricultural activities which is seasonal. This directly
impacts their ability to pay for electricity bills and the revenue generation/ profitability of project
developers. Minigrid developers are thus increasingly promoting enterprise development in the areas,
which will lead to growth in demand of electricity and help in income generation and hence increase
customer’s willingness and ability to pay for the electricity consumed.
31
3 STATUS OF MINIGRIDS IN SAARC MEMBER STATES
32
3.1 Framework for assessing minigrids status
The section lays out the framework for assessing the status of minigrid development in each of the
eight SAARC Member States. The assessment has been carried out using a multi-dimensional
framework mapping across nine categories (i) Status of access to electricity and minigrids, (ii) National
strategy for electricity access, (iii) Policy & Regulations for minigrids, (iv) Technical aspects of minigrids
(v) Business models for minigrids, (vi) Minigrids tariff, (vii) Financing for minigrids, (viii) Opportunities
for minigrids and (ix) Barriers to minigrids (See Error! Reference source not found.). Secondary data
as well as information collected through discussions with stakeholders in each country has been used
to carry out the assessment. The assessment provides a comparative analysis on minigrid
development in each country and provide cross-learning potential that could be exploited in the
SAARC Member States for scaling up minigrid deployment.
Status of access to electricity As per the general trend observed globally, the closer a country comes to 100% electrification,
and minigrids there is lesser demand for minigrid projects. This section will analyse the status of access to
electricity and installed minigrids in the country.
National strategy for Government strategies often vary across countries regarding use of minigrids for enhancing
electricity access access to electricity. This section will assess the national strategy for improving access to reliable
electricity and role of minigrids in the strategy.
Policy and regulations for There may be a varying degree of policy and regulatory measures adopted across the SMS to
minigrids support MG development. This section will present the policies and regulations implemented in
each SAARC Member State.
Technical aspects of Use of innovative technologies in generation, storage, O&M, revenue collection, etc. enhances
minigrids the viability and therefore attractiveness of MG. This section will discuss the technological focus
and advancements in each SAARC Member State.
Business models for Maturity of a MG business model ensures that the project is robust in design, therefore more
minigrids resilient to market dynamics. This section will analyse the various business models that have been
implemented in each country.
Minigrids tariff In most cases, MG tariffs are higher than grid tariffs which is primarily due to power from the grid
being subsidised and not reflective of the true costs of power. This section will analyse the MG
tariffs in the country and their affordability.
Financing for minigrids Each country has different level of financing available for MG project which may be donor grant,
public loan, commercial loan, equity, and debt financing, etc. This section will discuss the financing
landscape available in each country.
Opportunities for minigrids Each of the SAARC Member States have their unique opportunities for MG projects. These range
from access to electricity, high unmet demand, etc. This section will analyse the various
opportunities for MGs in each SAARC Member State.
Barriers to minigrids Key barriers to the sector are policy-level impediments, supply and demand mismatch, low plant
load factor of MG, lack of adequate financing. This section will discuss the country level barriers
for MG development.
33
3.2 Afghanistan
3.2.1 Status of access to electricity and minigrids
Afghanistan has about a third of its population connected to the electricity grid (ADB, 2020). The
country still depends heavily on imported electricity and fuels. Lack of domestic generation remains
the key challenge for energy security and energy access in Afghanistan. Energy security and access are
high development priorities for Afghanistan.
Since 2001, major efforts have been on reconstruction and expansion of the national electricity grid.
Despite these efforts, it is accepted that there are areas in the country that the national grid will not
serve in next 20-30 years. This is due to the slow progress of integration of the national grid, which
still operates as a few regional grids, which are supported by electricity imported from neighbouring
Uzbekistan, Iran, and Turkmenistan, among others.
In addition, secondary information indicates that the current electricity delivery infrastructure is
neither reliable nor economically attractive for most consumers. Frequent power outages create
discomfort and hindrances, and necessitate power options, especially for commercial and industrial
facilities. The delicate security situation in the country has often led to transmission and distribution
lines being damaged (due to arson), which have delayed and affected plans for electrification
(GardaWorld, 2021). This also implies greater need for localised networks such as minigrids. Thus, the
current energy access landscape offers promise for minigrid project development.
Historically, there were many micro hydropower units (about 40 kW or less) that were set up under
the National Solidarity Plan (NSP) between 2003 and 2013, although parts of NSP continued under the
National Area Based Development Programme (NABDP). Originally targeted for developing 5,000
villages, the NSP implemented about 2,500 village level electrification systems powered by micro
hydro units. Several solar home systems were also installed under the programme (Beath, Christia, &
Enikolopov, 2015). The management of these units were left to community level institutions called
Community Development Councils (CDCs).
However, most of these installations were not managed properly due to lack of technical resources in
CDCs, and without any operation and maintenance support, did not sustain for many years. Also, the
CDCs did not have the capacity to execute O&M for the assets. As a result, most of the NSP and NABDP
projects are in an inoperative state.
The most notable among recent initiatives in the direction of minigrid project development is the
United Nations Development Program (UNDP), Afghanistan and Ministry of Rural Rehabilitation and
Development (MRRD) supported rural energy programme. The programme is currently operational
under the title “Afghanistan Renewable Energy Market Transformation Initiative (AREMTI)” (GCF,
2020). Afghanistan Sustainable Energy for Rural Development (ASERD) (project was funded through
bilateral grant funding from Spain and South-Korea) programme laid the foundation for this current
programme by developing feasibility studies for 25 minigrid sites in 17 provinces of Afghanistan.
Recently, a hybrid solar-hydro minigrid project with a total capacity of 340-kW has been implemented
in Dar-i Noor district of Nangarhar Province. The project was commissioned under the ASERD
programme and was financially supported by the Republic of Korea and UNDP Afghanistan. This
project is expected to provide electricity to approximately 18,000 people (about 3,000 households)
and more than 80 Small and Medium Enterprises (SMEs) (UNDP, 2021). The AREMTI programme, on
34
other hand, proposes to implement three (3) solar minigrids with a combined capacity of 2.6 MW, in
the provinces of Kandahar, Parwan and Khost. In addition, the programme proposes to develop
construction designs for other 5 minigrids in Afghanistan.
There are several diesel-powered minigrids in operation in off-grid areas. While the national utility,
DABS operates diesel-powered minigrids in several provincial capitals (not connected to the grid),
private operators run diesel generators for providing lighting to rural communities using a
rudimentary mini or microgrid structure.
Although there is no dedicated minigrid policy, as shown in section 3.2.2, the strategy documents
clearly outline a role and scope for RE powered minigrids in the country. One of the landmark
regulations in the country was the demarcation of all RE projects up to 1 MW capacity, to be set up in
rural areas within the purview of the MRRD (AREP, article 4.7). This has contributed to the creation of
a nodal ministry for decentralised RE projects that include both standalone grid tied and minigrid
applications.
The MRRD, in collaboration with the erstwhile Ministry of Energy and Water (ministry is dissolved as
of the present date), had developed a draft National Rural Renewable Energy Policy (NRREP) (2013 –
2014) (Government of Afghanistan, Afghanistan Rural Renewable Energy Policy, 2013). The policy
encourages creation of an enabling environment towards full commercial operations of rural
renewable energy services. The policy was in line with the ANDS (2008 – 2013) and the policy thrust
provided by the National Priority Programmes (NPPs) which were drafted for the country to usher in
a regime of balanced growth and development. A total of 22 NPPs were drafted in 2009 covering six
35
strategic themes (Ministry of Finance, n.d.). Among these, rural decentralised development was one
key theme – addressed under the ‘Agriculture and Rural Development’ Cluster. The cluster NPPs
highlighted the need for RE based decentralised energy access in Afghanistan.
Around 2015 – 2016, the Afghan government also developed a draft Feed-in-Tariff (FiT) Policy for
various renewable energy project categories (e.g. wind, solar, biomass), specific to each Province.
However, the policy has not yet been given final shape.
36
Figure 26: 5 kW Wind Turbine in Sang-E-Nawishta Village of Kabul20
20
UNDP Afghanistan
37
The Bamiyan 1 MWp solar PV–diesel hybrid project (called Bamiyan Renewable Energy Program or
BREP), is providing electricity to consumers in Bamiyan town and the average power tariff that was
initially charged was as high as USD 1.95 per kWh. However, over time, the cost has reduced and as
of 2017 it was USD 0.25 per kWh, a significant improvement. It is also pertinent to note that consumer
demand for electricity from BREP has increased as of 2017 (USAID, 2018). This substantiates the view
that higher tariffs in minigrid projects might not be a deterrent to energy demand. It is also worth
noting that BREP introduced prepaid metering, which was also a first in the country and thus also
makes a case for successful implementation of on use of prepaid meters. Importantly, the recently
implemented solar PV–hydro hybrid project in Dara-i-Noor district of Nangarhar province has
provision for prepaid cards with smart meters, which allows the users to pay for the electricity prior
to their use and according to their energy needs (Abdul Haq Omari, 2021).
3.3 Bangladesh
3.3.1 Status of access to electricity and minigrids
Bangladesh is one of the world’s most rapidly growing developing economies and one of the most
vulnerable countries to climate change. The overall rate of electrification in Bangladesh increased
from 14.29% in 1991 to 32% in 2000 to 55.26% in 2010 and 92.2% in 2019 (see Figure 27). In the year
2019, 97.8% of urban population has access to electricity while only 88.85% of rural population has
access (World Bank, n.d.). During the consultation with Sustainable and Renewable Energy
Development Authority (SREDA), it was learnt that the country has achieved 99% electrification as of
2021. Renewable energy, from both on grid and off grid solar, wind, hydro, biogas, and biomass, has
40
3.05% share in the total electricity generation mix (Sustainable and Renewable Energy Development
Autho, n.d.). Solar home system is the most popular form of off grid renewable energy technology in
Bangladesh with 34.28% share. SHS provides electricity for lighting, mobile charging, and fan.
However, electricity demand of the off-grid community is not limited to these basic needs.
Realizing the above, Government of Bangladesh (GoB) had identified solar minigrid as an appropriate
solution to meet the electricity need of the rural community. Twenty-Seven (27) solar minigrids with
diesel generators as backup of total capacity 5.66 MW have been installed in Bangladesh as of August
2021. One of them is operated by distribution utility and rest by private companies. Bangladesh’s first
commercial solar minigrid, PGEL Solar MiniGrid Project, of 100 kW capacity started operating on
Sandwip Upazila, Chittagong in 2010 (Sustainable and Renewable Energy Development Autho, n.d.).
22 1 BDT = 0.012 USD as on 27th October 2021, same exchange rate has been used to convert BDT to USD in this report
23 (ESMAP, Mini grids in Bangladesh: A case study of an incipient market, 2017)
43
3.3.7 Financing for minigrids
IDCOL is the largest financier of infrastructure and RE projects in Bangladesh. Almost all the solar
minigrids in Bangladesh are financed and implemented by IDCOL (Sustainable and Renewable Energy
Development Authority, 2021). IDCOL receives funds from government and donors to finance solar
minigrid systems and to offer a standard subsidy package to the developer.
Grant of 50% of the total project cost and concessional loan up to 30% is provided to minigrid
developers by IDCOL. Remaining 20% comes as developer’s equity (Infrastructure Development
Company Limited , 2020). Renewable energy equipment and related raw materials for the
development of minigrid project are exempted from 15% Value Added Tax (VAT). The banks are
allowed to provide loans in rural areas worth up to BDT 150,000 (USD 1,74924) for setting up solar
minigrids (Sustainable and Renewable Energy Development Authority, 2021).
The first and only minigrid project financed by commercial bank in Bangladesh in Angira solar minigrid,
raising 67% through commercial debt taken from Uttara Bank, with the remaining 33% through equity
investment. The 50 kWp Angira solar minigrid was set up in 2014 in the Nur Mohammed Market in
the Manikganj district. It had an initial capacity of 30 kWp but was upgraded to 50kWp due to
customer demand for electricity. While the Angira minigrid is of a smaller capacity than the IDCOL
financed solar minigrids, its success could pave the way for larger commercially financed projects
(CDKN, 2019).
24
1 BDT = 0.012 USD as on 27th October 2021
44
made commitments to reduce unconditional 5% of Greenhouse Gas (GHG) emissions by 2030 in the
power, transport, and industry sectors and a conditional 15% reduction in GHG emissions by 2030
(Government of Bangladesh, 2020). Bangladesh has also committed to increase its share of renewable
energy electricity generation in country plans such as Draft Eighth Five Year Plan (FY 2021 to FY 2025),
Bangladesh Delta Plan 2100, and National Solar Energy Roadmap 2021-2041. Renewable Energy Policy
2008 mandates at least 10% of the total generation to be generated from RE sources. Minigrid has the
potential to become an integral part of Bangladesh’s strategy for increasing the share of RE to meet
its NDCs.
3.4 Bhutan
3.4.1 Status of access to electricity and minigrids
The Royal Government of Bhutan (RGoB) is one of the smallest but fastest growing country among the
South Asian countries. The country has aggressively pursued electrification through national grid,
decentralised distributed generation (DDG) in isolated, as well as, core protected areas and solar home
systems in most remote areas. During the stakeholder consultation with Department of Renewable
Energy (DoRE) of Bhutan, it was learnt that the country has reached almost 100% electrification mostly
through national grid.
25
1 BDT = 0.012 USD as on 27th October 2021
45
Hydropower projects are the major source of electricity in Bhutan. Other than large hydropower
projects, electricity is generated from micro/mini hydro and other renewable energy technologies
such as solar, wind and bioenergy. Figure 29 showcases the major electricity generation sources in
2019. Bhutan has also installed 13 to 14 diesel generator sets throughout the country, which are used
only as backup power.
26
(Dawa Gyelmo, 2021)
46
electrification will be achieved either by the extension of the grid or by the development of off-grid
electrification with promotion of renewable energy (Royal Government of Bhutan, 2001).
Alternative Renewable Energy Policy was formulated in 2013 with an objective to promote and
develop RE technologies in the country. AREP states that in rural areas where national grid is difficult
to reach, community-based initiatives in the form of decentralised distributed generation based on RE
sources should be given the priority (Royal Government of Bhutan, 2013).
47
Department of Renewable Energy shall not be considered for tariff determination (Bhutan Electricity
Authority, 2016).
3.5 India
3.5.1 Status of access to electricity and minigrids
India has made significant progress in last decade in providing electricity access to its population. Its
electrification rate has increased very rapidly (See Figure 30). In March 2019, the Government of India
declared full electrification of all households. However, as per IEA data27, the rate of national access
has grown from 43% in 2000 to more than 99.6% in 2019 and there are still around 5.5 million28 people
without access to electricity in India (IEA, n.d.).
27
India has dual electrification targets focusing on electrifying villages (a village is considered electrified if 10% of households
have access) and households. IEA methodology focuses on the share of the population with access to electricity in line with
the UN SDG tracking framework.
28
As per the Tracking SDG7 The Energy Progress Report 2021, the access to electricity in India has grown to 98% in 2019
with 30 million people without access to electricity. The Tracking SDG7 Report 2021 has referred to World Bank Global
Electrification Database. The World Bank Global Electrification Database derives estimates from a suite of standardized
household surveys that are conducted in most countries every two to three years, along with a multilevel nonparametric
model used to extrapolate data for the missing years. The IEA Energy Access Database sources data, where possible, from
government-reported values for household electrification (usually based on utility connections).
49
Proportion of the population with access to electricity
99.6%
100.0%
78.9%
80.0%
67.9%
57.7%
60.0%
43.0%
40.0%
20.0%
0.0%
2000 2005 2010 2015 2019
Minigrids in India have also expanded significantly over the last decade due to increased involvement
of private players, local banks, and the government through the Ministry of New and Renewable
Energy (MNRE)’s Remote Village Electrification Programme (RVEP) and the Village Energy Security
Programme (VESP) for providing reliable and access to electricity to remote villages (Graber,
Narayanan, Alfaro, & Palit, 2019). As per the MNRE, 214 MW of off-grid power plants including
micro/minigrids had been deployed in India by March 2020 (Centre for Science and Environment,
2020). Figure 31 provides the cumulative growth of off-grid plants in India. Another data source of
ESMAP has reported around 2,800 minigrids exist in India, which are powered mostly by diesel, solar,
biomass and hydro.
29 (IEA, n.d.)
30 (Centre for Science and Environment, 2020)
50
areas, Saubhagya scheme for grid connectivity to last mile households and Integrated Power
Development Scheme (IPDS) in urban areas to provide electricity access. In April 2018, the
Government declared that 100 % of the villages had been electrified under DDUGJY. Later, in March
2019, all households (including 96 % in rural areas and 4 % in urban areas) except 18,734 households
have been electrified by the States under Saubhagya scheme. Several schemes to enhance energy
access of remote villages through renewable energy-based off-grid and decentralised technologies
including minigrids have also been launched. The first minigrid project was pioneered in the 1990s
when WBREDA installed 25 kWp system in Kamalpur village in Sunderban delta region of West Bengal.
WBREDA has further set up more than 20 minigrids based on solar PV with an aggregated capacity of
around 1 MWp supplying electricity to around 10,000 households in West Bengal. CREDA, another
state agency in India, has electrified around 35,000 households with low capacity (1-6kWp) solar
minigrids in Chhattisgarh. Thereafter, minigrids connected to solar PV, biomass, or small hydro, have
been implemented in various states, notably Bihar, Chhattisgarh, Lakshadweep, Madhya Pradesh,
Odisha, Uttar Pradesh, Uttarakhand, and West Bengal.
Although decentralized energy systems such as minigrids have been instrumental in providing last mile
connectivity and reliable electricity, yet the government considers them merely as a stop-gap solution
till the grid arrives. Several reports have highlighted that government programme of providing
electricity through grid electrification may not be sufficient to provide reliable electricity in remote
villages, and therefore minigrids might also continue to operate in grid connected villages having
irregular electricity supply (Bhushan, et al., 2019).
51
• Further, the Government had sent a notification in the National Tariff Policy in January 2016, to
support the concerns of minigrid developers regarding future electrical grid reaching the area
of a microgrid before the useful life of the asset. The notification states that the microgrid owner
should receive a pre-determined tariff for the rest of the useful life of the asset (Jaffer, 2016).
But this has not been made into a regulation yet.
The anchor-business-community model, widely adopted and promoted by OMC Power - a renewable
energy service company– in India, is another model which prioritises large ‘anchor’ loads such as
commercial and industrial followed by businesses and households. This model works well in villages
with considerable commercial/industrial loads. Gram Power, another private minigrid developer, has
evolved ‘pay as you go’ model to electrify remote rural villages in India using advanced technologies
where provision of electricity is made on demand.
Other set of business models include those that cater to the varying needs of the local people with
emphasis on creation of local entrepreneurship by engaging with the community and encouraging
development of local commercial activities. Smart Power India, a large-scale renewable energy
31 TPRM is a partnership between Institute for Transformative Technologies (ITT), Tata Power and the Rockefeller Foundation
to provide power through mini grids to 25 million people across 10,000 rural villages in India.
52
initiative created by the Rockefeller foundation, has been field-testing new technologies and business
models that can take decentralized renewable energy from an off-grid alternative to a mainstream
component for widespread rural electrification.
Further, operational diesel based minigrids are being converted/ hybridised into solar/ wind/ diesel
minigrids in large and densely populated islands and hilly/ remote regions of India. WBREDA is
developing a 500-kW solar-wind hybrid project in Sagar Island of Sunderbans. Central government is
promoting hybridisation of diesel gensets with renewable energy in Andaman & Nicobar and
Lakshadweep islands where majority of the power generation comes from diesel-based units.
Convergence Energy Service Limited (CESL), a newly established subsidiary of Energy Efficiency
Services Limited (EESL) is solarizing the existing diesel minigrids in Zanskar valley in Union Territory
(UT) of Ladakh, in collaboration with Power Development Department (PDD), Ladakh and Autonomous
Hill Development Council, Kargil. The proposed solar-diesel hybrid minigrid projects are driven by the
Vision-2050 for UT of Ladakh, which aims to harness the potential of renewable energy in the state
and thus becoming 1st state in India running on 100% clean energy. CESL is exploring international
carbon finance market to monetize GHG reductions from such projects.
Mlinda, another project developer, is installing scalable and replicable model of minigrids to increase
access to energy and has already installed 39 minigrids in 40 villages by March 2020. The project has
connected 4,918 families and empowered 1250 small enterprises across states of Jharkhand and West
Bengal. The minigrids are designed to meet domestic as well as agricultural needs. The consumers pay
upfront connection fees and then pay for energy usage through pre-paid meters (Mlinda, 2018).
Minigrids are being promoted to provide electricity for public institutions in health care and education
sector and for enterprise development in rural areas following the PPP approach where the Corporate
Social Responsibility (CSR) funds/ government grants/ local area development schemes are being
matched with private sector equity and community contribution to install and operate minigrids.
Hamara Grid Private Limited, a minigrid developer, has initiated a project designed on the above
model wherein the District Administration (Public), the minigrid project developer (Private), and the
Village Development Board (People) are proposing to work together to electrify 1000 villages spread
over ten districts in the Northeast. The project will integrate clean, high quality, and reliable energy
with livelihoods, agriculture, health, education, and other public infrastructure such as streetlights.
Husk Power, a minigrid developer, builds village scale minigrids using rice husk gasifiers, capacity
usually ranging between 30 and 200 kW. The firm has replicated this minigrid model in several
projects. The company works only in locations where at least 250 households agree to take
connection. DESI Power, on the other hand, has focused on productive use of power and used husk-
based systems to displace diesel-based electricity supply to micro-enterprises. It has also used anchor
loads to improve the financial viability of the business. SunMoksha, clean energy technology provider,
has developed technological solutions for microgrid and irrigation sectors. Smart Nanogrid, one such
solution, is a smart-grid and IoT/cloud-enabled microgrid solutions to dynamically manage supply and
demand, and manage billing and payment.
Unmet electricity demand: As mentioned earlier in section 3.5.1, there are still 5.5 million people in
India that lack access to electricity and most of these people live in remote rural areas. While India
generates sufficient electricity and has necessary capacity to meet demand, it struggles to distribute
this electricity efficiently and effectively to rural areas. In many places, the power reliability is limited
by transmission capacity and electricity distribution companies’ ability to perform repair and
maintenance of the network in remote areas. Even in grid connected villages there are problems of
54
reliability (hours of supply) and quality (voltage) of electricity. Despite the government's ongoing
efforts to electrify last mile households in India, there remains a clear gap between demand and
supply. RE based minigrids can provide high quality reliable electricity for lighting and other productive
loads in households and has the potential to become an integral part of India's rural electrification
strategy, providing last mile electrification.
Further, while the central Government has completed the electrification drive under the Saubhagya
scheme, the focus was mainly on households, and therefore, the public welfare institutions,
(particularly rural health centres) have been left out of this scheme. These institutions usually rely on
diesel gensets. Thus, there is an opportunity for minigrids to scale up in these areas to electrify public
institutions and support enterprise development utilizing CSR funds and other health sector related
public funds.
Specific opportunities: Minigrid policies in two states of India - Uttar Pradesh and Bihar - have been
driving private sector interest in these states to develop RE based minigrid projects for providing last
mile electrification, reliable & quality power and push socio-economic development complementing
government efforts. An increased consumers’ aspirational need for additional appliances also
indicates an opportunity for continued expansion of minigrid system capacities.
The other challenge is to make electricity from minigrids as affordable as grid power and still be able
to recover the capital and operating expenditures in a reasonable time frame for sustainable
operations. Minigrid power can be 25 times as expensive as power from the grid per kWh, because
developers try to recover their investment within only a first few years as well as due to presence of
low demand for electricity.
The third challenge for minigrid developers is the lack of a credible and reliable source of finance to
meet upfront capital costs and regular operating costs. Minigrids face challenge in financing, due to
their longer paybacks, inherently risky business structures, untimely payment by consumers, improper
billing and payment mechanism, and the lack of financing entities willing and capable of extending
low-cost financing. There is also lack of patient capital32 available to finance minigrids.
32Patient capital is an investment that does not seek to maximize financial returns to investors, but seeks to maximize social
impact and to catalyze the creation of markets to combat poverty
55
3.6 Maldives
3.6.1 Status of access to electricity and minigrids
Maldives is the first country in South Asia to achieve universal access to electricity. In 2008, the country
reached 100% access to electricity and further by 2011, 24-hour electricity supply across all islands.
Each inhabited island has its own powerhouse and distribution facility, effectively operating as single,
isolated island power grids. Almost all the country’s current power needs are met through diesel fired
generation, although there are no proven reserves of fossil fuels in Maldives. Diesel fuel is imported
and transported to the dispersed generating locations.
The island country has a total of 290MW capacity of diesel generators installed in 186 inhabited
islands, around 144 MW of additional diesel genset capacity in Resort islands and 20 MW in industrial
islands. Two electric utilities, Fenaka Corporation Ltd. (FENAKA) and State Electric Company Ltd.
(STELCO) operate 148 and 35 powerhouses respectively. A very small capacity of 21.5 MW of
renewable energy systems has been installed till now across the country. The above Error! Reference
source not found.Figure 32 shows the trends of renewable energy installations in Maldives from 2008
– 2019 (ADB, 2020).
Most of the solar installations in the country are rooftop solar PV installed under net metering.
Recently, solar PV projects in hybrid mode with existing diesel generators are being successfully
implemented in several inhabited islands under the Preparing Outer Islands for Sustainable Energy
Development (POISED) project of Asian Development Bank (ADB). The project is transforming existing
diesel-based energy minigrids into hybrid renewable energy systems in 160 inhabited islands, out of
which installations on 48 islands have been commissioned.
33 (ADB, 2020)
56
3.6.2 National strategy for electricity sector
The Government of Maldives (GoM) aspires to reach net-zero global greenhouse gas emissions by
2030 with international assistance and private investments. The key priority of the government, in this
regard, is to reduce its dependence on imported diesel fuel and invest in renewable energy projects.
Over the past 10 years, government has introduced several strategies and initiatives to scale up the
renewable energy applications in the country. Maldives has developed a Strategic Action Plan (SAP),
which includes strategies and targets for development of clean energy in the country. The plan targets
to increase the share of renewable energy by 20% as compared to 2018 and install a minimum of 10
MW of solar PV under net metering regulations by 2023. The plan also targets to reduce distribution
losses and plans to establish smart minigrids in selected clusters of islands to address this issue.
59
Lack of concrete energy sector plans: There is a need to develop robust energy sector plans focusing
on hybrid renewable energy projects to meet the increasing electricity demand in the country, lower
electricity cost and reduce the import of diesel.
Lack of financing: The investments in renewable energy projects in the country have been driven
primarily by grants and loans from multilateral agencies. Due to its relatively small banking system,
Government of Maldives is facing liquidity crunch to fund these projects. Commercial bank financing
or private sector financing is in its nascent stage since they are still reluctant to accept the risks
associated with renewable energy technologies and invest in the sector. Private sector participation
is crucial for development of RE minigrids in the country.
Limited expertise and experience in RE technologies: Utility companies in Maldives have mainly
implemented conventional energy projects since the beginning of the country’s industrialization.
Therefore, there is limited knowledge and experience regarding renewable energy technologies, their
installation and operation and maintenance.
3.7 Nepal
3.7.1 Status of access to electricity and minigrids
Nepal was facing severe electricity shortage and the country was facing load shedding (power cuts)
up to 16 hours per day in households till early 2017 as well as in industries till early 2018 (Sushil Sah,
2019). Economic Survey of Nepal 2020/21 states that the overall rate of electrification has reached
93% (Ministry of Finance, 2021). The yearly trend of access to electricity is provided in Figure 34. The
major source of electricity in Nepal is grid connected large hydropower projects. However, Nepal has
difficult topography and scattered settlements, particularly in hills, thus extension of national
electricity grid for electrification of rural areas would be expensive. Hence, Nepal has been promoting
micro hydro for rural electrification since 1980s (Alternative Energy Promotion Centre , 2016).
Access to Electricity
100
% of population
80
60
40
20
0
Fiscal Year
35
(Ministry of Finance, Economic Survey 2077/78, 2021)
60
The solar minigrid in Nepal was piloted by Nepal Electricity Authority (NEA) with support of France in
1989 (Renewable Energy for Rural Livelihood, 2020). After 2011, Government of Nepal (GoN) has been
allocating budget and installing solar and solar-wind hybrid minigrids in each fiscal year (Santosh Rai,
2019). Alternative Energy Promotion Centre (AEPC) has different programs for the promotion of
renewable energy including minigrid sector focusing on rural electrification in Nepal. AEPC has
installed 11 solar-wind hybrid minigrid projects of total capacity 384 kW and 14 solar minigrid projects
of total capacity 711 kW until 2020 (includes working, under construction as well as planned projects).
AEPC has also developed 1,816 numbers of mini/micro run of the river hydro projects of total capacity
32,778.39 kW in off-grid areas under different programs (Santosh Rai, 2019).
During the stakeholder consultation, it was learnt that since last couple of years less than 50% of
mini/micro hydro minigrids have sustained due to different reasons including high tariff, operation
and maintenance issues, and natural disasters. Almost 274 mini/micro hydro were damaged by 2015
earthquake in Nepal. Out of 274, 116 projects are under rehabilitation with support from Renewable
Energy for Rural Livelihood (RERL) program, Department for International Development (DFID) and
GoN fund and 97 projects are rehabilitated and maintained by community themselves (Santosh Rai,
2019).
61
electricity consumption. The policy has the provision of additional financial support to targeted
beneficiaries including households headed by women and marginalized community. The white paper
of Ministry of Energy, Water Resource, and Irrigation (2018) has provisioned the policy to establish
the challenge fund to develop the 100 kW to 500 kW solar energy technologies at each local level.
Minigrid Special Program Operation Rules has been formulated in the year 2019 to facilitate
mountainous and upper hills solar minigrid program and Ujyalo Nepal Program. MHP Operation and
Management Guidelines provide details on sustainable operation including institutional strengthening
for smooth operation of the plants and promotion of productive electricity uses after the installation
of micro hydro. Technical standard for grid interconnection 2014 was approved by NEA to buy
electricity from an MHP when the national grid passes through its service area. This has opened
opportunity for the interconnection of micro hydro to the national grid (Renewable Energy for Rural
Livelihood, 2020).
62
Dubung Solar microgrid is the first in Nepal built in partnership between the community (user
community of Dubung), private sector (Saral Urja Nepal Pvt. Ltd.) and the government of Nepal. The
project developer company is jointly owned by user community of Dubung and Saral Urja. Private
sector involvement has helped in providing reliable electricity supply (Saral Urja Nepal, 2021).
36 1 NPR = 0.0083 USD as on 27th October 2021, same exchange rate has been used to convert NPR to USD in this report
63
Sustainable Energy Challenge Fund (SECF) is being implemented under AEPC’s CREF to provide Viability
Gap Funding (VGF) to make marginally feasible distributed RE projects bankable. SECF supports
technical, managerial and financial management to new and existing RE minigrid projects.
To attract the private sector in operation and management of minigrids, the RE subsidy policy 2016
has provisioned upfront kilowatt-based capital subsidy and the subsidy for energy consumed to cover
part of the operational expenditures. However, the new provision has not attracted the investors due
to the perceived risk in investing in community owned minigrids.
64
Despite the successful interconnection of several MHPs and solar PV projects to the national grid, the
policy for grid connection of minigrids is still ambiguous. CREF, although has been operational for some
years, it has not been able to attract private investment in minigrid projects. Project developers
continue to struggle to achieve financial closure on time as subsidy and their equity are not enough to
cover the total project cost and bank financing is difficult to access, if available the cost of financing is
very high as the financing institutions perceive high risk to invest in rural communities.
3.8 Pakistan
3.8.1 Status of access to electricity and minigrids
The electrification rate in the country has improved from 55.7% in 2005 to 79.2% in 2019. However,
there are still around 45 million37 people without access to electricity with majority falling in the rural
areas (IEA, n.d.). The installed power capacity as on June 2020 stands at 38,719 MW, which was more
than sufficient to meet the total demand in the country in FY 2019-20. Despite having surplus power
generation capacity, long hours of load shedding persist in several areas of the country (National
Electric Power Regulatory Authority, 2020) . The power cuts are more pronounced in the rural areas
compared to urban centres (Wheeldon, 2017).
Figure 35: Coverage and Projects Under PPAF KfW HRE Program38
The distributed solar industry in Pakistan evolved during the early 2010s at the time of growing power
shortages (ADB Institute, 2018). Pakistan Poverty Alleviation Fund has implemented more than 3,800
RE projects of 13.78 MW which include mini & micro hydropower projects, minigrid systems, solar
water pumping systems, wind energy projects, solar-wind hybrid, and biogas plants (Nafees Ahmad
Khan, 2021). Currently, PPAF is implementing Hydropower and Renewable Energy (HRE) project,
37
The access to electricity in Pakistan has grown to 74% in 2019 and there are 56 million people without access to electricity
as per the Tracking SDG7 The Energy Progress Report 2021. The Tracking SDG7 Report 2021 has referred to World Bank
Global Electrification Database. The World Bank Global Electrification Database derives estimates from a suite of
standardized household surveys that are conducted in most countries every two to three years, along with a multilevel
nonparametric model used to extrapolate data for the missing years. The IEA Energy Access Database sources data, where
possible, from government-reported values for household electrification (usually based on utility connections).
38 (Pakistan Poverty Alleviation Fund , 2021)
65
initiated in 2013, with funding from German Development Bank (KfW). Five mini/ micro hydro power
plants with total installed capacity of 803 kW have been implemented in Chitral, Upper Dir and Buner
Districts of Khyber Pakhtunkhwa. A total of 68 solar minigrid systems with installed capacity of 500
kW has been installed in remote and off-grid locations of Karak, Swabi and Lakki Marwat districts of
Khyber Pakhtunkhwa (Pakistan Poverty Alleviation Fund , 2021). The coverage and projects under HRE
program are shown in Error! Reference source not found.Figure 35.
Aga Khan Rural Support Programme (AKRSP) and Sarhad Rural Support Programme (SRSP), two
prominent Non-Governmental Organizations (NGOs) in Pakistan have implemented several micro
hydropower projects in some regions of Northern Pakistan since their inception (Energypedia, n.d.).
Private sector is also active in Pakistan and has developed several off-grid projects in rural Pakistan
and has helped electrified households through solar systems.
66
distribution system or sell electricity without a prior approval and license from both the national
energy regulatory authority and respective distribution company (Saleh, 2019).
39 1 PKR = 0.0057 USD as on 27th October 2021, same exchange rate has been used to convert PKR to USD in this report
67
On the contrary, the minigrids developed by PPAF or other initiatives under donor grant have shown
lower cost of electricity for domestic consumers, around PKR 6 (USD 0.034) per unit (found during
consultations with PPAF). These tariffs are determined considering the cost of operation and
maintenance of the systems as well as consumers’ ability to pay. Communities are actively involved in
setting electricity tariffs for domestic and commercial consumers. In minigrid projects developed
under SRSP programme, a one-time connection cost from domestic and commercial users were
collected and set aside in designated bank accounts for any unforeseen rehabilitation work. Adoption
of this approach has led to ensuring sustainable operation of the units in the long run (Ashden, n.d.).
40
1 EUR = 1.16 USD as on 27th October 2021
68
plug the gap in electricity access in unserved areas by providing electricity at an affordable cost and
also provide reliable electricity in underserved areas of the country.
Specific opportunities: Pakistan has very hard-to-reach geographic locations without access to
electricity where grid-connected electricity will not reach soon. The demand for electricity in these
rural regions is also low as compared to urban areas. Providing on-grid transmission to these villages
for low loads will prove to be expensive. Noticeably, these communities are also geographically
positioned in the highest solar insolation zones and/ or hydro resources. Decentralized generation
such as solar/ solar hybrid minigrids near the load centres offer promising solutions for providing basic
electrification and may also be scaled up to provide higher levels of services efficiently (Saleh, 2019).
69
Figure 36: Installed Capacity and Energy Generation in 2020 in Sri Lanka from different sources41
Total installed generation capacity in Sri Lanka in 2020 was 4,265 MW, up from 4,217 MW in the
previous year. The installed capacities and the corresponding energy generation data of different
sources in Sri Lanka are provided in the Error! Reference source not found.Figure 36. As one can
observe, bulk of the electricity supply in the country is met by thermal energy (coal and oil), followed
by hydropower. Also, within the renewable energy sources, mini and micro hydro have a larger share
in generation (Ceylon Electricity Board, 2021).
Reports indicate that Sri Lanka has managed to achieve near-complete electrification by 2017, and
policy documents indicate that the country is fully electrified as of the present date (Ministry of Power,
Energy and Business Development, 2019). The country has also committed, as part of its Intended
Nationally Determined Contributions (INDCs), to reduce intensity of GHG emissions from energy
sector by 20% till 2030 (Ministry of Mahaweli Development and Environment, 2016). This is a
challenging task, due to Sri Lanka’s dependence on fossil fuels (coal and oil) as shown above.
As far as the minigrid sector is concerned, there were over 250 community-level minigrids, primarily
driven by micro hydropower, which were installed between 1997 and 2012. However, with changes
in legal and regulatory provisions and the expansion of the national grid in isolated villages of Sri Lanka
by the Ceylon Electricity Board, more than 100 of these minigrids went out of existence because
households closer to the grid became customers of the CEB which was offering lower tariffs and more
hours of supply. Only a handful of these minigrids were converted into small power producers that
sell electricity to CEB (ESMAP, 2018).
The country has recently put up a plan to set up minigrids to power its outlying islands, about ten (10)
of which are inhabited. Previously, these islands were supplied with electricity from the diesel
generator sets owned by CEB and through a distribution network that covers only few consumers in
each island (ADB, 2016). Sri Lanka’s first hybrid minigrid was installed in Eluvathivu Island of Jaffna in
2016. The old diesel generator sets in the island were converted into solar-wind-diesel hybrid by the
Ceylon Electricity Board with the help of financing received from ADB.
41
(Ceylon Electricity Board, 2021)
70
Currently, Ceylon Electricity Board along with ADB is working to set up hybrid renewable energy-based
power systems in three small, isolated islands, Analaitivu, Delft and Nainativu (part of the Jaffna
Peninsula), under component 1 of ‘Supporting Electricity Supply Reliability Improvement’ project. The
project will promote and strengthen energy-based livelihoods through access to electrical appliances
and technologies, and Ministry of Power and Renewable Energy (MPRE) will be the executing agency.
The three islands are presently served by CEB-owned diesel generating plants through a distribution
network that covers parts of each island. The implementation work on these hybrid projects have not
started yet, although the contractor has already been selected in February 2021. Additionally, under
the same ADB project ‘Supporting Electricity Supply Reliability Improvement’, Lanka Electricity
Company (Private) Limited (LECO), an electric utility in the region, has proposed to implement a
microgrid as a pilot subproject within its franchised area.
More recently in the year 2021, the CEB, supported by ADB, has commissioned a utility scale, self-
contained RE powered project in the island of Mannar. The project includes a 100 MW capacity of
wind power system. This is the largest island-based wind powered RE grid in Sri Lanka (ADB, 2021).
42 1LKR = 0.005 USD as on 27th October 2021, same exchange rate has been used to convert LKR to USD in this report
73
3.9.9 Barriers to minigrids
Despite the presence of specific opportunities for minigrids in outer islands and availability of human
resources and use of latest technologies both in hybrid projects and utility scale projects, the minigrid
development in the country is mainly discouraged by the policy and regulations in power sector. As
mentioned in section 3.9.3 above, the regulatory provisions in NEPS 2019 does not allow for any
individual or entity to generate, transmit or distribute power. This prohibits setting up of minigrid
projects. Further, the country has achieved full electrification by 2019, as per their national policy
(NEPS 2019). As a result, there is no additional need or push from the government to set up minigrid
projects.
74
4 CASE STUDIES
75
4.1 Introduction
Building upon the discussion on technologies, policies, barriers, drivers, and opportunities for
minigrids in the SAARC Member States, this section deep dives into key aspects such as technological
innovation, business models, and community involvement through various case studies to analyse the
success factors and barriers for minigrid. Case studies have been chosen from the SAARC Member
States as well as globally. Figure 37 below presents the location of each case study on a world map.
The selected case studies have been discussed including technical features, financial aspects, business
model, tariff mechanism, project outcomes and challenges. Table 1 below provides the key highlights
of selected case studies.
Bambadinca PV minigrid, Guinea Bissau Bamiyan solar PV minigrid, Afghanistan Baglung minigrid, Nepal
MHP project in Sar Kalay, Pakistan Solar PV minigrid in Bheldi, Bihar, India Microgrids with interconnected SHS,
Bangladesh
43(USAID, n.d.);(Foster, Woods, & Hoffbeck, 2015); (IRENA, Renewable Power Generation Costs in 2019, 2020); (Chris
Greacen, 2019); (100% Renewable Energy Atlas , 2019)
77
to generate high quality, assured AC power (230V, 50 Hz) supply. At the time of construction, the
project was the largest off-grid solar PV installation in Afghanistan.
A study was undertaken by the lead contractor in the project, Sustainable Energy Systems
International (SESI), to ascertain average demand from households and other users, i.e., market,
public offices, and others. An assessment of factors influencing operations and management was also
conducted.
Based on the findings collected from the study, an average load of 200 watts was earmarked for each
household, with an average daily allocation of 1.5 kWh. This was estimated keeping in mind future
demand growth amongst households, as reliable power was made available. An assessment of factors
influencing operations and management was also conducted.
44
(Foster, Woods, & Hoffbeck, 2015)
45As per World Bank Cost trends, average median cost for mini grid project in 2013 was USD 6,200 per kW. Although there
could be variance between per kW and per MW costs, the per kW costs can be considered as a rough approximation. As
per IRENA, the global average cost of mini grid project is around USD 1 million per MW in 2019 (IRENA, Renewable Power
Generation Costs in 2019, 2020).
78
while the batteries were supplied by Crown Batteries, UK, who are specialists in providing storage
support to RE projects.
The entire financing was provided by NZMFAT. The approach for financing was to grant the capital
expenditure, while the operating expenditure was expected to be met from tariff revenues. The
overall business strategy to sustain the project is discussed in the following section on business model.
46 1 AFN = 0.011 USD as on 27th October 2021, same rate has been used to convert AFN to USD
79
users, the tariff was around AFN 45 (USD 0.5) per kWh. This could also be the result of DABS charging
a lower tariff to improve user acceptance and raise capacity utilisation. By 2016/17, the plant was
operating at optimal PV capacity.
It is notable to bear in mind that for the first time in this project, prepaid meters were introduced in
Afghanistan. These meters required users to deposit cash, as per their planned electricity demand,
into the local bank account of the utility, DABS. Once the cash was credited, the user’s entitlement
increases automatically.
4.2.7 Challenges
The biggest challenge in the project was to overcome the initial reluctance of the community to pay
what appeared to them as high tariff. As a result, capacity utilisation of the BREP was low in the first
year of operation.
Another key challenge is to successfully maintain the project over time, including but not limited to
recovering periodic costs of operation and maintenance of the asset, including recurrent expenses on
diesel and the distribution network. As mentioned below in this section, security constraints also
restrict movement of people and resources, which acts as a key constraint.
The project could only be completed by airlifting critical pieces of equipment, after facing delays in
import and transit through Wardak province, which was dangerous due to high insurgency in the
region. Due to relative inaccessibility of Bamiyan (the province is in the highlands and navigation
during winter is not possible due to snowfall), operation and maintenance was and remains a key
challenge. Finally, even though Bamiyan is politically amongst the most secure and peaceful provinces
in the country, political instability was and remains a threat to the long-term sustainability of the
system.
47SOLshare, founded in 2014, is an international social enterprise with operations in Bangladesh and India. It has created a
revolutionary new approach to bring affordable solar electricity to everyone in Bangladesh and beyond. It has built the
world’s first ICT enabled solar P2P electricity trading network for some of the most demanding and dynamic markets in the
world.
48
(SOLshare, n.d.); (Efficiency for Access Coalition, 2021); (SOLshare, n.d.); (The Business Standard, 2021); (Burger &
Weinmann, 2020); (Ashden, 2020); (Nelis Global, 2020)
81
Figure 39: Typical SOLshare Microgrid49
49 (SOLshare, n.d.)
82
is limited to cost of the cables required to form a microgrid and the installation of the SOLbox.
SOLshare has a hybrid form of financing. The microgrid projects are basically financed by Venture
Capital Funding and Social impact investors. SOLshare has been financing its projects through
monetary award prizes, grants and equity and has been receiving financing from international
organizations such as United Nations Department of Economic and Social Affairs (UNDESA) together
with Grameen Shakti, United Nations High Commissioner for Refugees (UNHCR) in the Rohingya
camps, SBK Foundation, the ADB and the KfW/DEG among many others.
83
• The household with SHS that sells 50% of its generated energy earns approximately USD 10 per
month. A producer (installs SHS just to sell energy) breaks even within two years, with a simple
return on investment of 173% after three years.
• With SOLshare, rural communities go from being solar power users to smart entrepreneurs,
who can sell surplus solar power in return for money. The existence of trading network acts as
a driver against pollution since communities are now more than willing to turn towards solar
energy generation.
• Currently, 4 million households are powered by SOLshare and an additional 1 million are
expected to be powered by the year 2030, including interconnecting them to the national grid
through a single point of common coupling.
• SOLgrids impact on ecosystem is lower as PV systems are constructed on rooftops of already
existing buildings, thereby avoiding potential land use change.
• 40% of the end users are women and children. Many women have started their own home-
grown businesses through access to energy, which has increased safety and allows women to
work and children to study after dark.
4.3.6 Challenges
Access to finance has been a major challenge for the SOLshare’s microgrid projects because of various
risk perceptions related to the company being a start-up with presence only in Bangladesh and India,
new technological concept, acceptance among consumers, financial viability, etc. Another challenge
was the geography of the project area. Most of the microgrids are in very remote areas and reaching
those communities is a humongous task.
Other major challenge for the expansion of SOLshare projects is the aggressive approach of
Bangladesh towards grid extension. SOLshare has built a grid box technology, which can connect the
microgrid to the national grid (when it arrives to that area) through the interconnection point. The
technology can control the entire network connected to it. However, this technology is currently in
research and development stage.
84
4.4 Solar PV minigrid in Bheldi, Saran District, Bihar, India
Smart planning, design, and management of minigrid systems
4.4.1 Introduction
The Bheldi minigrid50, set up in 2014-15, operates under the aegis of Smart Power India, which
supports decentralised, renewable energy powered minigrids in India. SPI has engaged with Tata
Power, one of the largest private sector players in the power sector in India, to realise a vision to
energise 10,000 minigrid projects in India. These projects will empower productive applications, as
well as support social infrastructure (e.g., health and education). The Bheldi project was initially
supported under Rockefeller Foundation’s Smart Power for Environmentally sound Economic
Development project. Rockefeller Foundation remains a supporter of the SPI-Tata Power programme
of activities. The site is located in Saran district (Parsa Block) of the state of Bihar in Eastern India.
Prior to the minigrid project, the site had no grid electricity connection. There were a handful of diesel
generator operators, who provided electricity to the Bheldi market, and to a few households in the
evening, by operating ~5 kVA diesel generator sets. The bill payment was calculated as a daily charge.
Some households who could afford had their captive DG sets.
In 2014, the project team conducted an initial survey of the project site in Bheldi and identified the
potential for a 40-kW solar PV unit to energise the Bheldi market, agricultural pumps, and other
residential and commercial loads. The team also carried out community level consultations to
ascertain the following:
• Operations of commercial and enterprise loads in the site, potential for adding new enterprises
• Community-level interest to adopt to solar power from their existing energy use practices
• Availability of land to set up the power station
• Willingness to pay for all consumer groups
As the SPEED programme advocated a market-based approach, attaining viability for a project was a
key consideration. As such, time and effort were devoted in ascertaining the 24-hour demand profile
at the site, which would determine sizing not only of the solar PV plant, but also of the battery bank.
Moreover, the viability of post commissioning operation and maintenance was assessed in detail51.
50
Specific details on this case study, mentioned here, are based on the information available with one of the authors
51 Developed under the aegis of Rockefeller Foundation’s SPEED project, not much information is publicly available. The
article throws some light on the project and its social impacts:
https://www.rockefellerfoundation.org/wp-content/uploads/SmartPower-Connect-May-2017.pdf
85
28 kW. Configuration of the inverters was done such to synchronise with the varying load profile of
the site. The distribution network was set up using reinforced wooden poles, which carried 4-core and
3.5-core cables of varying dimensions. Households were connected via single phase. Each household
was fitted with load limiters, an innovative element to manage power consumption of households.
The solar PV capacity was augmented to 40 kW as demand from the community increased and so were
the inverter and charge controller capacities to enhance the delivery capacity. Subsequently, smart
prepaid meters were also installed in the consumer premises.
The project cost appears higher, due to higher component costs, especially solar PV, as this project
was designed and executed in FY 2014-15. The financing of the project was made by a Special Purpose
Vehicle called TARA Urja, which acted as a Renewable Energy Service Company and invested in the
decentralised minigrid project, and then recovered the investment over time.
52
Source: SmartPower Connect
53 1 INR = 0.013 USD as on 27th October 2021, same exchange rate has been used to convert INR to USD in this report
86
4.4.4 Business model
As indicated above, the project is supported by Rockefeller Foundation through the RESCO named
TARA Urja. The salient features of the business model are:
• To better mirror the minigrid business, TARA Urja created a (wholly owned) subsidiary, TARA
Micro Utility Business (TARA MUB). TARA Urja, as the owner of the generation asset, sold bulk
power generated from the minigrid at a fixed rate to TARA MUB. This ensured that the
generation unit had a fixed revenue that was partially de-risked, due to TARA MUB making a
payment on a per kWh basis at the site
• For TARA MUB, its role was that of a distribution utility, with the focus to generate revenues
from each type of consumer over and above the amount that it had to pay to TARA Urja (the
generation utility). The difference between what TARA MUB would receive from consumers,
and in turn pay to TARA Urja, would cover for TARA MUB’s own expenses of operation and
maintenance of the distribution network, salary of staffs at the site and other overhead
expenses, and ensure that it could earn a profit on the investment as well
• As a result, TARA MUB introduced several innovations and modernizations in the distribution
architecture. One of the key aspects was the load limiter, a device that would let the consumer
use only as much current (amperes) as his entitlement. The load limiters were calibrated to
allow a fixed quantum of current (amperes) per period (say a week), which was determined
according to the bundle of the consumer. Upon expiry of the time, or of the consumer’s quota,
the consumer is required to make a prepayment (as per his bundle) to the site office, against
which he would receive a message on his registered mobile, as well as an enhancement of his
entitlement. This reduced the costs of revenue collection, and the officer in the site office
operated a cloud-based application whereby the entitlements of each consumer was
automatically tracked and updated on a real time basis. This further streamlined the revenue
collection process.
4.4.7 Challenges
Initial adoption of consumers was slow, due to the use of bundled tariff and tariff packages, which
was not familiar to the community and, despite community consultations that were done, prospective
users were not ready to adopt.
One of the key operational challenges was for the micro-utility business to remain viable. A minimum
level of capacity utilisation together with timely payments was required for the distribution utility to
generate enough revenue, to cover all maintenance expenses and make payment back to the
generation utility. This was a recurrent challenge in the initial months of project operation. The other
challenge in the project was to manage expectations of the consumers. As power was provided to
them, users’ demand tended to rise, beyond their rated demand. Demand for new gadgets and
appliances also grew in the site.
88
4.5 Baglung minigrid, Nepal
54 (Bhupendra Shakya, 2012); (Engineering Consultancy for Constructive Development Efforts, 2013); (Priti Kumar, 2015)
89
Figure 41: 6 MHPs (circles) in Baglung connected to form minigrid (rectangle)55
4.5.6 Challenges
The development cost of minigrid with interconnection of MHPs was relatively high and analysis shows
that even for an optimistic scenario of Plant Load Factor (PLF) doubling after the formation of the
minigrid, minigrids are not financially viable. Furthermore, the capital expenditure of a minigrid is
entirely site specific. So, minigrids should be assessed on a site-by-site basis for economic viability.
After the installation of minigrid, management of the grid with multiple MHPs connected was a
complex task. This required continuous support in technical and managerial aspect for an extended
period. The centralized load management system is not available in Baglung minigrid, and the load
management is being done with mutual understanding among the MHPs.
The MHPs are run of river projects, therefore, during dry season it was difficult to meet the increased
electricity demand. During wet season, because of no storage available, 70% of energy generated was
wasted. In the Baglung minigrid system, Feed in Tariffs are set at the same level for all MHPs in a
minigrid and do not consider the fact that operational cost for each MHP differs according to its size.
Thus, minigrid should ensure that operational cost of MHPs is met before setting tariff for the purchase
of power.
57
1 NPR = 0.0083 USD as on 27th October 2021
91
4.6 Solar hybrid minigrid, Tokelau
58(Power Technology, 2013); (Collaboration on Energy and Environmental Markets, n.d.); (New Zealand Ministry of Foreign
Affairs and Trade , 2013); (ITP Australia, n.d.); (EU-GIZ ACSE , 2016); (ITP Australia, 2013)
92
Figure 42: Installed solar PV system in Tokelau59
59
(ITP Australia, n.d.)
60 1 NZD = 0.72 USD as on 27th October 2021, same exchange rate has been used to convert NZD to USD in this report
61
1 NZD = 0.72 USD as on 27th October 2021
93
from consumers, which is used for purchasing the diesel fuel and salary payment of technicians and
operators.
4.6.6 Challenges
Since the solar PV systems were to be installed in an island set up with high temperatures and
humidity, it posed a challenge on both the design and installation of the system. The solar cables were
routed in an aluminium channel and UV stabilised conduit, and each equipment was manufactured
from either 316 stainless steel or anodised aluminium to avoid corrosion. Additionally, care was taken
to ensure that the battery and inverter rooms were well ventilated with passive heat controls.
During the project technical and financial review undertaken by ITP Australia in 2013, it was found
that the current tariff of NZD 0.50 (USD 0.36) per kWh is not sufficient to generate the revenue
required to fully finance the O&M including replacement of equipment. The study recommended that
a tariff of around NZD 0.77 (USD 0.55) per kWh is required for the same. However, during discussions
with stakeholders, it was discovered that the current tariff is already a burden on the consumers who
expected a lower tariff from the solar power system. Also, share of the household income spent on
electricity needs is higher than for the average New Zealand household, whereas the actual
consumption in Tokelau is significantly lower.
In the recent years, electricity demand from the community has increased, which has led to increased
diesel fuel consumption. In this regard, the Government of Tokelau has added 30kW of PV on each
island in 2016 and will be installing a further 210 kW of PV and almost 2 MWh of battery capacity to
meet the rising demand and restore the contribution of renewable energy to 90+%.
94
Award for switching from diesel-generated electricity to clean, renewable solar energy and providing
almost 90% of Tokelau’s electricity needs. The project developers have received two awards -
Sustainable Electricity Association New Zealand (SEANZ) ‘Best Solar PV Implementation Off-Shore’
award and New Zealand Innovators Award for the Tokelau Renewable Energy Project in the year 2012.
62 1 EUR = 1.16 USD as on 27th October 2021, same exchange rate has been used to convert EUR to USD in this report
63 (Wame,2014); (Xenakis, n.d.); (ARE & UNIDO ITPO, 2021); (ESMAP, 2017); (Xenakis, 2017); (UNIDO, 2017); (Ecowas Centre
for Renewable Energy and Energy Efficiency, 2020)
95
Figure 43: Bambadinca PV Minigrid64
64 (Xenakis, n.d.)
96
The tariffs were presented, published, and later adopted by the DGE in December 2014. The lowest
tariffs of 250 XOF/ kWh (0.44 USD65/ kWh) apply between 9 am and 6 pm, medium tariffs during the
evening hours (6 pm and 11:59 pm) at 320 XOF/kWh (0.57 USD/kWh) and highest during the night
between 12 am and 9 am, at 500 XOF/kWh (0.88 USD/kWh). To ensure the sustainability of the project,
awareness campaigns were organized on energy efficiency, electricity safety and importance of tariff
payments.
4.7.7 Challenges
• Tariff determination process was challenging since there was high local expectations, subsidies
were absent and there was price variety between the urban and rural.
• Limited financial management capacity led to payment problems for the replacement of spare
parts
• Political instability (coup of 2012) impacted the suppliers risk perception and hence the
project´s timeline
• Due to capacity limitations of the hybrid system, parts of the population have been left out.
65 1 XOF = 0.0018 USD as on 27th October 2021, same exchange rate has been used to convert XOF to USD in this report
97
for the project. The project also demonstrated a replicable model that can be implemented in areas
of Guinea-Bissau, where national grid will not reach in the near future. One such replication project
was Bissora minigrid, which is operating since 2015 and has an installed electric capacity of 312 kWp.
4.8 MHP project in Sar Kalay village, Khyber Pakhtunkhwa Province, Pakistan
66
Specific details on this case study are based on the information provided by PPAF team
98
Figure 44: Water channel at MHP plant site, Sar Kalay, Buner district
67
1 PKR = 0.0057 USD as on 27th October 2021
68
1 PKR = 0.0057 USD as on 27th October 2021
69 https://nrsp.org.pk
99
operators to run the plant. These operators were provided with hands-on training during installation
of systems as part of the project.
Apart from this, the O&M committee, in consultation with the beneficiary community, has set up a
tariff collection mechanism. Each household has an energy meter installed and based on their actual
consumption, electricity bill is collected and deposited in community bank account. The salaries of
plant operators and other operational expenses are paid out of this amount. The O&M expenses are
afforded by the users, who used to spend as much as PKR 5,000 (USD 28.5) per month on kerosene,
which is replaced by electricity from MHP whose monthly bill comes to around PKR 1,200 (USD 6.84)
per month.
The business model for the project hinges on user pays principle. The tariff is set at PKR 15 (USD 0.086)
per kWh for domestic and commercial users alike to recover all operating expenses. In addition, users
pay PKR 200 (about USD 1.14) as fixed charges for the electricity connection. Thus, the monthly bills
carry a fixed line charge and a variable charge per kWh of consumption.
4.8.6 Challenges
The construction of MHP was a very challenging task for local community as well as NRSP team. The
site of powerhouse and water channel is located in a deep trench surrounded by high mountains,
where transportation of machinery and construction material was only possible through donkeys or
on human shoulders. In this regard, the role of the community proved to be a key success factor. The
community was keen and proactive and collaborated with the PPAF /NRSP team throughout the
project development cycle.
The price of MHP electricity is kept at PKR 15 (USD 0.08670) per kWh, which was higher than the
average tariff charged by utilities under guidance from NEPRA during 2017 in Pakistan. This was a
challenge to overcome due to higher-than-normal electricity prices.
70
1 PKR = 0.0057 USD as on 27th October 2021
100
plant. The project has laid strong emphasis on empowerment of women, both in terms of quality of
life and for enterprise development. Other key highlights which were reported through consumers of
MHP are:
• The availability of electricity provided more free time to women, which they now utilize for
stitching of cloths and doing embroidery work, using tools and/or machines run on electricity.
Thus, supporting economic empowerment of women in Sar Kalay village
• Shops are now open till late in the evening (even up to 11 PM), and as a result of this daily
income has increased by 20% because people could buy grocery items from shop after sunset.
• Construction of MHP has also produced new opportunities for employment in the village. The
MHP plant operator is earning equal to that of a teacher. The project has provided a gateway
for other developmental activities in the village through Government and non-government
organizations.
• Access to and demand for electricity is the prime driver across minigrids in the SMS or globally. As
the case studies from Sar Kalay (Pakistan), Bambadinca (Guinea Bissau) demonstrate, consumers
are even willing to pay higher tariff for reliable electricity access
• Role of enterprises as productive loads evolves as one of the key factors supporting minigrid
development. Examples from Bamiyan (Afghanistan), Bheldi (India) and Sar Kalay (Pakistan) show
that enterprises enable a minigrid to charge full tariffs from industrial, commercial consumers,
while using these proceeds to subsidize domestic users (especially seen in Bamiyan). This enables
the minigrid to support its operations over time, covering key O&M expenses such as battery
replacement.
• Innovations in technical design and business models have proven to be instrumental in lowering
costs, overcoming operational barriers, and streamlining operations. Among the case studies,
SOLshare (Bangladesh), Bheldi (India), Bamiyan (Afghanistan) and Baglung (Nepal) are clear
examples where innovative design aspects were used to make projects more sustainable and
viable.
• Community engagement and involvement is a critical step, not only in early adoption of customers
for a minigrid project but also to ensure that communities (consumers) are able to upgrade to
operate smarter and lower-cost enterprises. As shown in the Tokelau as well as in Bamiyan
(Afghanistan), consumers replacing diesel with solar PV power benefitted in the long run from
better delivery. As in the case of Bambadinca (Guinea Bissau), the active involvement of
community from the start for the tariff setting and later, for the management and operation of
minigrid ensured success and sustainability.
101
Key barriers for minigrids
• It can be observed from the case studies that the cost of capital and O&M expenses for the project
are not fully offset by revenues from tariffs. One of the reasons could be that the unelectrified
areas are usually rural and the consumers not economically affluent, as a result their ability to pay
is also limited. One relevant example is the SOLshare model: even in presence of an innovative
financing mechanism and requiring minimal capital cost support, the project needed financial
inputs to sustain itself. While the site in Bamiyan, Afghanistan has demonstrated a way out
through higher tariffs from commercial and enterprise loads to cover for higher O&M outgo, the
site has faced constraints by way of limited ability to pay from consumers in the absence of
commercial and enterprise loads.
• The case studies have highlighted the barrier related to absence of advance project management
and technical skills among the operators of minigrid. These skills are essential for efficient
operation of minigrids using complex designs. For example, in SOLshare model (Bangladesh) and
Baglung minigrid (Nepal), advance technical skills and project management skills for managing
several sites at a time is an essential requirement for efficient operation.
• Introduction of any new technical concept or technologies in minigrid often trigger risk
perceptions related to its viability, consumer acceptance, among others and thus they require
additional financial support and risk coverage for financial viability. As in the case of SOLshare
model, the access to finance was an issue due to risk perception related to new technological
concept.
• Adoption of minigrid by consumers in remote areas usually builds up over a time and therefore
the capacity utilization factor of the minigrid project is lower at the beginning. In case of Bamiyan
case study, the adoption of consumers was very low at the start because prospective consumers
were not ready to adapt.
102
Key factors supporting minigrid development Key barriers for minigrid
sector
103
5 CONCLUSION AND RECOMMENDATIONS
104
5.1 Country wise summary and recommendations
The access to electricity in the SAARC Member States has improved considerably over the last few
years. Countries such as Maldives, Sri Lanka, Bangladesh, Bhutan, and India have either achieved or
are close to achieving 100% electrification of their population. Nepal and Pakistan still have a set of
large population without access to electricity whereas, Afghanistan has almost two third of its
population not connected to the main electric grid. While enhancing electricity access and achieving
100% electrification are the key drivers for promoting minigrids, the study shows that the drivers for
minigrids in the SAARC Member States also include increasing the renewable energy share in the
national energy mix; reducing diesel fuel consumption; adhering to environment related
commitments such as mandatory level of forest cover and net- zero transition; and increasing the
export of surplus electricity to neighbours.
The key prospects and drivers, barriers, and recommendations for minigrid sector in each of the SAARC
Member States have been discussed below in detail. The Table 2 provides the summarized version for
each country.
5.1.1 Afghanistan
105
providers, equipment manufacturers and suppliers, among others that are members of
the union.
ii. Barriers
a. There is no specific minigrid policy in Afghanistan, which will stimulate this market. While
the institutional framework is clear, with MRRD designated for all project development
under 1 MW, there is a need for more clarity on technical and operational aspects of
minigrids.
b. Although the private sector is actively participating in renewable energy projects, the
enabling environment for private sector growth and development is weak. Ancillary
services such as insurance, access to working capital and enforcement of contracts are not
well developed.
c. Further, governance and security situation also act as deterrents to private sector
development. Especially, there are safety and security concerns associated with
movement of goods and services across provinces in Afghanistan. Further, several
provinces are not recommended for investment, whether by private sector or through
PPP modes on account of security related concerns. As a result, the overall outlook for
private sector remains weak, especially with reference to the RE sector.
d. There is a dearth of technical expertise/ support for operation and maintenance of
minigrids. This includes lack of availability of spares, as well as non-availability of human
capital for carrying out O&M of a minigrid project and thus raising the operating costs of
a project.
iii. Recommendations
a. Although there is no specific policy and/or regulatory guidelines for minigrid deployment,
under the AREMTI, MRRD is intending to commission studies to develop best practices
handbook and other knowledge products. These are expected to form the mainstay for
future minigrid projects in Afghanistan. It is recommended that such products be
mainstreamed and widely disseminated as support documents for entrepreneurs and
other stakeholders in the sector. Such developments (as mentioned above) shall also
provide confidence to the private sector and other stakeholders for setting up, operation
and maintenance of minigrid projects.
Importantly, MRRD has a clear mandate to develop minigrid projects up to capacity of 1
MW per site.
In view of this, it is recommended that the national electricity utility DABS, and MRRD may
jointly develop and introduce a least cost electrification Master Plan for Afghanistan,
ensuring minigrids and grid extension initiatives complement each other in achieving
universal electricity access.
b. Capacities to be enhanced across key institutions and personnel for design, development,
and O&M of minigrids; especially on technical support that should be extended to minigrid
projects on the ground.
c. A mechanism for Business-to-Business network could be created to facilitate AREU
members in exploring collaborations and accessing technical know-how from other
countries in the region.
106
5.1.2 Bangladesh
107
d. Bangladesh is densely populated country with little land availability and has restrictions
on use of agricultural land. Thus, identification of land area for minigrid project
development is challenging.
iii. Recommendations
a. There are off-grid areas in remote islands of Bangladesh where population concentrations
are dispersed. Distribution utilities are responsible to provide electricity to those areas,
however, connecting them to national grid would be costly and time consuming.
Renewable energy based minigrid would be the least-cost option for providing reliable
access to electricity. MPEMR with the support of IDCOL or SREDA may formulate and
introduce a special policy for development of minigrids in remote areas covering tariff
regulations, financial support, grid arrival rules, among others.
b. Government is planning to connect the existing minigrids in Bangladesh to the national
grid within months. Existing minigrids need to be upgraded to match the requirements of
national grid and connect them to the national grid. MPEMR would need to formulate the
guidelines for the grid interconnection of minigrid infrastructure. In the meanwhile,
distribution utilities should continue to purchase the electricity from the minigrids that
are being connected to national grid at minigrid tariff and sell it to the consumers at
subsidized tariff.
c. SREDA may prioritize minigrid projects in the roadmap for providing electricity access to
remote areas where national grid would take longer time to reach and would not be cost
effective.
5.1.3 Bhutan
108
d. The country sells surplus electricity generated to the neighboring countries for generating
revenue for the country. There is an interest from the Government to produce RE
electricity locally to increase foreign revenue generation.
ii. Barriers
a. There is no dedicated policy and regulations regarding minigrid development in Bhutan.
There are no clear guidelines regarding arrival of national grid at the minigrid site, whether
the minigrid will be connected to the grid or how developers will be compensated. The
country has set no specific targets for electricity generation via minigrids.
b. The electricity tariffs in Bhutan are subsidized and public utilities like DGPC and BPC claim
that they do not obtain a fair return on their assets. In this scenario, private sector
participants may be unwilling to make investments in the absence of clear indication of
returns to investors.
c. Bhutan has piloted solar and wind minigrid projects only after 2014. The government as
well as the private sector lacks necessary technical and financial expertise to develop and
operate minigrid in the country.
iii. Recommendations
a. Department of renewable energy may formulate a national minigrid policy or regulation
to facilitate development of minigrid sector in the country. The policy/ regulation should
clearly mention the rules related to future of minigrid in the event of arrival of national
grid. It should also include measures for de-risking minigrid business models in the form
of financing schemes, tariff regulations, payment guarantees, etc.
b. Royal Government of Bhutan could set up national target for minigrid projects in the
country in terms of capacity or numbers and identify target community for project
development. This will show intent of the Government for development of minigrids in
the country and thus create private sector interest in the sector.
c. Bhutan Electricity Authority may formulate tariff regulation for minigrid sector and ensure
fair return on investment so that private sector participation in the sector will increase.
Private sector participation enhances development of the minigrid sector and helps to
meet customers’ demand of reliable electricity.
d. Capacity building trainings and vocational programs on renewable energy minigrid design
and operation should be developed engaging with development partners and local
educational institutions to ensure enough properly trained professionals are available in
the country to support private sector investment.
e. The geography of Bhutan is similar to that of Nepal. The study recommends that Bhutan
should replicate the lessons learnt from case studies in Nepal (discussed in section 4.4)
where MHPs operating in the country could be interconnected to form a minigrid for
reliable supply of electricity to the consumers.
5.1.4 India
110
capital71 available to finance minigrids. Minigrids usually take 12 to 18 months to build
power demand and attain a good capacity utilization. The financing mechanisms should
thus structure the investments accordingly.
iii. Recommendations
a. The draft national minigrid policy which has specified the guidelines for future arrival of
grid at minigrid site, financial incentives, tariff setting, etc. should be approved by the
MNRE. Considering the success of minigrid policies of two states (UP and Bihar) of India,
the study recommends other states to also develop specific minigrid policies to drive
private sector interest and scale up minigrid development.
b. Business models for minigrids need to be built around unreliable, poor-quality supply and
inability to operate livelihoods-based machinery on the national grid. Grid interactive
minigrid projects should be promoted to provide the last-mile-connectivity and support
the growth of local economies and livelihoods. Grid interactive minigrid can integrate with
grid where or when it is available. It will allow the system to export surplus power
generated and import when needed.
c. Project developers in India have started to engage with the community from the
beginning during the minigrid development which has helped them to increase the uptake
of productive appliances and thus improve the demand in these areas. This practice
should be adopted in future projects to increase the productive demand and thus reduce
the cost of electricity. Also, efforts to effect behavioral change at consumer end should
also be made a part of the minigrid establishment process. This will result in demand side
management through increased user awareness about the pattern of energy usage.
d. Design and implementation of innovative payment collection mechanism such as taking
3-6 months of payment as advance security deposit from rural customers to ensure
revenue visibility, combination of pre-paid metering and institutional Power Purchase
Agreements with an anchor client will improve the fund availability. A clarity in policy will
also give confidence to financiers and investors on returns from minigrid projects.
5.1.5 Maldives
71Patient capital is an investment that does not seek to maximize financial returns to investors, but seeks to maximize social
impact and to catalyze the creation of markets to combat poverty
111
c. Government of Maldives has also set a target to reach net-zero global GHG emissions by
2030 with international assistance and private investments. The key priority of the
government, in this regard, is to reduce its dependence on imported diesel fuel and invest
in renewable energy projects.
d. Under World Bank financed Accelerating Renewable Energy Integration and Sustainable
Energy project, hybridisation of fourteen island grids is being done. Three projects under
earlier WB program have been implemented or are in construction stage.
e. Preparing Outer Islands for Sustainable Energy Development project of ADB is
transforming existing diesel-based energy minigrids into hybrid renewable energy
systems in 160 inhabited islands, out of which installations on 48 islands have been
commissioned.
ii. Barriers
a. There is a need to develop robust energy sector plans focusing on hybrid renewable
energy projects to meet the increasing electricity demand in the country, lower electricity
cost and reduce the import of diesel.
b. Investments in renewable energy projects in the country have been driven primarily by
grants and loans from multilateral agencies. GoM faces a substantial foreign debt burden,
which limits opportunities for direct public financing of renewable energy expansion.
Commercial bank financing or private sector financing is in its nascent stage since they are
still reluctant to accept the risks associated with renewable energy technologies and
invest in the sector.
c. Utility companies in Maldives have been implementing only conventional energy projects
and only in last few years renewable energy projects have started to come up. Therefore,
there is limited experience and expertise available locally regarding renewable energy
technologies, their design, installation, and operation.
iii. Recommendations
a. Ministry of Environment and Energy with the support of Maldives Energy Authority and
Electric Utility Companies (FENAKA and STELCO) may develop national level energy plans
looking into the future energy demand and supply aspects, and identify potential sites and
targets for the deployment of renewable energy hybrid projects in the country.
b. To mobilize private interest and investment in the sector, de-risking mechanisms such as
power purchasing agreement arrangement should be developed and implemented in
future projects. A PPA guarantees a price for electricity to be sold and the private sector
earns a guaranteed return on its long-term investment. Also, coordination with
development finance institutions to source concessional financing should remain
important in the near-term.
c. Technical and vocational training on renewable energy technologies and projects should
be developed and delivered to utility companies, government departments, financing
institutions, project developers and professionals with the help of development partners
and local educational institutions, to ensure enough properly trained professionals to
support private sector investment.
112
5.1.6 Nepal
113
d. Project developers continue to struggle to achieve financial closure on time as subsidy and
their equity are not enough to cover the total project cost and bank financing is difficult
to access.
iii. Recommendations
a. Future minigrid projects should be designed and developed considering anchor loads such
as irrigation, local energy-based enterprises, health, school, etc. and future demand of
electricity in households for running modern appliances. Minigrid planning process should
include the community from the beginning to understand the productive uses that can be
connected at the end-user level to increase the uptake of productive appliances.
b. Electricity Regulatory Commission of Nepal may develop measures to reduce minigrid-
based electricity tariffs and bring them at a rate comparable to grid-based tariffs. This will
encourage minigrid consumers to use electricity as per their demand and not limit their
consumption due to high tariff. AEPC should encourage commercial bank financiers to
invest in minigrid projects and promote business models that are beneficial to the
investors as well.
c. AEPC may develop guidelines for minigrid implementation including design, tendering,
construction, and operation of future minigrids, tailored to Nepal based on data collected
from existing minigrids. The guideline should also clearly explain the interconnection of
minigrid to the national grid after its arrival.
d. Future minigrids should incorporate learnings from the existing successful minigrid
projects on technical, financial, and operational aspects.
5.1.7 Pakistan
115
5.1.8 Sri Lanka
116
b. Within the purview of this regulatory limitation, the grids installed in the islands and
proposed replacement of diesel grids by RE powered grids stand out as potential areas
where RE hybrid grid architecture can be used to support local economic development
based on securing sustainable livelihoods and an improved quality of life. The RE hybrid
minigrids can provide electricity at least cost compared to diesel-powered minigrids. This
niche application for minigrids should be explored further.
117
Table 2: Summary of Prospects, Drivers and Barriers with Specific Recommendations
Parameters
Prospects and drivers Barriers Recommendations
/ Countries
• Only one-third of population with electricity access • National electricity utility DABS, and MRRD to jointly
• Clear mandate given to MRRD by RE policy for development • No specific minigrid policy to stimulate the market develop and introduce a least cost electrification
of minigrids; Ongoing efforts to set up 25 minigrids in the • Weak enabling environment for private sector growth master plan
country by MRRD • Safety and security concerns associated with • Capacity building of key stakeholders and project
Afghanistan
• GCF supporting the development of 8 minigrids as well as movement of goods and services developers on minigrid design and O&M
capacity building and development of regulatory documents • Lack of technical expertise/ support for operation and • Creation of Business-to-Business network to facilitate
• Strong enterprise demand in several provinces and presence maintenance of minigrids AREU members in exploring collaborations and
of a strong renewable energy industry union accessing technical know-how
• No specific policy or strategy of the Government to • Formulate and introduce a special policy for
• Government’s focus to reach 100% electrification via develop minigrid projects development of minigrids in remote areas
expansion of national grid; opportunities for minigrids in • High minigrid tariff compared to tariff paid by the grid • Upgrade existing minigrids and connect them to
Bangladesh
remote off-grid islands only consumers national grid; Government to purchase electricity from
• Target to generate 10% of electricity from RE sources • Land availability and restrictions on use of agricultural future minigrids and sell to consumers at grid tariff
land • Prioritize minigrid projects in the roadmap
• Formulate minigrid policy or regulation with clear
• Reliability issue in electricity supply despite 100%
guidelines on future arrival of national grid and
electrification
• No dedicated policies or targets for electricity measures for de-risking minigrid business
• Government’s mandate to maintain 60% of the country’s
generation via minigrids • Set up national target for minigrid projects in the
land under forest covers, thus offering preference to
• Public electric utilities unable to generate fair returns country in terms of capacity or numbers
decentralized generation over expansion of T&D lines
Bhutan on their assets, resulting in private sector’s • Formulate tariff regulation for minigrid sector to
• Increased demand for reliable electricity for rural
unwillingness to enter the sector ensure fair return on investment
enterprises
• Lack of technical and financial expertise to develop • Capacity building trainings and vocational programs
• Interest of Government to produce RE electricity for local
and operate minigrid on minigrid
consumption, to enable more export of grid electricity for
• Replicate the lessons learnt from success stories from
revenue generation
Nepal since the geographies are same
• 5.5 million people still lack access to electricity despite • Lack of clarity in policies regarding future grid arrival • Draft national minigrid policy should be approved;
achieving 100% electrification; reliability and quality of at the place of minigrid site other states to also develop specific minigrid policies
electricity remains an issue in rural areas • Electrification of public infrastructures not included in • Develop business models around unreliable, poor-
• Minigrid policies in two states driving private sector the state minigrid policies quality supply and inability to operate enterprise loads
interest; minigrids being promoted to provide electricity for • Need to design and implement innovative business on the national grid
India
public institutions and enterprise development in rural models to promote minigrid • Engage with community from the beginning of the
areas • Minigrid power expensive compared to power from project to increase uptake of productive uses
• Diesel based minigrids being converted/ hybridized into RE the grid • Promote grid interactive minigrid projects
minigrids in large and densely populated islands and hilly • Lack of funds to finance the operational expenses as • Design and implementation of innovative payment
areas well as lack of patient capital to finance minigrids collection mechanism
118
Parameters
Prospects and drivers Barriers Recommendations
/ Countries
• According to ESMAP, around 1,905 minigrids are planned
• Government promoting hybridization of diesel minigrids • Need to develop robust energy sector plans focusing
• Develop concrete energy expansion plans for the
with RE to reduce dependency on diesel fuel and reduce on hybrid renewable energy projects
deployment of additional renewable energy hybrid
overall electricity cost • Limited opportunities for direct public financing.
projects
• Target to reach net zero GHG emissions in the country by Commercial bank financing or private financing in its
Maldives • Implementation of PPA arrangement in future
2030 nascent stage
projects to mobilize private investment
• Hybridization of 14 island grids being done under WB-ARISE • Private sector companies reluctant to accept the risks
• Provide technical and vocational training on
project and installation of RE hybrid minigrid in 160 associated with renewable energy technologies
renewable energy technologies and projects
inhabited islands under ADB - POISED project • Limited experience and expertise available locally
• Most of the minigrids implemented cater to basic
• 7% of the population lack access to electricity • Develop future minigrid projects considering anchor
lighting and fan only, with less focus on future energy
• Strong interest for minigrid development from rural loads and future demand of electricity in households
demand and productive loads
communities as well as local governments • Minigrid planning process to include community from
• Minigrid power expensive compared to power from
• Target of 12% RE generation in total energy mix by 2024 the beginning to increase uptake of productive uses
the grid
Nepal • Government targeting to install solar minigrid projects in • Develop measures to reduce minigrid-based electricity
• Policy for grid connection of minigrids still ambiguous
mountains and upper hill regions tariffs at a rate comparable to grid-based tariffs
despite successful interconnection of several MHPs
• WB program to mobilize RESCOs for minigrid development • Develop guidelines for minigrid implementation
and minigrids
• Improved know-how of minigrid design and operation in the including design, tendering, construction, and
• Project developers continue to struggle to achieve
country operation
financial closure on time
• Develop a least-cost approach for rural electrification
• Around 45 million people without access to electricity; long • Lack of institutional support at the national level for
outlining potential sites for minigrid
hours of load shedding in several grid connected areas rural electrification and distributed renewable energy
• Set in place legislation/regulations covering permitting
• Target of at least 20% and 30% RE generation capacity by projects
& licensing requirements, grid arrival rules, among
2025 and 2030 respectively • Lack of policies and regulations for minigrid sector,
others
• RE policy prioritizing mini/microgrid solutions as key necessary to build private sector interest
Pakistan • Establish financing programs or schemes utilizing
intervention to accomplish the targets • Dearth of private-sector investment in rural areas
government or donor funding available in the country
• Minigrids tariffs lower for domestic consumers, compared • Lack of standardization in minigrid design &
• Replicate the SOLshare model for providing access to
to grid electricity tariff installation
electricity in remote and hard to reach locations
• Private sector companies and not-for-profit companies’ • Lack of technical expertise available for O&M of
• Develop technical standards and grid connection
interest to develop off-grid projects minigrids
codes; Implement capacity building programs
119
Parameters
Prospects and drivers Barriers Recommendations
/ Countries
• Achieved 100% electrification and current focus on
• Limited scope for development of minigrids due to • Develop policy to support tail end generation and
centralized grid-based delivery supplemented by utility scale
government’s focus on centralized grid-based delivery enterprise development using RE minigrids
RE projects
Sri Lanka • Existing electricity regulatory provision restricts • Promote and implement RE hybrid minigrids to
• Potential and interest of government to energize outer
electricity transmission and distribution functions to provide electricity at least cost compared to diesel-
islands running on diesel generators through RE hybrid
CEB only powered minigrids to outer islands
minigrids
120
6 BIBLIOGRAPHY
121
100% Renewable Energy Atlas . (2019, 01 21). Bamiyan, Afghanistan. Retrieved from 100% Renewable
Energy Atlas : https://www.100-percent.org/bamiyan-afghanistan/
Aaron Zvi. (n.d.). How-to-calculate-carbon-dioxide-emissions-from-a-diesel-generator. Retrieved from
Hunker website: https://www.hunker.com/12284423/how-to-calculate-carbon-dioxide-
emissions-from-a-diesel-generator
Abdul Haq Omari. (2021, April 10). Nangarhar: Electricity to be Bought With Prepaid Cards. Retrieved
from Tolo News: https://tolonews.com/business-171272
Acumen. (2021, August 5). Investments/ companies. Retrieved from Acumen:
https://acumen.org/?investment=rve-sol
ADB. (2014). Project Administration Manual: POISED. ADB. Retrieved from
https://www.adb.org/projects/documents/preparing-outer-islands-sustainable-energy-
development-project-pam
ADB. (2016). Detailed Description of Project Components. ADB. Retrieved from
https://www.adb.org/sites/default/files/linked-documents/49216-002-sd-01.pdf
ADB. (2017). 100% Electricity Generation through Renewable Energy by 2050: Assessment of Sri
Lanka’s Power Sector. ADB. Retrieved from https://www.adb.org/publications/electricity-
generation-renewable-energy-2050-sri-lanka
ADB. (2017). Deployment of Hybrid Renewable Energy Systems in Mini Grids. Manila: ADB. Retrieved
from https://www.adb.org/sites/default/files/institutional-document/376151/hybrid-
renewable-energy-systems-minigrids.pdf
ADB. (2017). Developing Renewable Energy Mini Grids in Myanmar. Manila: ADB. Retrieved from
https://www.adb.org/sites/default/files/institutional-document/391606/developing-
renewable-mini-grids-myanmar-guidebook.pdf
ADB. (2019). Sri Lanka Energy Sector Assessment, Strategy, and Roadmap. ADB. Retrieved from
https://www.adb.org/sites/default/files/institutional-document/547381/sri-lanka-energy-
assessment-strategy-road-map.pdf
ADB. (2020). A Brighter Future for Maldives Powered by Renewables - Roadmap for the energy sector
2020- 2030. ADB. Retrieved from
https://www.adb.org/sites/default/files/publication/654021/renewables-roadmap-energy-
sector-maldives.pdf
ADB. (2020, September 30). ADB Approves $110 Million Grant to Enhance Power Supply in
Afghanistan. Retrieved from ADB: https://www.adb.org/news/adb-approves-110-million-
grant-enhance-power-supply-afghanistan
ADB. (2021, May 26). Helping Sri Lanka to go green - Project Result / Case Study . Retrieved from ADB:
https://www.adb.org/results/helping-sri-lanka-go-green
ADB Institute. (2018). Green Finance in Pakistan: Barriers and Solutions. ADB Institute. Retrieved from
https://www.adb.org/sites/default/files/publication/460346/adbi-wp880.pdf
ADB, & ITP India. (2017). Renewable Energy Roadmap for Afghanistan 2032. Manila: ADB. Retrieved
from
https://policy.asiapacificenergy.org/sites/default/files/Renewable%20Energy%20Roadmap%
20for%20Afghanistan%20RER2032.pdf
Afghanistan Renewable Energy Companies Union. (n.d.). About AREU. Retrieved from Afghanistan
Renewable Energy Companies Union: https://areu.af/about-us/about-areu/
Agenbroad, J., Carlin, K., Ernst, K., & Doig, S. (2018). Minigrids in the Money: Six Ways to Reduce
Minigrid Costs by 60% for Rural Electrification. Nigeria: Rocky Mountain Institute. Retrieved
from https://rmi.org/wp-content/uploads/2018/12/rmi-seeds-minigrid-report.pdf
Ajmal Haidari. (2020). Renewable Energy (Solar) and its Impact on Rural Households’ Welfare (Case
Study of Badakhshan Province, Afghanistan). Journal of Economics and Business, Vol.3 No.2.
Retrieved from https://papers.ssrn.com/sol3/papers.cfm?abstract_id=3649406
Alisha Pinto, Yoo, H. K., Portale, E., & Rysankova, D. (2019). Nepal Beyond Connections: Energy Access
Diagnostic Report Based on the Multi-Tier Framework. World Bank Group. Retrieved from
122
https://energydata.info/dataset/e4526938-1f13-45b2-b4f4-
467fbb02b722/resource/35124cc5-0ebf-49c7-b7df-ec7fc961eb1d/download/mtf-energy-
access-country-diagnostic-report_nepal-9.2019.pdf
Alternative Energy Development Board . (2019). Alternative & Renewable Energy Policy. Government
of Pakistan. Retrieved from https://www.aedb.org/images/ARE_Policy_2019_-
_Gazette_Notified.pdf
Alternative Energy Promotion Center. (2019). Progress at a Glance: A Year in Review FY 2075/76
(2018/19). Kathmandu: Alternative Energy Promotion Center. Retrieved from
https://www.aepc.gov.np/uploads/docs/progress-at-glance-a-year-in-review-fy-207576-
201819-1572879503.pdf
Alternative Energy Promotion Centre . (2016). Piloting sustainability monitoring for micro hydropower
plants. Kathmandu. Retrieved from
https://www.aepc.gov.np/rerl/public/uploads/documents/QPYUelyFoWy5600f1iCidbu8wXB
18hAt2z32RjnG.pdf
Alternative Energy Promotion Centre . (2017). Establishing Sustainable Model for Financing
Community-based Micro-hydro Projects (MHP) through Local Financial Institutions. Retrieved
from
https://www.aepc.gov.np/rerl/public/uploads/documents/JX2wah8VDqBiHYWKIZAxeeRu52
nhVEzQ4ixk53Ay.pdf
Alternative Energy Promotion Centre . (2019). Mini Grid Special Program Operation Rules. Kathmandu:
Alternative Energy Promotion Centre . Retrieved from
https://www.aepc.gov.np/uploads/docs/l-l-1577767651.pdf
Anu Bhambhani. (2020, October 20). Study sees 40 GW solar energy potential for Bangladesh.
Retrieved from Taiyang News: http://taiyangnews.info/markets/study-sees-40-gw-solar-
energy-potential-for-bangladesh/
ARE. (2019). Private Sector Driven Business Models for Clean Energy Mini-Grids - Lessons learnt from
South and South-East-Asia. Brussels: Alliance for Rural Electrification. Retrieved from
https://www.ruralelec.org/sites/default/files/2020-02-06%20-
%20Private%20Sector%20Driven%20Business%20Models%20of%20Clean%20Energy%20Min
i-Grids%20in%20SEA%20-%20Final.pdf
ARE, & UNIDO ITPO. (2021). Decentralised Renewable Energy Innovations to Boost Agri-Sector
Productivity & Address Global Food System Challenges. ARE, UNIDO ITPO. Retrieved from
https://www.ruralelec.org/sites/default/files/2020-02-05%20-
%20DRE%20%26%20Agri%20Publication%20-%20Final.pdf
Ashden. (2020). SOLShare / Giving villagers in Bangladesh the power to trade electricity. Retrieved
from Ashden: https://ashden.org/winners/solshare/
Ashden. (n.d.). Sarhad Rural Support Programme (SRSP) / The power of water brings new life to
mountain villages. Retrieved from Ashden: https://ashden.org/winners/sarhad-rural-support-
programme-srsp-1/
Bangladesh, G. o. (2020). National Solar Energy Roadmap 2021-2041. Dhaka: Government of
Bangladesh.
Beath, A., Christia, F., & Enikolopov, R. (2015). The National Solidarity Program: Assessing the Effects
of Community-Driven Development in Afghanistan. Washington DC: World Bank Group.
Retrieved from
https://openknowledge.worldbank.org/bitstream/handle/10986/22653/Infrastructure0deve
loping0economies.pdf?sequence=1&isAllowed=y
Bhupendra Shakya. (2012). Mini Grid Development in Nepal:An Experience from RERL. Proceeding of
Workshop on Experience sharing of Mini Grid and Biomass Gasifi cation. Kathmandu.
Retrieved from
https://www.researchgate.net/publication/286580026_Mini_Grid_Development_in_Nepal_
An_Experience_from_RERL
123
Bhushan, C., Bharti, P., Sreenivasan, P., Singh, M., Jhawar, P., Koshy, S. M., & Sambyal, S. (2019). The
State of Renewable Energy in India. New Delhi: Centre for Science and Environment. Retrieved
from https://shaktifoundation.in/wp-content/uploads/2019/04/State-of-Renewable-Energy-
in-India.pdf
Bhutan Electricity Authority. (2016). Tariff Determination Regulation. Bhutan: Royal Government of
Bhutan. Retrieved from https://www.moea.gov.bt/wp-content/uploads/2017/07/dhps2-
1.pdf
Bhutan Power Corporation. (2020). Meeting Bhutan's Electricity Needs. Bhutan: Bhutan Power
Corporation. Retrieved from https://www.bpc.bt/wp-content/uploads/2021/06/BPC-Annual-
Report-2020.pdf
Bhutta, Z. (2021, February 13). Govt jacks up power tariff by Rs1.95. Retrieved from The Express
Tribune: https://tribune.com.pk/story/2283789/govt-jacks-up-power-tariff-by-rs195
BNEF, & SEforAll. (2020). State of the Global Mini-Grids Market Report. BNEF, SEforAll. Retrieved from
https://www.seforall.org/system/files/2020-06/MGP-2020-SEforALL.pdf
Burger, C., & Weinmann, J. (2020). Business models beyond subsidies –which core competencies are
needed? In C. Burger, A. Froggatt, C. Mitchell, & J. Weinmann, Decentralised Energy — a
Global Game Changer (pp. 177–260). London: Ubiquity Press. Retrieved from
https://www.ubiquitypress.com/site/chapters/10.5334/bcf.k/download/3998/
Business Call to Action. (n.d.). Members. Retrieved from Business Call to Action:
https://www.businesscalltoaction.org/member/nizam-energy
CDKN. (2019). Solar mini grids: Investment case Bangladesh. Climate and Development Knowledge
Network. Retrieved from https://cdkn.org/wp-content/uploads/2019/09/Investment-case-
solar-mini-grids.pdf
Central Renewable Energy Fund . (2017). Vendor Finance Challenge Fund. Kathmandu. Retrieved from
https://www.aepc.gov.np/rerl/public/uploads/documents/XWQscyuu3U3yD63njF5MvGog9
SS5ml75w12C2zzS.pdf
Centre for Science and Environment. (2020). Renewabe energy factsheet 7 Mini Grids. Centre for
science and environment. Retrieved from https://cdn.cseindia.org/userfiles/07Factsheet-
Mini-Grid.pdf
Ceylon Electricity Board. (2021). Statistical Digest 2020. CEB. Retrieved from
https://ceb.lk/front_img/img_reports/1626946210CEB-Statistical_Digest-Form-2020-
Web_Version.pdf
Ceylon Electricity Board. (n.d.). Tariff Plan. Retrieved from Ceylon Electricity Board:
https://ceb.lk/commercial-tariff/en
Chris Greacen. (2019). Mini Grid Costing and Innovation: Mini grids for half a billion people. World
Bank. Retrieved from https://atainsights.com/wp-content/uploads/2019/06/4.A.Chris-
Greacen.World-Bank-consultant-notes.pdf
CIF. (2014, May 28). Afghanistan eoi. Retrieved from Climate Investment Funds:
https://www.climateinvestmentfunds.org/sites/cif_enc/files/meeting-
documents/afghanistan_eoi_0.pdf
CIF. (2019). POISED CIF-GDI Delivery Challenge Case Study. Climate Investment Funds. Retrieved from
https://www.climateinvestmentfunds.org/sites/cif_enc/files/knowledge-
documents/66436_191219_maldives_case_study_v7s.pdf
CLEAN, & Margdarshan Advisory & Consultancy Services. (2020). Sensitizing financial institutions
towards lending to decentralized renewable energy enterprises and end-users. New Delhi:
CLEAN. Retrieved from https://www.thecleannetwork.org/pdf/financial-report-final.pdf
Collaboration on Energy and Environmental Markets. (n.d.). Tokelau Case Study: Part 1 of a series on
Energy Resilience in Pacific Island Countries and Territories. Collaboration on Energy and
Environmental Markets. Retrieved from
http://www.ceem.unsw.edu.au/sites/default/files/event/documents/4-
PICTsEnergyResiliencePlanningWorkshopTokelauBruce_0.pdf
124
Dawa Gyelmo. (2021, October 6). Bhutan looks beyond hydropower to solar. Retrieved from The Third
Pole: https://www.thethirdpole.net/en/energy/bhutan-looks-beyond-hydropower-to-solar/
Duggal, S. (2021, June 22). Solar energy news. Retrieved from Saur Energy International:
https://www.saurenergy.com/solar-energy-news/the-maldives-opens-pre-qualification-for-
11-14-mw-solar-pv-tender
Ecowas Centre for Renewable Energy and Energy Efficiency. (2020). TOR - Technical Assistance to
ensure the long-term sustainability of the clean energy mini-grid projects in Bambadinca and
Bissorã in Guinea-Bissau. Ecowas Centre for Renewable Energy and Energy Efficiency.
Retrieved from
http://www.ecreee.org/sites/default/files/procurment/attachments/200603_tor_gefgb-
mini-grids.pdf
Efficiency for Access Coalition. (2021). Business Model Innovations Addressing Environmental
Sustainability and Circularity: Case Studies. Efficiency for Access Coalition. Retrieved from
https://endeva.org/publication/business-model-innovations-addressing-environmental-
sustainability-and-circularity
energymeteo. (2020). energymeteo. Retrieved from products/power_forecasts/wind-solar-power-
forecasts.php: https://www.energymeteo.com/products/power_forecasts/wind-solar-
power-forecasts.php
Energypedia. (n.d.). Pakistan Energy Situation. Retrieved from Energypedia:
https://energypedia.info/wiki/Pakistan_Energy_Situation
Engineering Consultancy for Constructive Development Efforts. (2013). Techno-Socio-Economic Study
of Baglung Mini Grid. Engineering Consultancy for Constructive Development Efforts.
Retrieved from Techno-Socio-Economic Study of Baglung Mini Grid
ESMAP. (2017). Benchmarking study of solar PV mini grids investment costs: preliminary results. World
Bank Group. Retrieved from
https://documents1.worldbank.org/curated/en/569621512389752401/pdf/121829-ESM-
PVHybridminigridsCostingbenchmarkTTAESMAPConfEdtemplateDecv-PUBLIC.pdf
ESMAP. (2017). Ghana mini-grids for last mile electrification. ESMAP. Retrieved from
https://www.eca-uk.com/wp-content/uploads/2017/08/ESMAP-
Ghana_Mini_grids_for_last_Mile_Electrification_Optimized.pdf
ESMAP. (2017). Mini grids in Bangladesh: A case study of an incipient market. Washington DC: World
Bank. Retrieved from
https://documents1.worldbank.org/curated/en/669331512390210193/pdf/ESM-
aBangladeshCountryCaseStudy-PUBLIC.pdf
ESMAP. (2018). Mini grids and the arrival of the main grid: Lessons from Cambodia, Sri Lanka, and
Indonesia. Washington DC: World Bank. Retrieved from
https://openknowledge.worldbank.org/bitstream/handle/10986/29018/134326.pdf?sequen
ce=6&isAllowed=y
ESMAP. (2019). Mini Grids for Half a Billion People: Market Outlook and Handbook for Decision
Makers. Executive Summary. Washington DC: World Bank. Retrieved from
https://openknowledge.worldbank.org/bitstream/handle/10986/31926/Mini-Grids-for-Half-
a-Billion-People-Market-Outlook-and-Handbook-for-Decision-Makers-Executive-
Summary.pdf?sequence=1&isAllowed=y
ESMAP. (2019). Mini Grids for Half a Billion People: Market Outlook and Handbook for Decision
Makers. Executive Summary. Washington DC: World Bank.
EU-GIZ ACSE . (2016). Case Study: Reducing Diesel Cost with Solar Hybrid Mini-Grids in Tokelau. EU-GIZ
ACSE Programme. Retrieved from http://acsepacific.org/wp-content/uploads/2017/03/GIZ-
ACSE_Tokelau-FS_22March2017.pdf
Foster, R., Woods, T., & Hoffbeck, I. (2015, November 08). Bamiyan 1 MWp Solar Mini-Grid
(Afghanistan). Solar World Congress (SWC). International Solar Energy Society (ISES).
Retrieved from Research Gate: https://www.researchgate.net/profile/Robert-Foster-
125
17/publication/283915024_Bamiyan_1_MWp_Solar_Mini-
Grid_Afghanistan/links/564a207908ae44e7a28d96dd/Bamiyan-1-MWp-Solar-Mini-Grid-
Afghanistan.pdf
GardaWorld. (2021, May 12). Afghanistan: Power disruptions likely in Kabul following May 12 attack
on transmission towers /update 1. Retrieved from Garda World:
https://www.garda.com/crisis24/news-alerts/477841/afghanistan-power-disruptions-likely-
in-kabul-following-may-12-attack-on-transmission-towers-update-1
GCF. (2020). Funding Proposal: Afghanistan Rural Energy Market Transformation Initiative –
Strengthening Resilience of Livelihoods Through Sustainable Energy Access. Green Climate
Fund. Retrieved from https://www.greenclimate.fund/sites/default/files/document/fp129-
undp-afghanistan_0.pdf
GCF. (n.d.). FP129 - Afghanistan Rural Energy Market Transformation Initiative – Strengthening
Resilience of Livelihoods Through Sustainable Energy Access. Retrieved from Green Climate
Fund: https://www.greenclimate.fund/project/fp129
GIZ IDEA . (2017). Enabling PV Afghanistan. GIZ. Retrieved from
https://www.solarwirtschaft.de/fileadmin/user_upload/report_enabling_pv_afg.pdf
GNESD. (2014). Renewable energy-based rural electrification: The Mini-Grid Experience from India.
New Delhi: The Energy and Resources Institute (TERI) for Global Network on Energy for
Sustainable Development (GNESD). Retrieved from https://unepdtu.org/wp-
content/uploads/2014/09/renewable-energy-based-rural-electrification-the-mini-grid-
experience-from-india.pdf
Government of Afghanistan. (2013). Afghanistan Rural Renewable Energy Policy. Kabul: Islamic
Rebuplic of Afghanistan. Retrieved from
https://policy.asiapacificenergy.org/sites/default/files/4.3-Rural-Renewable-Energy-
Policy.pdf
Government of Afghanistan. (2015). Renewable Energy Policy. Kabul: Ministry of Energy and Water.
Retrieved from https://policy.asiapacificenergy.org/sites/default/files/Afghanistan-
Renewable-Energy-Policy-English-and-Dari.pdf
Government of Bangladesh. (2020). National Solar Energy Roadmap 2021-2041. Dhaka: Government
of Bangladesh. Retrieved from
sreda.gov.bd/sites/default/files/files/sreda.portal.gov.bd/notices/fba98896_568a_4efd_a48
b_8d92bfc04049/2020-10-22-17-12-7b0e5a0c0dabd4c17492bcf3bd7488b4.pdf
Government of Bangladesh. (2020). National Solar Energy Roadmap 2021-2041. Dhaka: Government
of Bangladesh.
Graber, S., Narayanan, T., Alfaro, J., & Palit, D. (2019). Perceptions towards solar mini-grid systems in
India: A multistakeholder analysis. Natural Resources Forum 43, 253–266. Retrieved from
https://css.umich.edu/sites/default/files/publication/CSS19-49.pdf
GSEP. (2017). The Dhiffushi Solar Ice Project in the Republic of Maldives. Global Sustainable Electricity
Partnership (GSEP). Retrieved from
https://www.globalelectricity.org/content/uploads/FINAL-Dhiffushi-interactive-
publication.pdf
Harsha Wickramasinghe. (2014). Off-grid Village Hydro Schemes in Sri Lanka: A success story. Sri Lanka
Sustainable Energy Authority. Retrieved from
https://www.dmu.ac.uk/documents/technology-documents/research-
faculties/oasys/project-activities/sustainable-energy-for-all---regulation-and-
govern/experience-from-sri-lanka---mr-harsha-wickramasinghe.pdf
IEA. (2021). Tracking SDG7: The energy progress report. Washington DC: World Bank. Retrieved from
https://www.irena.org/publications/2021/Jun/Tracking-SDG-7-2021
IEA. (n.d.). SDG7: Data and Projections. Access to electricity. Retrieved from IEA:
https://www.iea.org/reports/sdg7-data-and-projections/access-to-electricity
126
IEA. (n.d.). Sri Lanka Key Energy Statistics 2018. Retrieved from IEA:
https://www.iea.org/countries/sri-lanka
IFC. (2017). Operational and Financial Performance of Mini-Grid DESCOS. IFC. Retrieved from
https://sun-connect-
news.org/fileadmin/DATEIEN/Dateien/New/IFC_Minigrids_Benchmarking_Report_Single_Pa
ges_January_2017.pdf
IGC. (2019, September 9). Flexible payment plans for improved access to off-grid energy in Pakistan.
Retrieved from International Growth Centre: https://www.theigc.org/blog/flexible-payment-
plans-for-improved-access-to-off-grid-energy-in-pakistan/
Infrastructure Development Company Limited . (2020). A year of resilience: Redesigning tomorrow.
Bangladesh: IDCOL. Retrieved from https://idcol.org/annual_report/IDCOL-Annual-
Report_2020.pdf
Institute for Transformative Technologies. (n.d.). Solar mini-grids. Retrieved from Institute for
transformative technologies: https://transformativetechnologies.org/portfolio/solar-mini-
grids/
IRENA. (2016). Innovation Outlook Renewable Mini-Grids. Abu Dhabi: IRENA. Retrieved from
https://www.irena.org/-
/media/Files/IRENA/Agency/Publication/2016/IRENA_Innovation_Outlook_Minigrids_2016.
pdf
IRENA. (2018). Renewables Readiness Assessment: Pakistan. International Renewable Energy Agency.
Retrieved from https://www.irena.org/-
/media/Files/IRENA/Agency/Publication/2018/Apr/IRENA_RRA_Pakistan_2018.pdf
IRENA. (2019). Renewable Readiness Assessment: Kingdom of Bhutan. Abu Dhabi: International
Renewable Energy. Retrieved from https://www.irena.org/-
/media/Files/IRENA/Agency/Publication/2019/Dec/IRENA_RRA_Bhutan_2019.pdf
IRENA. (2019). Renewables Readiness Assessment. Abu Dhabi: International Renewable Energy
Agency.
IRENA. (2020). Renewable Power Generation Costs in 2019. Abu Dhabi: International Renewable
Energy Agency. Retrieved from https://www.irena.org/-
/media/Files/IRENA/Agency/Publication/2020/Jun/IRENA_Power_Generation_Costs_2019.p
df
IRENA. (2021). Renewable Power Generation Costs in 2020. Abu Dhabi: International Renewable
Energy Agency. Retrieved from https://www.irena.org/-
/media/Files/IRENA/Agency/Publication/2021/Jun/IRENA_Power_Generation_Costs_2020.p
df
ITP Australia. (2013). Tokelau Renewable Energy Project Review. NZ MFAT. Retrieved from
http://prdrse4all.spc.int/system/files/energy_tokelau_pv_system_review_-_final.pdf
ITP Australia. (n.d.). Tokelau Renewable Energy Expansion Project. Retrieved from ITP Australia:
https://itpau.com.au/projects/tokelau-renewable-energy-expansion-project/
Jaffer, H. (2016). MINIGRIDS (India) Current Challenges and Future Strategies. Tata Center for
Technology and Design. Retrieved from https://www.selcofoundation.org/wp-
content/uploads/2017/04/IAP_MinigridsIndiaReportTATA_Huda.pdf
James Knuckles. (2019). State of the mini grid market globally - Mini Grids for Half a Billion People.
World Bank Group. Retrieved from https://atainsights.com/wp-
content/uploads/2019/06/2.B.James_.Knuckles.World-Bank-1.pdf
Kapila Subasinghe. (2017). Grid Interconnection of Off-grid Community-based Projects: What
happened when the Grid Arrived - Sri Lankan Experience. DFCC Bank. Retrieved from
https://energypedia.info/images/f/f2/Grid_Interconnection_-_Sri_Lanka.pdf
M Ramesh. (2019, April 23). The microgrid revolution in Bihar. Retrieved from The Hindu Business Line:
https://www.thehindubusinessline.com/specials/clean-tech/the-microgrid-revolution-in-
bihar/article26924569.ece
127
MGP. (2021, August 5). Who we are. Retrieved from Mini-Grids Partnership:
https://minigrids.org/about/
Ministry of Energy, Water Resources and Irrigation. (2021). Annual Development Program FY 2078/79.
Kathmandu: Government of Nepal. Retrieved from
https://www.moewri.gov.np/storage/listies/July2021/annual-development-program-2078-
79-with-cover.pdf
Ministry of Environment and Energy. (2013). Maldives SREP Investment Plan. Ministry of Environment
and Energy. Retrieved from
https://policy.asiapacificenergy.org/sites/default/files/Maldives%20SREP%202013-
2017%20%28EN%29.pdf
Ministry of Finance. (2021). Budget Speech 2078/79. Kathmandu: Ministry of Finance. Retrieved from
https://www.mof.gov.np/site/publication-detail/3064
Ministry of Finance. (2021). Economic Survey 2077/78. Kathmandu: Government of Nepal. Retrieved
from
https://www.mof.gov.np/uploads/document/file/1633341980_Economic%20Survey%20(En
gslish)%202020-21.pdf
Ministry of Finance. (n.d.). Background. Retrieved from Office of the Deputy Minister for Policy,
Ministry of Finance: http://policymof.gov.af/home/national-priority-programs/background/
Ministry of Law and Justice. (2003). The Electricity Act. Government of India. Retrieved from
https://cercind.gov.in/Act-with-amendment.pdf
Ministry of Mahaweli Development and Environment. (2016). Nationally Determined Contributions.
Government of Sri Lanka. Retrieved from
https://www4.unfccc.int/sites/ndcstaging/PublishedDocuments/Sri%20Lanka%20First/NDCs
%20of%20Sri%20Lanka.pdf
Ministry of New and Renewable Energy. (2016). Draft National Policy on RE based Micro and Mini
Grids. Government of India. Retrieved from
http://www.indiaenvironmentportal.org.in/files/file/draft-national-Mini_Micro-Grid-
Policy.pdf
Ministry of New and Renewable Energy. (n.d.). Bio energy - Current status. Retrieved from MNRE
Website: https://mnre.gov.in/bio-energy/current-status
Ministry of New and Renewable Energy. (n.d.). Small Hydro Current Status. Retrieved from MNRE
Website: https://mnre.gov.in/small-hydro/current-status
Ministry of New and Renewable Energy. (n.d.). Solar Energy: Overview. Retrieved from MNRE:
https://mnre.gov.in/solar/current-status/
Ministry of New and Renewable Energy. (n.d.). Wind Current Status. Retrieved from MNRE Website:
https://mnre.gov.in/wind/current-status/
Ministry of Power. (2016). Tariff Policy. Government of India. Retrieved from
https://powermin.gov.in/sites/default/files/webform/notices/Tariff_Policy-
Resolution_Dated_28012016.pdf
Ministry of Power, Energy and Business Development. (2019). National Energy Policy and Strategies
of Sri Lanka. Government of Sri Lanka. Retrieved from
http://www.energy.gov.lk/images/resources/downloads/national-energy-policy-2019-
en.pdf
Mlinda. (2018). Renewable Energy for Rural Communities. Retrieved from Mlinda:
https://www.mlinda.org/democratising-energy-supply/
MOXA. (2019). cdn-cms.azureedge.net. Retrieved from
Moxa/media/Global/Site%20Content/Case%20Studies/PDF/thingnario-EN_4.pdf:
https://cdn-
cms.azureedge.net/Moxa/media/Global/Site%20Content/Case%20Studies/PDF/thingnario-
EN_4.pdf
128
Nafees Ahmad Khan. (2021). Presentation - Renewable Energy Program. Pakistan Poverty Alleviation
Fund .
National Electric Power Regulatory Authority . (2020). State of Industry Report. NEPRA.
National Electric Power Regulatory Authority. (2020). State of Industry Report. National Electric Power
Regulatory Authority. Retrieved from
https://nepra.org.pk/publications/State%20of%20Industry%20Reports/State%20of%20Indus
try%20Report%202020.pdf
Nelis Global. (2020, November 3). SOLshare: Driving renewables adoption in Bangladesh by monetizing
solar energy for all. Retrieved from Nelis Global: https://socialmedia-
nelis.medium.com/solshare-driving-renewables-adoption-in-bangladesh-by-monetizing-
solar-energy-for-all-a39d3fe162ec
New Zealand Ministry of Foreign Affairs and Trade . (2013). Tokelau Renewable Energy Project Case
Study March 2013. New Zealand Ministry of Foreign Affairs and Trade. Retrieved from
http://prdrse4all.spc.int/system/files/trep-case-study.pdf
NREL. (2010). Afghanistan Resource Data and Geospatial Toolkit (GsT). National Renewable Energy
Laboratory.
Pakistan Poverty Alleviation Fund . (2021). Renewable energy programme. Pakistan Poverty
Alleviation Fund. Retrieved from https://www.ppaf.org.pk/HRE-programme
Power Technology. (2013, February 12). Tokelau – the world’s first solar power sufficient nation.
Retrieved from Power Technology: https://www.power-
technology.com/features/featuretokelau-world-first-solar-power-sufficient-nation/
Power Technology. (2016, September 25). Ghazanfar Group signs agreement to develop new gas
power plant in Afghanistan. Retrieved from Power Technology: https://www.power-
technology.com/uncategorised/newsghazanfar-group-signs-agreement-to-develop-new-gas-
power-plant-in-afghanistan-5014418/
Priti Kumar. (2015). Nepal - Scaling up electricity access through mini and micro hydropower
applications : a strategic stock-taking and developing a future roadmap. Washington, D.C.:
World Bank Group. Retrieved from
https://documents.worldbank.org/en/publication/documents-
reports/documentdetail/650931468288599171/nepal-scaling-up-electricity-access-through-
mini-and-micro-hydropower-applications-a-strategic-stock-taking-and-developing-a-future-
roadmap
Priyavrat Bhati, & Mandvi Singh. (2018). Mini-grids in Uttar Pradesh: Policy Lessons. New Delhi: Centre
for Science and Environment. Retrieved from
http://cdn.cseindia.org/attachments/0.58005500_1530179433_Mini-grid-in-UP-report.pdf
Renewable Energy for Rural Livelihood. (2019). RERL Quarterly Updates. Kathmandu: Renewable
Energy for Rural Livelihood. Retrieved from
http://www.aepc.gov.np/rerl/public/uploads/documents/HVhJgfdN3s18saWHYcxK1wEJALl2
h2cIU6joooHu.pdf
Renewable Energy for Rural Livelihood. (2020). Annual Progress Report. Kathmandu. Retrieved from
http://www.aepc.gov.np/rerl/public/uploads/documents/My504x18JCxI0hwAPt66NL7zCUfy
lu9BloSGvmdB.pdf
Renewable Energy for Rural Livelihood. (2020). Intervention in renewable energy for sustainable
development. Kathmandu: Renewable Energy for Rural Livelihood Program. Retrieved from
http://www.aepc.gov.np/rerl/public/uploads/documents/3YDLLh8AGKhgAjnab9cW5y4psuft
riw8Hf9yes27.pdf
Reon Energy. (n.d.). Uncategorized. Retrieved from Reonenergy: https://www.reonenergy.com/are-
solar-microgrids-a-solution-to-pakistans-energy-crisis/
Rockefeller Foundation. (2021, August 19). Smart Power India . Retrieved from Smart Power India :
https://smartpowerindia.org
129
Royal Government of Bhutan. (2001). Electricity Act of Bhutan. Bhutan: Royal Government of Bhutan.
Retrieved from
https://www.nab.gov.bt/assets/uploads/docs/acts/2014/Electricity_act_2001_Eng.pdf
Royal Government of Bhutan. (2013). Alternative Renewable Energy Policy. Bhutan: Royal
Government of Bhutan. Retrieved from https://www.moea.gov.bt/wp-
content/uploads/2017/07/Final-Alternative-RE-Policy-April-2013.pdf
Saleh, N. (2019, November 7). Country Report Pakistan. Retrieved from Energy Democracy:
https://energy-democracy.org/mini-grids-in-pakistan-bottom-up-option-for-renewable-
electrification/#_ftn1
Santosh Rai. (2019, September). Introduction to RE Mini Grid Projects in Nepal. Kathmandu. Retrieved
from
https://energypedia.info/images/6/6a/Session_0_Introduction_AEPC_Mr._Rai_090419.pdf
Saral Urja Nepal. (2021, July 29). Project details - Dubung. Retrieved from Saral Urja:
http://www.saralurja.com/project-details-dubung.php#details
SE4All. (2012). Rapid Assessment Gap Analysis. Bhutan: Royal Government of Bhutan. Retrieved from
https://www.seforall.org/sites/default/files/Bhutan_RAGA_EN_Released.pdf
Smart Power India. (First Edition). Demand Generation for Solar mini grid. Haryana: Smart Power India.
Solano-Peralta, M., Moner-Girona, M., van Sark, W., & Vallve, X. (2009). “Tropicalisation” of Feed-in
Tariffs: A custom-made support scheme for hybrid PV/diesel systems in isolated regions.
Renewable and Sustainable Energy Reviews, 13(9):2279-2294. Retrieved from Researchgate
website: https://www.researchgate.net/figure/a-LCOE-for-the-different-PV-scenarios-
compared-to-the-diesel-generation-system-
with_fig8_223178620#:~:text=The%20LCOE%20for%20the%20diesel,with%20diesel%20mar
ket%20prices%20(Fig.
SOLshare. (n.d.). From energy access in Bangladesh to the future of energy utilities globally . Retrieved
from SOLshare: https://me-solshare.com/
SOLshare. (n.d.). What we do. Retrieved from SOLshare website: https://me-solshare.com/what-we-
do/
Sri Lanka Sustainable Energy Authority. (2020). Renewable Energy Resource Development Plan 2021-
2026. Sri Lanka Sustainable Energy Authority. Retrieved from
http://www.energy.gov.lk/images/renewable-energy/renewable-energy-resource-
development-plan-en.pdf
SteamaCo. (2020). off-grid-smart-metering-platform. Retrieved from SteamaCo:
https://steama.co/off-grid-smart-metering-platform
Sushil Sah. (2019, November 25). Power-Less to Powerful. Retrieved from World Bank:
https://www.worldbank.org/en/news/feature/2019/11/25/power-less-to-powerful
Sustainable and Renewable Energy Development Autho. (n.d.). National Database of Renewable
Energy. Retrieved 07 07, 2021, from SREDA:
http://www.renewableenergy.gov.bd/index.php?id=7
Sustainable and Renewable Energy Development Authority. (2021, June 17). Solar Home System.
Retrieved from SREDA website: http://www.sreda.gov.bd/site/page/61db6522-9cf1-48c9-
8ea4-c30a53b01272/-
Sustainable and Renewable Energy Development Authority. (2021, July 7). SREDA. Retrieved from
National Database of Renewable Energy:
http://www.renewableenergy.gov.bd/index.php?id=1&i=5
Sustainable and Renewable Energy Development Authority. (2021, August 11). SREDA. Retrieved from
National Database of Renewable Energy:
http://www.renewableenergy.gov.bd/index.php?id=2&i=1
Sustainable Development Goals Partnership Platform. (n.d.). India plans to produce 175 GW of
renewable energy by 2022. Retrieved from Susatainable Development Goals Partnerships
Platform: https://sustainabledevelopment.un.org/partnership/?p=34566
130
The Business Standard. (2021, February 3). SOLshare: Using the Uber model to share solar power.
Retrieved from The Business Standard:
https://www.tbsnews.net/feature/panorama/solshare-using-uber-model-share-solar-
power-195445
Tom Kenning. (2017, September 25). Construction starts on 10MW Afghanistan solar project in
Kandahar. Retrieved from PV-Tech: https://www.pv-tech.org/construction-starts-on-10mw-
afghanistan-solar-project-in-kandahar/
Transmission and Generation Planning Branch. (2019). Long Term Generation and Expansion Plan
2020 - 2039 (Draft). Ceyloan Electricity Board. Retrieved from
https://ceb.lk/front_img/img_reports/1560836289LTGEP_2020-2039_(Draft).pdf
UNDP. (2021, April 5). Renewable Energy Lights Up Dar-i Noor. Retrieved from UNDP :
https://www.af.undp.org/content/afghanistan/en/home/presscenter/pressreleases/2021/R
enewableEnergyLightsUpDar-i-Noor.html
UNIDO. (2017). Renewable energy based mini grids: the UNIDO experience. UNIDO. Retrieved from
https://open.unido.org/api/documents/5367940/download/RENEWABLE%20ENERGY-
BASED%20MINI-GRIDS%20-%20THE%20UNIDO%20EXPERIENCE
USAID. (2018, February 13). Bamiyan Renewable Energy Program. Retrieved from USAID:
https://www.usaid.gov/energy/mini-grids/case-studies/afghanistan-hydropower
USAID. (2018, February 14). Energy/Mini-grids/ Technical design. Retrieved from USAID website:
https://www.usaid.gov/energy/mini-grids/technical-design/components
USAID. (2018, February 14). What are the technical components of a mini-grid? Retrieved from USAID
website: https://www.usaid.gov/energy/mini-grids/technical-design/components
USAID. (2018, February 13). What ownership models are used for mini-grids? Retrieved from USAID:
https://www.usaid.gov/energy/mini-grids/ownership/models/
USAID. (2020, February 4). Key steps in mini-grid technical design. Retrieved from USAID Website:
https://www.usaid.gov/energy/mini-grids/technical-design/key-steps/
USAID. (n.d.). Bamiyan Renewable Energy Program. Retrieved August 11, 2021, from USAID:
https://www.usaid.gov/energy/mini-grids/case-studies/afghanistan-hydropower
Wame. (2014). Bambadinca sta claro! Retrieved from Wame:
https://www.wame2030.org/project/1075/
Water and Energy Commission Secretariat. (2013). Nepal's Energy Sector Vision 2050 A.D. Nepal:
Government of Nepal. Retrieved from
https://wecs.gov.np/storage/listies/October2020/vision-2050.pdf
Wheeldon, S. (2017, November 28). Blogs. Retrieved from GOGLA: https://www.gogla.org/about-
us/blogs/off-grid-solar-a-new-hope-for-pakistans-double-energy-crisis
World Bank. (2021). Setting Course to Recovery. Washington DC: World Bank. Retrieved from
https://openknowledge.worldbank.org/bitstream/handle/10986/35363/Afghanistan-
Development-Update-Setting-Course-to-Recovery.pdf?sequence=2&isAllowed=y
World Bank. (n.d.). population data. Retrieved from World bank:
https://data.worldbank.org/indicator/EG.ELC.ACCS.RU.ZS?locations=BD
Xenakis, G. (2017, December 4). Community Programme for Access to Renewable Energy in
Bambadinca . Retrieved from ALER: https://www.aler-
renovaveis.org/en/communication/news/bambadinca/
Xenakis, G. (n.d.). Presentation of Bambadinca PV Mini Grid. TESE. Retrieved from https://www.aler-
renovaveis.org/contents/activitieseventsspeakersdocuments/georgios-
xenakis_tese_3623.pdf
131
7 ANNEXURE
132
7.1 Annexure 1: List of stakeholders and experts consulted for the study
133
7.2 Annexure 2: Solar GHI maps of SAARC Member States
The World Bank and the International Finance Corporation, collectively The World Bank Group, have
developed solar atlas for countries. The World Bank Group has used Solargis solar data and related
solar energy assessment services. The solar GHI maps of countries can be downloaded from
https://globalsolaratlas.info/map. This section provides the solar GHI maps of SAARC Member States.
AFGHANISTAN
134
BANGLADESH
135
BHUTAN
136
INDIA
137
MALDIVES
138
NEPAL
139
PAKISTAN
140
SRI LANKA
141
142