Updated Work Programme-Jinja
Updated Work Programme-Jinja
ID Task Task Name Duration Start Finish June 2023 July 2023
Mode 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21
1 Activity 44 days Mon 05/06/23 Thu 20/07/23
2 Forecourt works 21 days Mon 05/06/23 Sun 25/06/23
3 Paving works 8 days Tue 20/06/23 Tue 27/06/23
4 Plumbing works 5 days Tue 06/06/23 Sat 10/06/23
5 Tiling works 13 days Fri 16/06/23 Wed 28/06/23
6 Terrazzo works 9 days Mon 19/06/23 Tue 27/06/23
7 Tank base filling, pipe work and tank 11 days Wed 07/06/23 Sat 17/06/23
farm works
8 Electrical works 10 days Thu 29/06/23 Sat 08/07/23
9 Painting works 16 days Thu 29/06/23 Fri 14/07/23
10 Bollards and Kerbstones 17 days Sat 10/06/23 Mon 26/06/23
11 Alluminium works 4 days Mon 10/07/23 Thu 13/07/23
12 Demobilisation 4 days Mon 17/07/23 Thu 20/07/23
Page 1
UPDATED WORK PROGRAMME FOR TOTAL JINJA MAINSTREET
August 2023 September 2023 October 2023 November 2023 Decem
21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30
Page 2