Pending Compliance

Uploaded by

ravi raghav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

No. DMRC/GM/PROJECT/QA/DC-02/09/2021/214 Date: 30.10.

2024

Note

Name of Work: DC-02:“Part Design and Construction of Elevated Viaduct from Maujpur
(excluding) to Majlis Park (excluding) including Bridge across river Yamuna Integrated
Elevated Viaduct with PWD flyover at lower deck & metro line at the upper deck from
Yamuna Vihar to Bhajanpura and 08 Elevated Stations viz. Yamuna Vihar, Bhajan pura,
Khajuri Khas, Sonia Vihar, Soorghat, Jagatpur Village, Jharoda and Burari station(including
Entry & Exit structures at stations but excluding Architectural finishing, Pre-engineered steel
roof structure and roof sheeting of stations) from Chainage 0.000Mto12098.520M of
Majlis Park-Maujpur Corridor of Delhi MRTS Phase- IV Project.”

Contract No.: DC-02

Contractor: M/S LONGJIAN-KECJV.

Sub: Pending Compliance of observations raised by GC to DMRC up to 31.10.2024

The status of compliance of the observations made by GC to DMRC up to 31.10.2024 is


enclosed as Annexure-I. Compliance report for the pending observations shall be
submitted to Quality Cell, DMRC at the earliest.
Further, it is brought to your kind attention that 7 Nos. Quality Observations have been
pending closure for over 60 days.

Please look into this matter and instruct the contractor to expedite closure process of all
pending observation at the earliest

Encl: As above

Chief QA/QC Expert

Team Leader/GC

CPM-04

C/C to: 1. PED/Coordination Civil-1

2.CGM/Project
Annexure-I
Contract: DC-02

Status of Compliance of Quality Observations up to 31.10.2024

Observations of Quality walk Status of Compliance

S. No. Quality Nos. of Ref.No. Nos. of Ref. No.& Pending Remarks


walks no. Observation observatios Date observations
& s complied to be
Date complied

1 1st to145th 974 ------ 974 ------ 0 All observations are


complied
2 146th 10 E-387716 0 All observations are
E-377817 10
19.03.2024 E-418644 complied
3 147th 4 E-394727 1 Pending Observations:
E-377866 3
02.04.2024 Sl no.1: Crack identified in
third flight of staircase.

4 148th 12 E-399088 1 Pending Observations:


E-382426 11 E-418644
16.04.2024 S.no. 5- Some PEB column
base is found without
casting of the base
pedestal. Also, adequate
length of protrude of
anchors bolts is not
available to fix the nuts.,

5 149th 9 E-399088 0 All observations are


E-386445 9 E-418644 complied
30.04.2024
6 150th 12 E-403588 1 Pending
E-391949 11 E-418644
14.05.2024 Observations:
S.no.3- : Cracks
have been observed
in beam portion of
Pie-Girder between
Grid C3 to C4.
Similar type of cracks
is visible in beam at
multiple locations.
7 151th 5 E-403588 1 Pending
E-395492 4
21.05.2024 Observations:
S.no. 3-a) Some
Plywood material was
found inserted at the soffit
of connection beam in Pie
Girder b) Connection
beam edge was found not
aligned properly c) Soffit
of Pie Girder found
unfinished d) Some Tie-
rods are found in exposed
condition
8 152th 5 5 E-403588 0 All observations are
E-395493 E-418644 complied
28.05.2024
9 153rd 9 8 E-410856 1 Pending Observations:
E-398502 E-418644
04.06.2024 S.no.7: Major
honeycombing found in
column in Khajuri station..

10 154th 10 9 E-410856 1 Pending observations:


E-400083 E-418644
11.06.2024 S.no.5- No expansion gap
found between two U-
Girders. C6-C7 & C7-C8
RHS.
11 155th 5 5 E-410821 0 All observations are
E-401172 E-418644
18.06.2024 complied
12 156th 6 5 E-416203 1 Pending observations:
E-403984
25.06.2024 S.No.5- Protruding rods &
uneven surface in CLC beam
at Yamuna bridge.
13 157th 19 15 E-418639 4 Pending observation:
E-406238
02.07.2024 S.no.7- Bearing plate has
penetrated inside the face of
stressing end. Additionally,
HT strands were found to be
broken. As a result, stressing
operation has failed.
S.no.8- Water ingress has
been noticed at the soffit of
the pier cap and column
junction of station column
C-6
S.no.10- Mounting of HT
strands found exposed due
to incomplete capping during
grouting of ducts
S.no.14- IS 14268 Code for
‘Uncoated Stress Relieved
Low Relaxation Seven-Wire
(Ply) Strand for Pre-Stressed
Concrete – Specification’ has
revised in the year 2022 and
implementing for LRS
strands manufacturing from
02 March 2023.
14 158th 14 11 E-424605 03 Pending Observation:
E-408494
09.07.2024 S.no.6- The front wall of lift is
not vertically aligned due to
which an offset of 20-25mm
is visible in block and RCC
wall.
S.no.13- Chipping and
cutting work carried out at
the precast Pie- Girder for
hanging of structural steel
members.
S.no.14- cable no. 13 and 14
stressing is pending due to
chocking of duct.
15 159th 25 21 E-425361 04 Pending Observations:
E-411212
16.07.2014 S.no.5- : Lintels are not
provided around the cut-
outs. AAC block has been
cut in shape to make cut-
outs.
S.no.19-Cut out has been
made by core cutting method
in precast member in ASS
room. (Awaited for input from
design cell).
S.no.23- Awaited for vendor
approval letter.
S.no.25- Corrections shall
also be made in ITP and
submit for approval.
16 160th 5 5 E-425361 0 All observations are
E-413151
23.07.2024 complied.
17 161th 12 09 E-425368 03 S.no. 6- The testing shall
E-415031
31.07.2024 carried out in 6 months’
interval as mentioned in E.R.
and approved ITP. GC is
advised to comply as per the
Employer’s requirement and
Approved ITP.

Pending observation:
S.no.2- Bench Test for pre-
stressing strands is
conducted only once for
12K15 system. Minimum 6
no. of tests shall be
conducted for each system
as per the OCS.
S.no.8- Awaited for
approval from the Engineer.
S.no.9- Awaited approval of
ITP from the Engineer.
18 162nd 07 04 E-425368 03 Pending observation:
E-417956
06.08.2024 S.no.1- : 1st stage stressing
for Portal Beam C-8 was
completed long back,
however it was noticed that
grouting of the ducts has not
been completed yet.
S.no. 4- Unfinished concrete
being observed in column
and beam junction for
staircase from ground to
concourse.
S.no. 6- Cut outs has been
made by core cutting method
in precast pie-girder.
19 163th 04 03 E-428596 01 Pending observation:
E-421808
20.08.2024 S.no.1- HT strands found
unwrapped.
20 164th 06 05 E-428596 01 Pending observation:
E-423080
27.08.2024 S.no.5- Water seepage
observed in soffit of pier arm
CPC-03.
21 165th 13 12 E-43904 1 Pending Observation:
E-425288
03.09.2024 S.no.11- Chipping has been
performed in Pie-girder to
make cut-out larger.
22 166th 10 0 Nil 10 Compliance report not yet
E-428120
10.09.2024 received
23 167th 11 0 Nil 11 Compliance report not yet
E-430436
24.09.2024 received
24 168th 10 0 Nil 10 Compliance report not yet
E-436009
01.10.2024 received
25 169th 07 0 Nil 07 Compliance report not yet
E-436011
08.10.2024 received
26 170th 08 0 Nil 08 Compliance report not yet
E-437380
15.10.2024 received
27 171st 08 0 Nil 08 Compliance report not yet
E-438924
22.10.2024 received
Total 1220 1139 81

Quality Expert