Pending Compliance
Pending Compliance
2024
Note
Name of Work: DC-02:“Part Design and Construction of Elevated Viaduct from Maujpur
(excluding) to Majlis Park (excluding) including Bridge across river Yamuna Integrated
Elevated Viaduct with PWD flyover at lower deck & metro line at the upper deck from
Yamuna Vihar to Bhajanpura and 08 Elevated Stations viz. Yamuna Vihar, Bhajan pura,
Khajuri Khas, Sonia Vihar, Soorghat, Jagatpur Village, Jharoda and Burari station(including
Entry & Exit structures at stations but excluding Architectural finishing, Pre-engineered steel
roof structure and roof sheeting of stations) from Chainage 0.000Mto12098.520M of
Majlis Park-Maujpur Corridor of Delhi MRTS Phase- IV Project.”
Please look into this matter and instruct the contractor to expedite closure process of all
pending observation at the earliest
Encl: As above
Team Leader/GC
CPM-04
2.CGM/Project
Annexure-I
Contract: DC-02
Pending observation:
S.no.2- Bench Test for pre-
stressing strands is
conducted only once for
12K15 system. Minimum 6
no. of tests shall be
conducted for each system
as per the OCS.
S.no.8- Awaited for
approval from the Engineer.
S.no.9- Awaited approval of
ITP from the Engineer.
18 162nd 07 04 E-425368 03 Pending observation:
E-417956
06.08.2024 S.no.1- : 1st stage stressing
for Portal Beam C-8 was
completed long back,
however it was noticed that
grouting of the ducts has not
been completed yet.
S.no. 4- Unfinished concrete
being observed in column
and beam junction for
staircase from ground to
concourse.
S.no. 6- Cut outs has been
made by core cutting method
in precast pie-girder.
19 163th 04 03 E-428596 01 Pending observation:
E-421808
20.08.2024 S.no.1- HT strands found
unwrapped.
20 164th 06 05 E-428596 01 Pending observation:
E-423080
27.08.2024 S.no.5- Water seepage
observed in soffit of pier arm
CPC-03.
21 165th 13 12 E-43904 1 Pending Observation:
E-425288
03.09.2024 S.no.11- Chipping has been
performed in Pie-girder to
make cut-out larger.
22 166th 10 0 Nil 10 Compliance report not yet
E-428120
10.09.2024 received
23 167th 11 0 Nil 11 Compliance report not yet
E-430436
24.09.2024 received
24 168th 10 0 Nil 10 Compliance report not yet
E-436009
01.10.2024 received
25 169th 07 0 Nil 07 Compliance report not yet
E-436011
08.10.2024 received
26 170th 08 0 Nil 08 Compliance report not yet
E-437380
15.10.2024 received
27 171st 08 0 Nil 08 Compliance report not yet
E-438924
22.10.2024 received
Total 1220 1139 81
Quality Expert
Chief QA/QC Expert