Mechanical Flowline
Mechanical Flowline
: 0904570-BOM-002
NASHPA 11 PIPELINE CONSTRUCTION PACKAGE PREP. : AHK
REV. :1
DATE : 18-04-23
BOQ PIPELINE WORKS
SR# ITEM DESCRIPTION UNIT QTY. UNIT RATE TOTAL (PKR) REMARKS
(PKR)
i Receiving, Loading, transportation, unloading of pipes, bends and allied material at site.
ii Stringing of Pipeline along with ROW
iii Lowering in trench with proper arrangement as per standard.
iv Installation of Anchor Flanges & Insulation joints
v Installation of factory bends as per requirement.
vi Fabrication, Installation and testing of Field-cold bends as per site requirement.
vii Supply and placing of sand bags
viii Holiday testing and repair of damage coating
ix 20% Radiography
x Line locating of already layed different pipelines
xi Excavation of Test Pits where required for identification of any underground pipe / structure (Distance should be 25m).
xii All Cunsumables and any work required for completion
xiii Area must be cleared and re-instated after completion of work
1.1 JOINTS/ DIA INCHES
i The estimated Dia Inches of pipeline. DI 1480
1.2 INSULATION JOINT
Installation of Insulation joint includes the placing of I.J., welding. Work also
includes Lifting and Transportation from store and unloading at work site.
Placement and procurement of sand bags, for pipeline placement adjacent Sand bags to be re-utilized at
to pipe trench including lifting and placement at site complete in all respect overall pipeline section as per
as specified by the client. project specification.
TOTAL (PKR)
NOTES:
The Quantities taken in this BOQ are estimated only for bidding purpose. Contractor is responsible to estimate the quantities as per site requirements, drawings & tender documents
1
2 Contractor is responsible to add any missing / required item as per scope of works, drawings, specifications & tender documents.
3 OGDCL reserves the right to increase / decrease the quantum of work. However payment will be made on actual work done.
4 Contractor to comply with Relevant codes & standards, specifications and drawings.
6 In case of water logged area, Dewatering should be done by means of Pumps and its rate should be added as per requirement by the contractor.
7 For Water logged area Buyoncy weights should be placed on Flowline as per requirement and its rate should be added by the contractor.
9 During cold bending operation, angle of bend may varry according to site requirement
10 Mobilization / De-Mobilization, Equipment, Machinery, Tools, Manpower, Camping, utilities, etc required for completion of work.
12 Approval of client should be taken by the contractor before undertaking any kind of construction and installation work at site.