Mechanical Flowline

Uploaded by

Adeel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

OIL & GAS DEVELOPMENT COMPANY LIMITED DOC. NO.

: 0904570-BOM-002
NASHPA 11 PIPELINE CONSTRUCTION PACKAGE PREP. : AHK
REV. :1
DATE : 18-04-23
BOQ PIPELINE WORKS
SR# ITEM DESCRIPTION UNIT QTY. UNIT RATE TOTAL (PKR) REMARKS
(PKR)

1.0 PIPELINE WORKS

All welding to be done in


Fabrication, Internal cleaning & welding of pipeline Dia. 8" Sch. 80, Works
R.M 1800 accordance with API 1104 standard
includes but not limited to the followings:
Note 6 & 7

i Receiving, Loading, transportation, unloading of pipes, bends and allied material at site.
ii Stringing of Pipeline along with ROW
iii Lowering in trench with proper arrangement as per standard.
iv Installation of Anchor Flanges & Insulation joints
v Installation of factory bends as per requirement.
vi Fabrication, Installation and testing of Field-cold bends as per site requirement.
vii Supply and placing of sand bags
viii Holiday testing and repair of damage coating
ix 20% Radiography
x Line locating of already layed different pipelines
xi Excavation of Test Pits where required for identification of any underground pipe / structure (Distance should be 25m).
xii All Cunsumables and any work required for completion
xiii Area must be cleared and re-instated after completion of work
1.1 JOINTS/ DIA INCHES
i The estimated Dia Inches of pipeline. DI 1480
1.2 INSULATION JOINT

Installation of Insulation joint includes the placing of I.J., welding. Work also
includes Lifting and Transportation from store and unloading at work site.

i Dia. 8" Sch. 80. Nos. 2


1.3 SAND BAGS FOR PIPELINE PLACEMENT

Placement and procurement of sand bags, for pipeline placement adjacent Sand bags to be re-utilized at
to pipe trench including lifting and placement at site complete in all respect overall pipeline section as per
as specified by the client. project specification.

i (1 ft x 2 ft) wide 4" thick sand bag Bags -


1.4 INSTALLATION OF BENDS

Installation of Induction 45⁰ 5D bends , includes the placing of all kinds of


See Drawing #
bends between pipes and weld as per specification. Work also includes
0904570-DT-002
Lifting and Transportation from store and unloading at work site and
0904570-DT-003
operation of pipe bending machine.

i Dia. 8" Sch. 80. Nos. 4


1.5 INSTALLATION OF COLD BENDS
Installation of Cold bends , includes the placing of all kinds of bends
between pipes and weld as per specification. Work also includes Lifting and See Drawing #
Transportation from store and unloading at work site and operation of pipe 0904570-DT-101
bending machine.
i Dia. 8" Sch. 80. Nos. 19
1.6 HEAT SHRINKABLE SLEEVES
Heat shrinkable sleeve (preferably Raychem HTLP 80) & patches will be
provide by OGDCL at field store. Installation of sleeves which includes
shifting of sleeves from store to site, surface preperation, supply &
i Nos. 185
application of primer (Compound A+B) with application KIT complete in all
respect.

1.7 HYDROSTATIC TESTING & COMMISSIONING


Hydrostatic testing of pipeline as per project specification and Client
requirements.Contractor shall provide all material, tools, equipment, supply
of water, temprory test plugs, couplings, flanges, nuts, bolts, recorder
guage, cleaning and flushing and all necessary arrangements required for
M 1800
hydrostatic testing would be responsibility of contractor and should be done
as per relevant specification, Code & standard.

1.8 PIGGING OF PIPELINE


Line shall be cleaned, flush and made dry by using pigs as per specfication,
standard practice and to the satisfaction of the Engineer Incharge. Scope
also include supply of brand new pigs, pigging of pipeline and all R.M 1800
arrangements required for completion of work.
OIL & GAS DEVELOPMENT COMPANY LIMITED DOC. NO. : 0904570-BOM-002
NASHPA 11 PIPELINE CONSTRUCTION PACKAGE PREP. : AHK
REV. :1
DATE : 18-04-23
BOQ PIPELINE WORKS
SR# ITEM DESCRIPTION UNIT QTY. UNIT RATE TOTAL (PKR) REMARKS
(PKR)

2.0 CROSSING OF PIPELINE Note 8


Crossings along the route, including supply of all material, tools,
construction of supports, any civil works, re-instatement, casing pipes, seals,
insulators, vent, drains and insulation lining for pipeline as per relevant
standard's & Code, drawing's and specifications. Crossings includes Roads,
Water Courses, Nallah's and other crossings etc.

3.0 AS BUILD DRAWINGS


Preparing & Updating of "As build drawings" & should be done parallel with
lowering activity. Hard Copy (1 original & 2 Good Quality copy) and soft
R.M 1800
copy would be submitted to Engineer Incharge.

TOTAL (PKR)

NOTES:
The Quantities taken in this BOQ are estimated only for bidding purpose. Contractor is responsible to estimate the quantities as per site requirements, drawings & tender documents
1

2 Contractor is responsible to add any missing / required item as per scope of works, drawings, specifications & tender documents.

3 OGDCL reserves the right to increase / decrease the quantum of work. However payment will be made on actual work done.

4 Contractor to comply with Relevant codes & standards, specifications and drawings.

5 All area must be cleared and reinstated after completion of work

6 In case of water logged area, Dewatering should be done by means of Pumps and its rate should be added as per requirement by the contractor.

7 For Water logged area Buyoncy weights should be placed on Flowline as per requirement and its rate should be added by the contractor.

8 All crossings will be finalized as per site.

9 During cold bending operation, angle of bend may varry according to site requirement

10 Mobilization / De-Mobilization, Equipment, Machinery, Tools, Manpower, Camping, utilities, etc required for completion of work.

11 Estalishment of camp at nearist suitable location for execution of work at site

12 Approval of client should be taken by the contractor before undertaking any kind of construction and installation work at site.