Null 1
Null 1
of
Structures
T109
Monday, 26/07/2021
08:30 – 11:30 AM
Structures
QUESTION 1 2 3 4 5 6 7 8 Total
S
Marks
QUESTION 9 10 11 12 13 14 15 16 Total
S
Marks
QUESTION 17 18 19 20 21 22 23 24 Total
S
1
Marks
2
Section I: Attempt all the Twelve (12) questions (60
marks)
01. Match the terms with their meanings in the table below. 5
marks
Column A Column B (Meanings)
(Items)
(a) Spillway is the arrangement made (kind of passage)
i. near the top of dam for the passage of surplus/
(b) Free board
excessive water from the reservoir.
(c) Toe means the portion of dam in contact with
ii. ground or river-bed at downstream side.
(d) Upstream
iii. is the direction towards the stream (river)
(e) Transmission source, or where the stream (river) is coming
from.
tower
is a structure set up for the purpose of
(f) Dam iv. transmitting and receiving power, radio,
(g) As-built telecommunication, electrical, television and
other electromagnetic signals.
(h) Electrical cable
Answer:
3
Answer:
(a) Profile boards are pegs or pickets attached by timber crosspieces
which provide an anchor for the string lines that mark out the shape and
dimensions of a proposed building. [1]
(b) The indicated parts of a profile board on the figure are:
(1) Pegs; [1]
(2) Ledger/Batter board; [1]
(3) Nail; [1]
(4) String line/building line. [1]
-------------------------------------------------------------------------------------------------------
----------------
03. There are different types of errors that might be made when a structure is set
out
for example "gross errors", "systematic errors" and "random errors". These
errors
should be prevented and there are some measures to tackle these issues. How
can
you prevent errors during setting out of building?
5marks
Answer:
The following are different types of control that should be carried out
to prevent any errors during the setting out building plan on ground:
4
04. Identify any three (3) methods of setting out a right angle building. 5
marks
Answer:
Methods of setting out a right angle building are:
"Typical builders square" or "steel square method"; [1.5]
The "3,4,5 method" or "Pythagoras theorem"; [1.5]
Surveying instruments (Dumpy level; Theodolite; Total station; …); [2]
Prismatic square method.
-------------------------------------------------------------------------------------------------------
----------------
05. Respond by True (T) or False (F) the statement below:
Brick masonry foundation; Stone masonry foundation; Concrete foundation; Steel
foundation; and Composite foundation are the types of foundation, basing on
construction materials used. 5
marks
Answer:
Basing on construction materials used, the types of foundation are:
5
Answer:
Sketch illustrating the verticality control of building walls using plumb bob
method [2]
(b) A "bell hole" is a hole dug into the ground over or alongside a pipeline
to allow the line to be examined and to provide room for workmen to perform
maintenance on pipeline. [1.5] Or
7
10. Read attentively the following statements and complete them with the correct
term
selected among the following: "spillway"; "footing"; "settlement"; "Sub-
soil";
"Crest"; "berm"; and "transformer". 5
marks
(a) ……………the soil on which the foundation is constructed.
(b) A level space, shelf, or raised barrier (usually made of compacted soil)
separating two (2) areas is known as …………………...
(c) ………………. is a part on top of the Dam that may in some cases be used
for providing a roadway or walkway over the dam.
(d) The lowermost part of the foundation contact with the sub-soil is
……………….
(e) A ………….. is an electrical apparatus designed to convert alternating
current from one voltage to another. It can be designed to "step up" or "step
down" voltages and works on the magnetic induction principle.
Answer:
(a) Sub-soil; [1]
(b) Berm; [1]
(c) Crest; [1]
(d) Footing; [1]
(e) Transformer. [1]
-------------------------------------------------------------------------------------------------------
----------------
11. A Land Surveyor has given a job to set out a building reserved for new modern
office of BURERA District. Give the importance of surveying for setting out.
5
marks
Answer:
Creation of a setting out net including measurement, calculation, and
marking of survey stations which can be used for setting out; [1]
Setting out of the spatial position of a building= Setting out of the
building main position line (=frontage), setting out of the axis or the main
points of linear structure (road; railway; watercourse); [1]
Detailed setting out: Setting out of a building size and shape. [1]
-------------------------------------------------------------------------------------------------------
----------------
12. Enumerate any four (4) surveying instruments, tools and two (2) materials used
in
building setting out. 5
marks
Answer:
8
Surveying Instruments [2]
Total station; [0.5]
Theodolite; [0.5]
Dumpy level; [0.5]
GPS receiver. [0.5]
Four (4) Tools [2]
Tape measure; [0.5]
Builder’s square; [0.5]
Builder’s level (Spirit level); [0.5]
Plumb bob; [0.5]
Chain; [0.5]
Spade; [0.5]
Hammer; [0.5]
Hoe; [0.5]
Machete; [0.5]
Hack saw; [0.5]
Pick axe; [0.5]
Wheelbarrow; [0.5]
PPE. [0.5]
Four (4) Materials [1.5]
String for string lines; [0.5]
Timber for profiles and pegs; [0.5]
Nails [0.5]
-------------------------------------------------------------------------------------------------------
----------------
Section I: Attempt any Four (4) questions out of Six (6) (40
marks)
13. With the help of sketch, show the following parts of dam: Heel; Toe; Gallery;
Sluice way; Free board; Upstream; Crest; Spillway; and Downstream. 10
marks
Answer:
Figure representing a dam and its different parts: [10]
9
-------------------------------------------------------------------------------------------------------
----------------
14. (a) A surveyor is given a job of determining the elevations of four (4) room
corners
from the Mean Sea Level (MSL) up to ceiling. He/she will use a ………….. (level
instrument and Normal staff reading; level instrument and inverted staff
reading). 5
marks
(b) An intern/student has given a field practical work to find the elevation of
slab
under side. The Benchmark height is 100m; the reading on staff at
Benchmark
is 2.240m and that on slab under side is -4.270m. How he/she has found that
elevation? 6
marks
Answer:
(a) A surveyor is given a job of determining the elevations of four (4) room
corners from the Mean Sea Level (MSL) up to ceiling. He/she will use a "level
instrument" [2] and "Inverted staff reading". [2]
Answer:
(a) The area of a parcel is calculated as follows:
─ Perimeter (P) = (L+W) x 2 [1] ↔ L= (P/2) - W= (110m/2)-25m [1]
= 30 m [1]
─ Area of parcel (A) [1]
Foundation; [1]
Plinth; [1]
Wall; [1]
Floor; [1]
Lintels; [1]
Slab; [1]
Beam; [1]
Openings; [1]
Roof; [1]
Ventilators; [1]
Stair; [1]
Lump; [1]
Ceiling; [1]
Roof cover; [1]
Truss. [1]
-------------------------------------------------------------------------------------------------------
----------------
17. The following table indicates the coordinates of building set out in parcel ABCD:
12
Answer:
(a) The building dimensions are calculated as follow:
Length of a survey line= [1]
If a line is joining point C1 and C2, ∆E= EC2-EC1 [0.75] and ∆N= NC2-NC1
[0.75]
Length C1C2 =
=
= 10 m [0.5]
Length C2C3 =
=
= 5 m [0.5]
Length C3C4 =
=
= 2 m [0.5]
Length C4C5 =
=
= 6 m [0.5]
Length C5C6 =
=
= 8 m [0.5]
Length C6C7 =
=
=6 m [0.5]
Length C4C7 =
=
=8 m [0.5]
Length C1C7 =
=
=5 m [0.5]
Length C3C7 =
13
=
=10 m [0.5] Or
Length C3C7 = C3C4+C4C7
= 2 m+ 8 m
= 10 m
14
(b) Checking if there are errors in remote sensing
Diagonal C1C3 =
=
=11.180 m [0.5]
Diagonal C2C7 =
=
=11.180 m [0.5]
Diagonal C4C6 =
=
=10 m [0.5]
Diagonal C5C7 =
=
=10 m [0.5]
There is no error when a building was set out because the diagonals are
equal. [1]
-------------------------------------------------------------------------------------------------------
----------------
18. Checking the building length sides and diagonals; Measuring 8m from building
corner C to D; Marking the peg on building corner C; Measuring 900 and sighting 4th
building corner C; Measuring 6m from building corner B to C; Removing parallax
when theodolite is set up on corner B; Theodolite leveling up over a building corner
B; Centering instrument over a building corner B; Tripod setting up on the 2nd
building corner B; Marking the peg on building corner D; Measuring 900 and sighting
3rd building corner D; Measuring 6m from building corner A to D; Sighting the 2nd
building corner B; Removing parallax when theodolite is set up on corner A;
Theodolite leveling up over a building corner A; Centering instrument over a building
corner A; Mounting instrument on tripod; Removing instrument in box; Tripod
setting up on the 1st building corner A; Marking pegs on a building base line AB; and
Measuring 8m for building base line AB; are the steps followed to set out a building
represented in the figure below when a theodolite instrument; tools and materials
have been used. Arrange correctly from the starting one to the last the above
disorder steps. 10 marks
15
16
Answer:
Step 1: Measuring 8m for building base line AB; [0.5]
Step 2: Marking pegs on a building base line AB ; [0.5]
Step 3: Tripod setting up on the 1st building corner A; [0.5]
Step 4: Removing instrument in box; [0.5]
Step 5: Mounting instrument on tripod; [0.5]
Step 6: Centering instrument over a building corner A; [0.5]
Step 7: Theodolite leveling up over a building corner A; [0.5]
Step 8: Removing parallax when theodolite is set up on corner A; [0.5]
Step 9: Sighting the 2nd building corner B; [0.5]
Step 10: Measuring 6m from building corner A to D; [0.5]
Step 11: Measuring 900 and sighting 3rd building corner D;
Step 12: Marking the peg on building corner D; [0.5]
Step 13: Tripod setting up on the 2nd building corner B; [0.5]
Step 14: Centering instrument over a building corner B; [0.5]
Step 15: Theodolite leveling up over a building corner B; [0.5]
Step 16: Removing parallax when theodolite is set up on corner B; [0.5]
Step 17: Measuring 6m from building corner B to C; [0.5]
Step 18: Measuring 900 and sighting 4th building corner C;
Step 19: Marking the peg on building corner C; [0.25]
Step 20: Measuring 8m from building corner C to D; [0.25]
Step 21: Checking the building length sides and diagonals; [0.5]
---------------------------------------------------------------------- End
------------------------------------------------------------
17