Risk Assessment For Top 5 High Risk Works
Risk Assessment For Top 5 High Risk Works
(Physical, Chemical, Risk Level before Mitigate (H,S,M,L) Control Statement Risk Level after Mitigate
JOB STEP Biological, Potential Event
Psychological, L S R E L S R E
Job Description: Critical Works M/E
1. Lifting or Laying Material - Ensure crane capacity is suitable for the lifting of the material
(Using Crane & TMC) - Ensure the length of the boom is suitable with working distance and radius of
Material and
Crane collapses 3 5 15 High Risk the material’s location. 1 4 4 Medium Risk
Equipment Damage
- Preparing Lifting Plan
- Ensure that Operator and rigger has a valid license (Kemnaker)
- Ensure wire slings, shackles and crane are in good condition before use
Workers are hit by objects - Ensure wire slings, shackles and crane meets lifting capacity.
Sling disconnected lifted/head 3 5 15 High Risk - Ensure no one gets close to the working radius of the crane during lifting. 1 5 5 Medium Risk
Injury/scratches/fracture - Barricade the working area
- use Tagline instead of hands for directing the load
- Make sure crane capacity is suitable for the lifting of the test material.
- Make sure the length of the boom is suitable with the working distance and
radius of the material’s location.
- Ensure no one gets close to the working radius of the crane during lifting.
Workers pinched by
material failing 3 5 15 High Risk - Rigger must be in the safe working distance. 1 5 5 Medium Risk
material/injury/fracture
- Ensure workers keep safe working distance.
- material lashing should be fastened properly
- Barricade the working area
- Use Tagline instead of hands for directing the load
2. Installation Equipment
(Using electrical tools) - Ensure the tools used have been inspected, evidenced by sticker
- Ensure the tool is checked properly before use
- The power cable has been carefully checked, nothing is chipped
- Turn off the machine when the work is finished /after use
- Ensure cable must be elevated and secured on insulated S-hooks so cable are
Electrical power Electric shocked 3 5 15 High Risk 2 2 4 Medium Risk
caught in the water
- Ensure workers understand the correct way to use handtools
- Ensure distribution panel supplying power to the tools must be equipped with
an ELCB and must be grounded
- Use appropriate PPE
(Physical, Chemical, Risk Level before Mitigate (H,S,M,L) Control Statement Risk Level after Mitigate
JOB STEP Biological, Potential Event
Psychological, L S R E L S R E
- Ensure job rotation have been implementation
- Give a momentary pause while work is in progress.
4 2 8 Medium Risk - Provide sign / safety campaign 1 2 2 Low Risk
- Ensure worker are appropriate PPE (Earplug or earmuff)
Exposure of noise Hearing loss
- Inspect tools for any damage prior to each use. Check the handle & body
casing of the tools for cracks/another.
- Do not use drill or grinder above shoulder height or below knee level or in-
between legs. Never use an angle drill overhead.
- Drill Operator shall not wear loose clothing or jewelry. Ensure Long hair tied
back as appropriate for entanglement hazards control
-The RPM rating of the abrasive wheel/disc must not be lower than that of the
- Drill or Grinder can
machine
Motion (Drill, cutting disintegrate
3 5 15 High Risk - Ensure Portable Grinding and drill machine are fixed with guard, dead-man 2 3 6 Medium Risk
wheel, and grinder) - Injury
switch, cutting/grinding disc in good condition, handles as supplied by
- Activity stopped
manufacturer and never modify in any case
- Do not attempt to make an excessive depth of cut. Overstressing.The disc
increases the loading & susceptibility to twisting/binding of the disc in the cut &
the possibility of kickback or breakage.
- Make sure worker use correct PPE before work like gloves, safety goggles,
mask -, facshield, earplug.
4. Working at Heigh
( Using boomlift, Ladder or - Ensure all permit to work was approved
Scaffolding) - Scaffolder must be certified. and hae been inspected (green tag). Ensure
stable ground for the installation of scaffoldings or ladder.
- Ensure load on ladder and scaffolding are secure & evenly distributed. Do not
Scaffolding or ladder - Injury / LTI exceed manufacturer’s rated capacity.
- Activity Stop 2 4 8 Medium Risk 1 3 3 Low Risk
collapse - Property Damage
- Top 2 rungs not allowed to be used
- Makesure 2 workers hold a ladder for buddy system
- Ladder shall be not travelled when in working positions with personnel in the
working platform
- Ensure 100% tie off always while working at height.
4. Working at Heigh
( Using boomlift, Ladder or
Scaffolding)
(Physical, Chemical, Risk Level before Mitigate (H,S,M,L) Control Statement Risk Level after Mitigate
JOB STEP Biological, Potential Event
Psychological, L S R E L S R E
Likelihood (capability of frequency and avoidance): 1 = Rare; 2 = Remote; 3 = Occassional; 4 = Frequent; 5 = Almost Certain
Risk Assessment : Severity (severity of result, seriousness of accident): 1 = Negligible; 2 = Minor; 3 = Moderate; 4 = Major; 5 = Catastrophic
Risk Level = Likelihood × Severity = 1~25