July, 2020
ADOLA WOYU, ETHIOPIA
Adola Woyu Town Asset Management Plan
Adola Woyu Town Asset Management Plan
Table of Contents
List of Tables..................................................................................................................................v
List of Figures................................................................................................................................v
Executive Summary......................................................................................................................vi
Structure of the Asset Management Plan.................................................................................viii
1. Introduction............................................................................................................................1
1.1 Background Information of the Town..........................................................................................1
1.2 Topography of the town................................................................................................................2
1.3 Public Infrastructure Condition of the town.................................................................................4
1.4 Asset Management Plan (AMP)...................................................................................................6
1.5 Objective of the Asset Management Plan.....................................................................................9
1.5.1 General objective...................................................................................................................9
1.5.2 Specific Objectives for Asset Management Plan...................................................................9
1.6 Scope of the Asset Management Plan.........................................................................................10
1.6.1 Spatial Scope.......................................................................................................................10
1.6.2 Thematic Scope...................................................................................................................10
Step 1: Build the GIS Project and the Data Management Structure Creating.....................11
1.2Establishing of a GIS Project............................................................................................................12
a. The difference between Data and Information...............................................................................12
b. Defining the relationship between Spatial and Attribute Data.......................................................13
The Backdrop Image of the AMP..........................................................................................................13
c. The Geo-Database Structure...........................................................................................................14
d. Creating Tabular Database Structure..............................................................................................17
e. The Computer Directory Management Structure...........................................................................19
Step 2: Build the institutional framework and the asset management structure....................1
2.1 Situating the AMP within the town administration...........................................................................1
a. 2.2 Organization of the Team...........................................................................................................2
2.3.Overall Responsibility of the asset management plan unit................................................................3
2.4 Departmental responsible for the AMP in each asset category........................................................4
i|Page
Adola Woyu Town Asset Management Plan
List of Tables
List of Figures
FIGURE 1: LOCATION MAP OF ADOLA WOYU TOWN...................................................................................2
FIGURE 2: SHAPE AND SLOPE CLASSES OF ADOLA WOYU TOWN............................................................4
FIGURE 2: THE BACKDROP IMAGE (ORTHOPHOTO) OF ADOLA WOYU TOWN....................................14
FIGURE 3: ADOLA WOYU AMP GEODATABASE DESIGNED IN ARCGIS 10.1SOFTWARE....................15
FIGURE 4: EXAMPLE OF ATTRIBUTE DOMAIN AND SUBTYPE FOR ADOLA WOYU AMP GEO-
DATABASE.....................................................................................................................................................16
FIGURE 5: RELATIONAL DIAGRAM OF THE ATTRIBUTE DATABASES USED FOR THE AMP............18
FIGURE 5: PROPOSED ORGANIZATIONAL FRAMEWORK.............................................................................2
FIGURE 7: STORING MULTIPLE SETS OF ATTRIBUTES FOR A FEATURE PERFORMED USING
LINEAR REFERENCING...............................................................................................................................12
FIGURE 8: EVENT FEATURE MAP OF TABLE OF ROAD ASSET DONE BY THE INFRASTRUCTURE
DEPARTMENT OF ADOLA WOYU TOWN...............................................................................................14
FIGURE 6: DATA COLLECTION AND SUPERVISION CYCLE.......................................................................18
FIGURE 7: COVERAGE OF ROAD NETWORK BY SURFACE MATERIAL..................................................25
FIGURE 8: STREET LIGHT INSTALLATION AND TYPE OF POLE................................................................28
FIGURE 9 : DRAINAGE LINE BY SURFACE MATERIAL COVERAGE.........................................................30
FIGURE 10: PARTIAL VIEW OF INFORMAL SOLID WASTE DUMPING SITE...........................................31
FIGURE 11: CONDITION OF ALL ROADS BY SURFACE FINISHES.............................................................39
FIGURE 12: CONDITION OF DRAINAGE LINE BY SURFACE FINISH MATERIAL...................................42
FIGURE 13: PROPORTION OF MAINTENANCE DEFICIT OF ROAD SURFACING.....................................53
FIGURE 14: PROPORTION OF DRAINAGE MAINTENANCE DEFICIT BY MATERIAL.............................59
FIGURE 15: CONTRIBUTION OF STRATEGIC ACTIVITY AREAS FOR THE TOWN ASSET VALUE......66
v|Page
Adola Woyu Town Asset Management Plan
Executive Summary
Effective systems of Asset Management Plan (AMP) can strengthen the performance of a local economy
and community services significantly. Adola Woyu town administration council is responsible for the
management, operation and maintenance of the town infrastructure and basic municipal assets that
provides services to the community. This Asset Management Plan has been developed to ensure that the
Adola Woyu town administration continues to provide effective and comprehensive management of
municipal service and infrastructure assets.
The development of the Asset Management Plan follows the ten-step methodology defined in the
updated Asset Management Plan manual which is prepared by Ministry of Urban Development and
Housing. Accordingly, The UIIDP team and AMP focal person identified and defined four strategic
activity areas and main asset classes to be covered in this AMP study and for which a precise report was
submitted to the town administration in the inception report. Thus strategic activity areas are identified
and presented in the Terms of Reference (ToR) and detailed asset lists are presented in section 3.7 in this
AMP document.
In general, this Asset Management Plan provides the Adola Woyu town administration with the
following important information about its infrastructure and municipal service assets:
A proposed list of categories and sub-categories of the town assets.
A framework, system and the asset management structure for the geo-spatial data associated with
the infrastructure assets.
A complete infrastructure and municipal service asset inventory.
A framework for building and maintaining a condition indicator for existing assets.
A framework and structure for developing the maintenance and rehabilitation budget for each
assets, together with a breakdown of current maintenance and rehabilitation needs.
A detailed list of the Current Replacement Cost, Depreciated Replacement Cost, Current Value
and Asset Deficit of all inventoried assets.
A strategic analysis of the needs emerging from the completion of the first six steps of the AMP
and detailed recommendations for future development of existing and new infrastructure assets.
An implementation strategy for the asset management plan.
vi | P a g e
Adola Woyu Town Asset Management Plan
Section 1: Introduction
This is an introductory part which includes background information of Adola Woyu town, existing
public infrastructure condition of the town, Definition of Asset Management Plan, key benefits and
Principles of AMP, Objectives and scope of the Asset Management Plan.
Section 3: The Institutional Framework and the Asset Management Structure (Step 2)
This section explores the institutional framework for Asset Management and a comprehensive, integrated,
structure for managing the town. This step begins by looking at the institutional role of the AMP within
city. This includes defining the location of the AMP team in the administrative structure; looking at the
staffing and qualifications of the AMP focal person. The list of categories has been set out to incorporate
new assets into the AMP process.
vii | P a g e
Adola Woyu Town Asset Management Plan
The section discusses the issue of condition indicators, focusing on assets which require different
approaches to the analysis of infrastructure and municipal service asset condition. It then sets out a
proposal for defining the condition of all asset categories.
Section 7: The Replacement Cost and Existing Value of Asset Base (Step 6)
This section provides a summary of the current replacement cost of the town administration asset base.
In this step of the AMP process a list of unit rates are created for new works, and use this to assess the
current replacement cost, and the depreciated replacement cost (i.e. current value), asset deficit of all
municipal infrastructure assets owned by the town administration.
Section 8: Cost, and Prioritize, New Works Projects within the CIP Process (Step 7)
The section sets out the proposals for new capital investment over the next three-year period and by
working with the CIP team prioritise the new work projects. The tasks in this step comprises; Estimates
the project cost for the proposed new works using the list of unit costs created in step 6 and provide a
summary of all new works project proposals, broken down by asset subcategories.
Section 10: The 3-year Rolling Program for New Works and Maintenance Projects
This deals with Step-9 of the AMP, which takes the outcome of Section 7 & 8 and converts the budget for
approved new works, and the maintenance projects proposals into the 3-year rolling program.
Section 11: Manage the Transition of Completed New Works Projects & Maintenance
Activities across To the Existing Assets (Step 10)
viii | P a g e
Adola Woyu Town Asset Management Plan
Step 10 is extremely important, and critical to the ongoing success of the AMP process. This step deals
with the system of tracking the progress of all new works, through construction, to become part of the
existing asset base in the step 3 of the AMP and Modification of step 4 of the AMP to reflect the
updated status of completed maintenance projects.
ix | P a g e
Adola Woyu Town Asset
Management Plan
1. Introduction
Adola Woyu town is located in Guji Zone of the Oromia National Regional State at a
distance of about 470 km from Addis Ababa and 120km from the zone capital city of Nagele
town. The absolute location of the town is 5 0 53’00”N and 38059’00”E. It is entirely engulfed
with peasant association of Dole in the North and North East, Derartu in the North East,
Adamma Dhiba in the east, Gobicha in the south and south west and Bilu in the west.The
existing area under the town administration is 2824.9 hectares.
The shape of the town is more compact although there is sort of star shaped development
along the transport routes to Hawassa, Negelle.The relief of Adola Woyu town is not a
hindrance for infrastructure development. This is because of suitable topography except few
areas that have rugged topography. Elevation of the town ranges from 1696 to 1760 meters.
The average annual rainfall is from 1800 to 2200 mm.
According to the population and housing census conducted in 2007, the town total population
is estimated to be 31,755. Out of this 51% of the populations are males and the remaining
49% of the populations are females. The town was established and administered as a
municipality in 1936 E.C and leveled as categories ‘medium or B’ towns of the Oromia
Region and a mayor is appointed to govern the town Administration.
Some of the duties and responsibilities of the city administration includes:
1|Page
Adola Woyu Town Asset
Management Plan
The shape of the town is more compact although there is a sort of star shaped development
along the transport routes to Hawassa, Negelle, Shakiso and Harefema. This implies that
there are large vacant spaces in the interior of the town to any direction. Vacant spaces that
are located in different parts of the town should be utilized by infilling methods to have
compact development in the town.
2|Page
Adola Woyu Town Asset
Management Plan
The elevation of Adola Woyu town ranges from 1696 to 1760 meters. This implies that there
is small altitudinal variation (64 meters) between the lowest and highest points of the town
from where flush water originates affecting areas with low elevation.
The classification of the slope of the town is vital to determine the different land uses in the
town. The slope found within the town cannot be hindrance for the development of any land
uses with exception to areas with slope above 25%.
The average annual temperature of the town is 19 0C with lowest mean minimum in
November, December and January. During this time, the mean monthly temperature is 18.5 0C
for the years from 2004 to 2017.
AdolaWoyu town is characterized by bimodal type of rainfall with mean annual rainfall of
86.4mm. It occurs during autumn and spring.
The soil of Adola Woyu ranges from reddish brown to grey. It is deep soil and loose with
small clayey character. Therefore, the soil is good for the growth of different types of root
crops like sweet potatoes and cash crops like coffee and chat should be cultivated if water for
irrigation is available.
Natural vegetation of any area is the result of climate, soil, topography and human influence.
The different vegetation types of the town include podo carpus, junipers, acacia, olea,
avocado, mango and other artificial trees like eucalyptus are common because of the agro-
climatic condition of the town.
3|Page
Adola Woyu Town Asset
Management Plan
Until 2015 G.C the main sources of potable water for the population of the town are the two
bore holes dug within the boundary of the town located at the back of currently functioning
lavajo and near Oda Adola School. Besides there is a third bore hole found within the
boundary of the town .Because of the Shakiso-Adola water project completion the water
4|Page
Adola Woyu Town Asset
Management Plan
coverage of the town increased to 61 % with the client of 3000 in Adola town. At the same
time the daily water consumption of a town reached about 1260-1300 m 3 /day. The Adola
Shakiso water project designed for 20 years. the production capacity of the a dam is 116
m3/hrs and daily water provision service is for 18 hours. At present day there is enough
supply of water for 24 hrs.
c) Bus station
There is a bus station in Adola Woyu town at central, accessible and compatible location.
But, the existing bus station of the town is small in size compared to the number of vehicles
departing from and destined to the bus station.
d) General market
The general market in the town is on Saturday and Tuesday. The area of the general market is
about 2.7 hectares which can accommodate all commercial activities on the market days. It is
located at accessible, central and compatible location. The cattle market is found in a
compatible and accessible location. The market is also located in the direction of major cattle
flow direction that is usually from south, north and west direction
e) Abattoir
There is abattoir service in the town. However, the existing location of abattoir is
incompatible due to its location compared to the surrounding land uses. The topography of
the existing abattoir logs water during the rainy season. It also located between two seasonal
streams, which can have potential to flood the area. There is small impact of air pollution to
the surrounding areas because the wind direction to the surrounding uphill westward.
5|Page
Adola Woyu Town Asset
Management Plan
f) Waste disposal
There is no formal liquid and solid waste disposal site in Adola Woyu town. But there are
two informal sites for this purpose. However, Generation of both liquid and solid wastes in
the town needed to prepare for another waste disposal site according to the town plan.
g) Educational services
The town has Four (4) Kindergartens which are owned by private. The- town administration
doesn’t run pre-school program. In 2012, primary level schools are being provided by eight
(8) of which seven (7) are owned by the government while the remaining one (1) school is
privately owned. Adola Woyu town has 2(Two) secondary and one (1) preparatory schools.
The town also has government owned TVET college and TTC colleges. There are also 2
private colleges which train TVET programs.
h) Health Institution
According to data from Adola health office in 2018, there are two (2) high level health
institutions of which one is Hospital and the remaining one (1) is health center. On the other
side, the town has seventeen (17) private owned clinics.
Asset Management has been a key component of the Federal Government’s Urban Growth
and Development Strategy since its inception in 2008. It was a pre-requisite to the ULGDP
capacity building program that ran from 2008-2013, which in turn was part of the
government’s Plan for Accelerated and Sustained Development to End Poverty (PASDEP
6|Page
Adola Woyu Town Asset
Management Plan
2005/06-2009/10). This key role has been retained under ULGDP II, which is designed to run
from 2014-2019, and as such it has been supporting the government’s Growth and
Transformation Plans. The specific development objective of the ULGDP II is to bring about
improved performance in the planning, delivery and sustained provision of priority municipal
services and infrastructure development by urban local governments. In this respect, the
ability to create and operate an Asset Management Plan is central to both of these outcomes.
While the Asset Management Plan plays a critical role in supporting wider development
objectives, it also plays a role in a local political, economic and social context within the
cities themselves. Urban Infrastructure is expensive to construct and also expensive to
maintain. This makes it important to ensure that the solutions provided are cost effective, as
well as meeting the needs of the urban population. Asset Management provides an integrative
approach that links project-based capital investment planning with long-term operation and
maintenance needs and thereby provides a sustainable management system.
The integrated Asset Management Plan will incorporate any existing preventative
maintenance and risk management programs currently in place. The preventative
maintenance component will ensure that the day-to-day wear and tear of an asset is dealt with
to ensure that the asset can reach its expected useful life. Condition assessment and risk
management components ensure that The City Administration effectively manage the risk of
failure through due diligence. Good asset management results in informed and strategically
sound decisions that optimize investments, better manage risks, and take into account the
potential impact of other factors such as climate change. Through the implementation of an
integrated Asset Management Plan, the city can formalize the process of Asset Management
Planning. Through formalization of Asset Management Planning, the City can ensure it is
making the best possible decisions regarding the construction, operations, maintenance,
renewal, replacement, and disposal of all infrastructure assets. This will allow the City to
maximize the benefits, manage risks, and provide satisfactory level of services to the public
in a sustainable manner.
In summary, an Asset Management Plan provides cities with a detailed knowledge of their
asset base. It plays a critical role in empowering the city leadership that enables them to make
more effective strategic investment decisions; and it also empowers residents, by showing
them where the existing infrastructure is situated, and where new infrastructures can be
7|Page
Adola Woyu Town Asset
Management Plan
provided. In this way, the Asset Management Plan is the basic building block of urban
development.
8|Page
Adola Woyu Town Asset
Management Plan
2. Where is it?
3. What is its condition?
4. How much is it worth?
5. How much money needs to be spent on for maintenances?
6. How does the keep this information available for easy access in the future?
Moreover, a good Asset Management Plan should address the following questions:
1. Does the planned infrastructure address the strategic goals and objectives of the
City?
2. How much will it cost to build and maintain?
3. How will new infrastructure be prioritized to ensure that spending is matched with,
and balanced against, available income?
4. How do we program the construction of new infrastructure?
9|Page
Adola Woyu Town Asset
Management Plan
The overall scope of this assignment was to undertake study and prepare standard asset
management plan for the Adola Woyu town by registering and analyzing the existing
condition of all assets of the town administration based on the recently revised asset
management plan manual prepared by the Ministry of Urban Development and Housing.
Accordingly, the spatial and thematic scopes were stated as follows:
There are four major drivers of social and economic development embedded in the city’s
asset base covered by the AMP. These are:
The movement network.
The water supply network.
Environment services.
Social and economic services.
10 | P a g e
Adola Woyu Town Asset
Management Plan
Adola Woyu town is located in Guji Zone of the Oromia National Regional State
at a distance of about 470 km from Addis Ababa and 120km from the zone capital
city of Nagele town. The absolute location of the town is 50 53’00”N and
38059’00”E. It is entirely engulfed with peasant association of Dole in the North
and North East, Derartu in the North East, Adamma Dhiba in the east, Gobicha in
the south and south west and Bilu in the west.The existing area under the town
administration is 2824.9 hectares.
The shape of the town is more compact although there is sort of star shaped
development along the transport routes to Hawassa, Negelle.The relief of Adola
Woyu town is not a hindrance for infrastructure development. This is because of
suitable topography except few areas that have rugged topography. Elevation of
the town ranges from 1696 to 1760 meters. The average annual rainfall is from
1800 to 2200 mm.
This updated manual uses a Geographical Information System as the platform for
managing spatial data. There is a very good reason for making this choice, which
is summed up by the following explanation, namely that: “The use of spatial
11 | P a g e
Adola Woyu Town Asset
Management Plan
relational terms requires the selection of a reference frame and the construction of
a spatial template”; What this statement means is that, to build relationships
between spatial data, two shared components are required.
The first component (the reference frame) is a common (shared) spatial
referencing system, so that when a junction in a road (for example) is given a
coordinate, that coordinate is common to, and understood by all users of the
system. In Geographic Information System, there are two major coordinate
systems: that is; Geographic Coordinate System and Projected Coordinate System.
To describe it briefly the former (Geographic Coordinate System) is based on
three-dimension coordinate system (x, y and z) or Latitude, Longitude and
Elevation that is modelled in mathematical geometry which define the shape of the
Earth in a circle and more specifically modelling the Earth is a sphere. However,
the limitation with the Geographic Coordinate System is not suitable for area and
distance calculation since it is based in degree, minute and second or degree, grad
and radian.
Therefore, Geodesist`s have defined a datum based on a perfect ellipsoid for
countries to have different spatial reference system by projecting the three-
dimensional coordinate in to two dimension as done by Transverse Mercator who
is an American Mathematician and Geographer who developed the Universal
Transverse Mercator(UTM) projection by putting the Earth in a cylinder.
Accordingly, Ethiopia uses Adindan datum for a spatial reference for horizontal
measurement which fall in three Universal Transverse Mercator (UTM) projection
consists of (36, 37 and 38 UTM zones) with Clarke 1880 modified spheroid.
The two terms - data and information - are often used interchangeably. However, they are
quite distinct, and, since both are critical components of GIS, it is important to be clear about
the difference between them.
1) The term ‘data’ refers to raw facts. So, collecting facts about the road network, such
as the start and end points, length, width, material of surface finish and so on, is
12 | P a g e
Adola Woyu Town Asset
Management Plan
Data is stored in tables known as databases, and a blank table that provides a pre-defined list
of columns that define the data to be collected is known as a template. The relationship for
defining spatial data versus attribute data depends up on the technology that we apply for
preparing Asset Management Plan. Geographic Information System (GIS) provides better
platform for storing attribute data while the spatial data displayed as graphics in the display in
the drawing window of a specific GIS software. Geographic Information System is working
in Relational Database Management System with various sequential query languages.
In short spatial data in Infrastructure Asset Inventory and Management Plan is the road centre
line, drainage line, pedestrian walkway and road median which are represented in polyline in
feature geometry in GIS while the attribute data is the route id, node id, width of the road,
surface material, deterioration type, condition assessment and year of construction that will
be collected from the field survey in a city
The back drop image is an important component of the Infrastructure Asset Inventory and
Management Plan in which the vector layers or spatial templates or feature classes are
digitized from this georeferenced Ortho photo or Satellite Imagery. Contemporarily high
resolution Satellite Imagery Acquisition companies in the World are Geo-EYE, Digital
Globe, SKYSAT and SPOT PLEIADES. The first three belong to the United States of
America while the last one belong to France.
The other important option for a backdrop image for the AMP is high resolution Ortho Photo
in which high resolution Photo Camera will be mounted on an Air Plane and takes Aerial
View Shots of a place. These Snap shots of aerial picture of a place will be processed in
photogrammetry soft wares with a super computer or work station. Currently, the Information
13 | P a g e
Adola Woyu Town Asset
Management Plan
Network Security Agency (INSA) is mandated to perform this task in Ethiopia. Accordingly,
the Ministry of Urban Development and Housing (MUDH) in collaboration with INSA and
the Ethiopian Mapping Agency have captured Ortho Photo of 44% of the country’s coverage.
But Adola Woyu is used geo-referencing image which generate from Google Earth
I. Personal Geo-database
II. File Geo-database
III. ArcSDE Geo-database
14 | P a g e
Adola Woyu Town Asset
Management Plan
The Adola Woyu AMP geodatabase is designed in File Geo-database which has a Tera byte
memory which allow various raster and vector data to be stored within it.
15 | P a g e
Adola Woyu Town Asset
Management Plan
Besides, a person can easily manage data entry by choosing from the look up table instead of
consuming time for entering value just by writing; which obviously is different from one
person to another. For instance, if the data is not organized according to the aforementioned
approach of geo-database in uncontrolled manner, one person may write mistakenly
“concrete road” as ‘concrete road’, the others ‘concrete’ and so on, which makes difficult
the integrity of data for generating refined report on asset management plan. In conclusion,
the organization of data as mentioned above makes data entry to be simple as one can easily
choose the values from the already set look up table; even without having user interface
system.
The other advantage of attribute domain is sharing of the same attribute by different feature
class. For instance, the general condition assessment of all asset categories is modeled
(coded) as:1(Very Good), 2(Good), 3(Moderate),4(Poor) and 5(Severe) that is shared from
the geo-database by all feature class of Road, Walkways, Drainage, Land Sliding Retaining
and Flood Controlling Wall to describe the condition of the given infrastructure asset.
So, the attribute domain enforces data integrity by maintaining common values to share same
information that can be performed by different persons and different attributes of different
feature class to share the same attribute so as to realize consistency, validity and integrity of
data.
Figure 5: Example of Attribute Domain and Subtype for ADOLA WOYU AMP geo-database
16 | P a g e
Adola Woyu Town Asset
Management Plan
A tabular database has been compiled for an infrastructure asset categories and sub-
categories. The road is classified in to Asphalt Road, Cobble Road, Gravel Road, Red Ash
Road, Large Block Stone, Earth Pressed Road, Natural Earthen road, Concrete Bridge and
Culvert were classified by road surface material. A specific sub-category of the asset, say
asphalt road, consists of many fields or attributes such as carriage width in meter, left and
right carriage way Kerbing material and width, date of construction, road condition and so
on. The route is also divided along section of road in to a number of discrete sections for ease
of maintenance and quality definition for road, walkways, drainage and street signpost.
Similarly, for water distribution line, the main subset of the distribution line is categorized in
to DCI, GS, HDPE and PVC by material type. The same is true for point data like Street light
where the left and right side point data is captured including attributes of street light type
(Incandescent, Florescent, High Pressure Magnesium Light, High Pressure Sodium Light and
Light Emitting Diode) using hand held GPS.
A similar situation would apply to the linear elements of the water supply category. So, for
example, using the sub-category of water, steel distribution mains, and a similar set of
variations would apply, defining different elements (segments) of the sub-category by length,
class and diameter.
17 | P a g e
Adola Woyu Town Asset
Management Plan
For further elaboration of the approach for tabular database template pursuant to operational
manual, two examples are provided. The first one let us take a linear element of Road, its
category is Road and Movement Network, its sub-category is Cobble or Small Block Paved
Road, element is described by defining two node points (Node from, Node to), one defining
the start while the other defining the end respectively. The route is uniquely identified by
Route id. In the same manner, let us take a point element of pump, its category is Water
Supply Network, its sub-category is pump, its specific geographic location is identified by x,
y coordinates and described according to pipe material, dimension, discharge amount, year
installed and so on. The element is identified by unique number.
The spatial and non-spatial databases are linked with unique id, which makes the integration
versatile to accommodate data within the same geo-database system. More indicators are
developed for infrastructure asset management plan based on the operational manual and
tailoring variables to the context of Adola Woyu Town. The following table depicted below
shows sample road network and drainage tabular database templates used for Adola Woyu
Town Asset Inventory and management plan.
Table 1: Example of Tabular Database for Road Network Category and Sub-Category
Field Name Data Type Description of the Field Name
Route ID Text Route Identification Number
Node From Text Node From
Node To Text Node To
Length From Double Length From
Length To Double Length To
RoadMat Text Road Material
Length Double Actual Length in Metre
Deterioration Type Text Type of Deterioration
Deterioration Area Double Deterioration Area in m2
Condition Text Condition Assessment
Carriageway Width Double Carriage Width
CarraiageWayType Text Carriage Way Type
Kerbing Material Left Text Kerbing Material Left
Kerbing Left Width Double Kerbing Left Width in Centimetre
Kerbing Material Right Text Kerbing Material Right
Kerbing Right Width Double Kerbing Left Right in Centimetre
Construction Year Long Integer Date/Year Construction
Maintenance Year Long Integer Maintenance Year
Ownership Text Ownership of Road
The overall database structure of this AMP is established in the following form (adopted from
the manual). Thus, the spatial dataset (as a whole) holds the central place connected with all
the required Tabular Data Sets (TDS) of assets.
TDS1: is dataset that provides data on the physical condition of all assets;
TDS 2: is data set that provides data on the assets cost and value;
18 | P a g e
Adola Woyu Town Asset
Management Plan
Figure 6: Relational diagram of the attribute databases used for the AMP
The AMP computer directory management system of Adola Woyu Towny has been prepared
maintenance requirements and maintenance planning). These have been arranged in an
integrated form (Folders, Geo-database, Feature Dataset, Feature Classes, and tables for
viewing, manipulating, updating and analyzing spatial data. Besides, the directory also
contains Microsoft Word format report, and Ortho photo of the Town.
The other important technology selection for this project is choice of the appropriate
software. Arc Info ArcGIS 10.4.1 has been selected by the World Bank for Infrastructure
Asset Inventory and Management Plan as an ideal software for the preparation of Adola
Woyu AMP. This software is the product of Environmental Systems Research Institute
(ESRI, 2015 Redlands California USA) which are the most powerful GIS software for
entertaining large database which are compatible in any database soft wares like SQL Server
or Oracle and programming languages like C#, VB.Net, Python, and Java.
Desktop ArcGIS 10.1.1 has a number of extensions for instance Linear Referencing, Spatial
Analyst, Network Analyst, 3D Analyst, etc.…from the available extensions, Linear
Referencing, Network Analyst and Spatial Analysis will be chosen to perform the Asset
Management Plan study of the city. The details of these extensions are discussed in the
following sectio
19 | P a g e
Step 2: Build the institutional framework and the asset management
structure
The Asset Management Plan plays a key role in the City Administration. Adequate institutional
capacity for proper infrastructure delivery particularly for successful implementation of asset
management plan should consider as precondition.
The institutional framework for managing infrastructure and municipal services in Adola Woyu town
is formulated around the position of an Executive Mayor, and supported by a Cabinet. This Cabinet
comprises the Mayor, the Heads of the Bureaus of the town and other officials selected by the Mayor.
This system essentially divides the responsibilities between the Bureaus on the one side and, on the
other side, a City Manager, who reports to the Mayor. The role of the City Manager, who also has a
Deputy, is to manage the operational units that are responsible for the major municipal services and
infrastructure.
The existing staffing condition which takes overall responsibility for infrastructure development and
Assetmanagement plan in Adola Woyu town is not well organized and equipped when comparing
with the workload that will demanded.
As stipulated in Urban Infrastructure Asset Management Plan manual, the responsibility for
managing the asset management register should be an independent group/unit within the City
Administration, i.e. it should not fall under an existing department. Given the critical importance of
the asset management plan to the capital investment program, the head of this unit should be a senior
person who will work in close cooperation with the City Manager and the Mayor.
Given the critical importance of the asset management plan to the capital investment program, Adola
Woyu town administration has made a lot to build the implementation capacity of these departments
with materials and manpower. In addition to this, the city has established a department called UIIDP
coordination office which is equipped with Materials and technical staff, which is also responsible for
building and maintaining the Asset Management Plan for infrastructure.
1|Page
Adola Woyu Town Asset Management Plan
City Council
City Mayor
City Manager
UIIDP Coordinator
For the preparation of this Asset Inventory, the City Service of ADOLA WOYU has been established
under the CIP team. In connection with the relevant offices like Water Supply Service Office,
Infrastructure Development Process (Municipal Offices) has been giving input to the team. Hence the
following team members are highly engaged and took the responsibility of asset inventory,
maintenance and planning.
2|Page
Adola Woyu Town Asset Management Plan
3|Page
Adola Woyu Town Asset Management Plan
Maintaining a record of unit rates for all assets included in the asset management plan.
Building and maintaining a list of normal maintenance activities for for all feature classes of
assets included in the City’s AMP.
Building a list of assets that have a maintenance deficit, and assembling this list into a total
maintenance deficit that includes all of the City’s assets.
Building a list of assets that require rehabilitation or decommissioning.
Working with the CIP team to develop a list of new works projects and managing the new
works projects database.
Developing and prioritizing a list of maintenance activities for implementation.
Managing the tracking process for new works projects from approval through construction,
and their transfer to the existing database
Managing the tracking process for maintenance activities from approval through construction,
and their transfer to a change in the condition indicator
Managing the recording of progress of projects and maintenance activities against target and
providing a report on performance.
According to the updated AMP Manual, Working with the City Manager, Mayor, Department Heads
and Managers of Enterprises and Boards, identify a person who will be responsible for managing the
assets for those categories of assets that fall under their operational unit. That person will be
responsible for providing information to, and supporting, the AMP focal person, in all matters
relating to the town assets.
However in the case Adola Woyu town, the lack of clear institutional and organizational structures,
linked to the needs of the AMP, poses a serious risk to the long-term success of the AMP process. To
a large degree this is due to a lack of guidance and the fact that the AMP has been introduced as an
outcome, rather than as an on-going responsibility.
The implementation strategy begins with the establishment of a sustainable institutional and
organizational structure for the AMP within the city administration, which incorporates clearly
4|Page
Adola Woyu Town Asset Management Plan
defined roles and relationships for all parties involved with, or contributing towards, the AMP. This
involves the following actions on the part of each city:
Defining the AMP team as a formal, recognized, organizational unit within the City
Administration.
Defining the AMP unit’s relationship with the City Administration. It is recommended that
this unit be situated in the City Manager’s Office.
A staffing plan for the AMP team. The team requires at least two people, an AMP focal
person and an assistant, with the latter being responsible for ongoing survey work. Additional
staff will be required for start-up as mentioned in paragraph 3 below.
Providing a job description and ToR for the AMP focal person. In this regard, the role of the
AMP focal person is greatly expanded in the new AMP process.
Clearly defining the roles that all departments, and other administrative units, that are
responsible, operationally, for one or more categories of assets included in the AMP, have
with regard to the AMP.
“The term category defines a collection of assets which, when grouped together in a structured way,
provides the physical component of an infrastructure system or a service that is designed to serve a
specific, and clearly recognizable, function for the residents of the town.”
Building upon this definition, the total infrastructure assets of the town comprise the sum of all the
assets within the individual categories (sub categories)
The term ‘category’, as it applies to asset management that can be defined as a specific group of
assets that share a common purpose, and as such are managed together as a group. A water supply
5|Page
Adola Woyu Town Asset Management Plan
network is more than just the water pipes in the ground. There are valves, reservoirs, pumps,
standpipes and many other components. It is all of those components together that make up the
category of assets termed ‘The Water Supply Network’. Similarly, a school can be more than just a
building; it can include a boundary wall or fence; a paved area; a toilet block; a playing field, etc. So,
the category ‘school’ has to include all of these components.
In the new version of the AMP manual; it is clearly stated that the AMP that will be prepared in any
urban centre should incorporate all of the city’s physical assets. The list of Categories and Sub
Categories that belongs to the city Asset should been defined first before full deployment of field
survey launched. Accordingly, the list of infrastructure asset Categories has been defined in to four
strategic activity areas except municipal administration buildings. The allocation of asset categories
to the four strategic activity areas is shown in table 4 below.
The other important step that should be done after categorizing the infrastructure asset into four
strategic areas is defining the responsible organ (body) who manages the asset categories in the city
administration. Accordingly, the infrastructure asset categories have been categorized in to four
strategic activity areas as depicted in the table below.
Table 3: Allocation of Categories of Physical Assets to the Four Strategic Activity Areas
The Movement The Water Supply Environmental Social and Movable asset
Network Network Services Economic Services
Road Network Water Supply Urban drainage Abattoirs Construction
Transmission Line machinery,
Cycle Paths Water Supply Liquid waste Fire service vehicles and
Distribution Line Engineering
Footpaths Water resources Sanitation Municipal markets Equipment
Street Lighting Deep Well (Sour.) Solid waste MSE facilities
Pedestrian Pumps (Distribute.) Urban Greenery Schools
Walkways
Road structures Reservoir (District) Parks and play Health clinics
( Bridge, areas
Culverts)
Public Tap (Trans) Rivers Youth centres
Hydrants Wetlands Municipal
Valves (Transmits) Natural areas administration
building
6|Page
Adola Woyu Town Asset Management Plan
There are various departments in the Municipality that is responsible for each infrastructure Asset
Category which is responsible for the routine maintenance and other activities which is clearly stated
in the table below.
Table 4: Category of Infrastructure Asset and Responsible Body in the City`s Organogram
Categories of Responsible
No Responsible Body Remarks
Assets Person/Group
1 Roads Infrastructure Team Members Infrastructure Development
Development Main Of the process Main Business Process is
Business Process responsible to open new roads
based on the City’s Structure
Plan; While Design,
Construction, & Contract
Administration &Infrastructure
Process is responsible for
construction, Maintenance and
Management of the Road
2 Urban Infrastructure Team Members of Responsible for construction,
Drainage Systems. Development Main the process maintenance and management
Business Process of the
City`s Administration
7|Page
Adola Woyu Town Asset Management Plan
Categories of Responsible
No Responsible Body Remarks
Assets Person/Group
7 Education Buildings Education Bureau Team Members Responsible for maintenance &
Supervision of each facilities
and buildings in their respective
8 Health Service Health Bureau of the process sectors
Responsible for maintenance &
Buildings Supervision of each facilities
and buildings in their respective
9 MSEs and Market Each Sectorial Each Sectorial sectors
Responsible for maintenance &
Facilities Department of the Department of the Supervision of each facilities
City`s Administration City`s and buildings in their respective
Administration sectors
Once the list of asset categories that are included in the city’s AMP has been defined, the next step is
to link these to the GIS system. Each feature class should be tested against the GIS Protocol to ensure
that it comprises only one of the three defined features. Thus on the wider road a culvert might be
defined as a line feature, since it is of sufficient length to give it a start point and an end point, while
on a narrow access road a culvert might be defined simply as a point feature, since its short length
does not warrant defining both a start and an end point. In this situation, there are two options
available. In this Adola Woyu AMP; culverts have been defined as a line or polygon feature.
Having completed the list of feature classes and tested them against the GIS Protocol, the AMP focal
person can create a summary table of feature classes, listed according to their spatial feature, and
incorporate this into the City’s AMP. An example of such a summary is shown in the table below.
Table 5: The List of Feature Classes associated with their respective GIS feature type
Point Feature Line Feature Polygon Feature
Road furniture Asphalt road Paved area
Manhole Cobblestone road Round about
Pump Gravel/ red ash road Reservoir
Valve Compacted earth road Retention and detention ponds
Access box Cycle path Landfill site
Water meter Walkway Administrative boundary
Hydrant Retaining wall External site boundary
Public and communal toilet Drainage channel Internal boundary
Bucket collection point Pipe drainage Building and facility
Solid waste container Water pipeline network Bridge
Lighting pole and mast River channel center line Culvert
Construction plant Tunnel
Machinery Fence and boundary wall
8|Page
Adola Woyu Town Asset Management Plan
Vehicle
Table 6: The relationship between the operational sub-classes and their associated asset feature class
for the category road network
Operational Sub-Category Associated Feature Class
Asphalt Road Asphalt Road
Cobblestone Road Cobblestone Road
Gravel Road Gravel Road
Red Ash Road Red Ash Road
Compacted Earth Road Compacted Earth Road
Asphalt Walkway Walkway
Walkways – Other Surfaces Walkway
Roundabout at Grade Roundabout
Roundabout Elevated Roundabout
Bridge Bridge
Retaining Wall Retaining wall
Culvert Culvert
Overpass (Flyover) Overpass flyover
Pedestrian Footbridge Bridge
Traffic Signals Road furniture
All road signs Road furniture
Offices Building and facility
Workshops Building and facility
Fence Fence and boundary wall
Land External boundary
Road reserve External boundary
All construction plant Construction plant and machinery
All types of machinery Construction plant and machinery
All trucks Vehicles
All other vehicles Vehicles
An identifier (ID) is an alphanumeric string (a short list of characters that can include both letters and
numbers) that is attached to a single element of a feature class of asset and refers only to that element.
Because of this it is unique within a data set; hence it is termed a unique identifier.
The identifier does not contain all of the attribute data for an element; that is provided in the database.
The objective of the identifier is to be able to locate the element in both the spatial and the tabular
databases. It is also important to be able to distinguish the category and feature class to which the
9|Page
Adola Woyu Town Asset Management Plan
element belongs. This is particularly important for linear elements, where different services are
provided in the same vicinity (e.g. a road, a water main and an electrical cable for example).
Both the spatial and the tabular databases will have a unique identifier automatically each time a new
record is created. This is termed an auto-ID. While this auto-ID could be used internally by the GIS
software as the main identifier for an element, using it more widely is not recommended, since this
would have a number of serious disadvantages. Firstly, the auto-ID is simply a number, making it
difficult to link, mentally, with a specific element of infrastructure. Secondly each new database will
generate a new auto-ID table, so there is an immediate duplication, i.e.; the same element will have
different auto-IDs in different databases. To overcome these constraints, it is necessary to create a
unique identifier system that is tailored specifically to meet the needs of the asset management plan.
There is currently no single system of identifiers used for assets in Ethiopia. As a result, different
groups may already be generating identifier systems for the same assets. For example, the Bureaus of
Finance and Economic Development Use Pin Codes for asset identification. While it would be ideal
to have only one identifier system for all uses, it is also important to recognize that an identifier
system that has been created for a specific use may not be suited to another purpose.
As a result, the manual has produced a different identifier system, designed specifically for the Asset
Management Plan. This unique identifier, which is described below, has been tested in a number of
cities and has shown itself to be robust and versatile. At the same time some minor changes have been
made to the individual components of the identifier in response to user feedback. The unique
identifier is made up of four parts and, while it has been created specifically for asset management, it
has also been designed to provide an interface with other users of the asset infrastructure and services
that are likely to use the information generated by the asset database system. The unique identifier is
made up of four parts.
Identifier Component 1: This is a 4 character, alphabetic, code that is linked to the asset category
(with the first two letters) and the feature class (with the second two letters). This provides a quick
internal referencing system for the AMP itself. A list of codes for all categories and feature classes
included in the manual is listed in table 8 below.
Identifier Component 2: This is a 3-4 character, alpha-numeric, code indicating the major
characteristic of the asset. This links the asset to its primary user, and it is for the primary user to
define this specific component of the identifier. This is something that can be done at any time. In the
interim period this component has been given the code “xxxx”.
10 | P a g e
Adola Woyu Town Asset Management Plan
Identifier Component 4: This is a numeric code with 5 digits, followed by an underscore separator
and a further 2 digits. The 5-digit code is used to provide each element with a specific identifier,
while the two-digit code allows the element to be sub-divided to provide a higher level of detail for
the condition indicator. The four parts of the identifier are each separated by hyphens. Note that full
stops and backslashes should be avoided as these are computer reserved symbols. For instance, a
route segment of road located in Bishoftu with route Id “0001” will have a unique identifier of
RN_AS_BS_0001_00
Where:
The list of codes isshown in the tablebelow which represent the details of feature classes with their
associated codes. For instance, “RN” represent Road Network while “AS” represent Asphalt Road.
Likewise, the rest of the Asset Categories given their own specific codes.
11 | P a g e
Adola Woyu Town Asset Management Plan
boundary
Youth Centers YC Access box AC Internal boundary IB
Municipal Buildings MB
The spatial operating environment, which the consulting firm used for this assignment, is GIS and
Specifically Dynamic Segmentation tool from Linear Referencing extension of ArcGIS 10.4.1
software. This tool has so many advantages which are due to its versatility for data entry,
management, updating, and analysis; and besides for water assets; the company used Network
Analyst extension of ArcGIS 10.4.1.
Linear Referencing: is the method of storing geographic locations by using relative positions along a
measured linear feature. Distance measures are used to locate events along the line. In most data
models, linear features split at intersections where they connect with two or more line features and
frequently also split where key attribute values change, such as a change in the road name. However,
users often want to record many additional attributes about the roads. This could require that roads
may split into many tiny segments at each location where attribute values change. As an alternative,
these situations can be handled as linear referencing events along the roads as illustrated in the
concept figure below:
13 | P a g e
Adola Woyu Town Asset Management Plan
Figure 8: Storing Multiple Sets of Attributes for a Feature performed using Linear Referencing
Why We Use Linear Referencing?
Linear referencing is used for many reasons. The following are the two primary reasons:
Many locations are recorded as events along linear features—for example, locations of traffic
accidents are recorded using a convention such as "27 meters east of reference mile marker 35
along State Highway 287." Many sensors record conditions along linear features using
measures of distance or time along the lines—along pipelines, along roads, along streams, and
so forth.
Linear referencing is also used to associate multiple sets of attributes to portions of linear
features without requiring that underlying lines be segmented (split) each time that attribute
values change. For example, most road centerline feature classes are segmented where three
or more road segments intersect and where the road names change.
Dynamic segmentation is the process of computing the map locations of events stored and managed
in an event table using a linear referencing measurement system and displaying them on a map. The
term dynamic segmentation is derived from the concept that line features need not be split (in other
words, "segmented") each time an attribute value changes; you can "dynamically" locate the segment.
Using dynamic segmentation, multiple sets of attributes can be associated with any portion of an
existing linear feature independently of where it begins or ends. These attributes can be displayed,
queried, edited, and analyzed without affecting the underlying linear feature's geometry.
A route feature class is a line feature class that has a defined measurement system. These
measurement values can be used to locate events, assets, and conditions along its set of linear
features. In ArcGIS, the term route refers to any linear feature, such as a city street, highway, river, or
pipe that has a unique identifier and a common measurement system along each linear feature. There
are two primary data types that are used to implement linear referencing in ArcGIS:
14 | P a g e
Adola Woyu Town Asset Management Plan
Using dynamic segmentation, events from event tables are located on line features in a route feature
class.
Figure 9: Event Feature Map of Table of Road Asset done by the Infrastructure Department of Adola
Woyu Town
Infrastructure Asset Inventory needs large scale index map to understand road, culvert, bridge,
drainage features, and other categories of infrastructure assets. Accordingly; index map of the
15 | P a g e
Adola Woyu Town Asset Management Plan
infrastructure inventory has been prepared in 1:1200 scale A-3 paper size index map. The total A-3
size index maps printed for the inventory of road, road median, street light, and drainage lines.
The summary report of the infrastructure assets presented in the coming sections according to their
strategic areas in which the details are available in the annex table and further details can also be
referred from the ADOLA WOYU AMP Geo-database.
Total 121.2
Movement network
Total 22.22
Total No 613
16 | P a g e
Adola Woyu Town Asset Management Plan
Pipe Culvert No 3
Total No 14
Total 42
Table 7: Summary of inventoried assets (Water Supply Network)
Poly-Vinyl-Chloride)
Poly-Ethylene)
Isolating Valves No 9
Air Valves No 0
Anti-Vacuum Valves No 0
Valve Chambers No 58
Chlorinators No 1
Boreholes ` No 3
Reservoirs No 1
Yard connections No 0
Vacuum tankers no 0
Environmental Services
Disposal sites no 0
Communal toilets no 10
Sanitation
Public toilets no 2
Other no -
Area-based containers no 0
Solid Waste
Dust bin no 0
Open Dumping Site no 1 800Sq.m
Landfill site no
Road Median Greenery Km 8 4000 Sq.m
Parks Greenery
18 | P a g e
Adola Woyu Town Asset Management Plan
Artificial wetland no 0
Total no 0
Septic Tank no 0
Social & Economic Services
Daily/Guilt Market no 1
Total 3
MSE Shades no -
facilities
Shops no -
Secondary school no 2
19 | P a g e
Adola Woyu Town Asset Management Plan
Preparatory no 1
TVET college no 1
3.4.2. Roads
According to the infrastructure asset inventory result; there was a total Equivalent (7m width) length
of about 121.1 Kilometers of road in Adola Woyu city urban boundary. This number includes the
road network owned by the Ethiopian Road Authority.
20 | P a g e
Adola Woyu Town Asset Management Plan
Gravel
52%
The tables below provide a breakdown of the roads by surface type as well as by road classification.
The first table (9) shows the actual lengths of the road. The second table (10) shows the same roads
but with their equivalent length. This is the length of the road network for a condition where all roads
are 7m in width.
21 | P a g e
Adola Woyu Town Asset Management Plan
Table 12: Road Breakdown by Surface Type and Classification – Equivalent Length
Type of Road Primary Road in Secondary Road Collectors Road Total in km
km in km in km
Asphalt 22.00 0 0 22.00
Coble Stone 0.495 3.70 0.99 5.18
Gravel 5.209 41.805 14.271 61.72
Compacted Earth 0 35.175 1.242 32.305
Total 27.704 80.68 16.503 121.205
The Pedestrian walkway network consists of, Terrazzo Tile, Precast concrete and Cobble stone
pedestrian walkway surfaces. The Pedestrian walkway network is approximately 22.22 kilometers in
length, from the total length only 0.22km (i.e 0.15km, with a standard width of 3 meters) are owned
by the town municipal which is constructed from coble stone surface material.
22 | P a g e
Adola Woyu Town Asset Management Plan
According to the data obtained during the field work; there were no bridges in the town. Totally 16
under road cross culverts are registered with the total length of 131.43 meter. Out of the total culverts
50.0% of are RCC slab culvert, constructed with RCC slab concrete and 50.0%of culverts are pipe
culvert constructed with concrete pipe. From the total of culverts 4 are along Secondary road and the
others 12 are along Collector & Local roads.
23 | P a g e
Adola Woyu Town Asset Management Plan
Coverage %
13%
87%
The table presented below shows coverage of street lights along the roads in the town by the type of
poles. From the table, the total number of street lights along the roads is 1432 out of these, 906 are
wooden poles, and 204 poles are made of Steel.
1 Florescent lamp 75 75 -
2 Sodium lamp 42 42 -
24 | P a g e
Adola Woyu Town Asset Management Plan
550
450
350
250
150
50
Steel Pole Wooden Pole
No. of poles 526 117
This section provides a summary of the Machinery and Vehicles associated with the different
operational units. The details of Machineries and vehicles by types, capacity and functions such as
construction machines, freight services, and office vehicles by their plate number, capacity and
operational status are recorded.
25 | P a g e
Adola Woyu Town Asset Management Plan
7 Lo bed 1 Functional
8 Toyota Office Vehicle 2 Functional
9 Motor Cycle 30 Functional
Table 17: Drainage Network Inventory by material Type and Equivalent Length
Type of Drain Actual length/km Actual Area/m2 Length of Coverage %
Drainage / km
Converted to
1.5m
Cobble Drain 0.28 336.00 0.22 1.22%
Masonry Drain 9.22 12,908.00 8.61 40.09%
Earth Drain 13.5 20,250 13.50 58.70%
Total 23 33,494.00 22.33 100%
26 | P a g e
Adola Woyu Town Asset Management Plan
60.00%
50.00%
40.00% Series1
30.00%
20.00%
10.00%
0.00%
Cobble Masonry Earthn
There is no formal solid waste disposal site in Adola Woyu town. But there are two informal sites for
this purpose. However, Generation of solid wastes in the town needed to prepare for another waste
disposal site according to the town plan
27 | P a g e
Adola Woyu Town Asset Management Plan
28 | P a g e
Adola Woyu Town Asset Management Plan
The information about water supply that is listed below was obtained from the town Water Supply
Authority. Until 2015 G.C the main sources of potable water for the population of the town are the
two bore holes dug within the boundary of the town located at the back of currently functioning
Lavajo and near Oda Adola School. Besides there is a third bore hole found within the boundary of
the town.
Because of the Shakiso-Adola water project completion the water coverage of the town increased to
61 % with the client of 3000 in Adola town. At the same time the daily water consumption of a town
reached about 1260-1300 m3 /day.
The Adola-Shakiso water project designed for 20 years. The production capacity of the dam is
116m3/hrs. and daily water provision service is for 18 hours. At present day there is enough supply of
water for 24 hrs.
29 | P a g e
Adola Woyu Town Asset Management Plan
30 | P a g e
Adola Woyu Town Asset Management Plan
center 1, schools 11 and the town stadium that comprise football, basketball, hand ball fields, the
running truck and the tribune are inventoried.
31 | P a g e
Adola Woyu Town Asset Management Plan
For instance, for Gravel road, the following indicators of deteriorations are investigated on the ground:
Channeling, water washing, depression and differential settlement. Accordingly, a five-point scale can
be used as one of the recommended scale as per the Asset Management Manual prepared by the
Ministry of Urban Development and Housing.
In doing so, detailed quality indicators for condition assessment of each asset infrastructure were
developed and data collection is made accordingly. Simple condition assessments for road,
drainage, walk ways, street light, traffic sign post, bridges, and culverts and over passes asset
infrastructure are described as indicated in the table below.
Table 22: Condition Indicator Table for All Roads (Cobble, Gravel and Earthen Surface)
Indicativ
Leve Descriptio Detailed Description Type of Deterioration
l n e RUL
Indicativ
Leve Descriptio Detailed Description Type of Deterioration
l n e RUL
33 | P a g e
Adola Woyu Town Asset Management Plan
Table 23: Condition Indicator Table for Bridges, Culverts and Overpasses
Rating
Level Condition Indicator Type of Deterioration
Scale
1 Very Good No defects; as new None
Structurally sound and no serious None
2 Good cracking or scour requiring
attention
If there is minor crack in joint and
support
3 Moderate Minor maintenance required
If there is deposition of Sediments or
Alluvial in the Culvert
If there is erosion of Abutments and or
Scour, erosion of abutments and Piers;
4 Poor piers or Structural defects; some If there are structural defects which
rehabilitation work required needs some rehabilitation work is
needed
Serious structural damage that is a Serious Structural damage which needs
5 Very Poor
safety hazard complete rehabilitation
Table 24: Condition Indicator Table for Drainage Channels and Pipes
34 | P a g e
Adola Woyu Town Asset Management Plan
Road Surface Material Deterioration Area (m2) Surface Area Deterioration Percentage
(m2)
35 | P a g e
Adola Woyu Town Asset Management Plan
120.00%
100.00%
100.00% Deterioration Percentage
80.00%
60.00% 53.00%
45.00%
40.00%
20.00%
2.00%
0.00%
Cobble Gravel Earthen Total
Figure 14: Proportion of Surface area and Deterioration area by Road Surface
The Infrastructure Asset Inventory Result of Adola Woyu City Road further revealed that from the total
Adola Woyu City Gravel Road 35.74 kilometer length, about 33.76 kilometer is in good condition while
from the total of 3.077 km cobble stone road about 2.903kilometer is in good condition. On the other
hand, the city has a total of 19.16 kilometer of Earthen Road. From the quantity which is 18.2 km is
found under Good condition. While from the all surface of road the rest found under different condition
level as presented in the below table. The details of road surface condition assessment can be referred
from the table below.
36 | P a g e
Adola Woyu Town Asset Management Plan
Km Km Km Km Km
100
90
80
70
60
50
40 Condition Very Poor
30 Condition Poor
20 Condition Moderate
10 Condition Good
0 Condition Very Good
l
oa
d
oa
d
oa
d ta %)
R R R To on(
ne el n
di
ti
Sto r av arth n
e G E Co
bl ed d
Co
b ct oa
pa ll R
o m A
C
37 | P a g e
Adola Woyu Town Asset Management Plan
The details of road structures condition assessment can be referred from table 21 above.
Table 29: Condition of major road structures (Culverts)
Pipe Culvert 36 0 24 12 0 0
38 | P a g e
Adola Woyu Town Asset Management Plan
ALL Culvert 0 55 45 0 0
Condition
% Conditions
55
45
35
25
Axis Title 15
5
V.Good(K Good(Km) Moderate( Poor(Km) V.poor
m) Km)
% Con- 0 55 45 0 0
ditions
39 | P a g e
Adola Woyu Town Asset Management Plan
3 Concrete 15 √
Public stand pipe
4 Air Valve 9 √
5 Valve chamber 58 √
7 Pump Submersible 3 √
9 Reservoirs Concrete 1 √
Metal tanker 2 √
40 | P a g e
Adola Woyu Town Asset Management Plan
Condition Assessment has done using the five level condition indicators mentioned as table 22 above.
Accordingly, the inventory result revealed that about 11% are in very good condition which mainly
includes masonry and cobble drain while 41% of earth drains are in very poor condition.
10% 22%
64%
41 | P a g e
Adola Woyu Town Asset Management Plan
The very limited public and communal toilets are not such properly handled and managed. The
condition assessment report revealed that there is one public and four communal toilets that are found
in state of deteriorated conditions.
42 | P a g e
Adola Woyu Town Asset Management Plan
5.1 Introduction
This section of the AMP is devoted to prepare the maintenance budget guide which should identify the
maintenance need for all asset classes of the town. It is believed that the maintenance budget guide
besides identifying the need for preventing, maintaining, repairing, rehabilitating and replacing, will also
serve as staring and turning point to systematically plan for, and continually invest in preventing assets
and maintaining, renewal and replacing promptly and eventually tracks to development and application
of modern maintenance management system.
The Asset Management Plan has developed an integrated approach to maintenance activities that links
both the maintenance activities and the unit rates schedule to the condition indicators described in step 4.
Including AMP document of the city itself, various sources are reviewed to set baseline maintenance
rates for major infrastructure assets including Oromia Building Works Construction Enterprise and
Oromia Water Works Construction Enterprise, Oromia Road Works Enterprise, Oromia Urban
Development Housing and Construction Bureau and the Municipality’s different core process offices
and departments. Maintenance practice of those enterprises and bureaus are deeply reviewed and
checked. In compliant with the revised AMP manual, unit rate for different feature class of an asset
specific to each maintenance activity are employed. For buildings internationally employed industrial
standard methods are adapted that is a fixed percentage of investment or replacement cost method. For
water supply network asset also a fixed percentage of investment or replacement cost method is
employed; considering the remaining useful life for below ground assets. The same is applied for the
rest of non-infrastructure assets, including movable assets.
43 | P a g e
Adola Woyu Town Asset Management Plan
Accordingly, the following tables present the estimated baseline maintenance rate supposing that the
municipality should record actual maintenance expenditure to fine-tune the proposed rates annually.
Table 34: Maintenance Rate for the Movement Network – Road Surface
Feature Class Maintenance Activity Unit Maintenance
(Road Surface) Rate
Asphalt Surface Peeling m2 500
Crack m2 700
Depression m2 1,115.00
Pothole m2 1,015.00
Cobble Stone Lifting of Cobble Stone m2 500
Depression m2 200
Cobble Edge Failure m2 150
Siltation m2 120
Large Block stone Depression m2 350.00
Lifting of LB Stone m2 250.00
Siltation m2 170.00
Earth Pressed Channeling m2 85
Depression m2 140
Wash Away m2 40
Non Compaction m2 45
Gravel Depression m2 60
Channeling m2 45
Wash Away m2 30
Non Compaction m2 20
Red Ash Depression m2 250
Wash Away m2 120
Channeling m2 150
Non Compaction m2 78
Table 35: - Maintenance Rate for Different Deterioration Types – Walkway
Feature Class Maintenance Activity Unit Maintenance Rate
(Footpath)
Asphalt Surface Peeling m2 395.00
Cobble Stone Lifting of Cobble Stone m2 690.00
Precast Paving Block Surface Peeling m2 240
Concrete Surface Peeling m2 420.00
Red Ash Wash Away m2 105.00
Terrazzo/Clay Tile Surface Peeling m2 385.00
Lifting of Terrazzo m2 385.00
Edge Failure m2 600.00
44 | P a g e
Adola Woyu Town Asset Management Plan
Table 36: - Maintenance rate for different deterioration types – Road Structures
Feature Class Maintenance Activity Unit Maintenance
(Road Structure) Rate
Concrete Bridge Siltation m2 470.00
Culvert Slab Failure m2 45,0000
Siltation m2 100,000
Surface Peeling m2 250,000
Pipe Culvert Slab Failure Pcs 1,800.00
Siltation Pcs 10,000
Cracking Pcs 2000
Surface Peeling Pcs 550.00
Depression Pcs 675.00
Steel Crossing Siltation m2 120.00
No 4500
Sodium Lamp
No 3500
Florescent Lamp
Table 37: Maintenance Unit Rates for Water Supply Network - Below Ground Assets
Table 38: Maintenance Rate for Water Supply Network- above Ground Assets
45 | P a g e
Adola Woyu Town Asset Management Plan
Reservoir No 0.5 % of RC
Chlorinator No 1% of RC
Pump No 2 % of RC
46 | P a g e
Adola Woyu Town Asset Management Plan
Administrative Buildings m2 1% of RC 5 % of RC 10 % of RC 75 % of RC
The proportion of the movement network and drainage channels to be maintained as per the revised
manual is the amount of the deteriorated area identified by condition assessments. Estimation of normal
maintenance need is therefore determined based on the deterioration area that is considering percentage
of the segment found in different maintenance activity is supposed to get the retaining maintenance
measure.
Routine and periodic maintenance should carry out for movement network assets rated as good
performing. The target of normal maintenance measures is to preserve the existing good condition of
assets that is the desired asset condition level to ensure continues optimal use of the assets. Cognizing
that most of maintenance activities at this condition level are routine and periodic, the following are the
proposed maintenance measures for the movement network assets.
The total amount of routine and periodic maintenance budget estimated for movement network is Birr
1,816,387.50. The maintenance budget estimates of each movement network assets are presented in the
following pages.
Table 41: Routine and Periodic Maintenance cost for the Road Surfacing
Feature Frequency Normal Unit Quantity to Maintenance Estimated
Class operation Maintenance be Rate Maintenance
Activity Maintained Budget (Br)
47 | P a g e
Adola Woyu Town Asset Management Plan
Total 0
Culverts inspected and found in state of good condition will be retained by minor maintenance activities
in order to function properly and minimize the risk of deterioration. The following are some of major
preventive maintenance activities proposed for culverts;
Total 94500
48 | P a g e
Adola Woyu Town Asset Management Plan
The total maintenance requirement for all road surfaces is estimated to be Birr 18.34 Million. Of which
about Birr 15.5 Million is forecasted to restore the deteriorated Gravel road, this represents almost 66 %
of the maintenance deficit of road surfacing. The town would look into alternative options such as
upgrading the deteriorated gravel roads into cobble pavement which would be feasible than spending
much more maintenance fund for gravel road Whereas, about the maintenance deficit of cobble stone
road that constitute only 2 % of the maintenance need of road surfacing. The rest that constitute about 32
% or Birr 5.9 Million would need to address the maintenance deficit of compacted earth road.
49 | P a g e
Adola Woyu Town Asset Management Plan
Total 142360
The same could be recommending for earth pressed road. The feasible strategic option would be gradual
upgrading of deteriorated compacted earth road into gravel or cobble surface than spending much to
maintain it.
Maintenance needed%
85%
65%
45%
Axis Title 25%
5%
Cobble Stone Grave Road Earthn Road
The deteriorated pedestrian sidewalk road with similar surface of the road surfacing, as mentioned
earlier could be maintained by similar maintenance activities of road surfacing. The forecasted
maintenance need to restore the deteriorated cobble surface pedestrian walkway is nearly 52,800 Birr.
50 | P a g e
Adola Woyu Town Asset Management Plan
Maintenance activities of culverts will be varied based on the types and materials of culverts and the
damages and deterioration types and levels. Some of the major common maintenance activities
recommended to restore deteriorated culverts are the following;
Cleaning bottom and place concrete in bottom,
Install liner plate if capacity allows
Weld short piece of rebar across the crack on every other corrugation
Replace headwall, excavate and jack back into shape.
There are four slab culverts that are found in state of deteriorated condition and eight of the existing pipe
culverts are found in state of deteriorated condition. The estimated maintenance deficits for the
deteriorated culvert are about Birr 2.8 Million and it will be one of the priority maintenance need in
maintenance schedule of the town.
Table 45: Maintenance Deficits of Culverts
Area to
Mainte
Asset Sub be Maintenance
Condition nance Unit Maintenance Cost
Categories Maintai Rate
Activity
n
Rcc.Slab Surface
Moderate M2 34 3900 132,600
Culvert Peeling
Rcc.Slab Surface
Poor M2 0 250,000 0.00
Culvert Peeling
51 | P a g e
Adola Woyu Town Asset Management Plan
52 | P a g e
Adola Woyu Town Asset Management Plan
53 | P a g e
Adola Woyu Town Asset Management Plan
The following are some of periodic and routine maintenance activities to prevent the drainage network
from deterioration and to keep properly functioning;
Table 49: Routine and Periodic Maintenance Budget for Drainage Networks
Total 63,956.00
The drainage facilities assessed to be in the state of deteriorated condition need significant maintenance
and should be among the maintenance priority. This is because that failure to invest in maintenance of
54 | P a g e
Adola Woyu Town Asset Management Plan
deteriorated drainage networks would further affect, apart from the drainage network itself, the
operation and condition of the road network as the road condition directly dependent, among others, on
the condition and operation of drainage channels. The following are some of broad maintenance
activities recommended for some of deteriorated drainage network.
The maintenance forecast to correct accumulated drainage maintenance deficit of open masonry, cobble
drainage and earthen drainage lines combined covering as some as 7.4 km estimated about Birr 2.76
Million.
55 | P a g e
Adola Woyu Town Asset Management Plan
Deposition
Earthen Drain Poor Washing Ml 0 60 0
Sub-Total 3625.00
As depicted in the Figure below, open masonry drainage, constitutes the largest maintenance deficit
about 47%, Cognizing the significant impacts of drainage network on the road system the municipality
will pay attention and give priority to maintain the drainage network promptly.
Mantenance Required by %
Mantenance Required by %
99 1
The informal and poorly protected waste disposal-dumping site serves for both waste and liquid waste
dumping. The dumping site is without any compacting practice and traditional way though relatively the
waste are not so much piled up and scattered in and outside the compound. Until the town develops the
modern sanitary landfill, the dumping site should be prevented and maintained through different
mechanisms to minimize the potential environmental and health risks.
56 | P a g e
Adola Woyu Town Asset Management Plan
The public and communal toilets could pollute the surrounding environment and would bring health
risks of the users and people living or working around, let alone impacts on town images. The
municipality could keep public toilets clean and well-functioning through various ways.
In general the condition assessment report revealed that there one public toilets and 4 communal toilets
that are found in state of serious deteriorated conditions. The municipality should undertake corrective
maintenance and repairs with an estimated maintenance cost of Birr 150,000.
58 | P a g e
Adola Woyu Town Asset Management Plan
6.1 Introduction
This section of the AMP describes how to calculate the current replacement cost and the residual value
of the municipal infrastructure asset base for those assets that are included in the Asset Management
Plan. Asset valuation can be carried out by various methods and techniques. The method to value the
municipal asset here is based on the recommended technique in the national AMP manual, which is the
one most widely used in international practice when valuing fixed assets such as network infrastructure,
where there is a long-term investment that cannot easily be traded on the open market, is to use what is
known as Depreciated Replacement Cost (DRC). This approach uses the current replacement cost of the
asset as the basis for its valuation. However, it then takes into account the age of the asset and
depreciates it on the basis of how long it has been operational and how much operational life remains.
59 | P a g e
Adola Woyu Town Asset Management Plan
into account the local condition, local labor and resource availability and the corresponding price as well
as inflation factors.
The applied unit rate in this AMP is mainly based on the local unit rate provided by the municipality
with adjustment and incorporating additional unit rate for few assets for these not provided by the
municipality. The following are major procedure employed to determine the unit price of new assets.
Historical cost data and current actual cost of new assets of Adola Woyu town and other cities
are reviewed.
The current tender value of some important infrastructure assets are gathered from the town
construction office
The recent Asset Management Plan studies, particularly cities relatively near to Adola Woyu
(such as Shashemene and Hawassa) are reviewed.
List of unit rates applied are provided in the table below for new assets to evaluate the town
infrastructure and municipal facility assets.
Table 55: List of Unit Rate for New Assets
S/No. Asset Category by strategic activities Unit Unit Rate (ETB)
I Movement Network
1 Gravel road m2 770
2 Cobble stone road m2 988.47
3 Compacted earth road m2 350
4 Pedestrian side walk Cobble m2 420
5 RCC Slab Culverts(With Earth Work) No. 2,262,175.03
6 Pipe Culvert No. 120,000
7 Street Light Installation Km. 2,600,000
8 Sodium lamp No. 5000
9 LED Lamp with steel pole No. 80,000
10 Florescent lamp No. 4,200
II Environmental Service
1 Open masonry drain ml 4,705
2 Cobble stone drains ml 302
3 Earth drain ml 60
60 | P a g e
Adola Woyu Town Asset Management Plan
Replacement cost of the asset is a measure of replacement value or the cost of replacing an existing asset
with a modern asset of equivalent capacity. Replacement cost method of evaluation is one of widely
used and essential technique in the valuation of assets. Apart from valuing the municipal asset RC could
also give insight about the cost of replacement of existing asset to make sure there is sufficient funding
to maintain the network in the long-term.
Based on the inventory of the town asset base and unit rates provided above, current replacement costs
of the town assets are estimated. Accordingly, total current replacement cost of the town assets is
estimated to be about 713,856,506.51Birr.
A table of replacement cost of the Adola Woyu town assets by strategic activity area and supportive
activity area are shown below.
Table 56: Summary of current replacement cost of the town assets
61 | P a g e
Adola Woyu Town Asset Management Plan
Environmental Services 0
The Figure below demonstrates that Movement Network, by 46 % share, is the first most valued asset of
the town, followed by to 26 % share of Water Supply Network assets and 17 % share of Movable Assets
respectively. The Municipal administration buildings and Social and Economic strategic area share
about 14 % of the town assets. The Environmental Services assets largely constituted by drainage, share
about 5 % of the town assets.
62 | P a g e
Adola Woyu Town Asset Management Plan
Replacement by %
Series1
46%
23% 15%
4% 8% 4%
Figure 7: Contribution of Strategic Activity Areas for the town Asset Value
The Replacement cost of the movement network assets estimated as Birr 85.67 Million. That make the
movement network assets are largest valued assets accounting about 38 % of the town asset value.
Table 57: Current Replacement Cost of all Inventoried Movement Network Assets
Asset Sub-Categories Unit Quantity Unit Rate Replacement Cost
Cobble Stone Road m2 36,319.95 988.47 35,901,180.98
Gravel Road m2 432,062.46 770 332,688,094.2
Compacted Earthen Road m2 226,135.20 350 79,147,320
Curve Stone Pedestrianly
ml 220 420.00 92,400
Walkway
Street Light LED No 526 80,000 42,080,000
Sodium Lamp No 42 5000 210,000
Fluorescent Lamp No 75 4,200 315,000
RC Slab Culvert No 11 2,262,175.03 24,883,925.33
Pipe Culvert No 3 120,000 360,000
TOTAL CARRIED 515677920.51
63 | P a g e
Adola Woyu Town Asset Management Plan
Table 58: Current Replacement Cost of all Inventoried Water Supply Network Assets
Table 59: Current Replacement Cost of all Inventoried Environmental Service Assets
Asset Sub-Categories Unit Quantity Unit Rate Replacement Cost
Masonry Drainage Km 9.22 4,705,000 43,380,100
Cobble Stone Drainage Km 0.284 302,000 85,768
Earthen Drain Km 13.5 60,000 810,000
Public and Communal Toilet No 12 150,000 1,800,000
Greenery and Parks M2 4200 3,126.29 13,130,418
TOTAL CARRIED 59206286
64 | P a g e
Adola Woyu Town Asset Management Plan
Table 60: Current Replacement Cost of all Inventoried Social and Economic Strategic Assets
Table 61: Current Replacement Cost of all Inventoried Administration Office Buildings
Table 62: Current Replacement Cost of all Inventoried Machineries and Vehicles
Types of Movable Assets Unit Quantity Unit Rate Replacement Cost (ETB)
6.4.1 Introduction
The current value of assets is financial representation of the potential service value of the existing asset
base. Valuing of assets is a challenging task because of the absence of information on original cost of
66 | P a g e
Adola Woyu Town Asset Management Plan
construction cost and purchasing price of the assets. In addition, absences of records of construction and
procurement date of most of the assets and lack of standard for expected useful life (EUL) of assets are
additional challenges in asset valuing process. To minimize these and related challenges and to take into
account the possibility of value increment of the assets due to inflation pressure eventually, applying
depreciated replacement cost (DRC) for the valuation of assets is a common practice in some countries
and also recommended by the revised AMP manual.
According to the revised AMP manual, due to accelerated depreciation nature of infrastructure assets we
should have to deduct the maintenance deficit from DRC to reach to estimated current residual value of
the asset. For municipal services and facilities, on the other hand, DRC itself is supposed to represent
estimated current value of the asset without deducting maintenance deficit.
Depreciated Replacement Cost is simply computed based on replacement cost of assets less an
allowance for deterioration of condition to date, and based on the fraction of remaining useful life over
expected useful life. So DRC is thus computed as the ratio of the remaining useful life to the expected
useful life as a percentage of current replacement cost.
Due to accelerated depreciation nature of road network assets and drainage channel, however, to reach
to estimated current value, the maintenance deficit must be deducted from DRC. For water supply
network assets and the rest of environmental protection assets, excluding drainage network, and
buildings and facilities under social, economic and administration service as well as movable assets, the
estimated value of DRC is supposed to be represented or equal to estimated current value of assets.
This is because that the latter asset categories are not supposed to depreciate at accelerated rate thus the
value of DRC itself represent the estimated current value of the asset without deducting maintenance
deficit.
67 | P a g e
Adola Woyu Town Asset Management Plan
Where,
RUL is the remaining useful life
EUL is the expected useful life
CRC is the current replacement cost
MD is the maintenance deficit of the assets
Based on the above valuation technique to estimate the current value of the town assets, the estimated
current value of the town assets is 142,395,475.5 Birr, which is equal to about 62.57 % of the current
replacement cost. The different between the current value and the replacement value, which is about
85,176,731.7 Birr, represents the asset deficit; which is the value of the assets lost due to age and
maintenance deficit. Thus the deficit is about 34.43 % of the replacement value which implies the big
impact of maintenance negligence along with wear and tear of the assets due to age. It has to be noted
that for the assets which are serving beyond their expected useful life, Zero is assigned as their residual
value because assets will never assigned a negative value.
Table 63: Summary of Replacement Cost against Current Value and Asset Deficit
Current Depreciated
Asset Sub Maintenance Current Value Asset Deficit
Replacement Replacement
Categories Deficit (MD) (CV) (ETB)
Cost (CRC) Cost (DRC)
Cobble Stone 35,901,180.9
10,240,351.20 146,203.20 9,112,061 2,935,411
Road 8
332,688,094.
Gravel Road 22,500,251 2,624,380 7,020,985 22,979,351
2
68 | P a g e
Adola Woyu Town Asset Management Plan
Compacted
79,147,320 13,176,000 142,360 3,982,450 17,977,550
Earth Road
Pedestrian
92,400 84,480 116,600 31,680 73,920
walkway Coble
24,883,925.3
Culverts 6,400,000 132,600 3,565,980 4,434,020
3
Street Light 42,080,000 12,203,550 540,900 12,203,550 1,355,950
Borehole 15,000,000 12,000,000 150,000 12,000,000 3,000,000
Reservoir 3,000,000 2,400,000 15,000 2,400,000 600,000
Pumps 1,800,000 1,440,000 36,000 1,440,000 360,000
Chlorinator 500,000 400,000 5000 400,000 100,000
Treatment Plan 20,000,000 16,000,000 200,000 16,000,000 4,000,000
Distribution
10,260,000 8,208,000 1,000,000 8,208,000 2,052,000
Line
Transmission
8,980,000 7,184,000 500,000 7,184,000 1,796,000
Line
Masonry
43,380,100 6,426,000 791,088 4,093,600 3,046,400
Drainage
Cobble
85,768 704,700 3,625 545,700 237,300
Drainage
Earthen
810,000 644,400 0 338,400 735,600
Drainage
Toilet Blocks 1,800,000 0 530,000 1,650,000 150,000
Greenery and
13,130,418 378,000 460,000 378,000 252,000
Parks
Health
3,832,000 2,682,400 191,600 2,682,400 1,149,600
Buildings
School
9,708,600 5,339,730 485,430 5,339,730 4,368,870
Buildings
Market
1,933,500 1,546,800 96,675 1,546,800 386,700
Facilities
Sport Fields 1,725,000 1,035,000 86,250 1,035,000 690,000
Bus Station 1,278,200 766,920 63,910 766,920 511,280
Youth Centre 1,329,040 797,424 132,904 797,424 531,676
Abattoir
503,760 302,256 30,376 302,256 201,504
Facilities
Administrative
11,272,200 7,890,540 7,890,540 3,381,600
Buildings
Movable
47,850,000 31,480,000 1,245,250 31,480,000 7,870,000
Assets
182,938,068.0 172,230,802.2 142,395,476.0 85,176,732.0
Total 9,726,151.20
0 0 0 0
69 | P a g e
Adola Woyu Town Asset Management Plan
7. Cost, and Priorities, New Works Projects within the CIP Process
8. (Step 7)
8.1 Introduction
The work in step 7 of the AMP can be divided into three separate activities.
1. Building a budget for all new works project proposals.
2. Providing an overview of the expenditure allocation among the major activity areas.
3. Setting out the new works projects in order of priority.
Building the budget for new works projects involves the following activities,
Bring forward, from Step 6, the unit rates for asset replacement, to provide the basis for
estimating the cost of new works projects.
Calculate the cost of the new assets on a project-by-project basis using these rates and provide a
summary table of all new works projects, using the dataset template TDS 5.
Provide a summary table showing the breakdown of the total cost of new works by feature of
asset.
The purpose of this second activity is to assist the CIP team, and the executive, to create a balanced
investment in new infrastructure and municipal service assets; and to prioritise the new works projects to
support this.
70 | P a g e
Adola Woyu Town Asset Management Plan
The third activity is that of prioritising the new works projects. This activity will be carried out with the
AMP focal person working as a member of the CIP team. It is important to stress that this activity is an
integral part of the CIP process. The purpose of this section is to highlight a prioritisation process that
draws upon the specific skills and expertise of the AMP team, thereby enabling them to contribute
effectively in this critical important aspect of CIP process that will lead to a final list of new works
projects going forward to the executive for approval.
On the other hand the cost estimate of solid waste fill site, Abattoirs, Bus Station and accessory road and
drainage is taken from the BOQ prepared in the design study. The other point to be noted related to
costing new works is the conversion of unit of measurements for some assets which are proposed in
number but converted to convenient unit of measure to comply with the applied unit rate. Hence assets
such as culverts and bridges which are proposed in number converted to area for the purpose of
estimating construction cost and maintenance. In doing so, the average width and length of existing
culverts and bridges are considered to estimate the average area of culverts and bridges proposed. In
similar manner the proposed length of road supposed to be in equivalent length, i.e. 7 meter width for
road, to match with the corresponding unit rates which are established for the indicated equivalent length
of roads and drainage.
Unit cost information that has been established in step 6 for the valuation of the town assets are built
based on different sources including the recent projects and acquisition price of assets of the town and
the experience of other cities. The unit rates employed in the study should be utilized for preparation of
indicative budget, thus care should be taken when applying the unit rate during implementation and
tendering.
71 | P a g e
Adola Woyu Town Asset Management Plan
A new work project proposal has framed by three project years to assist prioritizing projects for
consideration within a rolling three years capital investment plan. As the Table below summarize, the
proposed new works estimated cost for the indicated project years is Birr 48,836,392.37.
72 | P a g e
Adola Woyu Town Asset Management Plan
The decision and approval criteria for funding and implementation of new work project proposal should
incorporate financial, environmental and socioeconomic considerations, with the objective to generate
sustainable benefits for the local government and more importantly for the residents.
Besides, direct and indirect job opportunities that can be created from the implementation of proposed
projects, the economic value of the proposed new works will also be significant to the city economy.
73 | P a g e
Adola Woyu Town Asset Management Plan
should take account urban planning and zoning considerations to the development of road networks and
facilities. Furthermore, much emphasis should give to the construction of drainage channels and
enhancement of public parks and greenery capital to address the effects of the climate changes.
74 | P a g e
Adola Woyu Town Asset Management Plan
The proposed new works are then prioritized by two approaches. The first is grouping new works based on the proposed
year of project developments. Thus projects proposed to commence in the first year should aggregately consider as priority
projects and again these projects prioritized from first rank to third ranks individually based on the factors explained above.
Under this group some projects would fully construct in the first year and some others would start extend to the second and
third year of the planning period. The second aggregate prioritized group is the projects proposed to commence in the 2nd
planning year. Projects under this subgroup are all new works to develop in the new areas. The budget for prioritized new
work projects in the first year of the planning period require as much about 15,428,859.00Birr. the detail new works
proposal plan for
75 | P a g e
Adola Woyu Town Asset Management Plan
76 | P a g e
Adola Woyu Town Asset Management Plan
77 | P a g e
Adola Woyu Town Asset Management Plan
9.1 Introduction
The purpose of bringing the maintenance deficit summary from Step 5 in this stage of AMP is to show
maintenance budget requirement parallel to three year capital investment rolling program together with
rehabilitation and new works. The maintenance budget guide prepared in Step 5 revealed that
maintenance practice of Adola Woyu town municipality is characterized by inadequate maintenance
activity which is now shown by huge maintenance deficit.
Besides inadequate maintenance funding the huge maintenance deficit is associated with absence of
periodic and consistent condition inspection of the infrastructure and facility assets. Limited resource
availability to fund maintenance can be also one of the reasons which would of course associate with the
absence of maintenance data management. That in turn could make difficult to identify and determine
which and how to maintain and what essentially needed to do so. The negative outcomes of inadequate
maintenance no doubts eventually results for assets falling below acceptable standards of service levels
and a risk of shortened lifespan of core infrastructure assets which were developed at expensive cost and
hard to replace.
Types and activities of maintenance and maintenance budget forecast are carried out in Step 5 for all
asset classes. The recommended maintenance activities are believed to be appropriate for different
condition levels of the asset, though they are generic and will need to make specific and detail for
specific asset during implementation.
78 | P a g e
Adola Woyu Town Asset Management Plan
The maintenance budget guide prepared in Step 5 identified different maintenance measures for all
strategic activity areas and subcategory classes and forecast the respective maintenance budget to carry
out the proposed maintenance actions and activities. The study identifies the town has huge maintenance
deficit which is nearly Birr 36.8 Million, apart from the preventive maintenance need estimated about
Birr 4.2 Million.
This section devoted for the preparation of maintenance plan to guide and schedule the overall
maintenance program and outline the maintenance priority. This is because that the municipality with
limited financial capacity could and would not afford to fund all maintenance need within a single year
or even within three year planning period.
The forecasted maintenance budget need for Routine and Periodic maintenance for all assets estimated
about Birr 1.2 Million.
Table 68: Maintenance budget for Routine and Periodic maintenance by activity areas
S/N Strategic and Supportive Activity Areas Budget for routine and periodic
maintenance (ETB/ year)
1 The Movement Network
1.1 Cobblestone Road 162,239.7
1.2 Gravel Road 217,023.03
1.3 Compacted Earth Road 0
1.4 Culverts 0
79 | P a g e
Adola Woyu Town Asset Management Plan
The final work in Step 8 is to define the maintenance activities that will be included in the budget for the
3-year rolling program. The maintenance program begins with the calculation of the maintenance deficit
in Step 5 of the AMP and this deficit is then brought forward to Step 8.
In total, the municipality needs to allocate about Birr 10.26mill address both routine and periodic
maintenance and maintenance required to eliminate the accumulated maintenance deficit. The routine
and periodic maintenance need is forecasted as some as Birr 4.2 Million, whereas the maintenance need
to eliminate the accumulated deficit is as some as Birr 9.7 Million.
81 | P a g e
Adola Woyu Town Asset Management Plan
The maintenance deficit that would have been brought forward from Step 5 of the AMP as indicated on
table 70 provides a summary of all required maintenance work for network infrastructure, and water
supply assets. At this point in step 8, there is a list of all the maintenance activities required to address
the maintenance deficit, together with a budget. On the premise that the maintenance deficit exceeds the
budget, then the next step is to prioritise the maintenance activities and thereby identify those activities
that will be carried out over the next three years. In order to do so the town has to prioritize the
maintenance deficit based on criteria set to identify the top maintenance priority assets.
According to the revised AMP Manual, A process required for prioritizing maintenance activities are
provided and this prioritization process are directly taken into account for this AMP preparation. Thus
prioritisation process should be based upon three criteria:
82 | P a g e
Adola Woyu Town Asset Management Plan
strategic focus is of a more practical nature, with three areas of importance: utilization/demand; negative
impact; and community needs. These three areas are discussed further below.
Asset Utilization/demand; this is particularly important for the movement network. Areas of heavy
traffic or pedestrian demand should be given priority for two reasons. Firstly, the disruptive impact, and
indirect cost, of asset deterioration is greater. Secondly, the heavy demand will accelerate the
deterioration at a faster rate is left unattended.
Negative impact: This refers to an external impact and is particularly relevant in terms of environment
and health impacts. These include flooding and health problems associated with deteriorated sanitation
and health services.
Community needs: Prioritizing maintenance activities should be particularly concerned with addressing
community concerns. Local communities and users have direct experience of poor or deteriorated
services and infrastructure and provide an important and valuable input to the prioritization process.
Employing the above criteria, the top maintenance priority are identified which would be rehabilitated
in 2013 E.C.
A
Gravel Road Kilta Mikael Asphalt m 26 10 2,6 45 1 Depr Poo
EBA Cobble 2
0 00. 117,000. essio r
Road 00 00 n
Gravel Road LEG Oda Ferenj m 19 10 1,9 45 1 Depr Poo
E Dola Wuha 2
0 00. 85,500.0 essio r
DUF kebele 00 0 n
A
Gravel Road Kilta Wako Prison m 25 11 3,0 45 1 Depr Poo
EBA Areri Road 2
5 .8 31. 136,437. essio r
9 95 75 n
Gravel Road Kilta Schoo Robe m 45 11 5,2 45 1 Depr Poo
EBA l berako 2
3.1 .5 11. 234,503. essio r
house 46 18 06 n
Selected soil or ODA N.Bus N.Bus m 15 15 22, 45 1 1 Depr Poo
2
Aggrigate DOL Station Station 0 0 500 ,012,500 essio r
material A .00 .00 n
LEG Getach Gizaw m 17 11 20, 45 1 Depr Poo
E ew Bet 2
63. .6 593 926,723. essio r
DUF House 17 8 .86 73 n
A
Total Carried Total 3,1
for Movement Carried 44,284.
Network
53
84 | P a g e
Adola Woyu Town Asset Management Plan
A. Movement Network
Equipments 1,022,000
85 | P a g e
Adola Woyu Town Asset Management Plan
10. Convert the Agreed Budget for all New Works and Maintenance
Projects to a 3-year Rolling Program (Step 9)
10.1 Introduction
The construction of the 3-year rolling program for all New Works is carried out by the full, multi-
disciplinary CIP team. The asset management focal person is a member of this team and at this stage of
the budget development process, which incorporates step 9 of the AMP. The role of the AMP is simply
to construct the program so that the projects can be tracked in step 10.
For the maintenance activities, the primary responsibility for creating an implementation program for
maintenance activities lies with the AMP focal person. Here, step 9 brings forward the budget for
routine and periodic maintenance from step 8 and updates the database of maintenance activities
associated with the maintenance deficit, to ensure that only approved maintenance activities are carried
forward. If the maintenance deficit budget is drawing on funding from the CIP budget, then the final list
of maintenance activities would have to be approved by the CIP team.
Once that is done, these activities would be allocated to the first year of the 3-year rolling program, and
a proposed budget made for years 2 and 3. In general the tasks for step 9 comprise:
Each New Works project that has been approved in Step 8 will be allocated to the 3-year rolling
program of work. There will be a number of reasons for the choice of which project is allocated to which
year. However, because the choice is made primarily on the basis of project prioritization, this can often
overlook practical considerations of capacity and availability of resources. To assist in maintaining this
balance and improving decision-making, the 3-year rolling program is carried out by the joint efforts of
the town CIP team particularly with the full engagement of AMP focal person and advice of UIIDP
86 | P a g e
Adola Woyu Town Asset Management Plan
coordinator. It has to be noted that the 3- year rolling program would amend based on budget availability
and the need of revising existing CIP document to incorporate the plan for the year 2011 EFY and so on.
Once this is done the AMP provide a full list of all approved new works projects set out in the format of
a 3-year rolling program, this table is included in the annex. From this table, the AMP generates a
summary budget table, with the projects grouped by strategic activity area.
The table below provides a summary of the three year rolling program for new work projects by major
strategic activity area. The total budget of Birr 92.6 Million are approved for three years new work
projects and it is assumed that the proposed fund will be available from various funds including the IDA,
Regional grants, town own revenue.
Table 72: Summary of the 3-year rolling program for new works projects by strategic activity area
The maintenance deficit budget and maintenance plan for rolling three years is developed in the
previous sections based on condition assessment and the maintenance rate established based on the
maintenance activities. The prioritised list of projects has been calculated in step 8. This is brought
forward into step 9 and becomes the budget for the first year of the AMP. A detailed list of approved,
and budgeted, maintenance projects included in the annex.
87 | P a g e
Adola Woyu Town Asset Management Plan
A similar budget is used for the following two years of the 3-year rolling plan, with the prioritization
process following the same procedure as was used for the first year budget. A summary of the budget for
reducing the maintenance deficit, broken down by strategic activity area is shown in table 74 below.
Table 3: The maintenance budget on the 3-year rolling program by strategic activity area
Strategic Activity Area 2013 EFY 2014 EFY 2015EFY Total Budget
for 3 years
Movement Network 4,166,285 4,600,664.00 5,031,968.0 13,798,916.5
Assets 0 3
Water Supply 0 0 0 0
Network
Environmental 0.00 1,016,123.00 2,057,899.0 3,074,022.00
Services 0
2013-2015 MAINTENANCE BY %
90
80
70
60
MAINTENANCE 2013-2015 BY %
50
Strategic Activity Area
40
30
20
10
0
1 2 3 4
Finger 20
88 | P a g e
Adola Woyu Town Asset Management Plan
Table 4: Three Year Maintenance Budget for the town for EFY 2013 to 2014 depending on CIP
S/ Infrastructure Maintenance Maintenance Maintenance Total Budget
N Category Budget for EFY Budget for EFY Budget for EFY for 3 years
2013 2014 2015
A Movement
Network
1 Roads
1.3 Compacted
Earth Road
2.1 Cobble
walkway
3 Road Structure
4.2 Fluorescent
lamp
89 | P a g e
Adola Woyu Town Asset Management Plan
B Water Supply
C Environmenta
l Services
3 Greenery and
park
D Social and -
economic
services
90 | P a g e
Adola Woyu Town Asset Management Plan
11. Manage the transition of all Completed New Works and Maintenance
12.1 Introduction
The main purpose of the final step of the AMP is to take responsibility for the database management for
new assets, and for the maintenance of existing assets, and carry this though the implementation phase to
a point where the new or maintenance works are complete and they can be incorporated into the AMP as
existing assets. The methodology and guidelines indicated in the manual for the implementation process,
measuring and assessing the implementation performance regarding new works and maintenance
projects are discussed in this section to guide the overall process of the implementation strategy and
performance measurement.
The wider implementation strategy for new works revolves around two major activities: procurement
and the management of cash flow. Both of these are described in detail in the CIP Manual and are the
responsibility of the full CIP coordinating team. This wider strategy is geared towards ensuring the
effective and efficient delivery of projects. In other words it is a project management process. What this
means though is that the responsibility for projects ends when they are completed successfully and
handed over to the City. The role of the AMP is to ensure that the completed projects, as well as
completed maintenance activities, are recorded in the following year’s asset management plan.
The updated AMP manual defines the components in Step 10 covers two distinct areas of
responsibilities. The first of these is to track new works maintenance projects and maintenance activities
going forward into the future. The second responsibility is to keep track of new works projects and
maintenance activities that were approved in past AMPs and to measure the outcomes against the
original approved projects.
The implementation strategy for new works revolves around three major activities: project management;
procurement; and construction management. The responsibility for all three of these activities rests with
91 | P a g e
Adola Woyu Town Asset Management Plan
the respective specialists in the town. For the maintenance projects, the status change for completed
projects will carried out by updating the condition level in the condition tabular dataset.
Step 10 of the AMP is essentially a monitoring and tracking exercise covering both New Works and
Maintenance projects. There are four parts to the first of these and three to the second. These
component parts are:
5. Table75 Implementation schedule for new works projects for year 1(2013 E.C)
92 | P a g e
Adola Woyu Town Asset Management Plan
Nov-
Greenery 19 19 Nov-19 Nov-19
19
20 19 20
30-
13-Sep- 26-Oct- 16- 23- 15-Jan- 3-Dec- 29-Jan-
3 MSC Shades Revised Nov-
19 19 Nov-19 Nov-19 20 19 20
19
Sub-total Economic &
Social Services
1. Confirm the final list of all maintenance activities for each of the three years.
2. Track the start and end dates for each maintenance activity and enter these in the tabular data set.
3. Once each maintenance activity has been completed, change the condition indicator for the asset
in question to reflect the new status.
Table76 Implementation schedule for Maintenance projects for year 1(2012 E.C
13- 3- 28- 2-
Existing 28-Sep- 7-Dec-
Roba Café to Sep- Oct- Oct- Nov- 2-Dec-19
Culvert 19 19 19
19 19 19
ELPHA to Existing 13- 28-Sep- 3- 28- 2- 2-Dec-19 7-Dec-
Sep-
Culvert 19 19 Oct- Oct- Nov- 19
94 | P a g e
Adola Woyu Town Asset Management Plan
19 19 19
13- 3- 28- 2-
Natnael Derartu 28-Sep- 7-Dec-
Sep- Oct- Oct- Nov- 2-Dec-19
House to chefe 19 19 19
19 19 19
13- 3- 28- 2-
Capitean 28-Sep- 7-Dec-
FM to Sep- Oct- Oct- Nov- 2-Dec-19
wefcho 19 19 19
19 19 19
13- 3- 28- 2-
Asegahegn Mamush 28-Sep- 7-Dec-
Sep- Oct- Oct- Nov- 2-Dec-19
wofcho to Shop 19 19 19
19 19 19
Tracking the New Works projects requires that the AMP team maintain a close working relationship
with the Project Manager for New Works; the Procurement Specialist; and the Construction Manager. If
this is done properly then the tracking of New Works, and the subsequent management of the New
Works database, is a relatively simple exercise, following the four tasks set out above.
The first of these is to confirm that all of the projects identified as approved under Step 9 will actually be
constructed. Issues of procurement or cash flow could still change this list, or change the years of the
construction starting date. At this point any projects that have been amended, or removed from the list of
new projects, should be updated or deleted from the New Works database TDS 3 and the proposed
starting dates for approved final proposals should be recorded in the field allocated to this purpose.
It is then important that the AMP focal person liaises with the Procurement Specialist so that (s) he is
aware of the date when each new contract is signed. As this is done the date should be entered in the
database, together with the contractual completion date.
During the construction phase the AMP focal person should liaise on a regular basis with the
Construction Manager. When the project has been completed, and handed over to the city, it should be
checked for any changes to the project that might have taken place between the original approval of the
project by the city and the completion of construction. This is important because it is the final ‘as built’
95 | P a g e
Adola Woyu Town Asset Management Plan
project that will be entered into the asset management database as an existing asset, not the original
project description.
At this point the project should be transferred from the New Works database to the set of databases for
existing assets. This is the feedback loop shown in the introduction to this manual. The database for
New Works will already have a breakdown of the project by feature class. This will then form the basis
for transforming the New Works into new assets in Step 3 (the spatial database and the physical attribute
dataset); defining the condition in Step 4 (the Condition Indicator database); and the Costing dataset in
Step 6 (the Cost and Value database).
The list below covers all the key dates that should be noted and entered into the fields provided in the
new works projects database.
Approval
Date of tender invitation
Date of tender closure
Date of signing of a contract
Date of start of activity
Date of project completion
Date of handover to the city
Date when the new projects is entered into the database for existing assets
96 | P a g e
Adola Woyu Town Asset Management Plan
The list below covers all the key dates that should be noted and entered into the fields provided in the
maintenance planning database.
Approval
Date of signing of a contract
Date of start of activity
Date of completion of activity
Date when the condition of the asset is updated
The integration of the AMP process into a GIS-based management system enables both new works
projects and maintenance activities to be tracked with a degree of accuracy that was not available in the
past. This means that, for the first time, it is possible to measure the performance of past projects and
activities against the original plan. The AMP is due for completion towards the end of the (Ethiopian
Calendar) year. This means that it is not possible to provide a complete analysis for the year in which the
assessment of existing assets is being carried out. To make the tracking process worthwhile, the analysis
should begin by focusing on the previous year, i.e. AMP year minus 2, where a full set of statistics
should be available. This provides the comparative analysis.
The tables below provide templates for measuring the performance of new works projects and
maintenance activities respectively. The table for maintenance is more comprehensive because it is able
to draw on activities completed in the year. Also, this is the more important table for the AMP since the
maintenance performance is more directly associated with the AMP, whereas the performance of new
works project starts falls under the CIP.
97 | P a g e
Adola Woyu Town Asset Management Plan
Considering the above templates to follow the implementation program of the new work and
maintenance projects, the city procurement proposal and proposed action plan are presented below
98 | P a g e