Tcee Notes
Tcee Notes
Module 1 : TRANSFORMERS
Syllabus: Electrical Tools, accessories: Tools, Accessories and Instruments required for
Installation, Maintenance and Repair Work, India Electricity Rules, Safely Codes Causes and
Prevention of Accidents, Artificial Respiration, and Workmen’s Safety Devices.
Transformers: Installation, Location Site Selection, Foundation Details, Code of Practice
for Terminal Plates, Polarity and Phase Sequence, Oil Tanks, Drying of Winding sand
General Inspection. Commissioning Tests As Per National and International Standards -
Volts Ratio Earth Resistance, Oil Strength, Insulation Tests, Impulse Tests Polarizing Index,
Load Temperature Rise Tests. Specific Tests for Determination of Performance Curves like
Efficiencies, Regulation Etc., Determination Mechanical Stress under Normal and Abnormal
Conditions.
Introduction:
Standards are evolved to meet a generally recognized demand, taking into
account the interest of manufacturers and users and fulfilling the needs of
economy.
The international standards published by IEC (International Electro technical
Commission) are accepted universally.
Indian Standards Institution (Bureau of Indian Standards) publishes IS
standards.
The manufacturers and users in India have to follow IS standards and IEC
standards.
The word specification or rating denotes the assigned numerical value of
capabilities.
The transformer is assigned with certain definite ratings. These assigned ratings
are guaranteed by the manufacturer.
This has been revised time to time and is now in five parts and is an exhaustive
standard on power transformers.
Standard specifications of a Power Transformer
Number of phases: single or polyphase
Frequency : 50Hz
KVA Rating : generally rated in MVA (like 200 MVA)
Rated voltages for each winding: 440KV/220KV, 220KV/66KV(greater than 33KV)
Connection symbol : star/delta
Requirements of on-load / off-load tap changers
Impedance voltage at rated current
Indoor or outdoor type
Type of cooling : ONAN,ONAF,OFAF,OFWF
Temperature rises and ambient temperature conditions including altitude and in
case of water cooling, chemical analysis of water.
Number of cooling banks, spare capacity and cooling pumps & fans.
Highest system voltage for each winding
Method of system earthing for each winding
Insulation levels
Over fluxing conditions
Details of auxiliary supply voltage (for fans, pumps, OLTC, motor alarm, control).
Controls of tap changers
Short circuit levels of the system
Vacuum and pressure withstanding values of the transformer tank
Noise level requirement
Number of rails and rail gauge for movement along shorter and longer axes
Fittings required with their vivid description
.
Standard specifications of a Distribution Transformer
Indian standard IS 2026 "Specification for Distribution Transformers" is the governing
standard on Distribution Transformers.
The following information must be available with enquiry and order for the design and
drafting of the transformer.
Number of phases: single or polyphone
Frequency : 50Hz
KVA Rating : generally rated in MVA or KVA (less than 200 MVA)
Rated voltages for each winding: 33KV/11KV, 11KV/440V(less than 33KV)
Connection symbol : delta/star
Requirements of on-load / off-load tap changers
Impedance voltage at rated current
Indoor or outdoor type
Type of cooling : ONAN,ONAF
Temperature rises and ambient temperature conditions including altitude and in
case of water cooling, chemical analysis of water.
Number of cooling banks, spare capacity and cooling pumps & fans.
Highest system voltage for each winding
2
Insulation levels
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Installation:
Location, site preparation and foundation details:
Location
The location factor deserves careful attention simply because of its long term
consequences. Any mistake in selection of a proper location could prove to be costly.
Transportation Facilities
The raw materials and end products require to have uninterrupted receipt and
dispatch facilities through good road connections, proper linking with ports and
railheads. Possibility of an in-plant rail siding has to be looked into depending on the
amount of raw materials and products to be handled.
Manpower Availability
Local availability of skilled and semi skilled manpower will add to the
efficient running
Environmental condition
Now-a-days, there is a great deal of awareness towards maintenance of natural
ecological balance. Regarding the effect of pollution from specific type of plants,
social obligations are to be met. The nature of the site selected should preferably
have some advantages to meet this requirement
Site preparation
The location may be indoor or outdoor.
For indoor installation, the following aspects should be considered:
(i) Ventilation Noise level
(ii) Space required for movement, maintenance etc
(iii) Trenches for cables
Minimum clearances between the transformer and the walls should be as
follows.
Clearance on all four sides of wall:1.25 m
Clearance on all three sides of wall: 1 m
Clearance on a wall on backside only: 0.5 m
The clearance of 0.5 m (minimum) should be provided between the top most point
of the
conservator and the roof.
Ventilation area: The ventilation area required is as follows.
Outlet: 2m2 per 1000 KVA
Inlet: 1m2 per 1000 KVA minimum
Indoor transformers having oil capacity of more than 2000 liters should be provided
with soak pits.
Power cables and control cables should never be run in the same conduit or cable
3
To send small and medium transformers trucks and large transformers road trailers
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Immediately after arrival at site, it should be inspected for possible damages during
transit.
The nitrogen gas pressure should be checked.
Positive pressure if not found, indicates that there is leakage, and there is a possibility
of the moisture entering the tank during transit.
This can be ascertained by dew point measurement which indicates the amount of
surface moisture content in transformer insulation.
Internal inspection should be carried out to the extent possible through inspection
covers.
Particular attention should be paid to the connections, bolt links, coil clamping bolts,
tap changers.
Current transformers and the general insulation.
Break down strength of oil of transformer tank and drums containing transformer oil
should be examined carefully.
An inspection of the transformer on arrival at site is to be carried out preferably in the
presence of the representative of the manufacturer.
4Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Shaped tanks: Here the profile of the tank body is suitably shaped to make it
more economical. The shaping is decided by the electrical layout, considerations of
transformer windings and terminal gear/tap changers mounting arrangements.
Bell shaped tanks: Tanks which are made into two separable parts are known
as bell type tanks. When the top portion is removed, the height of the lower portion is
such that there is accessibility to the core and winding for inspection and maintenance
Stub-end wagon type tanks: These tanks are of special construction and
designed to withstand dynamic loading during transit besides the static load. Such
5
large size transformers are not supported on girders thereby reducing the height during
Page
transport. The design is such that these tanks are supported from either end stub-end
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
wagons and the transformer hangs in the vertical position, with minimum
clearance between the bottom of the tank and railway track.
Testing of tanks:
The oil pressure and vacuum testing are conducted to ensure against leakages
and to check for strength.
Oil pressure test:
The oil is filled up to tank cover and the required pressure is applied
using pump.
The pressure is maintained for few hours and all the wildings are checked
for leakages.
In case of leakage, rectification is done by draining out the oil. The tank
deflection readings are measured before the starting of oil pressure, at full
oil pressure and after releasing the oil pressure.
Vacuum test:
The oil is completely drained.
After ensuring all the fitting, the vacuum pump is started and the required
vacuum is measured by a vacuum gauge.
During vacuum testing the air leakage points are detected by air leakage
detecting instrument.
If the leakages are found in casketed rims, the bolts are tightened.
The deflection reading at the starting and after maintaining full vacuum
for one hour and releasing the vacuum are taken to find out the
permanent deflection.
This shall be within specified allowable limits of deflection, depending
on the size of the tanks.
Measurement of stresses:
At various locations stresses are required to be measured.
The strain gauges are fixed to the tank structure with proper adhesive.
A gauge consists of a fine wire suitably fixed to the body of the structure.
Under load, strains are developed on the body.
This results in displacements of the points to which the ends of the gauges
are fixed.
This changes the resistance of the gauge wire, which is measured
electrically using a suitable electric / electronic bridge.
One typical strain gauge is Rosette delta with six wires connected to the
ends of wire gauges and brought to the bridge for measurement.
The bridge is set to null balance prior to the commencement of the
measurements.
The readings are simultaneously recorded.
The tank is subjected to full vacuum and readings are taken.
The strain gauges are fixed inside and outside the tank wall to compare the
top and bottom principal stresses on the surface.
The strain gauge gives values of strains in the direction of Rosettes from
which the two principal stresses and their directions are calculated.
6Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
acids present in the oil and is expressed in terms of milligrams of KOH required to
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
(up to 2 pap).
Page
During periodic maintenance crackle test, dielectric test, acidity test and moisture
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Drying of Transformers:
1) Only spirit type thermometers are to be used for temperature measurement. Mercury
thermometers shall not be used except in the pockets provided for this purpose.
2) The temperature of transformer oil in the top should not be more than 85°C. The
maximum sustained temperature to which anything in contact with the oil should be
raised, is 90°C.
3) Under no condition the transformer is left unattended during any part of the dry out
period. The transformer should be under constant observation throughout the dry out
process and all observations shall be carefully recorded.
4) It is recommended to keep firefighting equipment ready during dry-out period. Naked
lights and flames should be kept away while the drying operation is in progress.
5) process and all observations shall be carefully recorded.
6) It is recommended to keep firefighting equipment ready during dry-out period. Naked
lights and flames should be kept away while the drying operation is in progress.
Oil temperature
Page
By external heat:
The transformer may be placed in its own tank without oil.
Externally heated air is blown into the tank at the bottom through the main oil valve.
A small blower or fan should be used to get the proper circulation.
It is desired to-force as much of the heated air as possible through the ducts in the
transformer windings.
To accomplish this, baffles should be placed between the core and the case, closing
off as much of the space as possible.
The convenient way to get the heated air is by passing air through grid resistors.
The resistors are in fire proof box.
The temperature of the air should not exceed 115°C.
The heat may also be obtained by direct combustion but care is to be taken to avoid
the products of combustion entering into the transformer tank.
By both external and internal heat:
This is a combination of the hot air circulation and short circuit method.
The current circulated in the windings should, of course, be less than when drying out
is done by the method of short circuit alone.
11
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Testing of Transformers
Following tests are carried out when the work is at different stages, prior to the insertion of core
and coil assembly in the tank.
These tests help in locating any fault at an early stage.
1. Core insulation
2. Core Loss test
3. Check of ratio, polarity, vector relationship and winding resistance of transformer
assembly.
4. Preliminary Load Loss and impedance voltage measurements
The completely assembled transformer is subjected to the following final tests in accordance
with international standards.
These tests are
a)Routine tests: These tests are conducted on every transformer before it Leaves the factory,
to ensure that it is in accordance with the specifications.
1. Voltage ratio
2. Polarity test
3. Winding resistance test
4. Impedance voltage, short circuit impedance and Load Loss Measurement.
5. Dielectric tests
6. No Load Losses and current Measurement.
7. On Load tap changers
8. Power frequency withstand test
b) Type tests: These tests are performed on a single transformer which is representative of
batch of transformers, to demonstrate that they comply with specified requirements and are not
covered by routine tests.
1. Temperature rise test
2. Lightning impulse test
3. Air pressure test
4. Permissible flux density and over fluxing Noise Level test.
5. Sudden short circuit withstand test
C) Special Tests: The tests conducted other than routine or Type tests, based on the
agreement between the manufacturer and purchaser as asked for in the tenders/orders placed;
1. Zero sequence impedance on three phase transformers .
2. Acoustic sound level
3. Harmonics on the no-load current
4. Power taken by fan and oil-pump motors
5. Partial discharge test
6. Vibration test
7. Tan delta test
Special tests and type tests are to be performed in the presence of the purchaser or his
12
Routine Tests
1. Polarity testing
Polarity means the direction of the induced voltages in the primary and the secondary
winding of the transformer. If the two transformers are connected in parallel, then the polarity
should be known for the proper connection of the transformer. There are two types of polarity one
is Additive, and another is Subtractive.
Each of the terminals of the primary as well as the secondary winding of a transformer is
alternatively positive and negative with respect to each other as shown in the figure below. Let A1
and A2 be the positive and negative terminal respectively of the transformer primary and a1, a2 are
the positive and negative terminal of the secondary side of the transformer. If A1 is connected
to a1 and A2 is connected to a2 that means similar terminals of the transformer are connected, then
the polarity is said to be additive. If A1 is connected to a2 and A2 to a1, that means the opposite
terminals are connected to each other, and thus the voltmeter will read the subtractive polarity.
Connect the circuit as shown in fig and apply the voltage gradually. Now note down the
values of voltmeter V1,V2 andV3. If V3 reads V1 + V2 shows the proper connections and the
connections made permentanly. If V3 reads V1 - V2 shows the improper connection then
connection has to be changed
3. Ratio test
This test can be done using calibrated voltmeter .But it is preferable to do it by ratio-
testing apparatus called RATIOMETER. This consists of portable transformer with fixed
primary and secondary winding have large number of taps connected to a two selector switches,
one course and the other is fine, so that any desired could be obtained for direct reading.
The HV side of the transformer under test is connected to a low voltage mains supply
say 400 or 220 V and the induced voltage in the secondary is compared with the voltage output
of Ratiometer, after ensuring the two voltages are in opposition. Accurate readings are obtained
14
I0R0 =
where Ic --- is the charging current and Il --- is the leakage current
After sometime the charging current reduces to zero and only leakage current is present.
I0R0 =
Polarization Index: Polarization index gives the true idea about the quality of insulation and
also the extent of dryness. It depends upon the temperature at which insulation resistance is
measured.
Polarization index is the ratio of megger value taken for 60 sec to the megger value taken
for 15sec.
˃1
15
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
For calculating the load loss and impedance at different tap positions ,recording should be very
quick and also the interval between the measurements at different taps should be sufficient to
avoid errors due to momentary temperature rise Three watt meters are instead of two watt meters
to avoid large wattmeter multiplier constant. The power factor during load loss should be less
than 0.1 and wattcmeters suitable for such low power should be used.
LV winding is supplied with normal voltage. the input power measured will give no-load loss.
The no-load current and losses are useful in evaluating the efficiency of transformer
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
TYPE TESTS
1.Temperature Rise Test
The temperature rise test is one of the type tests which confirms the design for
temperature rise. The is called as Heat run test . The test simulates the conditions of continuous
rated load and occurrence of temperature rise
For standard tank, the dissipation constant is known. in such case it is necessary to
measure only transformer losses and to calculate the temperature rise of the coil and winding on
continuous loading .For non-standard tank, it is necessary to carry our temperature rise on the
transformer and different methods to obtain the temperature rise are as follows
1. Short circuit test
2. Back to Back test
3.Delta/Delta test
4. Open circuit test
Short circuit test
In this method One winding is short circuited and the Voltage applied to the other
equal to Full load losses of the transformer. The Measurement of temperature is done using
Thermocouples placed in the transformer.
Delta/Delta test
In this method the Full rated voltage is applied to one winding Which accounts for
full load iron losses. By external source full load current is circulated in another winding,Which
accounts for full load copper losses. As current circulated in winding the temperature in the
winding rises Record the temperature of the winding for every 15mins till it reaches steady
value.Time take to reach the final temperature is Thermal time constant.
This test is necessary for all indoor and outdoor transformer. Standard impulse wave of
specified amplitude is applied twice in succession. If there is no flash over and puncture of the
insulator, then the transformer is considered to have passed the test , on other hand ,if there is
puncture occurs ,is considered to have failed the test. During the test one wave should be applied
with reversal of polarity. The peak value and wave shape of the test voltage is recorded by means
of storage oscilloscope
18
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
1. Cooling
The oil act as an insulating medium and cooling medium. Heat generated is removed by the
oil and transferred to atmospheric air or water
The effective cooling ensures longer life due less thermal degradation
This method of transformer cooling is generally used in small transformers (upto 3 MVA). In
this method the transformer is allowed to cool by natural air flow surrounding it.
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Air Blast
For transformers rated more than 3 MVA, cooling by natural air method is
inadequate. In this method, air is forced on the core and windings with the help of fans or blowers.
The air supply must be filtered to prevent the accumulation of dust particles in ventilation ducts. This
method can be used for transformers upto 15 MVA.
21
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
2.Buchholz Relay
Buchholz relay is used for the protection of oil filled transformer from incipient
faults below oil level. This relay is installed between the transformer tank and conservator.
Whenever the fault occurs due to low oil level the relay gives the alarm. The arc due to the fault
causes the decomposition of oil. The product of decomposition contains more than 70% of
hydrogen gas, which being light, rises upwards and tries go in the conservator. The buchholz relay
is fitted in the leading to conservator . The gas get collected in the upper portion of relay, there by
the oil level in the relay drop down .The float, floating in the oil levelin the relay tilts down with
the lowering oil level. While doing so the mercury switch , attached to the float is closed and
mercury switch closes the alarm circuit. Thereby the operators know about there is some fault in
transformer and is disconnected as soon as possible. The gas sample is tested and testing gives
idea regarding the type of fault. The schematic diagram is as shown in the fig
3.TAP CHANGERS
The voltage variation is a normal phenomenon ,because of rapid growth of electrical load and
distribution network. It is necessary to maintain system voltage within the specified limit for the
better health of electrical equipment .The system voltage maybe adjusted by changing the tapping
on the power transformer. The variation in voltage may be brought in either by step or step less
control .But the practice proved that voltage variation is handled effectively in steps without
22
creating objectionable disturbance on the system. This variation is generally achieved by means of
tappings on the power transformer because of the smaller currents to be dealt with , are normally
Page
Off circuit tap changer: The economic method of changing the turns ratio of a
transformer is the use of off-circuit tap changer. As the name suggest ,it is necessary
to de-energize the transformer before changing the tap. A mechanical lock is provided
to prevent unauthorized operatin and inadvertent operation. The transformer are
normally provided with off-circuit taps with +2.5 percent and +5 percent on hv side.
The station transformers are preferably provided with OLTC with +10% in steps of
1.25 percent on hv side
4. Flow or oil level indicator: it is fitted in oil circulation system which indicates the Flow
rate. it is used for control purpose in combination with float switches for starting and stopping of
oil pumps
5.Pressure relief valve: It is fitted on the tank to act as an exit for gasses formed of oil. A up of
gaseous pressure .If this pressure is not relieves within few milliseconds ,the transformer tank gets
ruptured ,spilling oil over wide area..
6.Sudden pressure relay: (Rate of rise of pressure relay): The rate of rise of pressure relay
responds to sudden rise of pressure due to internal arcing. The relay is fitted on the tank
7. Conservator: It is a large cylinder connected by pipe to the transformer. The oil is filled upto
certain level in the conservator
8.Breather: one end of breather is connected to air cushion in conservation and the other end is
towards the external air
9.Oil temperature indicators: the thermocouple is placed in the pocker provided with the
tank near hot oil
10. Winding temperature indicator (Hot spot indicator)with alarm and tripping
contacts: Thermocouples are placed in the tank near hot oil. The indicator is provided with alarm
and tripping contacts
23
Page
TESTING AND COMMISSIONING OF POWER SYSTEM APPARATUS 15EE752
Introduction:
Synchronous generators and Synchronous Motors are called Synchronous
Machine
Synchronous generator is the major component of power system.
Based on the source of power generation they are classified a) Turbo Alternator
b) Gas turbo -generators c) Industrial Synchronous generators
The important step in selection of Synchronous Machines for specific application is deciding
the ratings considering all affecting parameters.
Voltage Rating: 11KV, 3.3KV,1.1KVetc
Excitation Voltage: 110V-1000V DC
Excitation Current: 10 to 100A
Power Rating: specified in KW
Type of Mounting: The mounting is to be specified like vertical mounting,
Horizontal mounting etc.
Rated Current and rated frequency with variation
Class of insulation: The class of insulation used for winding is to be given i. e class A,
E, B, F and H
Ambient temperature
Type of construction and bearing arrangements
Cooling system
Method of starting and drive details
Performance requirements with respect to efficiency and related parameter
INSTALLATION OF SYNCHRONOUS MACHINES
The rotor of a synchronous machine needs dc current for excitation. The field current is
supplied and controlled by the excitation system. An excitation system includes all the
equipment required for supply of field current and voltage regulator system. Excitation
response is the rate of change of exciter voltage and is expressed in terms of volts per
second.
The maximum voltage that may be attained by an exciter under specified condition of
load is termed as excitation ceiling voltage. The function of the excitation system is to
supply and regulate field current.
Brushless (static) excitation system:
control system. Rotating magnetic field of Dc excitation field of rotor induces 3 phase Ac
Page
EMF in stator armature winding. Flow of stator armature current Ia produces induced
revolving magnetic field in the air-gap, revolving At synchronous speed and locked with the
rotor magnetic field. The angle between the stator field and rotor field is the load angle
which increases with load and undergoes oscillation during disturbances.
The main exciter provides DC field Voltage and current to the rotor field winding of the
generator. The exciter terminal voltage decides the excitation current. The AVR controls
exciter terminal voltage and alternator excitation rotor field current to regulate generator
terminal voltage. The pilot exciter feeds power to the field winding of main exciter.
The AVR in the excitation system plays a very vital role Voltage control, controlling reactive
power supply, emf, Voltage and power factor of generator, and also maintaining power
system dynamic stability, and in protection of alternators by imposing several limits on
generators variables.
The Functions of an AVR
1. Regulation of terminal voltage automatically: To regulate the terminal voltage within
specified limits of the generator automatically under steady state operating condition of
varying load/pf. This is done by controlling field current by means of a feedback system
involving voltage transformer and AVR.
2. To facilitate reactive power load sharing with other generators operating in parallel
3. To regulate the voltage and load angle under abnormal conditions and transient
disturbing such as faults, power swings, sudden switching in of large loads, etc
4. To damp swing and electromagnetic oscillations in load angle under abnormal conditions
and transient/dynamic disturbing conditions rotor oscillations of synchronous generators and
ensure stable operation.
5. To ensure protection of generators and excitation system by giving tripping command
under appropriate abnormal conditions of variables.
6. Limiting Features: To inhibit the tripping of the generators unit by protection system under
permissible swings in active power and reactive power. AVR operates in close liaison with
the generator protection system and raises the operating limits for ensuring generator service
during disturbances.
4
Page
Cooling Methods
1. Open Pedestal: In this the stator and rotor ends are open to the outside ambient
temperature, the rotor being supported on pedestal bearings mounted on the bedplate.
2. Open End Bracket : In this the bearings forms part of the end shields which are fixed to
the stator housing . The air is in comparatively free contact with stator and rotor.
3. Protected or End-Cover type with guarded Openings: The protector may be Screen or
fine mesh covers.
4. Drip,Splash or hose proof: This is complete protected Machine with openings in the end
shield for Cooling.
5. Pipe or Duct Cooled: With the end covers Closed except for flanged openings for
connection to cooling pipes.
6. Totally Enclosed: In this type , the air will not be in contact with the ambient air, The
machine is totally air tight. Total enclosure may be associated with an internal rotor fan, an
external fan.
7. Flame proof or Explosion proof: This Motor is used in hazardous location such as mines,
chemical Industries.
Duty
The duty requirements shall explicitly be given by the purchasers as accurate as possible. The
Duty requirement may be declared numerically or with the aid of time sequence graphs. The duty
declaration for an electric motor is very important as the electric motors have the time rate of
temperature rise.
Classes of Duty:
S1 - continuous Duty: The motor is running long enough
S2 - short time Duty: Time of operation is very low
S3 - Intermittent periodic Duty: The motor operates for some time and then there is
rest period
S4 - intermittent periodic Duty with starting
S5 - continuous duty with intermittent periodic loading
S6 - continuous duty with starting & electric braking
S7 - continuous duty with periodic speed change
6
Page
Drying of Windings
The Insulation of Rotating machine is Hygroscopic(absorbs moisture) in nature. The
Moisture reduces the insulation resistance. It is essential to remove the moisture before
commissioning of the machine. The high resistance of Insulation gives the degree of dryness
of the insulation. The moisture is evaporated from winding due to thermal diffusion. The
moisture gradient depends on temperature gradient within wet insulation. The Desired
temperature is obtained by heating the winding. The insulation is measured by means of DC
Mega ohm meter(Megger). The Phase to Phase and Phase to earth insulation resistance
I0R60(Mega ohms). At the Working temperature of the machine should not be lower than the
Value found from the Equation.
𝑉𝑟𝑎𝑡𝑒𝑑
I0 R60 = 1000+0.01𝑃
Polarization Index: Is the ratio of insulation resistance of 60sec megger readings to the
insulation resistance of 15sec megger readings.
𝐼𝑜𝑅60
PI =
𝐼𝑜𝑅15
7
Page
The drying out procedure has three distinct phases.
In the beginning the insulation resistance decreases indicating that the moisture is
getting released within the insulation.
After few hours the insulation resistance reaches the steady state value indicating the
moisture content is distributed within the winding.
In the last stage the insulation resistance start increasing indicating the moisture is
expelled out. The drying out procedure is stopped when the desired value of hot
insulation resistance and polarization index are achieved for each winding .
at three phase
Page
The open circuit characteristics of a synchronous machine is the curve showing the
relationship between armature terminal voltage and field excitation. The prime
mover is run at rated speed. The excitation is varied in steps and corresponding no
load voltage is recorded. The characteristic curve may be plotted in per unit where
unit voltage and unit excitation corresponding to rated voltage and excitation current
on the air gap Line. The open circuit characteristics represent the relation between
the space fundamental component of the air gap flux and the miff on the magnetic
circuit when the field winding constitutes the only source. During no Load test the no
Load Losses of the machine can be obtained. The test circuit for No load test and NO
load characteristics are shown.
In this test, the synchronous generator terminals are shorted through ammeters as
shown in fig. and the field current is gradually increased till the ammeter current
reaches a maximum safe value (about 1.5 times rated current). The relation between
field current and short circuit current is drawn and is known as short circuit
characteristics. In sustained Short circuit test, the values of field current and armature
current refer to the steady state values and measured using indicating meters.
The sustained three phase short circuit test is also conducted by a retardation test on
the machine. The machine under test is driven by an electric motor at rated speed and
is excited to get the short circuit current in the armature. The machine under test is
retarded by putting off the supply to driving machine. The armature current in each
phase and the corresponding field current are noted. If the machine has retardation
above 4 percent of its rated speed per second, excitation from separate source is used
to get stable excitation during the test
10
Page
5. SHORT CIRCUIT RATION (SCR) OF SYNCHRONOUS MACHINE
The Short circuit ration of synchronous machine is defined as the ratio of field current
Ifoc required to obtain rated open circuit voltage to the field current Ifsc required for obtaining
rated sustained short circuit current when running at rated speed .
𝐼𝑓𝑜
SCR = =K
𝐼𝑓𝑠𝑐
The SCR is obtained from the data of the No load test and sustained short circuit test
conducted on a machine as shown in fig. The impedance in the steady state condition is is
known as the synchronous impedance and defined as the ratio of field current at rated
armature current on sustained symmetrical short circuit to the field current at normal open
circuit voltage on the air gap line.
11
Page
SUDDEN 3- SHORT CIRCUIT TEST
When an alternator is subjected to sudden short circuit, the current in all the three Phases
increases suddenly to a high value (10 to 8 times full Load current) during the First
quarter cycle. The flux crossing the air gap is Large during first couple of cycles. The
reactance during this period is Least and the short circuit current is high. This Reactance
offered during sub transient period is called as sub transient reactance X d΄΄. The First few
cycles are covered under sub transient state. After few cycles the decrement in rms value
of short circuit current is Less rapid than that during the first few cycles. This State is
called as Transient state and the reactance offered during this period is called as transient
reactance Xd΄. The circuit breaker contacts open during this period. Finally the transient
dies out and the current reaches a steady sinusoidal state called the steady state and the
reactance offered during this state is called as steady state reactance X d. Since the short
circuit current lag the voltage by 90°, the reactance involved is direct axis reactance.
The sudden 3-phase short circuit test is conducted at rated speed and at desired no
load voltage.
The 3 phases are shorted suddenly.
To measure short circuit current storage oscilloscope with proper probe multiplier is
used.
The terminal voltages of machine and excitation current and winding temperature are
measured just before the short circuit.
To obtain quantities corresponding to the unsaturated state of the machine, the test is
performed at several armature voltages of 0.1 and 0.3PU of rated value.
To get quantities corresponding to the saturated state of the machine, the test is
performed with rated at the terminals of the machine before applying the short circuit
to the armature winding.
To determine the machine quantities, oscillogram of the armature current in the
excitation is taken.
The short circuit is initiated by closing the circuit breaker
Fig A shows the test set up and fig B shows the oscillogram current
12
Page
The currents and reactance are given by the following expressions
I=
𝑶𝑨 𝑬𝒂
= ; X -- Steady state reactance = 𝐸𝑎
√𝟐 d
𝑿𝒅 𝐼
𝑶𝑩 𝑬
I' = = ; X' -- Transient state reactance = 𝐸𝑎
√𝟐 𝑿𝒅′
d 𝐼′
𝑶𝑪
I'' = = 𝑬𝒂 ; Xd'' -- Sub transientstate reactance = 𝐸𝑎
√𝟐 𝑿𝒅′′ 𝐼′′
During the slip test, subnormal symmetrical three phase voltage of magnitude 10 to
20% of the rated voltage is applied to the armature terminals of the machine. The
field of the alternator is either open circuited or short circuited. The prime mover is
run at slightly less than synchronous speed to get a slip of 0.01. Armature current and
voltages are measured using indicating instruments or recorded by using
oscilloscope. The ammeter & volt meter readings will indicate two values which are
to be taken as minimum and maximum quantities respectively. To find out Xq and
Xd
𝑉𝑚𝑖𝑛
Xq = ohm
√3 𝐼𝑚𝑎𝑥
𝑉𝑚𝑎
Xd = ohm
√3 𝐼𝑚𝑖𝑛
13
Page
If Imax do not coincide with Vmin, use in calculations Imax as a base and its
corresponding voltage.
If during the test, the residual voltage of the machine is in the limits of 0.1-0.3 of the
supply test voltage
9. VIBRATION TEST
The vibration test is carried out on the complete machine after assembly and
balancing of the machine. A set of three orthogonal accelerometers are fixed on each
bearing. The vibrations are measured in two directions normal to the shaft. For
vibration test the machine is run at no load without coupling to any machine .
Noise in Motors
The noise of a rotating machine is generated by a cooling air from its fan as it passed
through or over the machine. Some noise reduction is possible by substituting
unidirectional trailing bladed fans by the normal radial blades Further reduction is
achieved by inlet and outlet silencers or the adoption of closed ventilation circuit of
cooling air.
The noise is also caused by magnetic effects and dependent on the stator and rotor slots. It
c a large vibration of air-gap flux density. This may produce a penetrating note at
approximately slot frequency (e.g. 0.5 – 1.5kHz). The amplitude of stator permeance
variation may be the cause, but the amplitude also depends on higher order rotor m.m.f.
space harmonics. The frequency of the noise is twice the product of the supply frequency
with that integer nearest to the number of slot per pole.
an occur in machine with fractional number of open slots per pole, producing a relatively
10. LOW SLIP TEST
During the low slip test, sub normal symmetrical 3phase voltage is applied to the armature
terminals of the machine under test. The voltage should be such that the machine does not
pull in. The excitation winding should be open circuited and rotor should be driven by a
prime mover at a slip less than 0.01pu. There by the current induced by the damper winding
during synchronous operation will have negligible influence on the measurements. During
switching on and off of the supply, the excitation winding should be closed to avoid possible
damage. The armature current and voltage and slip ring voltage and Slip are measured by
indicating instruments or recorded by Oscillograph If the residual voltage measured before
the test is larger than 0.3 of the supply test voltage, the rotor should be demagnetized.
To determined Xq from the low slip test, armature current and voltage are measured to
maximum excitation winding voltage (U) and Xq is calculated using the formula
𝑉𝑚𝑖𝑛
Xq = ohm
√3 𝐼𝑚𝑎𝑥
𝑉𝑚𝑎𝑥
Xd = ohm
√3 𝐼𝑚𝑖𝑛
11. Temperature rise test:
The aim of this test is to find out the temperature rise on different parts of the motor while running at rated
conditions. During temperature rise test, the motor should be shielded from currents of air entering from adjacent
pulleys and other machines. A small current of air may cause great discrepancy in results obtained. The duration of
temperature rise test depends on the type of rating of the motor. For motors of continuous rating, the test should be
continued till the thermal equilibrium is reached. For motors of short time rating the duration of test corresponds to
the declared short time rating, the test should be continued till the thermal equilibrium is reached. Methods of
measuring temp The following methods are approved for determining the temperature of windings and other parts of
motor.
1) Embedded temperature detector method:
Embedded temperature detectors are resistance thermo-meters or thermocouples built
in the machine at points which are inaccessible when the m chine is assembled. This method
is generally employed for the slot portion of stator windings. At least six detectors to be built
in a machine suitably distributed around the circumference.
2) Resistance Method:
This method is generally used for stator whirling’s. Here temperature is
determined by the increase in the resistance of the windings.
3) Thermometer method:
In this method, the temperature is determined by thermometers placed at the
accessible surface of the rotor.
15 Page
ABNORMAL CONDITIONS AND EFFECTS ON SYNCHRONOUS
GENERATOR
Introduction:
Induction motors are widely used as industrial drives because of its simplicity,
reliability and low cost.
With the application of thyristor control, induction motor can be used for
variable speed drive.
Induction motor works with better efficiency appreciable over-load capacity and
maintenance required is minimum.
Three phase induction motor are available with various rating from fractional
HP to several thousand HP.
The important step in selection of induction motor for specific application is deciding the
ratings considering all affecting parameters.
Output Rating: The preferred output rating for induction motors upto and
including 110KW are 0.06, 0.09, 0.12, 0.18, 0.25, …….100KW
Type of Mounting:The mounting is to be specified like foot mounting, bed
mounting etc.
Rated voltage and rated frequency with variation
Class of insulation: The class of insulation used for winding is to be given i. e class A,
E, B, F and H
Ambient temperature
Type of construction and bearing arrangements
Type of enclose and cooling system
Method of starting and drive details
Performance requirements with respect to efficiency and related parameters
1Page
Testing and Commissioning of Power System Apparatus 15EE752
Rating plate giving the following details should be supplied with each motor
Types of Enclosures
Open ventilated motor
Ventilated motor
Drip proof motor
Water protected motor
Totally enclosed motor
Totally enclosed fan cooled motor
Environment proof motor
Weather proof motor
Hose proof motor
Duty
The duty requirements shall explicitly be given by the purchasers as accurate as possible. The
Duty requirement may be declared numerically or with the aid of time sequence graphs. The duty
declaration for an electric motor is very important as the electric motors have the time rate of
temperature rise.
Classes of Duty:
S1 - continuous Duty: The motor is running long enough
S2 - short time Duty: Time of operation is very low
S3 - Intermittent periodic Duty: The motor operates for some time and then there is
rest period
S4 - intermittent periodic Duty with starting
S5 - continuous duty with intermittent periodic loading
S6 - continuous duty with starting & electric braking
S7 - continuous duty with periodic speed change
Explosion Proof/Flame Proof
Flame-proof Enclosures are specially designed and built for installation in hazardous locations.
The hazardous locations include those which have
- Highly inflammable gases/vapours or liquids.
- Combustible dust
- Combustible fibres floating in air
- Highly inflammable liquids like petrol, napthal, benzene, ether, acetone, etc. This explosive
mixture of air and inflammable gas can explode in presence of electric arc or electric spark.
The primary consideration in the design of flame-proof enclosures is to prevent such
explosion. The flame-proof switchgear should be built such that
- The construction should be strong enough to with stand the high pressure from within, caused
by explosion of gas which enters the enclosure.
- The design should be such that the flame or spark within the enclosure should be carried out
3
of the enclosure
Page
- The flame- proof motors and switchgear should be installed, as for as possible away from
hazardous location. The motor and switch gear should be ‘flame-proof, or ‘ explosion -proof’
and should satisfy the codes and standards specified for such switchgear.
The Type 'n' Motor is an improved version of a normal Induction motor with the following
additional requirements.
• Non –sparking terminals
• Adequate clearances
• Welded end rings to prevent sparking while starting
• Adequate clearances between
• Stator and rotor
• Shaft and bearing
• Increased safety for terminal box
• Special enclosures
• Suitable axial and radial clearance between the fan and finned portions of the motor.
The electrical machine received at site must be placed in permanent storage within 4
days of their arrival.
The location in the store depends upon sequence of their handing over for
installation.
Before keeping in store the machine should pass on acceptance procedure intended to
check it for missing or damaged parts so as to take a necessary measure for avoiding
the violation of installation terms.
The electrical machines must be stored in dry, clean and well ventilated store room
protected against dam gases, coal dust etc.
The exposed metal surface of machine shall be coated with anti-corrosive grease and
4Page
All civil construction and foundation of the machine room should be fully completed
before the installation of the machine.
The machine room must have a enough space for the installation and dismounting of
machines
The cable conduit trenches should be cleaned and dried out
The machine room should be equipped with overhead travelling cranes of sufficient load
carrying capacity for handling assembled machines
Depending upon the size of the motor appropriate foundation is to be designed
The function of the foundation is to transmit the static and dynamic load of the running
motor to the ground.
The foundation should be strong to prevent displacement and vibration of a running
machine.
Three basic requirements of machine foundation are:
1. Horizontal level 2. Rigidity 3. Freedom from vibrations
It comprises the following essential features :
1) Foundation made on cement-concrete 2)Bed-plate 3) Foundation bolts
The machine is bolted to the Bed-plate. The Bed-plate is fixed on leveled foundation
The foundation bolts are used to securing the bed plate to the concrete foundation.
Rolled I-sections are placed in concrete on which the bed plate rest
1. Concrete Foundation
The machine with or without bed-plate should be securely bolted to solid, firm, level
foundation. The design of foundation depends on the size and speed of the machine .The
qualities of a good foundation are rigidity and freedom from vibration. The depth of
concrete foundation should be enough. For this excavation should be enough depth.The
depth should be depends on bearing capacity of soil.
Place the wooden farmers around the edges of the excavation at the floor
level.Also Place the I-shaped rolled sections in horizontal formation to provide
5Page
reinforcement to the concrete. The wooden farmers give the shape to the concrete plinth
Testing and Commissioning of Power System Apparatus 15EE752
3) Foundation bolts
The foundation bolts fix –up the bed –plate onto the concrete foundation. The lower
portion of the foundation bolts has an eye –shape or saw-tooth shape to provide grip in
the foundation. The foundation bolt is inserted in the holes of the bed plate with the
spring washer and plain packing washer between the nut and the plate flange. The
foundation bolts should be located with the bed plate hole before lowering bed plate .Fill
the space around the bolts with cement paste up to the surface level of foundation. Fill
up the cavities by using suitable rod for ramming the grouting and then it allowed to set
hard. After this the foundation nuts are tightened lightly, set carefully, aligned.
Vibrations
The excessive vibration in the rotating machine can be caused by one or many of the
following
3. If the motor does not vibrate when running alone, the vibration may be in the driven
equipment or caused by the shaft alinement
4. The shaft has to be aligned by using various method
Shaft Alignment
The perfect alignment of shaft of driving and driven machine is desired. The
misalignment will affects the machine operation. The radial and axial clearance between
the couplings of two shafts are measured after alignment. When the rotor is turned
through approximately 0ᵒ C,90ᵒC, 180ᵒC, 270ᵒC and 360ᵒC shall not differ by the
following values
- 0.03mm for 300 mm diameter coupling
- 0.5mm for 500 mm diameter coupling
The shaft of driven and driving machine is aligned by different methods. There are 3 steps
in the alignments
1. Axial positioning of the shafts
2. Paralleling the shaft axis
3. Centering of the shaft axis
The shaft of driving and driven machines is aligned on the bed plates in their final position
by using Shims under the feet of the machine. The feeler gauge is used to know the
difference by turning the rotor. The single point turn run over gauge is used to know the
difference in heights of vertical surfaces of couplings. Figure a & b shows the shaft
alignment procedure
7Page
Testing and Commissioning of Power System Apparatus 15EE752
Balancing of Rotor
It is essential that the rotor is to be mechanically balanced for smooth running
without developing vibrations. The balancing is obtained by adding or shifting weights
fixed on the rotor for counter balancing or the material from the rotor is etched /drilled out
from heavy side. The balancing can be achieved in two ways
a. Static balancing for low speed machines
b. Dynamic balancing for high speed machines
Static balancing: The rotor to be balanced is fixed on two knife edges of the balancing. The
centers or the knife edges must be in perfect horizontal plane. The well balanced rotor will remain
in standing in any position when turned about the axis in any direction, in any position and will
not oscillate. When the rotor is unbalanced, the heavier side is always try to come down and the
rotor cannot stay in any position. The balancing is achieved by addition of weight or removing
material from heavier portion of the rotor.
Dynamic balancing: This is carried out by using special balancing machines. The rotor of
themachine to be balanced is mounted on the axis of the balancing machine and driven at high
speed. If the rotor is unbalanced, it will vibrate at higher speeds. Dynamic balancing machine has
bearings supported by springs. To locate an unbalanced portion, one of the bearing is locked and
the other is left free to vibrate. An indicating needle is gently touched to the rotor and leaves a
mark at uneven portion. The same is repeated by rotating the rotor in reverse direction. The heavy
portion lies between the two marks which is removed or counter weight is placed.
8Page
Testing and Commissioning of Power System Apparatus 15EE752
Drying of Windings
The Insulation of Rotating machine is Hygroscopic (absorbs moisture) in nature. The
Moisture reduces the insulation resistance. It is essential to remove the moisture before
commissioning of the machine. The high resistance of Insulation gives the degree of dryness
of the insulation.
The different methods of Drying out are:
1. Drying out of induction motor by drying chamber and resistor heater
2.Drying out by radiating lamps
3. Drying out by circulating short circuit current
10
Page
Testing and Commissioning of Power System Apparatus 15EE752
Type Test:These tests are conducted on the machine to confirm the design
Routine Test: These tests are conducted on each motor to confirm proper manufacture
and to ensure trouble free performance at a site
Commissioning Test: These tests are conducted after installation before final
commissioning to ensure the machine is free from defects
Special Test: These tests are conducted to analyze the performance or for special
investigation
Development Test: These tests are conducted to analyze the effect of various design
parameters and stresses
Reliability Test: These tests are conducted to access the reliability of motor
The insulation resistance is done by using megger like transformer. (refer unit one and two
notes page 15-16) . If megger is not available we will go for volt-ammeter method.
The following are the methods to measure the winding resistance of the motor
1. The Drop of Potential or Voltmeter- Ammeter Method: In this simple method DC voltage
and current are measured by using volt meter connect in parallel and by ammeter connected in
series with the winding, when the values became steady.
11
Page
Testing and Commissioning of Power System Apparatus 15EE752
Since the resistance between two terminals is usually of 2 phases are in series, the resistance
perphase
Rdc = V/2I
The ac resistance is 1.5 times dc resistance because of proximity effect skin effect of ac current.
Rac = 1.5Rdc = 1.5V/2I = 1.5Rdc
2. Kelivin- Thompson double bridge Method:Resistance less than 1 ohm shall be measured by
Kelvin double bridge. The winding is connected at unknow resistance terminal of the bridge. And
the resistance is determined by varying the variable resister until the galvanometer shows zero
deflection. The variation of resistance between phases to the extended of 5 % may be permitted.
The three terminals of the motor are connected together and to the high voltage terminal of
test supply. The body is earthed and is connected to the earth terminal of test supply. In this
test, the test voltage is raised quickly to the maximum test voltage and applied for one
minute and reduced slowly to zero.
If the breakdown occurs, the test supply is automatically tripped. The test is conducted on
go/not go basis. While conducting the test, reference to the relevant standards and
manufactures instruction is to be made.
4. No load Test
This test is conducted to determine the no-load current, core loss and friction and
wind age losses. The motor is run on no-load at rated voltage and frequency until the input
power is constant. The readings of voltage, frequency, current and power are noted. This
test shall be preferably conducted immediately after the temperature rise test. The input
power is the sum of friction and wind age losses, core loss and no-load primary I2R loss.
The friction and wind age losses and core losses may be separated if required. The test setup
is as shown.
6. Load Test
The test with the load are conducted for the determination of performance such as efficiency,
power factor, speed and temperature raise. For all the test with load, the machine shall be
properly aligned and secured fastened.
13
The motor may be loaded by AC or DC coupled generator either directly or by belt. The
output of generator is measured and its effeminacy at various loads must be known to
Page
Testing and Commissioning of Power System Apparatus 15EE752
calculate the output of the motor under test. The input to the motor is measured by using Watt
meters. When belt drive is used, the power loss in the belt should be considered. When a
pony break is used, for large machines, then break gets extremely hot, so the observation
must be taken very quickly. This method is suitable for small machines testing in the
laboratory.
The aim of this test is to find out the temperature rise on different parts of the motor
while running at rated conditions. During temperature rise test, the motor should be shielded
from currents of air entering from adjacent pulleys and other machines. A small current of
air may cause great discrepancy in results obtained. The duration of temperature rise test
depends on the type of rating of the motor. For motors of continuous rating, the test should
be continued till the thermal equilibrium is reached. For motors of short time rating the
duration of test corresponds to the declared short time rating, the test should be continued till
the thermal equilibrium is reached. Methods of measuring temp The following methods are
approved for determining the temperature of windings and other parts of motor.
1) Embedded temperature detector method:
Embedded temperature detectors are resistance thermo-meters or thermocouples built
in the machine at points which are inaccessible when the m chine is assembled. This method
is generally employed for the slot portion of stator windings. At least six detectors to be built
in a machine suitably distributed around the circumference.
2) Resistance Method:
This method is generally used for stator windings. Here temperature is determined
by the increase in the resistance of the windings.
The temperature is determined by the formula
T2 – Ta = x(235+T1)+T1-Ta
b) Stroboscopic Method:
In this method, the disc is painted with alternate black and white strips and it is attached
to motor shaft.The disc is illuminated by neon lamp from stroboscope.The complete
apparent revolution of disc correspondence to slip per pair of poles. Slip is calculated
using
9. Noise in Motors
The noise of a rotating machine is generated by a cooling air from its fan as it passed
through or over the machine. Some noise reduction is possible by substituting
unidirectional trailing bladed fans by the normal radial blades Further reduction is
achieved by inlet and outlet silencers or the adoption of closed ventilation circuit of
cooling air.
15
The noise is also caused by magnetic effects and dependent on the stator and rotor slots. It
can occur in machine with fractional number of open slots per pole, producing a relatively
Page
Testing and Commissioning of Power System Apparatus 15EE752
a large vibration of air-gap flux density. This may produce a penetrating note at
approximately slot frequency (e.g. 0.5 – 1.5kHz). The amplitude of stator permeance
variation may be the cause, but the amplitude also depends on higher order rotor m.m.f.
space harmonics. The frequency of the noise is twice the product of the supply frequency
with that integer nearest to the number of slot per pole.
Various steps in installation of a large rotation machine received in dismantled condition are:
Installation of bed plate and the leveling of bed plate
Installation of the bearing pedestals and leveling of the bearing
pedestals
Checks on stator and rotor
Assembly of the rotor onto the shaft
Installation of the stator
Installing the rotor in the stator
Checking of the air gap between stator and rotor
Installation of the the driven and drive machine in the similar fashion.
Preparation of shaft couplings
Mounting of shaft couplings on shaft
Preparation of shafts and alignment of shafts.
Installation of cooling systems
Drying out
Testing
Commissioning
16
Page
Testing and Commissioning of Power System Apparatus 15EE752
Each of the above activities should be carried out by technically skilled staff. The
instruction manual supplied by the manufacturer should be referred in practice. Shaft
alignment should be, perfect to get trouble free mechanical performance of the
generator with the driven equipment. The rating plate is of definite dimensions as per IS
Code. The ratings are etched or engraved and is fixed to the machine in a clearly visible
position
2. Single phasing: one of the supply lines gets disconnected due to the rupturing of the
fuse or open circuit in one of three supply connections. In such case motor continues to
run with the single supply. If the motor is loaded to its full rate load, it draws excessive
current on single phasing. The windings get overheated and damage the insulation of the
winding.
The single phasing also causes the unbalanced load resulting in excessive heating of the
rotor due to negative sequence component.
Protection: the motor should be protected with the negative phase sequence relay,
thermal overload relays and static single phasing relays.
3. Internal faults in the motor: It is mainly due to the overloading, abnormal supply
conditions which results in failure of insulation resistance and temperature rise
Protection: the motor should be protected with the differential protection, over current
relay the motor should be protected with the s,HRC fuses
4. Stalling: If the motor dos not start due to the excessive load, it draws heavy current . It
should be immediately disconnected from the supply.
Protection: the motor should be protected with the thermal relays and instantaneous O.C
relays.
6. Switching surges:
Protection: the motor should be protected with the RC surge modifiers, Zno arresters near
motor terminals
17
Page
Testing and Commissioning of Power System Apparatus 15EE752
Storage of spares
The repeated inspection leads to wastage of time and money. The neglected/hardly Inspection
leads to failure.
The frequency of inspection must depend on
Importance of the machine
Duty cycle
Age
Overloads, service conditions
The maintenance schedule is always recommended by the manufacture
EVERY WEEK
ONCE A YEAR
20
Page
Testing and Commissioning of Power System Apparatus (15EE752)
Syllabus:
Laying of Underground Cables: Inspection, Storage, Transportation and Handling of
Cables, Cable Handing Equipment, Cable Laying Depths and Clearances from other
Services such as Water Sewerage, Gas, Heating and other Mains, Series of Power and
Telecommunication Cables and Coordination with these Services, Excavation of Trenches,
Cable Jointing and Terminations Testing and Commissioning. Location of Faults using
Megger, Effect of Open or Loose Neutral Connections, Provision of Proper Fuses on Service
Lines and Their Effect on System, Causes and Dim, and Flickering Lights.
Introduction:
An underground cable essentially consists of one or more conductors covered
with suitable insulation and surrounded by a protecting cover.
Although several types of cables are available, the type of cable to be used will
depend upon the working voltage and service requirements.
In general, a cable must fulfill the following necessary requirements:
1. Direct laying:
This method of laying underground cables is simple and cheap and is much favored in
modern practice.
In this method, a trench of about 1•5 meters deep and 45 cm wide is dug.
The trench is covered with a layer of fine sand (of about 10 cm thickness) and the
cable is laid over this sand bed.
1 Page
Testing and Commissioning of Power System Apparatus (15EE752)
The sand prevents the entry of moisture from the ground and thus protects the cable
from decay.
After the cable has been laid in the trench, it is covered with another layer of sand of
about 10 cm thickness..
Advantages
Disadvantages
This method of laying cables is used in open areas where excavation can be done
conveniently and at low cost.
2. Draw-in system:
In this method, conduit or duct of glazed stone or cast iron or concrete are laid in the
ground with manholes at suitable positions along the cable route.
Three of the ducts carry transmission cables and the fourth duct carries relay
protection connection, pilot wires.
Care must be taken that where the duct line changes direction; depths, dips and offsets
be made with a very long radius or it will be difficult to pull a large cable between the
manholes. The distance between the manholes should not be too long so as to simplify
the pulling in of the cables.
The cables to be laid in this way need not be armored but must be provided with
serving of hessian and jute in order to protect them when being pulled into the ducts.
Advantages
(i) Repairs, alterations or additions to the cable network can be made without
opening the ground.
(ii) As the cables are not armored, therefore, joints become simpler and
maintenance cost is reduced considerably.
(iii) There are very less chances of fault occurrence due to strong mechanical
protection pro-vided by the system.
2
Disadvantages
Page
Testing and Commissioning of Power System Apparatus (15EE752)
3. Solid system:
In this method of laying, the cable is laid in open pipes or troughs dug out in earth
along the cable route.
The toughing is of cast iron, stoneware, asphalt or treated wood.
After the cable is laid in position, the troughing is filled with a bituminous or asphaltic
compound and covered over.
Cables laid in this manner are usually plain lead covered because troughing affords
good mechanical protection.
Disadvantages
2. Discontinuity
Page
Testing and Commissioning of Power System Apparatus (15EE752)
3. Earth fault
Murray Loop Test For finding out the exact position of fault, cables are to be repaired
without digging the whole cable route trench.
For this purpose, the Murray loop test which is based upon the principle of wheat-
stone bridge, and bridge Megger is used.
The Murray loop test is used for the location of faults on lines of low resistance, such
as power cables and telephone cables.
Cable fault location is required anywhere where the fault cannot be seen.
This is a multi-step process that must be performed as safely and as quickly as
possible to prevent customers going without power.
Step 1 –
Cable isolation and safety procedures: A cable fault is nearly always a
permanent fault.
This means that the cable in question will be in a condition where the protection
devices at one or both ends of the cable will have tripped, leaving the cable
isolated but NOT earthed (grounded).
The first task is for the authorized person on the site to make the cable safe by
isolating and then earthing (grounding) one or both ends.
Only after the appropriate procedures have been carried out can any testing
personnel be allowed to approach the cable and prepare for testing.
Step 2 –
Cable identification: Where multiple cables exist, cable identification testing will
identify the correct cable to work on.
Clear identification before a cable is cut is intrinsic to safe maintenance work.
Any mistakes here can be fatal and may cause much longer outages for the connected
customers.
Step 3 –
Cable tracing: When an underground cable is first laid, it rarely runs in a straight
line, but rather meanders in depth and direction.
Cable tracing is done to determine that the route of the cable is following the
expected path.
Step 4 –
Fault identification: The first major procedure is to determine the phase on which the
fault has occurred and if it is of low or high resistance.
This test determines the correct technique, and therefore equipment, needed to
4 Page
Typically, if the fault is found to be below 100 Ohms, a low voltage pulse (eg: 40 V)
from a TDR (time domain reflect meter) can be used.
If the fault is a higher resistance (> 100 Ohm), a low voltage pulse will likely not see
it. For these types of faults, an impulse generator (shock discharge) or bridge, will be
necessary.
Step 5 –
Remember:
a) If it is a low resistance fault, pre-location is likely to be the only means necessary for
location.
b) For high resistance faults, ARM (arc reflection) or ICE (impulse current) techniques on an
SWG (surge wave generator) should be used. Alternatively, the decay method with an HV
DC tester (bridge) can be used for pre-location.
Step 6 –
Pinpointing: The aforementioned test methods will get the operator within 5%
distance of the fault.
Acoustic pinpointing techniques must be employed at this stage in order to narrow the
margin of error to 0.1%.
In most cases, shock discharge generators are used for pinpointing in conjunction
with acoustic methods.
The discharge creates a loud noise, which is pinpointed precisely using an acoustic
pinpointing device.
This device evaluates the time difference between the acoustic signal (speed of
sound) and the electromagnetic (nearly the speed of light) impulse of the shock
discharge.
When the shortest time difference is indicated, the exact fault location is revealed.
Step 7 –
Re-energization of the cable: Once all testing and repairs are completed, the
Safety/Testing documentation is cancelled and the cable is handed back to the
appropriate operators so they can reinstate it and re-energies the loads on the
newly repaired cable.
5 Page
Testing and Commissioning of Power System Apparatus (15EE752)
Module 5
Syllabus:
Switchgear and Protective Devices: Standards, Types, Specification, Installation,
Commissioning Tests, Maintenance Schedule, Type and Routine Tests.
Domestic Installation: Introduction, Testing of Electrical Installation of a Building, Testing
of Insulation Resistance to Earth, Testing of Insulation and Resistance between Conductors
Continuity or Open Circuit Test, Short Circuit Test, Testing of Earthing Continuity, Location
of Faults, IE Rules for Domestic Installation
Introduction:
The term switchgear includes wide range of equipment used for switching,
interruption, measurement, control, indication etc.
The necessary units are arranged in a sequence.
The components are enclosed in sheet metal enclosure or cast iron enclosures.
Hence the name metal clad switchgear or metal enclosed switchgear.
The components of indoor switchgear include
(1) switching and interruption components viz. switches, switch fuse combinations,
circuit breakers, HRC fuses, isolators and earthling switches
(2) measuring components viz. CT, PT, meters etc.
Faults occur on power system due to several reasons and no part of the power system
is left unprotected.
The unhealthy part is isolated immediately upon the occurrence of the fault by
protective devices like relays and circuit breakers.
The functions of different devices used in protection are mentioned below.
1. Relay: It is used to sense the change in the operating quantity when it exceeds certain
preset value.
2. Fuse: It is a simple protective device which breaks the circuit when the current exceeds
the rated value. After the clearance of the abnormality, the fuse element is to be replaced
to resume normal operation.
3. Circuit breaker: It is used to break or make the circuit upon receiving the signal from
the associated relay under abnormal and normal conditions respectively. Based on the
location the making may be manual, semi-auto enclosure or auto closure.
4.Isolators: Isolators are used to isolate during off-load to ensure that the circuit breaker is
de energized for scheduled or unscheduled maintenance activity and is provided with
interlocking provision.
5. Load break switch: This is used to disconnect the load and overload currents and not
short circuit current.
1 Page
Testing and Commissioning of Power System Apparatus (15EE752)
Circuit breaker
A circuit breaker is capable of breaking & making the circuits under abnormal and
normal conditions respectively.
The parts of circuit breaker include
a) Poles with interrupter, porcelain, arc quenching medium
b)Operating mechanism
c) Support structure
d) Control cabinet
Upon the occurrence of the fault, the current in the secondary side of CT is more than
the current under normal condition and relay connected to the CT actuates and
thereby closes its contacts.
Battery supplies the" current to energize the trip coil of the circuit breaker to open the
contacts.
After resuming the normal condition, the battery circuit is open & circuit breaker
contacts are closed.
According to the method of control of the closing operation, circuit breakers are
classified as (IS 1011 (Part-II)-1982).
Rated current: The circuit breaker is defined by the following currents rated thermal current
rated uninterrupted current
Rated frequency: The rated frequency of the equipment is so chosen as to suit the service
frequency Rated short circuit breaking and making capacities:
The rated short circuit breaking current is the highest value of short circuit current
which the circuit breaker is capable of breaking under specified conditions of
recovery voltage and power frequency recovery voltage.
The rated making current must be at least 2.5 times the rms value of ac component of
rated breaking current.
Rated short time withstand current: It is the rams value of the current that the circuit
breaker can carry in a fully closed position during specified time.
Short circuit performance category: The rated short circuit performance category
of the equipment states the rated operating sequence and the condition of the circuit
breaker after performing this sequence at the rated short circuit making and breaking
capacities.
For the same circuit breaker the value of the rated short circuit breaking and
corresponding making capacities may be different for different short circuit
performance categories.
The following characteristics should also be considered while selecting the circuit
breakers.
a) For control circuits: Rated control supply voltage and type (ac or dc) of current.
b) For air supply system: Rated pressure and its limits and volumes of air at
atmospheric pressure required for each closing and opening operation.
C) For shunt release and under voltage release: Rated voltage & kind of current.
d) For over current release: Rated thermal current, kind of current and range of
settings.
e) For auxiliary switches: Rated voltage & current The circuit breakers intended for
circuit operating below 1000 volts ac or 1200 volts dc are covered under the group
low voltage circuit breaker.
Types of test:
1. No Load mechanical operation test: This test is to verify speed of travel, operating time
and closing time and is carried out at 85% and 110% rated voltage of shunt trip release.
3. Temperature rise test: Steady temperature of conducting part and insulating parts measured
for rated continuous alternating current.
4. Dielectric tests:
1.2/50 IPSec Lightning impulse withstand
One minute power frequency voltage withstand
250/2500 Ills switching impulse withstand
5. Short time current test: Rated short circuit current is passed through closed breaker for less
or 3 secs.
6. Short circuit breaking and making tests: This test is conducted at 10%, 30%, 60% and
100% rated short circuit braking current with specified operating sequence and specified
TRV (transient recovery voltage).
7. Line charging current breaking test: This test is conducted for circuit breakers 72.5 KV and
above.
8. Cable charging current breaking test: This test is applicable to circuit breakers intended for
long cable network.
9. Single capacitor bank breaking test: This test is applicable for circuit breakers used for
capacitor switching.
10. Small inductive current breaking test: This test is to be conducted on circuit breakers with
reactors, transformers, motors etc.
Commissioning tests:
After the installation, the circuit breakers and protective gear are subjected to certain
tests at site to ensure proper assembly and readiness of the circuit breaker.
The commissioning tests include:
Mechanical operation tests
Measurement of travel, simultaneous closure of contacts Measurement of insulation
resistance between terminals of pole Pre commissioning checks
Checking close and open operation by energizing the manual operating signal
Checking close and open operation by energizing relays etc
The insulation resistance is measured using Megger. It consists of a built in hand
driven dc generator.
The two terminals of Megger are connected across the insulation i.e. one to the
4
Then the dc generator is driven & corresponding resistance indicated by the Megger
is recorded.
For the switchgear 1000V or 2500V mugger is preferred.
Insulation resistance of the control circuit, trip circuit, relay circuit etc. is measured
using 500V mugger.
a) Tested part: R – phase earthed part: Y - phase, B - phase, frame of the circuit breaker
2) With breaker open: This test is conducted on breaker contacts by shorting R, Y, B phases
on bus bar side~ Voltage is applied from other side consecutively to each phase.
breaker by keeping the contacts in the closed position, continuously till the steady
Page
temperature is reached.
Testing and Commissioning of Power System Apparatus (15EE752)
Readings of various conducting, insulating and structural parts are taken at an interval
of one or half an hour.
When steady temperature is reached, the maximum temperature rise of each part
should be less than the permitted values.
The different tests to be carried out on live circuit breakers are as follows.
Type tests: To be conducted to confirm the design, on the first piece manufactured.
Temperature rise limits test
Dielectric tests
Short circuit making and breaking tests
Short time withstand current test
Mechanical endurance test
Overload performance
Routine tests: To be conducted to predict the performance behavior on each circuit breaker.
Mechanical operation tests
Calibration of releases
Dielectric tests
Insulation resistance test
For low voltage load control, the switchgear used may be one of the following
Low voltage air breaks circuit breaker
Low voltage contactor
Switch fuse combination
Miniature circuit breaker
Molded case breaker
The maintenance procedure differs from breaker to breaker based upon the quenching
medium used.
4) Checking of insulators
Page
5) Checking of relays
Testing and Commissioning of Power System Apparatus (15EE752)
Types of fuse:
The following details pertaining to fuse are considered while selecting the fuse for
particular application.
Rated current
Minimum fusing current
Perspective current
Pre-arcing time
Arcing time
Total operating time
Fusing factor
10Page