0% found this document useful (0 votes)
6 views

9 Risk

Uploaded by

Ifrah Mansoor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

9 Risk

Uploaded by

Ifrah Mansoor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 37

Risk Management

Anne Banks Pidduck


Adapted from John Musser

1
Risk Management
• Problems that haven’t happened yet
• Why is it hard?
• Some are wary of bearing bad news
– No one wants to be the messenger
– Or seen as “a worrier”
• Define a strategy early in your project

2
Risk Management
• Identification, Analysis, Control
• Goal: avoid a crisis
• Thayer: Risk Mgmt versus Project Mgmt
– For a specific project versus all projects
– Proactive versus reactive

3
Project Risk
• Characterized by:
– Uncertainty (0 < probability < 1)
– An associated loss (money, life, reputation, etc)
– Manageable – some action can control it
• Risk Exposure
– Product of probability and potential loss
• Problem
– A risk that has materialized
4
Types of Risks
• Schedule Risks
• Schedule compression (customer, marketing, etc.)
• Cost Risks
• Unreasonable budgets
• Requirements Risks
• Incorrect
• Incomplete
• Unclear or inconsistent
• Volatile

5
Types of Risks
• Quality Risks
• Operational Risks
• Most of the “Classic Mistakes”
– Classic mistakes are made more often

6
Risk Management Process

Risk Identification

Risk Assesment Risk Analysis

Risk Prioritization

Risk Management
Risk Management Planning

Risk Control Risk Resolution

Risk Monitoring

“Software Risk Management”, Boehm, 1989

7
Risk Identification
• Get your team involved in this process
– Don’t go it alone
• Produces a list of risks with potential to
disrupt your project’s schedule
• Use a checklist or similar source to
brainstorm possible risks

8
Risk Analysis
• Determine impact of each risk
• Risk Exposure (RE) or Impact
– RE = Probability of loss * size of loss
– Example: Risk is “Facilities not ready on time”
• Probability is 25%, size is 4 weeks, RE is 1 week
– Ex: Risk is “Inadequate design. Redesign required.”
• Probability is 15%, size is 10 weeks, RE is 1.5 weeks
– Statistically are “expected values”
– Sum all RE’s to get total expected overrun

9
Risk Analysis ..2
• Estimating size of loss
– Loss is easier to see than probability
• You can break this down into “chunks” (like WBS)
• Estimating probability of loss
– Use team member estimates and a risk-estimate review
– Use Delphi or group-consensus techniques
– Use gambling analogy “How much would you bet?”
– Use “adjective calibration”: highly likely, probably,
improbable, unlikely, highly unlikely

10
Risk Prioritization
• Remember the 80-20 rule
• Often want larger-loss risks higher
– Or higher probability items
• Possibly group ‘related risks’
• Helps identify which risks to ignore
– Those at the bottom

11
Types of Unknowns
• Known Unknowns
– Information you know someone else has
• Unknown Unknowns
– Information that does not yet exist

12
Risk Control
• Risk Management Plan
– Can be one paragraph per risk
– McConnell’s example

13
Risk Resolution
• Risk Avoidance
– Don’t do it
– Scrub from system
– Off-load to another party
• Risk Assumption
– Don’t do anything about it
– Accept that it might occur
– But still watch for it
14
Risk Resolution
• Problem control
– Develop contingency plans
– Allocate extra test resources
• Risk Transfer
– To another part of the project (or team)
– Move off the critical path at least
• Knowledge Acquisition
– Investigate, maybe with a prototype
– Buy information or expertise about it
– Do research
15
Risk Monitoring
• Top 10 Risk List
• Rank
• Previous Rank
• Weeks on List
• Risk Name
• Risk Resolution Status
• A low-overhead best practice
• Interim project post-mortems
– After various major milestones

16
Risk Communication
• Don’t be afraid to convey the risks
• Use your judgment to balance

17
Miniature Milestones
• A risk-reduction technique
• Use of small goals within project schedule
– One of McConnell’s Best Practices (Ch. 27)
• Fine-grained approach to plan & track
• Reduces risk of undetected project slippage
• Pros
– Enhances status visibility
– Good for project recovery
• Cons
– Increases project tracking effort
18
Miniature Milestones ..2
• Can be used throughout the development cycle
• Works well with hard-to-manage project activities
or methods such as with evolutionary prototyping
• Reduces unpleasant surprises
• Success factors
– Overcoming resistance from those managed
– Staying true to ‘miniature’ nature
• Can improve motivation through achievements

19
Miniature Milestones ..3
• Requires a detailed schedule
• Have early milestones
– 1 to 2 days to 1 to 2 weeks
• Encourages iterative development
• Use binary milestones
– Done or not done (100%)

20
Feature-Set Control
• Class mistake avoidance
• Early Stages
– 1. Minimal Specification
– 2. Requirements Scrubbing
– 3. Versioned Development
• Mid-Project
– Effective change control
• Late-Project
– Feature cuts
21
Traditional Specifications
• Drive for “traditional” specifications
– Necessity
– Downstream cost avoidance
– Full control over all aspects
• As McConnell notes:
• “But the goal is not to build exactly what you said
you would at the beginning. It is to build the best
possible software within the available time.”
• Idealistic but worth remembering
22
Minimal Specification
• This is not XP (extreme programming)
• Traditional specification issues
– Wasted effort because too much detail
– Obsolescence
– Details do not guarantee success
– Overly constrained design
– User assumption that costs are equal

23
Minimal Specification ..2
Costs and Risks
– Omission of key requirements
– Unclear or impossible goals
– Gold plating
– Used for the wrong reasons
• Lazy substitute for doing good requirements

24
Minimal Specification ..3
Benefits
– Improved morale and motivation
– Opportunistic efficiency
– Shorter requirements phase
Success Factors
– Used only when requirements are flexible
– Capture most important items
– Involve key users
25
Requirements Scrubbing
• Removing a feature from the product
– Eliminates all effort: specification, design,
development, test, documentation
– The earlier the better
– Typically done during or right after
Requirements

26
Requirements Scrubbing ..2
• Less risky than minimal specification
• Aims
– Eliminate all but absolutely necessary
requirements
– Simplify all complicated requirements
– Substitute cheaper items

27
Versioned Development
• Eliminate work from the current version
• “Let’s put it in release 1.1”
– You’re still saying “Yes”, not “No”
• By next revision, the list has changed
anyway

28
Mid-Project Feature-Creep
• Average project has 25% change in
requirements during development
• Sources of change
– Marketing: want to meet customer’s check-list
– Developers: want to perfect deficiencies
– Users: want more functionality or now ‘know’
what they want
• They will all try to insert these mid-project
29
Mid-Project Feature-Creep ..2
• The devil is in the details
• Trivial feature can have weeks of
impact
• Developers can insert things when
you’re not looking
• No specification can cover all details;
you must.
30
Change Control Board (CCB)
• Representatives from each stakeholder party
– Development, QA, Marketing, Management,
Customer Support
• Perform “change analysis”
– Importance, priority, cost, benefit
• Triage
– Allocating scare resources
– Some will not receive treatment
– Life-critical to the project
31
Change Control

Change CM
Control System
System
CM Tool

“Quality Software Project Management”, Futrell, Shafer, Shafer

32
Configuration Control
• A management support function
• Includes
– Program code changes
– Requirements and design changes
– Version release changes
• Essential for developed items
– Code, documentation, and so on

33
Configuration Control Terminology

• Software Configuration Control Item (SCCI)


– a.k.a. Source Item (SI)
– Anything suitable for configuration control
– Source code, documents, diagrams, and so on
• Change Control: process of controlling changes
– Proposal, evaluation, approval, scheduling,
implementation, tracking

34
Configuration Control Terminology ..2

• Version Control
– Controlling software version releases
– Recording and saving releases
– Documenting release differences
• Configuration Control
– Process of evaluating, approving and disapproving, and
managing changes to SCCIs.

35
SCM
• Software Configuration Management
• Formal engineering discipline
• Methods and tools to identify and manage
software throughout its use

36
Configuration Control Needs
• Establish clearly defined management authority
• Setup control standards, procedures and guidelines
– All team members must be aware of these
• Requires appropriate tools and infrastructure
• Configuration Management Plan must be
produced during planning phase
– Often part of Software Development Plan

37

You might also like