0% found this document useful (0 votes)
304 views5 pages

0024-00-Risk Assessment For Metal Guard Rail Works

Uploaded by

Jeffry M.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
304 views5 pages

0024-00-Risk Assessment For Metal Guard Rail Works

Uploaded by

Jeffry M.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

Project Title: UPGRADING THE EXISTING ROAD FROM UMM AL ZOMOUL TO TAWI ARBAIN RA No.

: 54300-OOSIT-ZZ-AJC-CIV-RA-0024-00

Contract No.: PD/CA/BPS/SY/R324/P313-2017-DOT/18/016 Revision: 00

Document Title: RISK ASSESSMENT FOR METAL GUARD RAIL INSTALLATION WORKS Page: Page 1 of 5

RESIDUAL RISK
POTENTIAL RISK RATING Control Measure RATING
RISK
SN ACTIVITY HAZARDS
HARM/DAMAGE Probability Severity Rating (Refer to Hierarchy of Control) Probability Severity Rating
(P) (S) (PxS) (P) (S) (PxS) YES
Increase dust levels & air emission  Speed limits to be followed specially when
Resulting of Air pollution and driving on unpaved roads (dirt road)
Use of access
roads
disturbing the surrounding
neighbours Habitat destruction.
2 3 6  Avoid dust generating activities during
excessively windy periods.
1 3 3 √
 Provide an adequate water supply for dust
suppression.
 TBT prior to start the activity.
 Maintain good house keeping
Snake & scorpion
 Check for snakes, scorpions and bees around
Site
clearance,
bites
Bee stings and other
Stings/Fatality 3 3 9 the area including equipment cabin.
 Personal protective equipment must be
1 3 3 √
1 vermin
preparation & worn at all times.
survey works  Close supervision by the foreman.
 Proper training and monitoring minimize
manual handling.
 Use mechanical aid (ALARP)
Manual Handling
Work related upper limb  Only skilled / competent personnel to
Operations
Slips, trips and
disorders/cuts, abrasions/
foot/toe injuries/eye injuries
3 2 6 perform such activity.
 Follow the installation procedure, avoid
1 2 2 √
caught in between.
shortcuts.
 Personal protective equipment must be
worn at all times.
2 Mechanical Underground utility Electrocution , Explosion, 4 4  Secure NOC’s, as built drawings, Excavation 1 3
excavation services Flooding, Damage to property 16 Permit from Project Manager and or site 4 √
using Engineer.
 Survey team must accurately identify and
excavator
marked the location and route of the existing
with Auger Utilities.
attachment  Follow the certain depth to mount the sign
to mount the post.
metal  Manual digging only and use none electrical
guardrail post conductive tools whilst digging near the
electrical line.
 Don’t use pick axe for digging around the
cable.
 Use cable detector to locate existing
electrical lines.
 All existing underground utilities if any shall
be dealt with accordingly.
 Close supervision by the Foreman.

AL JABER Transport & General Contracting Est. P.O. Box: 2175, Abu Dhabi, UAE. Tel.: +(971 2) 5554300 , Fax.: +(971 2) 5553370
Project Title: UPGRADING THE EXISTING ROAD FROM UMM AL ZOMOUL TO TAWI ARBAIN RA No.: 54300-OOSIT-ZZ-AJC-CIV-RA-0024-00

Contract No.: PD/CA/BPS/SY/R324/P313-2017-DOT/18/016 Revision: 00

Document Title: RISK ASSESSMENT FOR METAL GUARD RAIL INSTALLATION WORKS Page: Page 2 of 5

 Access and egress to be provided on the


Slips trips and falls
due to improper
access/egress
Physical injuries 2 3 6 trench with proper steps/ramps and stair
case ladder to be provided each 25meter.
1 3 3 √
 Walkways must be clear at all times
 Licensed / certified operator Plant and
Equipment operators.
 Follow site speed limit as posted 20kph.
 Machine movement must be controlled by a
competent banks man or Flag man
Transporting ,  Proper barricading, warning signs, and
loading and lightings
unloading of Lifting using shovel  Personnel to be briefed on the task and
metal boom attachments responsibilities (Toolbox Talk).
Equipment  Proper training and guidance for all new
guardrail
3 accessories
using shovel
Movement
Road surprises
machine/property damage
Physical injuries
4 4 16 workers.
 New personnel may not be allowed to work
1 3 4 √
Over-speeding alone.
with /Overloading /  Ensure there is NOBODY behind the
attachment’s Collision EQUIPMENT while loading and unloading is
boom and in progress
slings  Avoid reversing, Otherwise in the presence
of certified banks man
 Means of safe access and egress
 Personal protective equipment must be
worn at all times
 Continuous supervision
4 Manual and Manual handling work related injuries such as cuts, 4 4  Avoid lifting or carrying load more than 1 3
Mechanical Slips Trips and Fall abrasions, foot/toe injuries and 16 your body weight. 4 √
installation of Cuts & bruises, being eye injuries machine/property  Use mechanical lifting equipment if
struck by the load damage necessary.
metal
Physical injuries  Do not walk across the path of equipment
guardrail  Ensure there is NOBODY behind or
barrier underneath load.
 Availability of first aid box and first aider.
 Lift with your leg not with your back
 Call for help
 Use the right tools for the right jobs
 Toolbox talks for personnel before the
work
 Housekeeping must be maintained at all
the time at the work site
 Access must be cleared from construction
debris/other obstructions
 Always wear your PPE (gloves)
 Close supervision by foreman

AL JABER Transport & General Contracting Est. P.O. Box: 2175, Abu Dhabi, UAE. Tel.: +(971 2) 5554300 , Fax.: +(971 2) 5553370
Project Title: UPGRADING THE EXISTING ROAD FROM UMM AL ZOMOUL TO TAWI ARBAIN RA No.: 54300-OOSIT-ZZ-AJC-CIV-RA-0024-00

Contract No.: PD/CA/BPS/SY/R324/P313-2017-DOT/18/016 Revision: 00

Document Title: RISK ASSESSMENT FOR METAL GUARD RAIL INSTALLATION WORKS Page: Page 3 of 5

 Only licensed / certified personnel must


operate the machine.
 Follow site speed limit 20kph.
 Machine movement must be controlled by a
competent banks man or Flag man
Plant and equipment
movement
machine/property damage
Physical injuries Fatality
4 4 16  Kept away from the equipment working area
at least 15 meters radius.
1 4 4 √
 Equipment must be in fully stopped prior to
work near the equipment.
 Praying, resting, and sleeping beside or
underneath of any vehicles or equipment is
strictly prohibited.
 Secure NOC’s, as built drawings, Excavation
Permit from Project Manager and or site
Engineer. Work activity shall be done inside
TDP only.
 Survey team must accurately identify and
marked the location and route of the existing
Utilities.
 Follow the certain depth to mount the
guardrail post.
Used of Electric
power tools (Drill,
Generator)
Electrocution , Fire and Explosion,
Damage to property
4 4 16  All electrical power tools must be checked
and tagged by a certified electrician prior to
1 3 4 √
use.
 Inspect the electrical lines from possible
damage used industrial socket only.
 All existing underground utilities if any shall
be dealt with accordingly.
 Generators must be fitted with earth leakage
circuit breaker and it must be placed on a
drip tray possible oil leakage.
 Close supervision by the Foreman.
 All plant to be services as per manufacturer's
Could result on hearing loss, recommendations.
Noise Emissions
from vehicles
deafness, CEMP violation 3 2 6  Noise monitoring to be undertaken to
observe 85dBa.
1 2 2 √
 Use of appropriate PPE.
5 Backfilling and Plant and Equipment machine/property damage 3 4  Only skilled / competent personnel must 1 4
reinstatement Movement 12 operate the machine. 4 √
works  Machine movement must be controlled by a
competent banks man or Flag man Machine
movement must be controlled by a
competent banks man or Flag man
 Kept away from the equipment working area
at least 15 meters radius.
 Equipment must be in fully stopped prior to

AL JABER Transport & General Contracting Est. P.O. Box: 2175, Abu Dhabi, UAE. Tel.: +(971 2) 5554300 , Fax.: +(971 2) 5553370
Project Title: UPGRADING THE EXISTING ROAD FROM UMM AL ZOMOUL TO TAWI ARBAIN RA No.: 54300-OOSIT-ZZ-AJC-CIV-RA-0024-00

Contract No.: PD/CA/BPS/SY/R324/P313-2017-DOT/18/016 Revision: 00

Document Title: RISK ASSESSMENT FOR METAL GUARD RAIL INSTALLATION WORKS Page: Page 4 of 5

work near the equipment.


 Praying, resting, and sleeping beside or
underneath of any vehicles or equipment is
strictly prohibited.
 Access and egress to be provided on the
trench with proper steps/ramps and ladder
Slips trips and falls
due to improper
access/egress
Physical injuries 2 3 6 to be provided each 25meter
 Walkways must be clear at all times
1 3 3 √
maintaining good housekeeping.
 Proper stocking of construction materials
 Heavy loads are not to be carried by hand;
mechanical means of lifting should used if
work related injuries such as cuts,
Manual Handling abrasions, foot/toe injuries and
eye injuries
3 2 6 required (ALARP).
 Call for help do not lift more than your
2 2 4 √
weight.
 Lift with your leg an d not with your back
 Dust suppression by wetting as necessary.
Upper respiratory infections /
 Carefully controlled people / vehicle/plant
Dust/ Emission (Air
pollution)
Poor visibility / Operatives struck
by moving vehicles.
2 3 6 separation regime to be in place.
 All vehicles to be fitted with reversing
1 3 3 √
alarms.
 All plant to be services as per manufacturer's
Could result on hearing loss,
Noise Emissions
from vehicles
deafness, CEMP violation 3 2 6 recommendations.
 Noise monitoring to be undertaken to
2 2 4 √
observe 85dBa action levels.
 No Equipment movement during bad
weather condition (poor visibility).
 Allowing workers to self pace where
applicable and take rests in the shaded area
when they can to cool down.
Inclement
6 Weather
Condition
Sandstorm and
Foggy
Eye injuries/ Vehicular accident,
collision, overturn, Heat Stress
3 4 12  Probation of shaded area for resting, enough
supply of cool drinking water and hydrolytes.
1 4 4 √
 Probation of suitable PPE’s
 Probation of First Aiders
 Emergency Contact numbers must be posted
in all working area.
 Close supervision
 Maintain housekeeping to avoid attracting
snake/rats and other insects/vermin
Inadequate  Waste segregation
Site welfare maintenance of  Regular waste disposal
7 facilities and
Maintenance
Welfare Facilities
Environmental
Bad Odours
Health Effects
2 3 6  Provision of well maintained Portable toilets
 Provision of well maintained rest areas and
1 3 3 √
Pollution water stations
 Provision of First aid boxes and certified first
aider
AL JABER Transport & General Contracting Est. P.O. Box: 2175, Abu Dhabi, UAE. Tel.: +(971 2) 5554300 , Fax.: +(971 2) 5553370
Project Title: UPGRADING THE EXISTING ROAD FROM UMM AL ZOMOUL TO TAWI ARBAIN RA No.: 54300-OOSIT-ZZ-AJC-CIV-RA-0024-00

Contract No.: PD/CA/BPS/SY/R324/P313-2017-DOT/18/016 Revision: 00

Document Title: RISK ASSESSMENT FOR METAL GUARD RAIL INSTALLATION WORKS Page: Page 5 of 5

 Close supervision
 CEMP Induction and Trainings
Environmental Pollution  Minimize and segregate waste and empty
Bad Odours regularly
8
Waste
Management
Inadequate waste
management
Health Effects
Epidemic outbreak Food and
2 3 6  Provision of Waste segregation
 Regular waste disposal
1 3 3 √

Construction waste accumulation  Reduce, Reuse Recycle


 Close supervision

Risk Rating Matrix


SEVERITY
PROBABILITY
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastropic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent Almost Certain (5) 5 10 15 20 25
Absolutely Unacceptable High
15 - 25 Extreme Risk Activity should not proceed in current form
Unacceptable High
8 - 12 High Risk Activity should be modified to include remedial planning and action and be subject to detailed HSE assessment
Acceptable but must be managed at ALARP
4Conducted
-6 by: Moderate Risk Reviewed by:
Activity can operate subject to management and / or modification
Approved by:
Engr. Fadi Al Bitar , Construction Manager Bonie Ceralvo, HSE Coordinator
Acceptable without required further action Engr. Khalifa Nasser, Project Manager
1-3 Low Risk No action required unless escalation of risk is possible
Hierarchy
Signature: of Control ( Controls identified maybe a mixture
Signature:
of the hierarchy in order to provide minimum operator exposure) Signature:
Elimination Eliminate the hazard
Date Prepared: 13th December, 2018
Substitution Date:
Provide an alternative isthcapable
that13 December, 2018
of performing the same task and is safer to use. Date: 13th December, 2018
Engineering Controls Provide or construct a physical barrier or guard.
Administartive Controls
Develop policies,procedures practices and guidelines, in consultation with employees,to metigate the risk.Provide training, instruction and supervision about the hazard.

Personal Protective Equipment Personal Equipment designed to protect the individual from the hazard.

(Refer to AD EHSMS CoP 05 - Risk Management) www.ead.ae

AL JABER Transport & General Contracting Est. P.O. Box: 2175, Abu Dhabi, UAE. Tel.: +(971 2) 5554300 , Fax.: +(971 2) 5553370

You might also like