Anex-1 - Colculation For L90 Line Differential Relay
Anex-1 - Colculation For L90 Line Differential Relay
SETTING
OPERATING RESULT
RESTRAIN RESULT
ENTER BY USER
K factor 1.1 internal culculation x1 3.30579
TIME CONSTANT 1 min x2 0.20661
Ɵ alarm% 0.9
I fault injected 2 A
I nominal 1 A
Note : To test we use two stages 1st prefault for Calculating the overtemperature
5 min. 2nd stage injected current The thermal replica is calculated individually for each phase. METHOD decides whether the
highest of the three calculated temperatures (Θ max) or their arithmetic average (Average Θ) or
the temperature calculated from the phase with maximum current (Θ from Imax) should be
decisive for the thermal alarm and tripping stage.
Since an overload usually occurs in a balanced way, this setting is of minor importance. If
unbalanced overloads are to be expected, however, these options lead to different results.
Averaging should only be used if a rapid thermal equilibrium is possible in the protected object,
e.g. with belted cables. If the three phases are, however, more or less thermally isolated (e.g.
SETTING
single conductor cables or overhead lines), one of the maximum settings should be chosen at
TRIP RESULT any rate.
ALARM RESULT
T IP Time Dial 0.2 Sec inverse Time Test:
IP> pickup 1. Formula for IEC curve when selected to normal inverse
2 A
curve:
I injected 5 A
INVERSE Sec. I p > = 0.5A, I o > = 0.5A
very inverse Sec. T = 0.14TP / {( I/IP )0.02 – 1} seconds
Extremely inverse Sec.
2. For IEC curve is very inverse curve:
long time inverse Sec.
I p > = 0.5A, I o > = 0.5A
T = 13.5 TP / {( I/IP ) – 1} seconds
T 3I0P Time Dial 0.2 Sec
3. For IEC curve is extremely curve:
3I0P> pickup 2 A
I injected 5 A I p > = 0.5A, I o > = 0.5A
INVERSE Sec. T = 80 TP / {( I/IP )2 – 1} Seconds
very inverse Sec.
Extremely inverse Sec. 4. For IEC curve is long inverse:
long time inverse Sec. I p > = 0.5A, I o > = 0.5A
T = 120TP / {( I/IP ) – 1} (SEC)
where
Fault locator
Reactance per Km 0.188 ohm/Km
The measurement of the distance to a fault is an
important supplement to the protection functions.
Availability
length reactance
of the line for power transmission within the system can
Total line 1 28.2 be increased when the fault is located.
SETTING
OPERATING RESULT