Lecture 2 - Block Day 1 - Contractual Arrangements
Lecture 2 - Block Day 1 - Contractual Arrangements
CONTRACTUAL ARRANGEMENTS
BLOCK DAY 01
Chinthaka Atapattu
Senior Tutor in Quantity Surveying & Construction Law
School of Built Environment
Massey University
❑ Introduction
❑ Contract Types
❑ Terminologies
Procurement
strategy Contract payment types
Procurement phases
Terminologies Hybrid
Retrieved from:
https://giphy.com
Retrieved from:
https://giphy.com
Terminologies Hybrid
QUESTIONS…
• ARE LUMP SUM AND FIXED PRICE CONTRACTS THE
SAME?
QUESTIONS…
• WHO BEARS MORE RISK IN THIS CONTRACT TYPE?
Incentive contracts
• Payment is based on the services provided in
accordance with an agreed-upon scope, budget,
schedule and quantity.
• Example: Fixed-price incentive contracts, cost-
reimbursable incentive contracts.
Hybrid contracts
• A combination of 2 or more contracts.
• Example: Combination of unit-price, fixed-price and
provisional sums.
• Let’s get familiar with some • Allowance allocated for works that you know you
terminologies… need to achieve the project’s objective, but you still
haven’t got the details on the scope of those works
Provisional (level of uncertainty high).
sums • Example: Office work-stations (cubicles) are needed
but there was no detail design at the time the project
was tendered out.
Retrieved from:
• Contractor is reimbursed for all the costs incurred for the
https://giphy.com Cost plus fixed completion of the works, PLUS a pre-agreed fixed
percentage percentage.
• Example: Cost + Fixed 10% of costs
• Let’s get familiar with • An agreed ceiling price for the project
some • The final price cannot exceed the ceiling price.
terminologies… Guaranteed
maximum price • Example: GMP is $1.50 million. The final costs of the
(GMP) project is $1.60 million. The contractor is to be paid only
$1.50 million because that is the maximum ceiling agreed
to be paid in the contract.
Cost plus fixed So if the actual cost is less than the target cost, both the
fee with an client and contractor will share the cost savings.
agreement for
cost-savings If the actual cost exceeds the target cost, both the client and
contract contractor will share the cost overrun.
Chinthaka Atapattu
Senior Tutor in Quantity Surveying & Construction Law
School of Built Environment
Massey University