Bid Form Dominic Construction
Bid Form Dominic Construction
Note : Please find attached detailed cost breakdown as per scopes of work.
Submitted by:
EXCLUDED ITEMS:
1.00 Construction & Contractors Bond (Refundable; Required by AAVA)
2.00 Landscaping Works
3.00 Supply & Installation of Swimming Pool & Jacuzzi System
4.00 Supply & Installation of Flat Clay Roof Tiles
5.00 Supply of Floor & Wall Tiles
6.00 Supply of Door Hardwares
7.00 Supply & Installation of Kitchen Counters & Cabinets
8.00 Supply & Installation of Wardrobe Cabinets
9.00 Supply & Installation of Toilet Undercabinet w/ Countertop
10.00 Supply & Installation of Elevator Unit
11.00 Supply of Chandelier
12.00 Supply of Ceiling Fans
13.00 Supply, Mounting & Installation of 75KVA 3Phase Generator
14.00 Supply & Installation of Gigabit Network Switch
15.00 Supply & Installation of Telephone Handset
16.00 Supply & Installation of Home Automation System
17.00 Supply & Installation of Intercom System
18.00 Kitchen Equipments & Appliances
19.00 Furnitures
SUBMITTED BY:
Page 3 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
Retaining wall 58,013.94 kgs. 58.69 16.81 3,404,838.14 975,214.33 4,380,052.47
Suspended Slab, Beams, Stairs, 3,000psi, 3/4, 14d 11,792.63 kgs. 58.69 16.81 692,109.45 198,234.11 890,343.56
Columns, Lintel beams, roof beams 15,165.60 kgs. 58.69 16.81 890,069.06 254,933.74 1,145,002.80
Slab on grade 4,618.25 kgs. 58.69 16.81 271,045.09 77,632.78 348,677.87
Pond 768.97 kgs. 58.69 16.81 45,130.75 12,926.36 58,057.11
Ledge 2,661.60 kgs. 58.69 16.81 156,209.30 44,741.50 200,950.80
Cistern 1,966.77 kgs. 58.69 16.81 115,429.73 33,061.40 148,491.13
Pool, Jacuzzi 3,799.07 kgs. 58.69 16.81 222,967.42 63,862.37 286,829.79
Trenches - kgs. 58.69 16.81 - - -
Sump pit, catch basins, drainage junction box 760.83 kgs. 58.69 16.81 44,653.11 12,789.55 57,442.66
3.00 Formworks - - - - -
Footing, wall footing 114.24 sq.m. 684.59 672.58 78,207.56 76,835.54 155,043.10
Footing Tie Beams, Grade Beams 172.16 sq.m. 684.59 672.58 117,859.01 115,791.37 233,650.38
Retaining wall 1,858.28 sq.m. 684.59 672.58 1,272,159.91 1,249,841.96 2,522,001.87
Suspended Slab, Beams, Stairs, 3,000psi, 3/4, 14d 1,224.30 sq.m. 684.59 672.58 838,143.54 823,439.69 1,661,583.23
Columns, Lintel beams, roof beams 519.44 sq.m. 684.59 672.58 355,603.43 349,364.96 704,968.39
Slab on grade 35.66 sq.m. 684.59 672.58 24,409.74 23,981.51 48,391.25
Pond 18.72 sq.m. 684.59 672.58 12,815.52 12,590.70 25,406.22
Ledge 66.50 sq.m. 684.59 672.58 45,525.24 44,726.57 90,251.81
Cistern 54.96 sq.m. 684.59 672.58 37,625.07 36,965.00 74,590.07
Pool, Jacuzzi 93.94 sq.m. 684.59 672.58 64,310.38 63,182.17 127,492.55
Trenches 22.50 sq.m. 684.59 672.58 15,403.28 15,133.05 30,536.33
Sump pit, catch basins, drainage junction box 69.84 sq.m. 684.59 672.58 47,811.77 46,972.99 94,784.76
4.00 Tie Wire 2,216.00 kgs. 90.08 - 199,617.28 - 199,617.28
SUB-TOTAL III.a. 15,336,573.22 6,172,535.33 21,509,108.55
b. 2" CONCRETE TOPPING (Refer to Architectural Works) 1,451.94 sqm 259.42 462.40 376,662.12 671,376.78 1,048,038.90
SUB-TOTAL III.b.
- - - - -
c. STRUCTURAL STEEL - - - - -
1.00 Steel columns 98,790.15 kg. 73.76 36.14 7,286,761.46 3,570,276.02 10,857,037.48
2.00 Steel beams 145,287.22 kg. 73.76 36.14 10,716,385.35 5,250,680.13 15,967,065.48
3.00 Roof framing works kg. - - - - -
3.01 Steel trusses 9,294.00 kg. 57.84 28.34 537,564.96 263,391.96 800,956.92
3.02 Roof purlins 2,652.00 kg. 57.84 28.34 153,391.68 75,157.68 228,549.36
3.03 Welding rods and consumables 1.00 lot 73,407.43 41,108.16 73,407.43 41,108.16 114,515.59
3.04 Anchor bolts 962.63 kg. 180.16 100.89 173,427.42 97,119.74 270,547.16
3.05 Plate connections 934.72 kg. 57.84 28.34 54,064.20 26,489.96 80,554.16
- - - - -
SUB-TOTAL III.c. 18,995,002.50 9,324,223.65 28,319,226.15
Page 4 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
5.00 Linear Plastering (Doors & Windows) 932.95 lm 180.16 168.15 168,079.55 156,874.87 324,954.42
6.00 Drip Mould 142.20 lm 120.10 168.15 17,078.22 23,910.93 40,989.15
7.00 RC Ledge with C-Chanel Edge included; see Item III.a.1.01, III.a.2, III.a.3
SUB-TOTAL IV.a. 2,825,175.13 2,580,212.85 5,405,387.98
b. ROOFING WORKS
1.00 Flat Clay roof tiles excluded
1.01 Contractor's Admin/Supervision fee only 1.00 lot - 174,337.95 - 174,337.95 174,337.95
1.02 Site preparation prior installation 1.00 lot 60,051.89 12,610.90 60,051.89 12,610.90 72,662.79
2.00 Supply and installation of GA. 24 Prepainted longspan metal roof undersheeting with 50mm thk rockwool roof
insulation blanket, foil-faced on both sides with chicken wire mesh; to include all necessary pre-painted bended 1.00 lot 2,594,934.42 391,300.06 2,594,934.42 391,300.06 2,986,234.48
materials (Ridge roll, flashing, etc) with complete accessories.
Supply and installation of Ga. 22 prepainted GI roof eaves end trim on 3mm x 38mm steel flat bar brackets
3.00 1.00 lot 116,110.33 65,021.78 116,110.33 65,021.78 181,132.11
spaced at 300mm (see detail)
4.00 Supply and installation of 12mm thk. Hardie Senepa Fascia Board, to include all necessary fixing accessories. 128.90 lm 540.47 302.66 69,666.58 39,012.87 108,679.45
d. FLOOR FINISHES
1.00 Installation of Owner Supplied Floor Tile
1.01 Natural stone tiles (FF-01) 32.28 sq.m OSM 2,233.16 - 72,093.10 72,093.10
1.02 600mm x 1200mm Homogenous floor tiles (FF-02) 381.28 sq.m OSM 2,233.16 - 851,450.31 851,450.31
1.03 600mm x 60mm Homogenous floor tiles (FF-03) 231.99 sq.m OSM 2,233.16 - 518,068.11 518,068.11
1.04 450mm x900mm Homogenous floor tiles (FF-04) 104.21 sq.m OSM 2,233.16 - 232,725.20 232,725.20
1.05 Engineered wood flooring, to include complete underlays as recommended by supplier (FF-05) 307.10 sq.m 4,203.63 840.73 1,290,941.50 258,189.53 1,549,131.03
WPC Floor Decking by Biowood, to include all necessary surface preparation and fixing accessories
1.06 1.00 lot 2,152,932.25 - 2,152,932.25 - 2,152,932.25
(FF-06)
1.07 17.5 x 17.5 non-skid paver tiles (FF-07) 423.42 sq.m OSM 2,233.16 - 945,569.97 945,569.97
1.08 300 x 600mm Non-Skid Floor Tile (FF-08) n/a - 2,233.16 - - -
1.09 Epoxy Floor Finish (FF-09) 29.85 sq.m 4,203.63 840.73 125,458.18 25,091.75 150,549.93
1.10 600 x 600mm Homogenous Tile Non-Skid (FF-11) 70.57 sq.m OSM 2,233.16 - 157,602.59 157,602.59
Page 5 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
e. WALL FINISHES
1.00 600mm x 600mm Homogenous wall tiles 374.72 sq.m OSM 2,233.16 - 836,809.16 836,809.16
1.01 All toilets - - - - -
2.00 Board formed concrete finish n/a - - - - -
3.00 Plain plaster painted finish included; see Item IV.a.4
f. CEILING FINISHES
1.00 Supply and installation of 12mm thk. Boral (tapered-edge) gypsum board ceiling on standard metal ceiling
653.40 sq.m 674.67 504.44 440,829.38 329,601.10 770,430.48
frame, paint finish (CF-03)
2.00 Supply and installation of 12mm thk. moisture-resistant Boral (tapered-edge) gypsum board ceiling on standard
251.03 sq.m 819.88 504.44 205,814.07 126,629.32 332,443.39
metal ceiling frame, paint finish (CF-02)
3.00 Supply and installation of exposed slab soffit, smooth plaster painted finish (CF-00) 295.15 sq.m 120.10 84.07 35,447.52 24,813.26 60,260.78
4.00 Supply and installation of from 1"x6" Biowood roof ceiling eaves on metal ceiling furrings spaced at 300mm
n/a - - - - -
OC, to include complete mounting accessories
5.00
Supply & Installation of 10mm thk Fiber Cement Board Ceiling on standard metal ceiling, paint finish (CF-04) 78.62 sq.m 773.04 504.44 60,776.40 39,659.07 100,435.47
6.00
Supply & Installation of Walnut Wood Plastic Composite Cladding (CF-01) 292.46 sq.m 7,206.23 2,101.82 2,107,539.81 614,699.96 2,722,239.77
7.00 Curtain Cove 106.40 lm 848.84 767.09 90,316.58 81,618.38 171,934.96
8.00 Lighting Cove 34.12 lm 417.86 252.22 14,257.38 8,605.75 22,863.13
Page 6 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
W-5 1.00 sets 1,363,336.50 - 1,363,336.50 - 1,363,336.50
W-6 1.00 sets 480,552.68 - 480,552.68 - 480,552.68
W-7 1.00 sets 355,650.96 - 355,650.96 - 355,650.96
W-8 1.00 sets 207,578.74 - 207,578.74 - 207,578.74
W-9 1.00 sets 35,070.30 13,384.36 35,070.30 13,384.36 48,454.66
W-10 1.00 sets 422,241.94 - 422,241.94 - 422,241.94
W-11 1.00 sets 465,446.34 - 465,446.34 - 465,446.34
W-12 1.00 sets 334,374.21 - 334,374.21 - 334,374.21
W-13 1.00 sets 863,359.96 - 863,359.96 - 863,359.96
W-14 1.00 sets 733,057.67 - 733,057.67 - 733,057.67
W-15 1.00 sets 303,972.76 - 303,972.76 - 303,972.76
W-16 1.00 sets 111,145.16 - 111,145.16 - 111,145.16
W-17 1.00 sets 620,038.87 - 620,038.87 - 620,038.87
W-18 1.00 sets 251,366.58 - 251,366.58 - 251,366.58
W-19 1.00 sets 418,394.15 - 418,394.15 - 418,394.15
W-20 1.00 sets 428,415.53 - 428,415.53 - 428,415.53
W-21 1.00 sets 109,466.27 - 109,466.27 - 109,466.27
W-22 1.00 sets 344,297.06 - 344,297.06 - 344,297.06
W-23 1.00 sets 180,143.69 - 180,143.69 - 180,143.69
W-24 1.00 sets 108,129.37 - 108,129.37 - 108,129.37
W-25 1.00 sets 186,052.25 - 186,052.25 - 186,052.25
W-26 3.00 sets 89,464.00 - 268,392.00 - 268,392.00
W-27 2.00 sets 62,525.84 - 125,051.68 - 125,051.68
W-28 1.00 sets 196,121.74 - 196,121.74 - 196,121.74
W-29 1.00 sets 178,153.87 - 178,153.87 - 178,153.87
W-30 1.00 sets 391,462.82 - 391,462.82 - 391,462.82
W-31 1.00 sets 83,114.83 - 83,114.83 - 83,114.83
W-32 1.00 sets 158,282.28 - 158,282.28 - 158,282.28
W-33 2.00 sets 102,786.28 - 205,572.56 - 205,572.56
W-34 4.00 sets 89,370.45 - 357,481.80 - 357,481.80
W-35 2.00 sets 80,853.58 - 161,707.16 - 161,707.16
W-36 2.00 sets 33,064.57 12,089.65 66,129.14 24,179.30 90,308.44
W-37 1.00 sets 294,595.16 - 294,595.16 - 294,595.16
W-38 1.00 sets 125,863.55 - 125,863.55 - 125,863.55
W-39 1.00 sets 199,869.23 - 199,869.23 - 199,869.23
W-40 2.00 sets 42,833.90 - 85,667.80 - 85,667.80
W-41 2.00 sets 105,568.96 - 211,137.92 - 211,137.92
W-42 2.00 sets 215,891.55 - 431,783.10 - 431,783.10
W-43 2.00 sets 74,891.37 - 149,782.74 - 149,782.74
W-44 1.00 sets 101,433.12 - 101,433.12 - 101,433.12
W-45 1.00 sets 104,609.68 - 104,609.68 - 104,609.68
- - - - -
3.00 Supply and installation of Door Jambs - - - - -
3.01 3"x8" kd Narra wooden door jamb included - - - - -
3.02 2"x6" Guijo door jamb included - - - - -
3.03 2"x4" Guijo door jamb included - - - - -
- - - - -
4.00 Insect Screens for uPVC Doors & Windows 1.00 lot 1,677,578.56 - 1,677,578.56 - 1,677,578.56
Supply and installaiton of 2"x14"x4' KD Narra wooden stair treads, to include complete mounting accessories, lm
1.00 74.39 10,506.58 5,883.69 781,587.05 437,689.13 1,219,276.18
as shown on detials.
Supply and installation of from 1"x6"x4' KD Narra wooden stair riser cladding, to include complete mounting lm
2.00 74.39 1,181.82 661.82 87,915.88 49,232.95 137,148.83
accessories, as shown on details.
3.00 Supply and installation of 1"x2" creosoted wood sleeper for stair treads 74.39 lm 393.94 220.61 29,305.29 16,411.23 45,716.52
Supply and installation of from 2"x3" Narra Handrail, varnish finish; to include complete mounting accessories,
4.00 44.00 lm 1,863.11 1,043.34 81,976.84 45,906.96 127,883.80
as shown on details.
i. SPECIALTIES
Page 7 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
3.00 Wardrobe Cabinets excluded
4.00 Shower enclosure 1.00 lot 699,148.10 - 699,148.10 - 699,148.10
5.00 Elevator (Owner Supplied) excluded
j. PAINTING WORKS
1.00 Wall Painting (Interior) 1,833.43 sq.m 240.21 252.22 440,408.20 462,427.69 902,835.89
2.00 Wall Painting (Exterior) 828.42 sq.m 780.67 420.36 646,723.15 348,234.90 994,958.05
3.00 Ceiling (Latex Painting) 1,492.04 sq.m 240.21 252.22 358,403.00 376,322.41 734,725.41
4.00 Doors - - - - -
a. Duco n/a - - - - -
b. Varnish 47.00 sets 9,007.78 4,203.63 423,365.66 197,570.61 620,936.27
c. QDE n/a - - - - -
d. Epoxy 6.00 sets 6,005.19 3,362.91 36,031.14 20,177.46 56,208.60
5.00 Stair tread, handrails, wood planks, eaves - - - - -
a. Varnish finish 96.71 sq.m 1,441.25 840.73 139,379.42 81,304.74 220,684.16
6.00 Canopy steel frame, exterior steel railing, steel roof trusses, purlins (epoxy paint finish) 4,016.67 sq.m 240.21 252.22 964,845.36 1,013,085.62 1,977,930.98
7.00 Others to complete the work (please identify) sq.m - - - - -
7.00
Supply and installation of steel gate, 50mm x 100mm x t=1.5mm steel frame, to include heavy-duty pillow block
1.00 lot 161,959.56 162,125.59 161,959.56 162,125.59 324,085.15
and complete mounting accessories (verify approved design), epoxy paint finish
- - - - -
8.00 Others to complete the work ( please identify) - - - - -
Stone Wall Cladding at Guard House 1.00 lot 133,440.10 - 133,440.10 - 133,440.10
Stone Wall Cladding at Main House 1.00 lot 1,332,786.80 - 1,332,786.80 - 1,332,786.80
Biowood Vertical Slats on Steel Frame 1.00 lot 2,057,425.72 - 2,057,425.72 - 2,057,425.72
NOTE:
THIS SCOPE OF WORK SHALL SERVE AS A GUIDE FOR EVALUATION OF THE WORK AND PROGRESS
PAYMENTS BUT SHALL NOT BE CONSTRUED AS THE EXCLUSION FROM THE SCOPE OF WORK. ALL ITEMS
CALLING FOR LABOR AND MATERIAL NOT LISTED ABOVE BUT CALLED FOR IN THE PLANS, DETAILS, AND
SPECIFICATIONS SHALL BE DEEMED AS PART OF THE SCOPE OF WORK AND SHALL BE ACCOMPLISHED BY
THE CONTRACTOR AS IF MENTIONED ABOVE.
Submitted by:
Page 8 of 17
PROJECT : PROPOSED 2-STOREY RESIDENCE
LOCATION : Avocado Street, Ayala Alabang, Muntinlupa City
OWNER : MR. & MRS. MANUEL PALAGANAS
SUBJECT : BID FORM
DATE : FEBRUARY 15, 2024
E. Wall Caps
1.0 100mm diameter 2.00 pcs. 1,345.16 753.29 2,690.32 1,506.58 4,196.90
2.0 150mm diameter 7.00 pcs. 1,345.16 753.29 9,416.12 5,273.03 14,689.15
3.0 200mm diameter 3.00 pcs. 1,345.16 753.29 4,035.48 2,259.87 6,295.35
- - -
F. Duct Hangers & Support 1.00 lot 15,979.98 12,046.45 15,979.98 12,046.45 28,026.43
- - -
G. Duct tape 10.00 pcs. 270.23 132.41 2,702.30 1,324.10 4,026.40
- - -
H. Duct clips 150.00 pcs. 22.52 11.03 3,378.00 1,654.50 5,032.50
- - -
H. Adhesives 1.00 gal 1,167.41 572.03 1,167.41 572.03 1,739.44
- - -
I. Duct Sealants 1.00 gal. 1,801.56 882.76 1,801.56 882.76 2,684.32
- - -
J. Canvass cloth 1.00 roll 3,753.24 1,839.09 3,753.24 1,839.09 5,592.33
B. Pipe Insulation
1.0 6mm (1/4") Ø 120.00 lm. 519.67 291.01 62,360.40 34,921.20 97,281.60
2.0 9.5mm (3/8") Ø 240.00 lm. 519.67 291.01 124,720.80 69,842.40 194,563.20
3.0 12.7mm (1/2") Ø 180.00 lm. 519.67 291.01 93,540.60 52,381.80 145,922.40
4.0 15.86mm (5/8") Ø 198.00 lm. 519.67 291.01 102,894.66 57,619.98 160,514.64
5.0 19.05mm (3/4") Ø 42.00 lm. 519.67 291.01 21,826.14 12,222.42 34,048.56
C. Filters
1.0 pc.
2.0 pc.
3.0 pc.
D. Sight glass
1.0 pc.
2.0 pc.
3.0 pc.
E. Pipe hangers & supports 1.00 lot 64,325.00 48,491.16 64,325.00 48,491.16 112,816.16
Page 9 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
C. Ventilating Fans
1.0 EF-1 CEILING CASSETTE TYPE @ 50 CFM 5.00 pcs. 4,035.49 2,824.84 20,177.45 14,124.20 34,301.65
2.0 EF-2 CEILING CASSETTE TYPE @ 70 CFM 4.00 pcs. 4,035.49 2,824.84 16,141.96 11,299.36 27,441.32
3.0 EF-3 CEILING CASSETTE TYPE @ 100 CFM 3.00 pcs. 4,035.49 2,824.84 12,106.47 8,474.52 20,580.99
4.0 EF-4 CEILING CASSETTE TYPE @ 150 CFM 2.00 pcs. 4,035.49 2,824.84 8,070.98 5,649.68 13,720.66
5.0 EF-5 CEILING CASSETTE TYPE @ 200 CFM 3.00 pcs. 4,035.49 2,824.84 12,106.47 8,474.52 20,580.99
6.0 EF-6 INLINE TYPE KFAN @ 1800 CFM 1.00 pcs. 21,186.31 6,591.30 21,186.31 6,591.30 27,777.61
7.0 KEF-1 RANGE HOOD TYPE @ 800 CFM 2.00 pcs. 31,368.28 13,174.68 62,736.56 26,349.36 89,085.92
8.0 OF-1 OSCILLATING FAN @ 1,500 CFM 6.00 pcs. 4,702.06 2,304.01 28,212.36 13,824.06 42,036.42
BID SUMMARY
I. DUCT WORKS 1.00 lot 197,909.84 113,030.05 197,909.84 113,030.05 310,939.89
II. REFRIGERANT PIPING & ACCESSORIES 1.00 lot 1,968,838.70 1,118,965.11 1,968,838.70 1,118,965.11 3,087,803.81
III. MECHANICAL EQUIPMENTS 1.00 lot 2,350,641.48 967,460.95 2,350,641.48 967,460.95 3,318,102.43
IV. GENERAL EXPENSES 1.00 lot - 121,064.61 - 121,064.61 121,064.61
Page 10 of 17
PROJECT : PROPOSED 2-STOREY RESIDENCE
LOCATION : Avocado Street, Ayala Alabang, Muntinlupa City
OWNER : MR. & MRS. MANUEL PALAGANAS
SUBJECT : BID FORM
DATE : FEBRUARY 15, 2024
I. POWER SYSTEM
A. Distribution, Power and Lighting Panel "Gentec", "LJ" or
"Systems PowerMark" with Molded Case Circuit Breaker
"ABB", "Eaton", "GE", "Schneider" or "Siemens". Complete in
place.
Page 11 of 17
UNIT COST SUBTOTAL COST TOTAL
ITEM DESCRIPTION / PARTICULARS QTY UNIT
MATERIAL LABOR MATERIAL LABOR AMOUNT
b. Malleable C-clamp complete with base fastened to slab by
1 lot
stud bolt and nut "Hilti" or equivalent. 24,824.25 13,901.58 24,824.25 13,901.58 38,725.83
c.
"ENIstrut" trapeze hangers complete with 10 mm ø round
bars, fittings, and accessories fastened to slab by stud bolt 1 lot
and nut "Hilti" or equivalent. 39,718.80 22,242.53 39,718.80 22,242.53 61,961.33
F. Terminal lugs, solderless connectors and wire nuts. 1 lot 19,817.12 11,097.59 19,817.12 11,097.59 30,914.71
Page 12 of 17
UNIT COST SUBTOTAL COST TOTAL
ITEM DESCRIPTION / PARTICULARS QTY UNIT
MATERIAL LABOR MATERIAL LABOR AMOUNT
B. Color-coded wires and cables "Phelps Dodge", "Duraflex",
"Columbia" or "Philflex". Complete in Place.
1.0 3.5 mm2 THHN 9600 lm 40.28 22.56 386,688.00 216,576.00 603,264.00
a. 15 mm ø IMC pipe, locknut and bushing 1200 lm 209.04 117.06 250,848.00 140,472.00 391,320.00
b. 15 mm ø PVC pipe, locknut and bushing 720 lm 42.44 23.77 30,556.80 17,114.40 47,671.20
c. 20 mm ø PVC pipe, locknut and bushing 480 lm 63.75 35.70 30,600.00 17,136.00 47,736.00
d. Metallic flexible conduit and connector 900 lm 59.45 33.29 53,505.00 29,961.00 83,466.00
e. Utility boxes, 2 mm thick, deep type 1 lot 11,890.27 6,658.55 11,890.27 6,658.55 18,548.82
f. Octagonal boxes, 2 mm thick, deep type 1 lot 71,341.64 39,951.32 71,341.64 39,951.32 111,292.96
g. Square boxes 1 lot 22,195.18 12,429.30 22,195.18 12,429.30 34,624.48
E. Lever nut splicing connector similar to "Wago". 1 lot 13,211.42 7,398.39 13,211.42 7,398.39 20,609.81
Page 13 of 17
UNIT COST SUBTOTAL COST TOTAL
ITEM DESCRIPTION / PARTICULARS QTY UNIT
MATERIAL LABOR MATERIAL LABOR AMOUNT
g. 25 mm ø PVC pipe, locknut and bushing 200 lm 91.87 51.45 18,374.00 10,290.00 28,664.00
h. Utility boxes, 2 mm thick, deep type 1 lot 3,302.85 1,849.60 3,302.85 1,849.60 5,152.45
i. Octagonal boxes, 2 mm thick, deep type 1 lot 3,963.42 2,219.52 3,963.42 2,219.52 6,182.94
j. Pull boxes, square boxes and auxiliary gutters 1 lot 2,774.40 1,553.66 2,774.40 1,553.66 4,328.06
B. Wiring devices
1.0 Telephone Outlet 11 sets 528.46 295.94 5,813.06 3,255.34 9,068.40
2.0 Data Outlet 11 sets 726.63 406.91 7,992.93 4,476.01 12,468.94
3.0 Intercom Unit - All Master 11 sets 6,605.71 3,699.20 72,662.81 40,691.20 113,354.01
4.0 CATV Outlet 6 sets 594.51 332.93 3,567.06 1,997.58 5,564.64
5.0 24Port Patch Panel 2 sets 10,569.13 5,918.71 21,138.26 11,837.42 32,975.68
6.0 Data Cabinet 1 assy 50,203.38 28,113.89 50,203.38 28,113.89 78,317.27
B.
Closed Circuit Television Cabling. "Axess", "Belden", "Clipsal",
"LS Cable", "Panduit" or "Nexans". Complete in place.
1.0 Category 6 UTP cable 915 lm 39.63 22.20 36,261.45 20,313.00 56,574.45
2.0 Others (Please specify)
Page 14 of 17
UNIT COST SUBTOTAL COST TOTAL
ITEM DESCRIPTION / PARTICULARS QTY UNIT
MATERIAL LABOR MATERIAL LABOR AMOUNT
2.0 Metallic Conduit Support
a. 10 mm ø round bar complete fastened to slab by stud bolt
1 lot
and nut "Hilti" or equivalent. 5,595.03 3,133.22 5,595.03 3,133.22 8,728.25
b. Malleable C-clamp complete with base fastened to slab by
1 lot
stud bolt and nut "Hilti" or equivalent. 3,996.45 2,238.01 3,996.45 2,238.01 6,234.46
c.
"ENI-strut", "Erico", "Hilti", "Unistrut" trapeze hangers
complete with 10 mm ø round bars, fittings, and 1 lot
accessories fastened to slab by stud bolt and nut "Hilti" or
equivalent. 6,394.33 3,580.82 6,394.33 3,580.82 9,975.15
SUB-TOTAL (IV.E)
T O T A L P R O J E C T C O S T 10,549,803.89
Amount in Words
Notes:
1. All unit costs shall include the direct cost of materials, labor and mark-up including VAT.
2. lm - linear meter
Page 15 of 17
PROJECT : PROPOSED 2-STOREY RESIDENCE
LOCATION : Avocado Street, Ayala Alabang, Muntinlupa City
OWNER : MR. & MRS. MANUEL PALAGANAS
SUBJECT : BID FORM
DATE : FEBRUARY 15, 2024
a. Water closets
a.1 Flush tank 15.00 sets 44,561.58 3,329.28 668,423.70 49,939.20 718,362.90
b. Lavatory
b.1 Counter top 17.00 sets 17,217.12 2,774.40 292,691.04 47,164.80 339,855.84
c. Shower and in-bath fittings 15.00 sets 19,978.83 2,774.40 299,682.45 41,616.00 341,298.45
d. Toilet accessories (please identify):
d.1 Toilet paper holder 15.00 sets 5,073.18 1,109.76 76,097.70 16,646.40 92,744.10
d.2 hook 15.00 sets 4,121.96 1,109.76 61,829.40 16,646.40 78,475.80
e. Bath tub 1.00 sets 155,727.91 18,495.98 155,727.91 18,495.98 174,223.89
f. Kitchen sink and kitchen faucets, to include complete
mounting accessories 2.00 sets 14,981.75 2,774.40 29,963.50 5,548.80 35,512.30
d. Grease Trap Cap. = 7GPM 2.00 sets 17,835.41 2,774.40 35,670.82 5,548.80 41,219.62
b. Gate Valves
- 20 mm. dia.. 2.00 pcs 1,429.48 701.00 2,858.96 1,402.00 4,260.96
- 25 mm. dia.. 6.00 pcs 1,429.48 701.00 8,576.88 4,206.00 12,782.88
- 32 mm. dia.. 6.00 pcs 1,429.48 701.00 8,576.88 4,206.00 12,782.88
- 40 mm. dia.. 15.00 pcs 2,782.32 1,558.10 41,734.80 23,371.50 65,106.30
c. Check Valves
- 40 mm. dia.. 3.00 pcs 2,782.32 1,558.10 8,346.96 4,674.30 13,021.26
d. Y-strainer
- 40 mm. dia.. 3.00 pcs 2,782.32 1,558.10 8,346.96 4,674.30 13,021.26
e. Water Meter
- 25 mm. dia. 1.00 pcs 4,624.00 2,265.76 4,624.00 2,265.76 6,889.76
- - -
f. Hose Bibb - - -
- 20 mm. dia.. 5.00 pcs 726.63 356.05 3,633.15 1,780.25 5,413.40
- - -
g. Float Valve - - -
- 25 mm. dia.. 1.00 pcs 4,161.60 2,039.18 4,161.60 2,039.18 6,200.78
Page 16 of 17
UNIT COST SUBTOTAL COST
ITEM DESCRIPTION / PARTICULARS QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
- 150 mm. dia.. 18.00 lm 1,100.40 693.25 19,807.20 12,478.50 32,285.70
Diaphragm Tank
Cap. 1.00 sets 52,845.66 - 52,845.66 - 52,845.66
2 - Sets Duplex Type Sump Pump 1.00 sets 158,536.98 18,495.98 158,536.98 18,495.98 177,032.96
1 - Set Duplex Type Sewage Pump 1.00 sets 158,536.98 18,495.98 158,536.98 18,495.98 177,032.96
Instantaneous Type
Multi Point EWH 2.00 sets 16,704.84 8,185.37 33,409.68 16,370.74 49,780.42
T O T A L P R O J E C T C O S T 5,449,848.44
Page 17 of 17