BEW Remaining Works 111424
BEW Remaining Works 111424
Predecessors 17 Nov '24 24 Nov '24 01 Dec '24 08 Dec '24 15 Dec '24
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 BULK EARTHWORKS PROJECT(Remaining Works) 35 days? Thu 14/11/24 Thu 19/12/24
2 PROCESS PLANT 35 days Thu 14/11/24 Thu 19/12/24
3 Armco Guard Railing 5 days Sat 16/11/24 Thu 21/11/24 4FF
4 Safety bunds, 1.5 m high, 1V on 1.5H side 7 days Thu 14/11/24 Thu 21/11/24 7FF
slopes, 1.0 m crest
7 Type R Channel Lining, (Lined Canal) 7 days Thu 14/11/24 Thu 21/11/24
8 Gabion baskets, including wire baskets&rock 35 days Thu 14/11/24 Thu 19/12/24
9 ROM PAD 35 days Thu 14/11/24 Thu 19/12/24
10 Armco Guard Railing 5 days Sat 14/12/24 Thu 19/12/24 11FF
11 Safety bunds, 1.5 m high, 1V on 1.5H side 5 days Sat 14/12/24 Thu 19/12/24 12FF
slopes, 1.0 m crest
16 Anchor trench inc exc, place liner in trench, 20 days Thu 14/11/24 Wed 04/12/24
backfilling&compaction
17 Ponds and Overflow Channel HDPE 30 days Tue 19/11/24 Thu 19/12/24 16SS+5 days
18 Trenching and excavation 15 days Wed 04/12/24 Thu 19/12/24 17FF
19 HV SWITCHYARD ROAD AND PAD 35 days Thu 14/11/24 Thu 19/12/24
20 Geotextile BTG 350 30 days Thu 14/11/24 Sat 14/12/24
21 Safety bunds, 1.0 m high, 1V on 1.5H side 30 days Tue 19/11/24 Thu 19/12/24 12FF
slopes, 0.5 m crest
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Project3
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 14/11/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress