0% found this document useful (0 votes)
28 views

BEW Remaining Works 111424

Uploaded by

cmsrmisurigao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views

BEW Remaining Works 111424

Uploaded by

cmsrmisurigao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start Finish Predecessors 17 Nov '24 24 Nov '24 01 Dec '24 08 Dec '24

Predecessors 17 Nov '24 24 Nov '24 01 Dec '24 08 Dec '24 15 Dec '24
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 BULK EARTHWORKS PROJECT(Remaining Works) 35 days? Thu 14/11/24 Thu 19/12/24
2 PROCESS PLANT 35 days Thu 14/11/24 Thu 19/12/24
3 Armco Guard Railing 5 days Sat 16/11/24 Thu 21/11/24 4FF
4 Safety bunds, 1.5 m high, 1V on 1.5H side 7 days Thu 14/11/24 Thu 21/11/24 7FF
slopes, 1.0 m crest

5 Road Sign Allowance 5 days Sat 14/12/24 Thu 19/12/24 8FF


6 Ø900 OD HDPE Double Wall (Headwall& 15 days Fri 29/11/24 Sat 14/12/24 5SF
wingwall included)

7 Type R Channel Lining, (Lined Canal) 7 days Thu 14/11/24 Thu 21/11/24
8 Gabion baskets, including wire baskets&rock 35 days Thu 14/11/24 Thu 19/12/24
9 ROM PAD 35 days Thu 14/11/24 Thu 19/12/24
10 Armco Guard Railing 5 days Sat 14/12/24 Thu 19/12/24 11FF
11 Safety bunds, 1.5 m high, 1V on 1.5H side 5 days Sat 14/12/24 Thu 19/12/24 12FF
slopes, 1.0 m crest

12 Road Sign Allowance 5 days Sat 14/12/24 Thu 19/12/24 5SS


13 Type R Channel Lining, (Lined Canal) 7 days Thu 21/11/24 Thu 28/11/24 7
14 Geotextile BTG 350 7 days Thu 21/11/24 Thu 28/11/24 13SS
15 Ponds and Overflow Channel 35 days Thu 14/11/24 Thu 19/12/24

16 Anchor trench inc exc, place liner in trench, 20 days Thu 14/11/24 Wed 04/12/24
backfilling&compaction

17 Ponds and Overflow Channel HDPE 30 days Tue 19/11/24 Thu 19/12/24 16SS+5 days
18 Trenching and excavation 15 days Wed 04/12/24 Thu 19/12/24 17FF
19 HV SWITCHYARD ROAD AND PAD 35 days Thu 14/11/24 Thu 19/12/24
20 Geotextile BTG 350 30 days Thu 14/11/24 Sat 14/12/24
21 Safety bunds, 1.0 m high, 1V on 1.5H side 30 days Tue 19/11/24 Thu 19/12/24 12FF
slopes, 0.5 m crest

22 Road Sign Allowance 5 days Sat 14/12/24 Thu 19/12/24 12FF


23 Type R Channel Lining, 30 days Thu 14/11/24 Sat 14/12/24 20SS
24 DIVERSION DRAIN 35 days Thu 14/11/24 Thu 19/12/24
25 Trench Final Trim 7 days Thu 14/11/24 Thu 21/11/24
26 Geotextile BTG 350 35 days Thu 14/11/24 Thu 19/12/24 25FF
27 Type R Channel Lining 35 days Thu 14/11/24 Thu 19/12/24 25FF
28 Concrete Drop structure 30 days Tue 19/11/24 Thu 19/12/24 26FF
29 Stone Pitching 7 days Thu 12/12/24 Thu 19/12/24 28FF
30 Trenching 7 days Thu 14/11/24 Thu 21/11/24 25SS
31 ADDITIONAL WORKS FOR APPROVAL Thu 14/11/24
32 Select Fill (Crushed and Stockpile) Thu 14/11/24
33 Aggregates Surface Coarse Thu 14/11/24
34 Riprap Slope Protection&Buttress Thu 14/11/24
35 Buttress Support (South Batter) Thu 14/11/24
36 Slope Protection and Batter (Supply Road) Thu 14/11/24
37 Slope Protection and Batter (HV Swithchard) Thu 14/11/24
38 Clean Water Pond Thu 14/11/24
39 Access Road to Compressor&Water Tank Thu 14/11/24
40 DEMOBILIZATION 30 days Tue 19/11/24 Thu 19/12/24
41 Waste Dump Clean-up 30 days Tue 19/11/24 Thu 19/12/24 27FF
42 Demobilization 15 days Wed 04/12/24 Thu 19/12/24 27FF

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Project3
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 14/11/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1

You might also like