1. Reference International Standard was updated to ISO
1 9001:2008. 01 04 Aug 10
2. Amended according to ISO 9001:2008 requirements.
1. Incorporate the Production Planning procedure
including the critical points.
2. Establish new forms for Production Planning use.
3. Update the Duties and Responsibilities for Production.
4. Revision of some Production Forms.
2 02 24 Aug 10
5. Other forms were considered obsolete and were
removed from the procedure.
6. Identification and Control over Measuring Equipment
was established.
7. Modification on the procedure format
i Covering Page 01
ii Amendment Records 02
iii Index 03
1 Purpose 04
2 Scope 04
5 Procedure 07
6 Work Instruction 10
7 Appendices 10
8 Related Records 10
9 Related Documents 11
10 Reference Documents 11
To demonstrate the performance and to evaluate the effectiveness of this procedure thru their
related activities, this shall include data generated as a result of monitoring and measurement
through the following:
To monitor the results of production productivity by comparing the production plan
against the production output within three (3) consecutive months.
To monitor the results of product quality by comparing the product inspected against
the product accepted within three (3) consecutive months.
2. Scope
The scope of this document applies to all production and production planning activities that are
carried out by the Alu-Nasa and all personnel dealing with these activities.
3.2. Definitions
Quality related activity
Machining (Cutting, Shearing, Drilling, Milling, Crimping, Slitting, Lathe, Notching,
Punching, Routing, Grooving, Folding, Bending, Rolling, Grinding, Polishing,
Buffing) assembly, structural bonding, packaging & dispatching
Position: Foreman
o Responsible in allocating work per instruction of General Foreman in order to meet
the production schedule.
o Responsible for monitoring and checking every piece of materials to be fabricated in
every designated area in accordance with the “Fabrication Order (OSP-14-FRM-
09)” released.
Position: Fabricator
o Responsible for executing the fabrication day to day activities in the production.
o Ensure that the measuring devices used are calibrated and accurate.
o Ensure that fabricated materials are correct in accordance with material cutting list
to meet the product requirements.
o Responsible for the assembly of all fabricated materials as per instruction of in
charge Foreman in accordance with cutting list material to meet the product
requirements.
Position: Helper
o Assisting in the day to day fabrication activities in the production.
o Assisting the fabrication for proper handling, packing, storage and protection of
materials to ensure that the product is in safe, secure and in a proper area.
5.2.2. When deciding whether WI’s are required for individual operations, the following
points should be assessed.
The importance of the individual operation and its potential impact on quality.
The complexity of the operation.
Any history of quality problems linked with operations.
The general level of competency of operators.
Work instructions are prepared by the Section Manager, reviewed by the Quality
Management Representative, and approved by the Regional General Manager.
They are then made available for all operators at required locations throughout
the department.
The Section Manager decides what training, if any, is required for the concerned
operators. Refer to “Competence, Awareness & Training (OSP-10)” quality
system procedure.
5.4.3. Traceability is the system used to trace the history of products through production
and inspection and testing, in case of product complaints.
5.4.4. The traceability of products produced by the Production Section should be recorded
as follows:
To maintain the “Fabrication Order (OSP-14-FRM-09)” records, detailing date of
manufacture and processes required for manufacture.
To maintain the inspection records.
5.6.2. All outgoing material/product should be marked with project specific markings to
ensure that every material/product should have proper identification and traceability
to prevent mixing of items during production and servicing activities in accordance
with “Fabrication Order (OSP-14-FRM-09)”.
5.6.3. Upon dispatch of materials/products to site, each specific unit/items should be
itemized and the project number in “Delivery Order (OSP-19-FRM-05)” should be
specified for the purpose of identification and traceability.
5.6.4. Upon delivery to site, each materials/product should check the identification/marking
against the “Setting-out Drawings” to ensure correct installation.
Document No.: OSP-16 Revision No.: 02
Page 9 of 11
Document Title: Production and Production Planning Revision Date: 24 Aug 2010
This document is property of Alu Nasa. It cannot be reproduced or transmitted to a third party without prior authorization.
5.7 Production Planning
5.7.1 Production Planner will receive Work Order and Material Take-Off documents from
Technical Department which will then be logged on the “Work Order Register”
(OSP-16-FRM-10) and “Material Take Off Register” (OSP-16-FRM-11)
5.7.2 All received technical documents will be checked by the Production Planner whether
it is complete, correct or adequate to the project. “Technical Documents Checklist”
(OSP-16-FRM-12) will be used to log all status of the received documents. In case
of incomplete, wrong or inadequate documents, Production Planner shall give
immediate feedback to Technical Department and wait until all documents are
complete to start the planning.
5.7.3 Production Planner will check the Material availability thru “Material Tracking
Register” (OSP-16-FRM-13) in coordination with the Store. If material is not
available, purchases requisition must be made by the Store In- Charge.
5.7.4 Production Planning shall consider other factors that are significant in generating
the “Production Plan” (OSP-16-FRM-14). This shall include but not limited to:
Priority, Deadline from Client, Availability of resources and Dispatch schedule.
These will be coordinated to different departments of the organization
5.7.5 Once “Production Plan” (OSP-16-FRM-14) is complete, a copy will be distributed to
the Section Manager along with other Technical Documents.
5.7.6 During actual production, Production Planner shall constantly coordinate with the
Section Manager regarding the status of the project. Progress of the project will be
monitored thru “Production Status Completion Register” (OSP-16-FRM-15).
5.7.7 Production Planner shall validate whether the plan has been executed based on
schedule. Any delays must be justified by the Section Manager and maybe re-
considered on the next plan.
6. Work Instruction
OSP-16-WI-01 Work Instruction - Machining
OSP-16-WI-02 Work Instruction - Assembly
OSP-16-WI-03 Work Instruction - Structural Glazing Application & Testing
Control
OSP-16-WI-04 Work Instruction - Remedial Work
7. Appendices
OSP-16-Appx-01 Organization Chart
8. Related Records
OSP-16-FRM-01 Production Monitoring Register
OSP-16-FRM-03 Material Handover Note
OSP-16-FRM-04 Daily Production Report
OSP-16-FRM-05 Manpower Allocation
OSP-16-FRM-07 Scrap Records
OSP-16-FRM-09 Daily Production Report Summary
OSP-16-FRM-10 Work Order Register
OSP-16-FRM-11 Material Take Off Register
9. Related Documents
QSP-05 Control of Non-Conforming
QSP-06 Corrective Action
OSP-10 Competence, Awareness & Training
OSP-18 Client Property
QSP-05-FRM-01 Non Conforming Report
OSP-19-FRM-04 Material Issue Voucher
OSP-19-FRM-05 Delivery Order
Project Programme