PQP Template-Rev.02
PQP Template-Rev.02
Company
PROJECT
FOR
CLIENT
05
04
03
02
01
00
Amendments History
05
04
03
02
01 -
00 - Original issue
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 3 of 66
Table of Contents
1.0 Introduction...............................................................................................................................................................5
2.0 Scope......................................................................................................................................................................... 6
3.0 Inputs.........................................................................................................................................................................6
4.0 Objectives..................................................................................................................................................................6
5.0 Management Responsibilities...................................................................................................................................7
6.0 Control of (( COM )) Duments and Data...................................................................................................................7
7.0 Control of Records...................................................................................................................................................10
8.0 Resources................................................................................................................................................................ 11
8.1 Provision of Resources........................................................................................................................................11
8.2 Materials............................................................................................................................................................. 12
8.3 Human Resources and Training.........................................................................................................................12
8.4 Infrastructure and Work Environment...............................................................................................................12
9.0 Requirements..........................................................................................................................................................13
10.0 Customer Communication...................................................................................................................................... 13
11.0 Design and Development........................................................................................................................................15
12.0 Purchasing............................................................................................................................................................... 15
13.0 Construction Activities............................................................................................................................................17
13.1 Materials Approvals and Samples......................................................................................................................17
13.2 Method Statements............................................................................................................................................17
13.3 Shop Drawings.................................................................................................................................................... 17
13.4 PIP’s / ITP’s..........................................................................................................................................................18
13.5 Construction Supervision....................................................................................................................................18
13.6 Plant and Equipment..........................................................................................................................................18
13.7 Construction Inspection......................................................................................................................................18
14.0 Identification and Traceability................................................................................................................................20
15.0 Client Property........................................................................................................................................................ 20
16.0 Preservation of Product..........................................................................................................................................21
17.0 Control of Nonconforming Product.........................................................................................................................21
18.0 Monitoring and Measurement................................................................................................................................22
19.0 Control of Inspection, Measuring and Test Equipment..........................................................................................25
20.0 Audits...................................................................................................................................................................... 27
21.0 Servicing.................................................................................................................................................................. 28
22.0 Statistical Techniques..............................................................................................................................................28
23.0 Contract Review......................................................................................................................................................28
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 4 of 66
24.0 Attachments............................................................................................................................................................ 29
Attachment 1: Acronyms, Abbreviations and Definitions Used......................................................................................30
Attachment 2: Project Organisation Chart.......................................................................................................................34
Attachment 3: Roles and Responsibilities Related to this PQP.......................................................................................35
Attachment 4: List of Works Intended to be Subcontracted...........................................................................................49
Attachment 5: List of Proposed Method Statements......................................................................................................50
Attachment 6: ISO 9001 Certificate..................................................................................................................................52
Attachment 7: Quality and Environment Policy...............................................................................................................53
Attachment 8: List of Standard Forms.............................................................................................................................54
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 5 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 6 of 66
Introduction
This Project Quality Plan (PQP) forms part of the overall (( COMPANY )) Quality Management
system (QMS) and is modelled upon ISO 10005: Quality Management Systems - Guidelines for Quality
Plans (2005). Its goals are to increase confidence that specified requirements will be met, provide
greater assurance that pr (( COMPANY )) esses are in control, to engender motivation and to provide
a structured approach to project execution. The entirety of the (( COMPANY )) QMS is based upon
the Plan-Do-Check-Act (PDCA) cycle for continuous improvement depicted below.
The Project Quality Plan (PQP) is the (( COMPANY )) principal (( COMPANY )) Document for Quality
describing the necessary Quality Assurance (Quality Planning) and Quality Control (Quality Verification)
arrangements to be implemented for the Project to achieve the quality requirements described in the
Contract Specifications and Drawings for engineering, pr (( COMPANY )) urement, construction,
commissioning and hand-over.
This PQP is a project-specific reference ((COMPANY )) Document for Quality combining the necessary
elements of (( COMPANY )) ISO 9001 certified Quality Management Systems (QMS). It is not the aim
of the PQP to reproduce the QMS or ((COMPANY)) Perdures but as necessary to explain the
application of the QMS and state key pr (( COMPANY )) edural points relevant to the quality
arrangements.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 7 of 66
The PQP is to be implemented by all ((COMPANY)) Project employees and subcontractors and
suppliers. The PQP shall therefore be distributed as a controlled ((COMPANY NAME)) Document to
required ((COMPANY)) personnel and subcontractors and suppliers by ((COMPANY)) Document
Control.
1.0 Scope
This Project Quality Plan (PQP) has been developed for <INSERT PROJECT REFERENCE AND TITLE
HERE> using a standard template, based upon ISO 10005, to define all those activities necessary to
ensure that the engineering, procurement, construction, commissioning and hand-over are as per
specified requirements.
PQP Control: The PQP shall be drafted by the QC Manager, distributed to required personnel by the
((COMPANY)) Document Controller and thereafter maintained in a current state by the
QC Manager with revisions being distributed to prior holders of the ((COMPANY))
Document.
2.0 Inputs
Ensure submittals approval: 1st time @ >85% / 2nd time @ >95% / 3rd time @ 100%
Ensure the cost of non-conformance < 0.5% of contract value
Ensure first and foremost that the work is carried out safely;
Provide a well-defined organisation with a clear definition of responsibility;
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 8 of 66
Generally, the responsibilities of the personnel involved in the planning, executing, controlling and
monitoring works are defined in referenced (( COMPANY )) Document s including but not limited to:
Project Plans
Quality Pr (( COMPANY )) edures and Work Instructions
Method Statements
Project Inspection Plans / Inspection and Testing Plans
Job Description / Job Profiles
Subcontract Agreements
Subcontractors / Suppliers shall nominate to the (( COMPANY )) Project Manager for acceptance a
competent Quality Representative for their Works. The Quality Representative shall be a sufficiently
senior person in the Subcontractor / Supplier organisation, with necessary authority to achieve all
quality requirements by managing required resources with his programmes constraints. The Quality
Representative shall be a full-time on-site, as necessary, unless agreed otherwise with
(( COMPANY )) .
The Project Manager is responsible for the successful overall completion of the Project including
compliance with the company’s QMS and attainment of the above objectives.
The Project Manager shall assign the levels of authority applicable to specific job functions and have
maintained on an ongoing basis the Project Approved Signatories List.
The Project Quality Manager is responsible for all quality assurance and quality control activities,
required to plan and verify Works satisfy the Contract (( COMPANY )) Document s. The Quality
Manager reports both to (( COMPANY )) Quality Director and to the Project Manager for the daily
construction activities.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 9 of 66
Senior employees will serve to guide Project Strategy with Project Manager and where necessary will
assist to define, monitor and action Project Objectives and Targets; and support the Project Manager
with necessary resources. Such personnel will include, but not limited to, Business Unit Director,
Deputy Business Director (as needed), the Corporate Quality and HSE Director and (as needed)
Business Unit Functional Managers for Pr (( COMPANY )) urement
All (( COMPANY )) Document s and data related to the Project shall be developed in accordance with
standard Company pr (( COMPANY )) edures, made identifiable to the Project through reference
numbering and titling, reviewed and approved prior to release as indicated on each (( COMPANY ))
Document type and distributed for use and/or information in accordance with the Project
(( COMPANY )) Document Distribution Matrix authorised by the Project Manager.
Shop Drawings will use an approved “Title Bl (( COMPANY )) k” with a designated numbering
and coding system for the design / engineering works. The Engineering Manager will ensure
drawings submission details are established and managed by (( COMPANY )) Document Control:
internal and external transmittal requirements; FTP prot (( COMPANY )) ols as necessary; hard
copy drawing sizes; number of hard copies; CAD software and drawing requirements for soft
copies; change control; revision sequencing; (( COMPANY )) Document Distribution Matrix; and
codes internal to (( COMPANY )) and external from (( COMPANY )) . The Engineering Manager
is responsible for ensuring adequate checking and coordination of all Shop Drawings prior to
external submission. Drawings for internal review or comments will not be “controlled copy”. All
Shop Drawings will be registered in MS Excel spreadsheets or proprietary (( COMPANY ))
Document control software with sufficient details to enable monitoring, traceability and
reporting of status and progress.
As-Built Drawings: As-built Drawings are required (numbers and formats) shall be established by
the Engineering Manager for each work unit / activity with reference to the Contract
Specifications. During Construction as-built drawings will be marked-up by hand on an ongoing
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 10 of 66
basis by nominated persons from (( COMPANY )) or Subcontractors. The as-built drawings will
record actual construction, dimensions and l (( COMPANY )) ations, and include as necessary
DCR’s, FCR’s and NCR’s, etc.
The (( COMPANY )) Document Controller will maintain in a defined and organised system
“Master Files” of all necessary internal-origin technical (( COMPANY )) Document ation.
Superseded editions or revisions of technical (( COMPANY )) Document ation will be retained but
clearly identified and segregated to avoid accidental usage.
Recipients of all “controlled copy” (( COMPANY )) Document ation are responsible for ensuring
superseded copies are stamped as such, or destroyed.
Emails: Emails will be written and distributed in strict accordance with (( COMPANY )) Policy
and Pr (( COMPANY )) edures and are regarded as “non-contractual” correspondence.
Drawings: Drawings received from the Owner Representative as IFC or reviewed shop drawings,
or from subcontractors, or from 3 rd Parties will be immediately stamped and registered in MS
Excel spreadsheets or proprietary (( COMPANY )) Document control software by the
(( COMPANY )) Document Controller with sufficient details to enable monitoring, traceability and
reporting of status. Prior to internal distribution, the Engineering Manager or nominated person
is responsible for ensuring adequate checking and coordination of the drawings, e.g. against
those drawings issued previously for the same discipline, or comparing between disciplines such
as Civil and Mechanical. The subsequent distribution of “controlled copy” drawings to nominated
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 11 of 66
The (( COMPANY )) Document Controller will maintain in an organised system “Master Files” of
all necessary incoming technical (( COMPANY )) Document ation. Superseded editions or
revisions of technical (( COMPANY )) Document ation will be retained but clearly identified and
segregated to avoid accidental usage.
Recipients of all “controlled copy” (( COMPANY )) Document ation are responsible for ensuring
the superseded copies are stamped as such, or destroyed.
Emails: Emails will be written and distributed in strict accordance with (( COMPANY )) Policy
and Pr (( COMPANY )) edures and are regarded as non-contractual correspondence.
Filing and archiving of technical (( COMPANY )) Document ation (excluding emails) will be in
accordance with Contract (( COMPANY )) Document s and (( COMPANY )) Pr (( COMPANY ))
edures, by nominated persons, using a standard coding system, and stored in approved adequate l
(( COMPANY )) ations.
Note: Refer to QMP-001 Rev. 02: (( COMPANY )) Document and Records Control pr (( COMPANY ))
edure
Quality Records
The Company as a matter of course retains pertinent records for specified minimum retention periods
dependent upon their nature and applicable client, statutory or regulatory stipulations.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 12 of 66
Records to be handed over to the client throughout the construction period and upon completion
shall be detailed in the Project Inspection Plan (PIP) / ITP’s.
The scope of records generally includes: all (( COMPANY )) and third party inspection and testing of
records verifying conformity with the Contract Specifications; or required by the Owner
Representative, governmental or l (( COMPANY )) al authority regulations; or (( COMPANY ))
requirements, and further includes but is not limited to:
All records shall be legible, date stamped, and project-referenced. Records will be generated,
maintained and stored in hard and soft copy formats in designated filing systems with appropriate
access, security and fire protection. Soft copy records will be “backed-up” daily and weekly in
accordance with (( COMPANY )) IT Pr (( COMPANY )) edures.
Submission of records to the Owner Representative will generally be in accordance with the Contract
Specifications, General and Special Contract Conditions. These handover (( COMPANY )) Document
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 13 of 66
ation “Packages” will be an organised, indexed and complete compilation of necessary as-built
drawings and records verifying compliance with the Contract Specifications, and checked by
nominated (( COMPANY )) personnel prior to formal submission to the Owner Representative.
Retention periods of all records will satisfy first Contract requirements, l (( COMPANY )) al
regulations, and thirdly (( COMPANY )) Company requirements. (( COMPANY )) will appoint
nominated persons to manage the identification, archiving, retention and disposition of project
records in accordance with (( COMPANY )) Pr (( COMPANY )) edures to achieve the
aforementioned requirements.
Note: Refer to QMP-001 Rev. 02: (( COMPANY )) Document s and Records Control pr (( COMPANY ))
edure
7.0 Resources
The successful execution of the Project shall be assured through the timely provision of resources,
both material and human, to match demand histograms derived from the Works Schedule.
Any specific infrastructure and/or work environment requirements shall be determined and catered
for as works pr (( COMPANY )) eed.
7.2 Materials
The specific characteristics to which materials are to conform are detailed in the Project Inspection
Plan (PIP) / ITP’s under the headings of acceptance criteria and control (( COMPANY )) Document s.
Personnel shall be deployed entirely upon their competence to fulfil the specific roles to which they
are to be assigned.
Orientation and awareness training appraising them of the specific nature and critical success
factors of the Project;
Quality Induction: awareness training of the Quality Management System (QMS);
Health and Safety Induction: described separately in the Project Health Safety and Environment
(HSE) Plan
and, thereafter, be scheduled to receive awareness training as deemed appropriate to their specific
roles. Such awareness training comprises standard format PowerPoint presentations covering PEP’s,
PDP’s, PQP’s, PIP’s / ITP’s and PCPs, pr (( COMPANY )) edures, method statements and the like:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 14 of 66
Quality System Training: overview of (( COMPANY )) QMS and PQP every 3-4 months.
Method Statements: Workforce is technically briefed by Tool Box talks, prior to activity
commencement, and each work shift or day.
Project inspection Plan: Prior to activity commencement, and then once per month, or other
necessary frequency.
The workforce shall be appraised of required methods embodied (( COMPANY )) Document ed in the
method statements applicable to their work prior to its commencement and thereafter at intervals as
required to ensure adherence to requirements.
The objective managing infrastructure is to continuously enable and support the Project Management
Team with facilities to achieve the Works and comply with the Contract Specifications.
Particular requirements for Infrastructure Scope includes but not limited to tooling, plant and
equipment, buildings, power, water, data, support services, transport, and their storage, fabrication,
construction, installation and maintenance shall be determined and provided by the Project Manager
as applicable to specific works and detailed within method statements or with (( COMPANY )) or
Project-Specific Pr (( COMPANY )) edures.
The objective of managing work environments is to ensure continuous compliance of people, plant /
equipment and materials with the Contract Specifications. Where work environments (temperature,
humidity, etc) have a direct effect upon quality the control measures to be deployed shall be detailed
within method statements and the criteria to establish their attainment determined and detailed
within PIP’s / ITP’s.
Plant and Equipment shall be suitable and sufficient and fit for purpose; and controlled for usage and
by competent operators; and maintained to Manufacturer Recommendations, or where there are
none to International Standards.
Materials shall be controlled in accordance with the Project Inspection Plan (PIP’s) and the HSE Plan;
transported, stored and used in accordance with Manufacture Recommendations and Method
Statements for their actual work environment; and inspected and tested in accordance with
approved PIP’s / ITP’s.
8.0 Requirements
The PIP / ITP details specified requirements (sample submissions, m (( COMPANY )) k-ups and trials
required, target values and ranges to be attained) and when, how and by whom these are to be
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 15 of 66
Any conflicts or ambiguities in specified requirements shall be formally resolved using Requests for
Information (RFI’s) and any amendments made referred to in revisions to the PIP / ITP.
Interfacing and the means of communication with the client shall be defined within the specific roles
and responsibilities of assigned personnel and within this and other Project Plans and Pr (( COMPANY
)) edures.
All communication made to or received from the client shall be formally (( COMPANY )) Document
ed, logged and retained. Correspondence will be strictly managed as Section 6.0: Control of
(( COMPANY )) Document s and Data.
Any verbal agreements made with the client shall be confirmed formally at the earliest opportunity
thereafter using a Confirmation of Verbal Instruction (CVI) form.
Any client compliments that may be received shall be directed to the Project Manager for distribution
to and/or acknowledgement of those concerned.
Any client complaints that may be received shall be directed to the Project Manager to determine the
nature and extent of any investigation and reporting required. All “Customer Complaints” shall be
recorded.
Meetings
As general principles (( COMPANY )) will aim to minimise numbers of meetings; always have a
Chairperson and Scribe; f (( COMPANY )) us on actions; and ensure meetings are adequately
recorded by Minutes or Action List; and followed-up and close-out.
Internal Meetings: The Project Manager will establish and issue the Weekly Meetings Schedule in
accordance with his Managers. The minimum meetings will be:
External Meetings: Will be included on the Weekly Meetings Schedule by the Project Manager, who
will also decide the optimum list of (( COMPANY )) attendees for all external meetings. The
minimum external meetings, subject to requirements of the Client/Client’s Representative, are
estimated as:
Reports
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 16 of 66
The following reports shall be submitted to the Client/Client’s Representative in accordance with
Project Controls:
Narrative Report: includes but not limited to a description of the problem areas (current and
anticipated), delaying factors, and their impact, and an explanation of corrective actions taken or
proposed
Management Summary Schedule
Manpower and Progress Curves
Project Cost Report
Project Change Register
Total Cash Flow Curve
Commitment Report
Material Status Report
Major activities completed during the reporting period
Major items scheduled to complete during the next reporting period
Field manpower status report by discipline (daily/weekly/monthly)
Field equipment status report by discipline (daily/weekly/monthly)
Field work status report by discipline (daily)
Construction progress report (weekly/monthly)
Report on work volume achieved during a previous month for invoicing purposes (monthly)
Inventory (as required)
Inspection schedule, plan, report (as required)
Test record (as required)
Quality control report (as required)
Loss/damage report (as required)
Other plans and reports to be submitted by (( COMPANY )) in accordance with the provisions of
the Subcontract or instructions from time to time given by the Contractor (as required)
Shop drawings for (( COMPANY )) ’s fabrication work (as required)
Mark-up drawings for as-built drawings (prior to issuance of certificate of initial acceptance)
All necessary work pr (( COMPANY )) edure (as required)
Where Contractor design is required this has been (( COMPANY )) Document ed separately as the
Project Design Plan (PDP) which defines applicable codes, standards, specifications, quality
characteristics and regulatory requirements; design and development input and output criteria;
required schedule and attendees of design reviews.
The Engineering Pr (( COMPANY )) ess defines and describes methods, responsibilities and controls
for design and development aspects such as:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 17 of 66
The pr (( COMPANY )) ess for the control of design changes requests and their authorisation for
issue, review, approval to pr (( COMPANY )) eed or rejection and verification of implementation are
(( COMPANY )) Document ed in the Design Management pr (( COMPANY )) edure.
Any errors or omissions, conflicts of ambiguities in design requirements shall be formally resolved
using Request for Information (RFI’s) or Field Change Requests (FCR’s) pr (( COMPANY )) essed in
accordance with Contract Specifications and (( COMPANY )) Engineering and (( COMPANY ))
Document Control Pr (( COMPANY )) edures.
11.0 Purchasing
All items purchased for incorporation into the Works shall be as specified requirements or as
subsequently agreed.
All Subcontractors and Suppliers/Vendors shall be approved as necessary in accordance with the
Project Contract General/Special Conditions, and subsequently pr (( COMPANY )) ured in accordance
with (( COMPANY )) Pr (( COMPANY )) edures and Client’s Sourcing and Pr (( COMPANY ))
urement Pr (( COMPANY )) edures. Subcontractors and Suppliers shall be selected from
(( COMPANY )) “Approved Lists” based on their abilities to meet several specified requirements
including: specification requirements, schedule, reliability, partnering approach and pricing.
Technical characteristics shall be defined fully and unambiguously, together with any pre-delivery
verification (Factory Acceptance Tests (FAT’s)) and monitoring activities to satisfy specified, statutory
or regulatory requirements.
Irrespective of any preceding verification conducted all deliveries to the Project shall be inspected
upon receipt.
As necessary depending on factors of schedule, value and criticality, subcontractors and suppliers will
be managed by:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 18 of 66
All materials for incorporation into the Works shall be pr (( COMPANY )) ured to achieve Contract
Specification requirements, or as subsequently approved in Project Contract General/Special
Conditions, and purchased in accordance with (( COMPANY )) Pr (( COMPANY )) edures. Generally
purchasing of permanent materials and products will pr (( COMPANY )) eed only after Client/Client’s
Representative acceptance.
Off-site inspection and testing by QA/QC and/or Client/Client’s Representative as required, (e.g.
Factory Acceptance Tests) or other pre-delivery verification activities satisfying the Contract
Specifications or other approved requirements, will be (( COMPANY )) Document ed in Project
Inspection Plans.
Temporary materials and products, unless stated otherwise in the Contract Specifications, will not be
submitted for acceptance by the Client/Client’s Representative. However, (( COMPANY )) Pr
(( COMPANY )) edures will continue to control the purchasing and QA/QC pr (( COMPANY )) esses,
and ensure temporary materials and products are “fit for purpose”.
Receiving Inspection
All permanent materials and products will be subject to receiving inspection by QA/QC, and as
necessary acceptances by the Client/Client’s Representative, to verify conformance to Contract
Specifications or other approved requirements prior to incorporation in the Works. These Material
Inspection Reports or Material Receiving Reports are classified as Quality Reports.
Construction activities shall be managed through the use of Method Statements, Project Inspection
Plans (PIP’s / IPT’s), IFC and Shop Drawings, Engineering Submittals Schedules and, as necessary,
Project Specific Plans and Pr (( COMPANY )) edures. (Refer to Attachment 1 and Attachment 5).
All Construction activities are to commence progress and complete within a system of permanent
controlled conditions. These controlled conditions are a set of requirements:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 19 of 66
Materials approvals and samples will be submitted on an (( COMPANY )) -approved Standard Forms
in accordance with Contract Specifications, following review by Design / Engineering Offices and as
necessary by QA/QC, and to satisfy Programme requirements.
Shop Drawings shall be submitted on approved drawing formats, software and title bl (( COMPANY ))
ks in accordance with the Contract Specifications and the Project Design Plan, and be coordinated with
interfacing disciplines, other Contractors Works, and as necessary Design and Engineering Changes
whether proposed by the Client’s Representative or (( COMPANY )) , and to satisfy Programme
requirements.
PIPs / ITP’s with Check sheets will be submitted on (( COMPANY )) -approved Standard Forms and be
reviewed by the Quality Manager, Design/Engineering as necessary, and Project Manager. PIP’s / ITP’s
will be submitted as required in Contract Specifications, and in addition as instructed by the Quality
Manager and Project Manager, and to satisfy the Programme requirements. PIP’s / ITP’s identify
sample submissions to be made, m (( COMPANY )) k-ups and trials to be undertaken, together with
those characteristics required to be inspected, tested, verified and validated to confirm specified,
statutory and regulatory requirements have been attained. PCPs, where required, shall (( COMPANY ))
Document the pr (( COMPANY )) esses and techniques to be adopted, together with details of states
and regulations, industry codes of practice, personnel competence, client operational staff training,
(( COMPANY )) Document s,, test results, reports and the like to substantiate the satisfactory
completion of commissioning activities, development of operating manuals to facilitate future
operation and maintenance, and client acceptance of the various system of which the Works are
comprised.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 20 of 66
Construction Supervision from Site Manager, Construction Manager, Engineers and Foreman, etc. will
be competent by their qualifications, experience and skills; the number of Supervisors provided will
ensure adequate full time provision during all works shifts; and a clear chain of communication and
authority will be maintained.
Plant and equipment shall satisfy the requirements of the Project HSE Plan and Method Statements,
and be fit for purpose at all times. Additional regulatory requirements for certification, Operators will
use, check and maintain their plant and equipment in accordance with methods and frequencies from
manufacturer or (( COMPANY )) requirements or recognised Industry-Standard practice. Plant and
equipment confirmed or suspected as defective or malfunctioning will be immediately notified to the
next highest level of Construction Supervision, or as needed directly to the Health and Safety team, for
action including removal from Site, suspension from use, or repair.
The Site/Construction Manager and PQM is responsible for performing inspection and testing to verify
that field construction and installation activities of (( COMPANY )) and Subcontractors meet the
requirements of the Project Specification.
A quality control representative in accordance with quality pr (( COMPANY )) edures will inspect
construction and installation activities. Construction, installation and testing activities, which do not
confirm to quality control pr (( COMPANY )) edure requirements, will be (( COMPANY )) Document
ed on appropriate forms and non-conformance reports may be issued by quality control
representatives for such condition.
Inspection and testing (( COMPANY )) Document s will be filed and maintained in accordance with
(( COMPANY )) pr (( COMPANY )) edures, reports and records will be available for review by the
Client.
Phases of Inspection:
Preparatory Inspection: Inspections are to be performed prior to the beginning of any major
definable feature of work. A meeting will be scheduled and the following items to be discussed
shall include but not limited to:
o Review each paragraph of the applicable specifications and drawings;
o Check that all materials, for that specific feature of work, comply with the submittals and
specifications;
o Status of the submitted materials and shop drawings
o Go through the whole sequence of execution and the required level of workmanship;
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 21 of 66
Initial Inspections: Initial inspections must be performed at the beginning of any major definable
feature of work and must be repeated at any time new work force is added and whenever work
does not comply with required quality. The initial inspection shall follow, but not limited to the
following:
o Ensure that all work is in full compliance with IFC drawings / plans and Specifications;
o Review the minutes of prep meeting (as necessary);
o Ensure that all quality control are effective to convey the specified requirements;
o Establish a level of workmanship needed and compare with the required sample if required;
o Resolve all the differences for the specific feature of work;
o Check safety compliance and potential problems encountered;
o Inform NREA in advance of such inspection and have all forms checked.
Follow-up Inspections: Inspections are to be performed daily to ensure that the controlled
established during preparatory and initial inspections continue to provide a product that conforms
to the Contract Requirements. All deficiencies shall be rectified prior to any start of the additional
features of work which may be affected by the defective work. This phase of inspection is an
ongoing phase until the end of the project
Pre-final Inspection: At the completion stage of all work or increments thereof, the
Site/Construction Manager and PQM will perform a pre-final inspection and develop a “punch list”
of all deficiencies noted. This list will be formally (( COMPANY )) Document ed along with the
estimated date by which the deficiencies will be corrected. The Site/Construction Manager and
PQM will perform a follow up inspection to ensure that all deficiencies have been corrected before
notifying the Contracting Officer’s representative. The inspections and corrections required will be
accomplished within the time stated for completion of the entire work or increment thereof.
Note: Refer to PRO-QUA-01 Rev 01: Inspection and Testing Pr (( COMPANY )) edure
Attachment 5 provides details of Method Statements to be developed
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 22 of 66
Identification is, where appropriate and specified, labelling, marking etc. of identical products,
materials or components for the necessary purposes of distinguishing them form each other.
Traceability is the system or pr (( COMPANY )) ess enabling at a point in time forward or backward
“tracing” of products, materials or components between sources and final l (( COMPANY )) ations.
Client property shall be treated as though supplied by (( COMPANY )) in that it shall be subject to
receipt inspection to ensure that it meets specified requirements and where found to be:
Acceptable, stored in accordance with Manufacturer Recommendations, or as a minimum in
accordance with (( COMPANY )) Pr (( COMPANY )) edures or Industry-Standard Practice;
appropriately and clearly identified as ‘client property’ prior to its incorporation into the Works;
Client property that has been found to be damaged, mislaid or is otherwise unsuitable shall be
notified to the client for determination of means of redress.
Materials, products and components for incorporation into the Works shall be packaged handled,
transported, delivered, stored and their integrity preserved throughout all stages of construction and
commissioning until final hand-over to the client.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 23 of 66
Suitable means of protection against damage, abuse, misuse, unauthorised use and deterioration
shall be exercised to the extent necessary to preserve original characteristics and fitness for purpose
throughout pr (( COMPANY )) urement, delivery, storage, incorporation, commissioning and hand-
over.
Preservation Pr (( COMPANY )) edure should follow Client and Vendor requirements and satisfy the
contractual requirement.
NCR’s may be raised by QA/QC for off-site or on-site works, materials, products or components not
complying with the Contract Specifications.
Where work elements, goods, materials, products or components received, are found through
inspection, testing, surveillance or audit, etc. to be nonconforming to specified requirements a Non-
conformance Report (NCR) shall be raised which shall unambiguously:
and subsequently:
record observations made of corrective and preventive actions taken and their acceptability.
Generally for NCR’s affecting compliance with Contract Specifications, acceptance by the Client
Representative will be required for correction, corrective and preventive actions.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 24 of 66
These NCR’s are issued by the Client, Client’s Representative, or other parties to the (( COMPANY ))
Project Manager shall be managed in an identical controlled pr (( COMPANY )) edure to Internal
NCR’s, except as noted below.
On receipt of an external NCR the Project Manager will review and determine its accuracy and
completeness. Where the NCR is disputed or requiring further information, the Project Manager shall
respond in writing within 7days of receipt. Having accepted the NCR the Project Manager will assign a
named Actioner to propose correction, corrective and preventive actions, and complete distribution
to other relevant (( COMPANY )) personnel.
The Project Manager and Quality Manager will review the adequacy of the correction, corrective and
preventive action prior to submission to the originator of the NCR. Following acceptance of the
proposed correction, corrective / preventative actions by the originator, these will be implemented to
achieve a planned closing / close out date, and verified as for Internal NCR’s.
To close out the NCR a full package of (( COMPANY )) Document ation and records showing actions
taken, approvals and verification will be submitted by the Project Manager or Quality Manager to the
originator.
review all NCR’s for legitimacy, acceptability of proposed corrective actions and preventive
actions and those actions actually taken;
undertake trend analysis of NCR’s on a monthly basis to highlight incidence rates per section of
the Works and the effectiveness of corrective and preventive actions undertaken.
Note: Refer to QMP-005 Rev. 02: Control of Non-Conforming Products pr (( COMPANY )) edure;
Refer to QMP-006 Rev. 02: Corrective and Preventive Action pr (( COMPANY )) edure
The monitoring and measurement to be applied to the Works has necessarily been detailed
separately in the Project Inspection Plan (PIP) or the Inspection and Testing Plan (ITP).
The inspection and testing to be implemented for the Works is stated in the Contract Specifications
and managed by (( COMPANY )) in Project Inspection Plans (PIP’s / ITP’s), check sheets, Pr
(( COMPANY )) edures and Method Statements.
Each PIP/ITP has sub-headings of submissions, alternatives, trials and works, each one detailing:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 25 of 66
Attached to the PIP’s / IPT’s will be relevant check sheets to record the results of inspections and
tests.
PIP’s / ITP’s will be managed by the Quality Manager using a PIP Schedule to determine the number
of PIP’s ITP’s for each discipline (e.g. Civil, MEP, Architectural, etc.) in accordance with the Contract
Specifications and (( COMPANY )) requirements; the works are on-site or off-site; planned
submission dates; and the Responsible Persons for each PIP / ITP.
All PIP’s / ITP’s will be drafted on an (( COMPANY )) -approved standard form and reviewed by the
Quality Manager prior to Client Representative submission. It is the Responsible Person who is
required to submit the PIP ITP on time, and action comments returned on the PIP, appropriate with
(( COMPANY )) Programme.
All inspection and testing by (( COMPANY )) 3 rd Parties shall be performed by competent and
authorised persons in compliance with Contract Specifications and (( COMPANY )) requirements
(e.g. PIP’s / ITP’s).
Inspection Stages
(( COMPANY )) will manage and implement the following inspection stages as required by the
Contract Specifications, (( COMPANY )) Pr (( COMPANY )) edures, Method Statements, PIP’s / ITP’s,
etc., which are summarised as:
Site Material Receiving Inspections: preventive action to stop nonconforming materials being
incorporated in the Works, and verification of conformity to the Contract Specifications.
Site In-Pr (( COMPANY )) ess Inspection: verifying at planned, key intervals that materials and
workmanship comply with Contract Specifications.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 26 of 66
Site Final Inspection: verification that all preceding materials and workmanship comply with the
Contract Specifications prior to follow-on works, releases or handovers.
If at any stage for inspection works are unacceptable it shall be notified to the party submitting it, for
repair or rework prior to re-inspection.
Notice periods for inspections shall be in accordance with the Contract and be a working, practical
agreement with Client’s Representative. Off-site inspections shall have a minimum three day notice
period (except as noted in the Contract); and site inspections should be notified the day prior to
inspection being required.
Store Inspection
The importance of materials management both in Stores and (after release) on-site requires that
monthly the Quality Manager will arrange a Stores Inspection and maintain records.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 27 of 66
A list of tests required verifying that control measures are adequate to provide a product, which
conforms to Contract Specifications. It includes the test name, specification paragraph, features of
work to be tested and test frequency.
Each QC representative will issue the required and specified tests to be carried on by the approved
Testing Agency / Laboratory / Third Party. The appropriate manufacturer or supplier will follow all
their necessary tests and as required by the contract.
Retest only if there is some reasons to doubt the validity of the first test;
Rework failing material, retest to confirm rework is successful;
Remove failing material
Punch lists
Punch lists issued for a works scope by Client / Client’s Representative following a joint inspection or
“Walk Down” with (( COMPANY )) will be received in accordance with (( COMPANY )) Document
Control Pr (( COMPANY )) edure. The Project / Site Manager and Quality Manager will review each
Punch list and:
All inspection, measuring and test (IMT) equipment used to establish the Works (surveying
equipment) or measure and test the quality of the Works (gauges, laboratory equipment and the like)
shall be registered and maintained in a Master Calibration Schedule (MCS) by the Quality Manager.
The MCS will be maintained and record as a minimum for each IMT item: Serial Number;
Manufacturer Name; Description and Model Number; Date of last calibration; Calibration frequency;
Date of next calibration; Date received onsite and condition (e.g. new, used, damaged); Authorised
Party to perform the calibration; and Date entered / removed from service (as required).
All IMT calibration will be performed by competent, authorised parties in accordance with National or
International Metrology Standards, and at frequencies specified by those Standards or at frequencies
specified by the Manufacturer or (( COMPANY )) Pr (( COMPANY )) edures, to assure continuous
valid IMT Calibration, accuracy and precision.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 28 of 66
All IMT periodic (daily, weekly, monthly, etc.) verification will be performed by competent, authorised
parties in accordance with Manufacturer Recommendations at frequencies specified by the
Manufacturer or (( COMPANY )) Pr (( COMPANY )) edures, to assure continuous IMT accuracy and
precision. Similarly to the MCS, a Master Verification Schedule (MVS) shall be maintained by the
Quality Manager with necessary input from defined Responsible Persons for their IMT.
The MVS will be maintained on (( COMPANY )) Standard and record as a minimum for each IMT
item: Serial Number; Description and Model Number; dates of last and current verifications; Verification
frequency; Date of future verification; Authorised Party to perform verifications; Verification
result; and Description of corrections made in accordance with Manufacturer Recommendations (if any).
Maintenance
All periodic maintenance will be performed by competent, authorised parties in accordance with
Manufacturer Recommendations at frequencies specified by the Manufacturer or (( COMPANY )) Pr
(( COMPANY )) edures, to assure continuous IMT accuracy and precision. The Responsible Person for
the IMT will ensure major maintenance is recorded in the MCS or MVS and is traceable and filed in an
organised system. Major maintenance is generally defined as including: that performed by a
Manufacturer or 3rd Party; involves permanent replacement or changes to hardware and software;
and is costed. Minor maintenance includes normal tasks such as cleaning, lubrication, small
adjustments, etc.
3rd Part Organisations and Subcontractors are required to manage their IMT in accordance with
International Standards such as ISO 9001 or ISO 17025, and implement National or International
Metrology Standards and Manufacturer Recommendations, for calibration, maintenance and periodic
verification. (( COMPANY )) shall be permitted to request necessary and relevant (( COMPANY ))
Document ation and records from 3rd Party Organisations and Subcontractors to verify calibration,
maintenance and periodic verification requirements are established and maintained.
Nonconformity
Where IMT is damaged, suspected of being inaccurate whilst in use or has subsequently been found
to be out of calibration or periodic verification requirements upon periodic checking it shall be
quarantined until corrected. In all such cases NCR’s shall be raised and its prior use since being in a
known state of calibration or correct functioning will be appraised to determine if there have been
any risks or detrimental effects upon the Works.
Note: Refer to PRO-QUA-02 Rev 01: Monitoring and Measurement Equipment (MME) Control Pr
(( COMPANY )) edure
19.0 Audits
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 29 of 66
The auditing of this project forms part of the Corporate Quality Dept’s Rolling Quality Audit Schedule
covering all current projects. Audits will be conducted on and at intervals of:
Establishment (1 month)
Engineering design (1 month)
Works execution (3 months)
Commissioning (3months)
Hand-over (3 month)
Defects liability period (6 months)
Audits will be conducted by competent and qualified auditors generally in accordance with ISO
19011: Guidelines for Quality and Environmental Management Systems Auditing.
Recommendations: Activities deemed to have been performed not as well as possible and
where improvement is readily achievable and if not undertaken could
result in a future Observation or Corrective Action Request becoming
necessary.
Pr (( COMPANY )) ess Improvements: These Improvements whilst not classified as audit findings,
nevertheless identify issues worthy of action to prevent future possible nonconformities, and
improve performance or implementation of the Quality System
Collective analysis of Corrective Action Requests across all (( COMPANY )) projects will form an
input into the periodic management review of the QMS undertaken by (( COMPANY )) .
All Audit Notifications and Audit Reports will be issued to relevant (( COMPANY )) Directors, Project
Manager and Quality Manger for distribution and action.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 30 of 66
20.0 Servicing
(( COMPANY )) will establish and implement arrangements to ensure suitable and sufficient
completion of Contract Requirements for necessary servicing and maintenance during the twenty four
months (as specified) warranty period. These arrangements may include but not limited to:
(( COMPANY )) or Subcontractor / Supplier service and maintenance agreements; standard or special
warranties; nominated and competent servicing and maintenance personnel from (( COMPANY ))
and/or Subcontractors / Suppliers; stores on-site or off-site for consumables and spare parts, etc.
Client (or equivalent Party or additional Parties) Training will be provided by (( COMPANY )) or
Subcontractors / Suppliers as specified in the Project Contract Conditions / Specifications, or as
instructed by the Client’s Representative. All Training provided by (( COMPANY )) / Subcontractors /
Suppliers will be (( COMPANY )) Document ed and recorded, and delivered professionally by
competent persons, in accordance with (( COMPANY )) or Subcontractors / Suppliers’ Pr
(( COMPANY )) edures.
International Standard and Industry-Standard recognised statistical techniques such as control charts
will be employed in accordance with (( COMPANY )) Pr (( COMPANY )) edures to verify specific
materials or works conformity as required in the Contract Specifications.
The Quality Manager may elect to employ additional statistical techniques as considered necessary to
control or verify conformity of works or materials to the Contract Specifications.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 31 of 66
Ambiguities or conflicts in requirements identified at any stage in Contract Review will be resolved by
an (( COMPANY )) nominated Senior Manager in accordance with the Contract using
(( COMPANY )) Pr (( COMPANY )) edures, such as Tender Queries (or equivalent), Request for
Information (RFI), Design or Field Change Requests, or Letters / Minutes and Meetings.
23.0 Attachments
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 32 of 66
Acronyms:
Abbreviations:
Definitions:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 33 of 66
Method Statement: A (( COMPANY )) Document defining how specific works of a ‘one off’ nature are
to be controlled in terms of:
responsibilities;
interface arrangements;
sequencing;
methodology;
equipment and materials
special considerations;
risk assessments for health & safety and environmental.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 34 of 66
site inspections;
pre-commissioning checks and start-up pr (( COMPANY )) edures;
functional tests and verification pr (( COMPANY )) edures;
diagnostic monitoring;
operation and maintenance manuals;
training of owner’s operation and maintenance personnel;
commissioning report;
warranty period.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 35 of 66
site rules;
safety and environmental monitoring;
subcontractor management;
incident reporting and investigation;
permits to work system;
induction and training requirements;
plant and equipment management;
chemical management
waste management.
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 36 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 37 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 38 of 66
Establish, maintain and monitor the implementation of the Project Design Plan
(PDP)
Establishment, maintenance and monitoring of a design submission programme
Ensure the appropriate assignment of responsibilities to competent designers,
timely design reviews, adequate design verification methodologies and validation
proposals
Ensure due consideration is afforded to statutory and regulatory requirements
and that their selection is reviewed for adequacy and recorded
Ensuring the resolution of incomplete, ambiguous or conflicting requirements via
use of RFI’s, expedite and disseminate responses as required to ensure inform all
concerned
Ensure that permanent works designs allow adequately for temporary loading
conditions to be encountered during construction
Ensure that, at appropriate stages, (( COMPANY )) Document ed reviews of the
evolving design are planned and conducted and that participants represent all
functions concerned with the design stage under review, together with any other
specialists deemed required
Conduct ‘buildability’ reviews with construction personnel as appropriate to
highlight their concerns, if any, with and suggested improvements to evolving
designs and feedback of this information to design team
Ensure pertinent details of the evolving design are disseminated as applicable to
each designer involved
Ensure designs are (( COMPANY )) Document ed fully and expressed in terms
readily able to be verified and validated against design briefs, design output
meets design input requirements, cite acceptance criteria, identify those design
characteristics crucial to its safe and proper functioning
Ensure that, at appropriate stages, (( COMPANY )) Document ed design
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 39 of 66
Materials Approvals:
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 40 of 66
Technical Assistance:
Health & Safety & Principally but not necessarily limited to:
Environmental
Manager: Review of methodologies and risk assessments proposed in Method Statements
to ensure due consideration has been paid to establishing safe methods of work
and mitigation of avoidable risks
Records maintenance
Ensure implementation of the HSE Management System on the project
Ensure that Project HSE Management policy, plans and pr (( COMPANY )) edures
are implemented effectively and are suitable for their purposes and use for
which they are intended
Produce and develop the Project HSE Training Plan and ensure implementation
of the plan and ensure that training records are maintained
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 41 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 42 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 43 of 66
Assist in plan and space analysis in order to provide clear, traceable and
coordinated interpretations of the design/drawings for construction
Act as liaison with subcontractors in expediting drawings and related information
Maintain accurate up-to-date logs (RFI, Vendor/Subcontractor, Purchase, Owner,
etc.), track responses and advise the Project Manager of the status of RFI’s
Coordinate submittals and pr (( COMPANY )) ure all close-out (( COMPANY ))
Document s including warranties and Operating and Maintenance Manuals
Monitor field work, including contract work, to ensure compliance with company
standards, pr (( COMPANY )) edures, specifications and codes
Participate in the continuous updating and accurate generation of as-built
(( COMPANY )) Document s
Coordinate periodic job-related photographs for records
Obtain quotations for Notices of Change
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 44 of 66
Responsible for the Cost Breakdown Structure, Cost Coding Structure, Cost
Accounts and Cost Monitoring System
Responsible for the estimate / work plan, final estimate report and
implementation of project cost control measures
Establish Cost Reporting, estimating pr (( COMPANY )) ess and recording
estimates for the project
Produce Risk Analysis based on the cost and analyze the findings
Develop Subcontract requirements on Cost reporting during update
Provide trend reports
Analyze cost date on monthly basis and report findings
Report Cost Variances / changes and justify impact
Report issues with Cost impact and recommend actions
Provide mitigating solutions on time overruns
Maintain Delays Log and analyze the impact for potential claims
Analyze Risk Exposure on monthly basis on variances and exceptions
Review close out cost reports
Develop and evaluate Claims reports
Perform As-Built analysis on completed schedule
Ensure control points (survey stations) are established site-wide checks on the
structures
Overall control of earthworks setting out and site-wide setting out
Ensure information to set out works is provided by Client and Consultant
General surveys for design team when required
General supervision and training of all site engineers
Ensuring instrument checks are carried out regularly and recorded
Control of instruments used on site
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 45 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 46 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 47 of 66
Manage all matters regarding the security of the site in accordance with the
Contract and Safety Plan
Advise the Project Manager and his managers on all matters regarding security
Carry out the roles and responsibilities in the Emergency Plan
Ensuring his staff are vigilant to health and safety concerns whilst undertaking
their ongoing surveillance activities and report any perceived problems to the
Safety Team
Ensuring his staff are vigilant to environmental concerns whilst undertaking their
ongoing surveillance activities and report any perceived to the Environmental
Manager
Ensuring the overall of the site area and its offices, compounds and facilities
Administering the site security pass scheme
Administering parking permits
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 48 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 49 of 66
Assisting the General Foreman in controlling the activities on the project and
executing his responsibilities
Maintaining accurate records of the plant, labour and materials used in the
construction of the works
Ensure that works are constructed to the required quality and specification
Organise the work in accordance with Method Statements and Risk Assessments
so as to establish safe systems of work for all persons
Maintain at all times safe access and egress to work areas taking steps to inform
supervisors and secure any areas found to be exposed and in need of repair
Coordinate operations with others (even if no contractual link exists) who may
be affected by the work under (( COMPANY )) control
Ensuring working methods are as detailed in method statements
Ensuring works are checked in a timely manner and use made of inspection
check sheets denoted in the PIP’s / ITP’s
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 50 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 51 of 66
# Works Subcontractor
1 TBC TBC
2 TBC TBC
3 TBC TBC
4 TBC TBC
5 TBC TBC
6 TBC TBC
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 52 of 66
# Reference # Title
1 BMS-01 Site Establishment
2 BMS-02 Ground Investigation
3 BMS-03 Surveying
4 BMS-04 Dewatering
5 BMS-05 Earthworks
6 BMS-06 Tower Cranes & Hoists
7 BMS-07 Underground Services Installation
8 BMS-08 General Concrete Production
9 BMS-09 General In Situ Concrete
10 BMS-10 General Pre-cast Concrete
11 BMS-11 Waterproofing Systems Application
12 BMS-12 Joint Sealants Application
13 BMS-13 Structural Steelwork Fabrication
14 BMS-14 Structural Steelwork Erection
15 BMS-15 Heavy Equipment Installation
16 BMS-16 Electrical Installation
17 BMS-17 Mechanical Installation
18 BMS-18 Doors, Windows & Louvers
19 BMS-19 Masonry
20 BMS-20 Plastering
21 BMS-21 Roofing
22 BMS-22 Metal Cladding
23 BMS-23 Screeding
24 BMS-24 Plumbing
25 BMS-25 Dry Walling
26 BMS-26 Suspended Ceilings
27 BMS-27 Raised Floors
28 BMS-28 Tiling & Marble Work
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 53 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 54 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 55 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 56 of 66
# Reference # Title
1 FM-QUA-00-001 REV. 00 General Inspection Form (Civil)
2 FM-QUA-00-008 REV. 00 Daily Inspection Request
3 FM-QUA-00-009 REV. 00 Request for Inspection
4 FM-QUA-00-010 REV. 00 Letter of Transmittal
5 FM-QUA-00-011 REV. 00 (( COMPANY )) Document Distribution Request Form
6 FM-QUA-00-013 REV. 00 Project Distribution Matrix
7 FM-QUA-00-016 REV. 00 QC (( COMPANY )) Document ation Package
8 FM-QUA-00-018 REV. 00 Material Approval Request
9 FM-QUA-00-019 REV. 00 Application for New Work Start
10 FM-QUA-00-020 REV. 00 Technical Query
11 FM-QUA-00-022 REV. 00 Major Purchase Order Record
12 FM-QUA-00-024 REV. 00 Material Receiving Report
13 FM-QUA-00-026 REV. 00 Requisition Form
14 FM-QUA-00-027 REV. 00 St (( COMPANY )) k Record Card
15 FM-QUA-00-028 REV. 00 IM & TE Register
16 FM-QUA-00-031 REV. 00 Project QMS Audit Schedule
17 FM-QUA-00-032 REV. 01 Quality Audit Status Log
18 FM-QUA-00-033 REV. 01 Quality Audit Checklist
19 FM-QUA-00-034 REV. 01 Corrective Action Request (CAR)
20 FM-QUA-00-037 REV. 01 Non-Conformance Report
21 FM-QUA-00-038 REV. 01 N CR Report Log
22 FM-QUA-00-041 REV. 00 QA/QC Monthly Report
23 FM-QUA-00-047 REV. 00 Confirmation of Verbal Site Instructions
24 FM-QUA-00-048 REV. 00 Day Work Sheet
25 FM-QUA-00-049 REV. 00 Subcontractor Status Report for XXXX Project
26 FM-QUA-00-050 REV. 00 Material Discrepancy Report (Material/Equipment)
27 FM-QUA-00-051 REV. 00 Preservation and Protection Log Report
28 FM-QUA-00-052 REV. 00 Field Warehouse Requisition (Return)
29 FM-QUA-00-053 REV. 00 Field Additional Material Requisition (Return)
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 57 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 58 of 66
Basins/Other Pits
62 FM-QUA-03-026 REV. 00 Inspection Form for Earthbound Tank Foundation
63 Acceptance Criteria for Questionable Water Supplies for
FM-QUA-03-027 REV. 00
Concrete According to ASTM C94
64 Acceptance Criteria for Water Supplies for Concrete
FM-QUA-03-028 REV. 00
According to ASTM C94
65 Compressive Strength of Test Cubes of Grout Specimens
FM-QUA-03-040 REV. 00
as per ASTM C109
66 Compressive Strength of Test Cubes of Mortar Specimens
FM-QUA-03-041 REV. 00
as per ASTM C109
67 Compressive Strength of Test Cylinders of Concrete
FM-QUA-03-042 REV. 00
Specimens as per ASTM C39
68 Compressive Strength of Test Cylinders of Light Weight
FM-QUA-03-043 REV. 00
Concrete Specimens as per ASTM C39
69 FM-QUA-03-044 REV. 00 Concrete Crushing Schedule of Next Week
70 FM-QUA-03-045 REV. 00 Concrete Pouring Report
71 FM-QUA-03-046 REV. 00 Concrete Cube Compression Test Report
72 FM-QUA-03-047 REV. 00 Concrete Mix Design
73 FM-QUA-03-048 REV. 00 Concrete Mixing Order No. xxxxx
74 FM-QUA-03-049 REV. 00 Concrete Statistical Analysis
75 Fresh Concrete Testing in Laboratory as per BS 1881:Part
FM-QUA-03-052 REV. 00
124 & BS 1881:Part 106
76 FM-QUA-03-059 REV. 00 Setting Time of Concrete
77 FM-QUA-04-001 REV. 00 Alignment Inspection Report (Horizontal Vessel)
78 FM-QUA-04-002 REV. 00 Inspection Record for Internal Refractory Casting
79 Inspection Record for Internal Refractory Gunning
FM-QUA-04-003 REV. 00
Application
80 FM-QUA-04-004 REV. 00 Inspection Record for Internal Refractory Brick Lining
81 FM-QUA-04-005 REV. 00 Inspection Record for Internal Refractory Plastic Lining
82 Absorption of Concrete Masonry Units According to ASTM
FM-QUA-04-006 REV. 00
C140/ASTM C90
83 Compressive Strength of Concrete Masonry Prism
FM-QUA-04-007 REV. 00
According to ASTM E447
84 Compressive Strength of Concrete Masonry Unit
FM-QUA-04-008 REV. 00
According to ASTM C140
85 Moisture Content of Concrete Masonry Units According to
FM-QUA-04-009 REV. 00
ASTM C140
86 FM-QUA-05-001 REV.00 Welding Data Sheet
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 59 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 60 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 61 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 62 of 66
Test)
179 FM-QUA-26-023 REV. 00 MV Switchgear Testing Report (Insulation Test)
180 FM-QUA-26-024 REV. 00 MV Switchgear Energisation Report (Functional Test)
181 FM-QUA-26-025 REV. 00 PV System Testing Report (Continuity Test)
182 FM-QUA-26-026 REV. 00 PV System Testing Report (Insulation Test)
183 FM-QUA-26-027 REV. 00 PV System Testing Report (Performance Test)
184 Lightning Protection System Testing Report (Continuity
FM-QUA-26-028 REV. 00
Test)
185 FM-QUA-26-029 REV. 00 Lightning Protection System Testing Report
186 FM-QUA-26-030 REV. 00 Inspection Form from Duct Banks
187 FM-QUA-27-001 REV. 00 Telephone System Record
188 FM-QUA-27-002 REV. 00 Structured Cabling System Record
189 FM-QUA-27-003 REV. 00 Structured Cabling System Report (Twisted Pair Cables)
190 FM-QUA-27-004 REV. 00 Structured Cabling Testing Report (Optical Fibre Cables)
200 FM-QUA-28-001 REV. 00 Fire Alarm System Record
201 FM-QUA-28-002 REV. 00 Fire Alarm Testing Report (Functional Test)
202 FM-QUA-31-005 REV. 00 In-situ Soil Density Test – Nuclear Method
203 FM-QUA-31-006 REV. 00 Inspection Form for U/G Lines (Civil)
204 FM-QUA-31-007 REV. 00 R (( COMPANY )) k Breaking Excavation Report
205 FM-QUA-31-008 REV. 00 Pile Record Sheet
207 FM-QUA-31-009 REV. 00 Inspection Form for Piling Works
208 FM-QUA-31-010 REV. 00 Method: Temporary Casing
209 FM-QUA-31-011 REV. 00 Grout Pour Card
210 FM-QUA-31-012 REV. 00 California Bearing Ratio as per BS 1377:Part 4 Test Method
211 FM-QUA-31-013 REV. 00 Compaction Test Modified Pr (( COMPANY )) tor Test
212 FM-QUA-31-014 REV. 00 Density of Soil in Place by Sand-Cone Method
213 FM-QUA-31-015 REV. 00 Determination of Atterberg Limits
214 FM-QUA-31-022 REV. 00 Plate Bearing Test
215 FM-QUA-32-001 REV. 00 Inspection Form (Road Works)
216 Application Rate of Bituminous Distributors as per ASTM
FM-QUA-32-002 REV. 00
D2995
217 FM-QUA-32-003 REV. 00 Asphalt Batch Plant Control Report
218 FM-QUA-32-004 REV. 00 Asphalt Compaction Testing as per AASHTO T230
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 63 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 64 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 65 of 66
�
Form: PQP Template
PROJECT QUALITY PLAN
Ref ……………. Rev 00
Project Name: …………………
Date ……………. Page 66 of 66
313 FM-QUA-44-001 REV. 00 Final Setting, Vertical and Final alignment of Frames
314 FM-QUA-45-001 REV. 00 WQT as Run Sheet
�
Form: PQP Template