Monitoring and Controlling Template Finnal
Monitoring and Controlling Template Finnal
PAGE 1
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template
A. Risk Assessment
PAGE 2
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template
compliance
standards.
Key: L=Low, M=Medium, H=High
B. Gantt Chart
PAGE 3
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template
System
$8,800.00
Requirements $9,350.00 $9,200.00 -$550.00 0.942 -$400.00 0.957
Utilities $14,080.00
$8,550.00 $17,600.00 $6,530.00 1.646 $6,480.00 0.8
Code
$4,000.00 $2,500.00
Enforcement
$24,000.00 0.615 $20,000.00 0.167
$6,500.00
Payment
$6,890.00
Processing
$9,500.00 $33,200.00 -$2,610.00 0.726 -$26,310.00 0.208
Total $44,370.00
0.942
$47,250.00 $105,200.00 $8,720.00 -$51,930.00 0.421
System
Requirements $9,750.00 $400.00 20 days 2024-03-29
Code $24,500.00
Enforcement $18,000.00 37 days 2024-05-02
Payment
Processing
$10,000.00 $3,110.00 62 days 2024-06-14
PAGE 4
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template
Schedule Performance: The schedule variance (SV) shows whether the project is ahead or behind
schedule. Negative SV indicates delays, while positive SV indicates ahead-of-schedule progress. In this
case, System Requirements and Payment Processing are significantly behind schedule, while Utilities
and Public Housing are ahead of schedule.
Cost Performance: The cost variance (CV) indicates whether the project is under or over budget.
Negative CV suggests overruns, while positive CV indicates cost savings. Code Enforcement is
significantly over budget, while Utilities and Public Housing are performing well under budget.
Estimates: The estimated completion dates and total costs provide insights into when each
workgroup is expected to finish and how much it will cost. These estimates help in planning and
resource allocation.
Interpretation: The analysis indicates that there are significant schedule delays and cost overruns in
certain workgroups, while others are performing relatively well. It's crucial to address the issues in the
lagging workgroups to ensure overall project success. Adjustments may be needed in resource
allocation and project management strategies to mitigate risks and improve performance.
140
120
100
80
Day
Remaining Tasks
60
Actual Tasks Done
40
20
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35
PAGE 5
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template
Initial Tasks: At the start of the project on Day 1, there were 117 tasks remaining to be completed.
Progress Trend: The burndown chart shows a consistent downward trend, indicating that tasks are
being completed steadily over time.
Completion Rate: Initially, the team completed 3 tasks on Day 1, followed by 5 tasks on Day 2. The
completion rate fluctuates slightly over the course of the project but generally averages around 3
tasks per day.
Efficiency: The team demonstrates efficiency in task execution, as evidenced by the steady decline in
the number of remaining tasks. Despite fluctuations in the completion rate, the overall trend shows
progress towards task completion.
Completion Milestones: The team reaches various completion milestones throughout the project.
By Day 15, the team has completed approximately 50% of the tasks, and by Day 30, they have
completed around 75% of the tasks.
Early Completion: The slope of the burndown chart suggests that tasks are being completed at a
slightly faster rate than anticipated. This early completion may allow the team some buffer time for
addressing any unforeseen challenges or additional tasks that may arise.
Remaining Work: As of Day 36, all tasks have been completed, indicating the successful completion
of the project within the planned duration.
Overall, the burndown chart reflects the team's effective progress in completing tasks and their ability
to maintain momentum throughout the project. This analysis provides valuable insights into the
team's performance and can inform future project planning and execution strategies.
E. Mitigation Plan
In the mitigation plan for the Merrilton Mobile Payment Portal project, implementing three strategies
can positively impact schedule and budget performance:
Strategy: Implement a system for regular progress monitoring and reporting. This involves setting up
weekly or bi-weekly meetings to review project progress, identify any potential delays or budget
overruns, and discuss strategies for mitigation.
Positive Impact: By closely monitoring progress, the project team can quickly identify any issues or
risks that may impact schedule or budget. Early detection allows for timely intervention and
mitigation, minimizing the impact on project timelines and costs. Additionally, regular reporting
ensures transparency and accountability, facilitating effective decision-making and resource
allocation.
Strategy: Develop a comprehensive risk management plan that identifies potential risks and
uncertainties that could affect project schedule and budget. Implement contingency plans to address
high-priority risks and mitigate their impact.
Positive Impact: Proactively addressing risks minimizes their likelihood and impact on the project. By
identifying risks early on and developing contingency plans, the project team can effectively respond
to unforeseen events or issues, reducing the probability of schedule delays or budget overruns.
PAGE 6
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template
Contingency planning ensures that resources are allocated efficiently and that the project remains on
track even in the face of challenges.
Strategy: Establish clear lines of communication with stakeholders, including the project sponsor,
team members, vendors, and end-users. Provide regular updates on project progress, milestones
achieved, and any changes to the schedule or budget.
Positive Impact: Engaging stakeholders throughout the project lifecycle fosters collaboration and
alignment of expectations. Effective communication ensures that stakeholders are informed of project
developments and potential impacts on schedule and budget. By actively involving stakeholders, the
project team can gain valuable insights, address concerns promptly, and secure necessary support
and resources to keep the project on track.
Implementing these mitigation strategies will enhance the project team's ability to manage schedule
and budget performance effectively, mitigate risks, and ensure successful project delivery.
PAGE 7