PH Ar 2013
PH Ar 2013
Confidential
Government of Odisha
HOUSING AND URBAN DEVELOPMENT DEPARTMENT
P.H. ENGINEERING
ANALYSIS OF RATES
2013
The following drafts have been prepared during the process of revision.
a) The Public Health Engineering Schedule of Rates, 2013
b) The Public Health Engineering Analysis of Rates, 2013
GUIDING PRINCIPLES
GUIDING PRINCIPLES
(b) The rates of materials (CI pipes, GI pipes, PVC pipes, Concrete
pipes & water tanks etc) are based on the prevailing rates
concluded by DGS&D/EP&M as the case may be (for PH materials
borne under DGS&D/EP&M rate contract). The DGS&D/EP&M rates
are subject to variation from time to time depending on the price
variation clause of the terms and conditions of DGS&D/EP&M rate
contract.
(c) In case of store items for which both DGS&D and EP&M rate
contracts exist, the rates concluded by Directorate of Export
Promotion & Marketing (EP&M) will prevail as per Industrial policy of
Government of Odisha and accordingly the EP&M rate have been
considered.
(d) The items not covered either under DGS&D or EP&M rate contracts,
but indicated in the list of 'Rates of materials' appended in this SoR
are based on price list of manufacture’s of medium quality of
material (neither heavy nor light).
e) The DGS&D and EP&M rates indicated in the cost of materials are
basic rates only, over and above which required taxes and duties
like Excise Duty, Central Sales Tax, VAT, conveyance charges etc.,
as applicable are to be considered to arrive at the landing cost.
(f) The rates of materials are indicative only and shall be applicable
exclusively for estimation purposes. These however should not be
considered for payment.
(g) The lump sum provision of rates against certain items indicated in
the Schedule of Rates is inclusive of cost of material, labour,
conveyance, taxes and duties etc.
NOTES
1. 10% (Ten per cent) extra over & above the labour charges of
schedule of rates admissible for item of works inside jail premises as
per approved PWD SoR, 2006.
2. As per the decision taken in the review taken by Hon’ble Minister,
Finance, Odisha and basing on the instruction communicated in R.D.
Department Lr. No. 414 dated 01.02.2012, the Analysis of Rates,
pertaining to drilling of H.P Tube Wells and large dia Tube Wells
(production wells) by various drilling methods, has been prepared by
the technical committee of RWS&S considering the current labour
rate & cost of P.O.L.
2.1.1 Laying in trenches Centrifugally Cast (spun) Iron S/S Pressure pipes Class-LA, A & B
conforming to IS:1536 - 2001 of the following nominal diameter as per specification complete.
(Earthwork in trenches, jointing of pipes, specials and fittings to be measured separately)
80mm dia
a. Materials
80mm dia CI pipe Class-LA 1.00 Mtr 664.49 664.49
b. Labour for laying
Taking an average of 10m of 200mm dia CI pipe Class-A
Weight of (2 pieces of 5m length pipe)=2 x 257 kg=514 kg
Plumber Fitter(S) 0.17 Each 190.00 32.30
Helper to plumber or fitter 0.17 Each 170.00 28.90
Male worker 1.33 Each 150.00 199.50
260.70
Rate per 100 kg or 1 Qntl is 260.70 ÷ 5.14 = 50.72
For 1m of 80mm dia CI pipe (Weight of CI pipes for 1.00metre
=[0.59Q/3.66m]=0.161Q) 0.161 Qntl 50.72 8.17
(a+b) 672.66
c. Add Contractor's Profit & Overhead charges 15% of 672.66 100.90
Total (a+b+c) Rate per each Mtr 773.56
say 773.60
N.B.: For 100mm to 1000mm dia please refer Annexure-1
2.1.2 Laying in trenches Centrifugally Cast (spun) Iron flanged pipes Class-A & B conforming to
IS:1536 - 2001 with screwed flanges of the following nominal diameter as per specification
complete. (Earthwork in trenches, jointing of pipes, specials and fittings to be measured and paid
for separately)
80mm dia
a. Materials
80mm dia CI pipe 1.00 Mtr 837.83 837.83
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia CI pipe (Weight of CI pipes for 1.00metre)
Weight of CI pipes for 10metres=[(2 x 4.30 x 10)/2] + (10 x 16)=43 + 160 =
203 kg or 2.03Q 0.203 Qntl 50.72 10.30
(a+b) 848.13
c. Add Contractor's Profit & Overhead charges 15% of 848.13 127.22
Total (a+b+c) Rate per each Mtr Total 975.35
say 975.30
N.B.: For 100mm to 1000mm dia please refer Annexure-2
2.1.3 Laying in trenches Vertically Cast Iron Socket and Spigot pipes Class-A & B conforming to
IS:1537 - 1976 of the following nominal diameter as per specification complete.(Earthwork in
trenches, jointing of pipes, specials and fittings to be measured and paid for separately)
80mm dia
a. Materials
80mm dia CI pipe 1.00 Mtr 721.70 721.70
1
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia CI pipe (Weight of CI pipes for 1.00metre)
Weight of CI pipes for 10metres=[0.64Q/3.66m]x10=1.75Q
0.175 Qntl 50.72 8.88
(a+b) 730.58
c. Add Contractor's Profit & Overhead charges 15% of 730.58 109.59
Total (a+b+c) Rate per each Mtr Total 840.17
say 840.20
N.B.: For 100mm to 1000mm dia please refer Annexure-3
2.1.4 Laying in trenches Vertically Cast Iron flanged pipes of Class- A & B conforming to IS:1537 -
1976 of the following nominal diameter as per specification complete. (Earthwork in trenches,
jointing of pipes, specials and fittings to be measured and paid for separately)
80mm dia
a. Materials
80mm dia CI pipe 1.00 Mtr 813.07 813.07
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia CI pipe (Weight of CI pipes for 1.00metre)
Weight of CI pipes for 10metres=(16+3.70)x10=197 kg or 1.97 Qntl
0.197 Qntl 50.72 9.99
(a+b) 823.06
c. Add Contractor's Profit & Overhead charges 15% of 823.06 123.46
Total (a+b+c) Rate per each Mtr Total 946.52
say 946.50
N.B.: For 100mm to 1000mm dia please refer Annexure-4
2.1.5 Laying in trenches horizontal Cast Iron Double flanged pipes of Class-B conforming to
IS:7181 - 1986 of the following nominal diameter as per specification complete. (Earthwork in
trenches, jointing of pipes, specials and fittings to be measured and paid for separately)
[i] 80mm dia
a. Materials
80mm dia CI pipe 1.00 Mtr 928.63 928.63
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia CI pipe (Weight of CI pipes for 1.00metre)
Weight of CI pipes for 10metres=(3.70 x 2/2.75) x 10 + (19.80 x 10) =
198 + 27.00 = 225 kg or 2.25 Qntl 0.225 Qntl 50.72 11.41
(a+b) 940.04
c. Add Contractor's Profit & Overhead charges 15% of 940.042 141.01
Total (a+b+c) Rate per each Mtr Total 1081.05
say 1081.00
N.B.: For 100mm to 1000mm dia please refer Annexure-5
2.1.6 Laying in trenches Centrifugally Cast (Spun) Iron low pressure (LP) pipes conforming to
IS:6163 - 1978 of the following nominal diameter as per specification complete. (Earthwork in
trenches, jointing of pipes, specials and fittings to be measured and paid for separately)
80mm dia
a. Materials
80mm dia CI pipe 1.00 Mtr 495.27 495.27
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia CI pipe (Weight of CI pipes for 1.00metre)
2
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Weight of CI pipes for 10metres=[0.44Q/3.66m]x10=1.20 Qntls
0.12 Qntl 50.72 6.09
(a+b) 501.36
c. Add Contractor's Profit & Overhead charges 15% of 501.36 75.20
Total (a+b+c) Rate per each Mtr Total 576.56
say 576.60
N.B.: For 100mm to 1000mm dia please refer Annexure-6
2.1.7 Laying in trenches Centrifugally Cast (Spun) Ductile Iron pressure, socket and spigot
pipes Class K9 & K7 without cement mortar lining conforming to IS:8329 - 2000 of the
following nominal diameter as per specification complete. (Earthwork in trenches, jointing of pipes,
specials and fittings to be measured and paid for separately)
80mm dia
a. Materials
80mm dia DI K-7 pipe 1.00 Mtr 638.5 638.50
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia DI K-7 pipe (Weight of DI pipes for 1.00metre)
Weight of DI pipes for 10metres=(52x10)/4.0=130 kg=1.30 qntl
0.13 Qntl 50.72 6.59
(a+b) 645.09
c. Add Contractor's Profit & Overhead charges 15% of 645.09 96.76
Total (a+b+c) Rate per each Mtr Total 741.85
say 741.90
N.B.: For 100mm to 1000mm dia please refer Annexure-7
2.1.8 Laying in trenches Centrifugally Cast (Spun) Ductile Iron Pressure Flanged pipes Class-
K9 & K7 with screwed or welded flanges conforming to IS:8329 - 2000 of the following
nominal diameter as per specification complete. (Earthwork in trenches, jointing of pipes, specials
and fittings to be measured and paid for separately)
80mm dia
a. Materials
80mm dia DI K-9 pipe 1.00 Mtr 687.62 687.62
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 80mm dia DI K-9 pipe (Weight of DI pipes for 1.00metre
Weight of DI pipes for 1metre=12.20+(3.00x2)/4=13.70 kg=0.14 qntl
0.14 Qntl 50.72 7.10
(a+b) 694.72
c. Add Contractor's Profit & Overhead charges 15% of 694.72 104.21
Total (a+b+c) Rate per each Mtr Total 798.93
say 798.90
N.B.: For 100mm to 1000mm dia please refer Annexure-8
2.1.9 Laying in trenches double socket Cast Iron Bends conforming to IS:1538 - 1993 (Part-x) of the
following nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes,
specials and fittings to be measured and paid separately)
Details of cost of 1 quintal of socket and spigot specials such as Bends, Tees,
Crosses, Tappers, Caps etc
a. Materials
80mm dia Cast Iron Bend 0.18 Qntl 4127.24 742.90
b. Labour for laying Tees
For average take details for 10 numbers Tees of 200mm x 150mm size Weight of
Tees = 74 kg x 10 = 740 kgs or 7.40 quintals
Plumber (Fitter) 2nd class 0.93 Each 190.00 176.70
3
Sl No Description Quantity Unit
Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Helper to plumber or fitter 0.62 Each
170.00 105.40
Male worker (unskilled) 2.48 Each
150.00 372.00
654.10
Rate per each quintal is 654.10 ÷ 7.40 = 88.39
For 1 No. 80mm dia Cast Iron Bend 0.18 Qntl 88.39 15.91
(a+b) 758.81
c. Add Contractor's Profit & Overhead charges 15% 758.81 113.82
Total (a+b+c) Rate per each Total 872.63
say 872.60
N.B.: o o o o
For 100mm to 1000mm dia and 90 , 45 , 22.50 & 11.25 bend please refer Annexure-9
2.1.10 Laying in trenches all socket Cast Iron Tees conforming to IS:1538 - 1993 (part-XI) of the
following nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes,
specials and fittings to be measured and paid for separately)
a. Materials
80mm dia Cast IronTee 0.23 Qntl 4127.24 949.27
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No. 80mm dia Cast Iron Tee 0.23 Qntl 88.39 20.33
(a+b) 969.60
c. Add Contractor's Profit & Overhead charges 15% 969.60 145.44
Total (a+b+c) Rate per each Total 1115.04
say 1115.00
N.B.: For higher size Tees please refer Annexure-10
2.1.11 Laying in trenches Cast Iron Plugs conforming to IS:1538 - 1993 (part-XVI) of the following
nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes, specials
and fittings to be measured and paid for separately)
a. Materials
80mm dia Cast Iron Plug
0.03 Qntl 4127.24 123.82
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No. 80mm dia Cast Iron Plug 0.03 Qntl 88.39 2.65
(a+b) 126.47
c. Add Contractor's Profit & Overhead charges 15% 126.47 18.97
Total (a+b+c) Rate per each Total 145.44
say 145.40
N.B.: For higher size Plugs please refer Annexure-11
2.1.12 Laying in trenches Double Flanged Bends conforming to IS:1538 - 1993 (Part-XVIII) of the
following nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes,
specials and fittings to be measured and paid for separately)
Labour for laying of Double Flanged Bends same as per Double Socket Cast Iron Bends
a. Materials
80mm dia Cast Iron Double Flanged Bend 0.13 Qntl 4127.24 536.54
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No. 80mm dia Cast Iron Double Flanged Bend
0.13 Qntl 88.39 11.49
(a+b) 548.03
c. Add Contractor's Profit & Overhead charges 15% 548.03 82.20
Total (a+b+c) Rate per each Total 630.23
say 630.20
N.B.: For higher size of double flange bends please refer Annexure-12
4
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.1.13 Laying in trenches Double Flanged Duckfoot Bend conforming to IS:1538 - 1993 (part-XVIII) of
the following nominal diameter as per specification complete. (Earth work in trenches, jointing of
pipes, specials and fittings to be measured and paid for separately)
Double Flanged 90° bend
a. Materials
80mm dia Cast Iron Double Flanged Duckfoot Bend
0.21 Qntl 4127.24 866.72
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Double Flanged Duckfoot Bend
0.21 Qntl 88.39 18.56
(a+b) 885.28
c. Add Contractor's Profit & Overhead charges 15% 885.28 132.79
Total (a+b+c) Rate per each Total 1018.07
say 1018.10
N.B.: For higher size of double flange Duckfoot Bends please refer Annexure-13
2.1.14 Laying in trenches all flanged Tees conforming to IS:1538 - 1993 (Part-XIX) of the following
nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes, specials
and fittings to be measured and paid for separately)
80mm dia Cast Iron all flanged Tee
a. Materials
80mm x 80mm dia Cast Iron Tee 0.21 Qntl 4127.24 866.72
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Tee 0.21 Qntl 88.39 18.56
(a+b) 885.28
c. Add Contractor's Profit & Overhead charges 15% 885.28 132.79
Total (a+b+c) Rate per each Total 1018.07
say 1018.10
N.B.: For higher size of Cast Iron Tee please refer Annexure-14
2.1.15 Laying in trenches all Socket Cast Iron Crosses conforming to IS:1538 - 1993 (part-XIII) of the
following nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes,
specials and fittings to be measured and paid for separately)
All Socket Cast Iron Crosses
a. Materials
80mm dia Cast Iron Cross 0.30 Qntl 4127.24 1238.17
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Cross 0.30 Qntl 88.39 26.52
(a+b) 1264.69
c. Add Contractor's Profit & Overhead charges 15% 1264.69 189.70
Total (a+b+c) Rate per each Total 1454.39
say 1454.40
N.B.: For higher size of Cast Iron Cross please refer Annexure-15
2.1.16 Laying in trenches Cast Iron Collars conforming to IS:1538 - 1993 (Part-IX) of the following
nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes, specials
and fittings to be measured and paid for separately)
Cast Iron Collar
a. Materials
80mm dia Cast Iron Collar 0.14 Qntl 4127.24 577.81
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
5
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
For 1 No 80mm dia Cast Iron Collar 0.14 Qntl 88.39 12.37
(a+b) 590.18
c. Add Contractor's Profit & Overhead charges 15% 590.18 88.53
Total (a+b+c) Rate per each Total 678.71
say 678.70
N.B.: For higher size of Collars please refer Annexure-16
2.1.17 Laying in trenches Cast Iron Caps conforming to IS:1538 - 1993 (Part-XV) of the following
nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes, specials
and fittings to be measured and paid for separately)
Cast Iron Caps
a. Materials
80mm dia Cast Iron cap 0.07 Qntl 4127.24 288.91
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Cap 0.07 Qntl 88.39 6.19
(a+b) 295.10
c. Add Contractor's Profit & Overhead charges 15% 295.10 44.27
Total (a+b+c) Rate per each Total 339.37
say 339.40
N.B.: For higher size of Caps please refer Annexure-17
2.1.18 Laying in trenches Cast Iron Flanged Sockets conforming to IS:1538 - 1993 (Part-VII) of the
following nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes,
specials and fittings to be measured and paid for separately)
Cast Iron Flanged Sockets
a. Materials
80mm dia Cast Iron flanged socket 0.13 Qntl 4127.24 536.54
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron flanged socket 0.13 Qntl 88.39 11.49
(a+b) 548.03
c. Add Contractor's Profit & Overhead charges 15% 548.03 82.20
Total (a+b+c) Rate per each Total 630.23
say 630.20
N.B.: For higher size of Flanged Sockets please refer Annexure-18
2.1.19 Laying in trenches Cast Iron Flanged Spigots conforming to IS:1538 - 1993 (Part-VII) of the
following nominal diameter as per specification complete. (Earth work in trenches, jointing of pipes,
specials and fittings to be measured and paid for separately)
Cast Iron Flanged Spigots
a. Materials
80mm dia Cast Iron flanged spigot 0.12 Qntl 4127.24 495.27
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron flanged spigot 0.12 Qntl 88.39 10.61
(a+b) 505.88
c. Add Contractor's Profit & Overhead charges 15% 505.88 75.88
Total (a+b+c) Rate per each Total 581.76
say 581.80
N.B.: For higher size of Flanged Spigots please refer Annexure-19
6
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.1.20 Laying in trenches Cast Iron all Flanged Crosses conforming to IS:1538 - 1993 (Part-XX)-1976
of the following nominal diameter as per specification complete. (Earth work in trenches, jointing of
pipes, specials and fittings to be measured and paid for separately)
Cast Iron all Flanged Crosses
a. Materials
80mm dia Cast Iron all Flanged Cross 0.27 Qntl 4127.24 1114.36
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron all Flanged Cross
0.27 Qntl 88.39 23.87
(a+b) 1138.23
c. Add Contractor's Profit & Overhead charges 15% 1138.23 170.73
Total (a+b+c) Rate per each Total 1308.96
say 1309.00
N.B.: For higher size of all Flanged crosses please refer Annexure-20
2.1.21 Laying in trenches Cast Iron Double Flanged Tapers conforming to IS:1538 - 1993 (Part-XXI)
of the following nominal diameter as per specification complete. (Earth work in trenches, jointing of
pipes, specials and fittings to be measured and paid for separately)
Cast Iron Double Flanged Tapers
a. Materials
100mmx80mm Cast Iron Double Flanged Taper
0.12 Qntl 4127.24 495.27
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Double Flanged Taper
0.12 Qntl 88.39 10.61
(a+b) 505.88
c. Add Contractor's Profit & Overhead charges 15% 505.88 75.88
Total (a+b+c) Rate per each Total 581.76
say 581.80
N.B.: For higher size of double Flanged Tapers please refer Annexure-21
2.1.22 Laying in trenches Cast Iron Double Socket Tee with flanged branch - (for Air Valves and
Hydrant Tees) conforming to IS:1538 - 1993 (Part-XII) of the following nominal diameter as per
specification complete. (Earth work in trenches, jointing of pipes, specials and fittings to be
measured and paid for separately)
a. Materials
80mm dia Cast Iron Double Socket Tee with flanged branch
0.22 Qntl 4127.24 907.99
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Double Socket Tee with flanged branch
0.22 Qntl 88.39 19.45
(a+b) 927.44
c. Add Contractor's Profit & Overhead charges 15% 927.44 139.12
Total (a+b+c) Rate per each Total 1066.56
say 1066.60
N.B.: For higher size of double Socket Tees please refer Annexure-22
2.1.23 Laying in trenches Cast Iron Bell-mouth piece conforming to IS:1538 - 1993 (Part-XVII) of the
following nominal diameter as per specification complete.
a. Materials
80mmx125mm Cast Iron Bell-mouth piece 0.07 Qntl 4127.24 288.91
7
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for laying Tees
Rate per each quintal vide item No.2.1.9 88.39
For 1 No 80mm dia Cast Iron Bell-mouth piece 0.07 Qntl 88.39 6.19
(a+b) 295.10
c. Add Contractor's Profit & Overhead charges 15% 295.10 44.27
Total (a+b+c) Rate per each 339.37
say 339.40
N.B.: For higher size of Bell Mouth Pieces please refer Annexure-23
2.1.24 Making lead caulked joint conforming to IS:3114-1994 with molten lead conforming to IS 782,
to Spun Iron or Cast Iron pipes and fittings of the following nominal diameter including testing of
the joints as per specification all complete.
[i] 80 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=1.80 kg per each joint=18 kg
18.00 Kg 150.00 2700.00
Weight of spun yarn gasket for 10 joints=1.00kg
1.00 Kg 50.00 50.00
Fire wood 0.19 Qntl 385.00 73.15
Kerosene oil 0.38 Litre 30.00 11.40
b. Labour charges for jointing
Plumber Fitter(S) 1 Each 190.00 190.00
Helper to plumber or fitter 1 Each 170.00 170.00
Male worker 2 Each 150.00 300.00
(a+b) 3494.55
c. Add Contractor's Profit & Overhead charges 15% 3494.55 524.18
Total (a+b+c) 4018.73
Rate per each joint is 4,018.73 ÷ 10 = 401.87
say 401.90
[ ii ] 100 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=2.20kg per each joint=22kg
22.00 Kg 150.00 3300.00
Weight of spun yarn gasket for 10 joints=1.80kg
1.80 Kg 50.00 90.00
Fire wood 0.28 Qntl 385.00 107.80
Kerosene oil 0.38 Litre 30.00 11.40
b. Labour charges for jointing
Plumber Fitter(S) 1 Each 190.00 190.00
Helper to plumber or fitter 1 Each 170.00 170.00
Male worker 2 Each 150.00 300.00
(a+b) 4169.20
c. Add Contractor's Profit & Overhead charges 15% 4169.20 625.38
Total (a+b+c) 4794.58
Rate per each joint is 4,794.58 ÷ 10 = 479.46
say 479.50
8
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iii ] 125 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=2.60kg per each joint=26kg
26.00 Kg 150.00 3900.00
Weight of spun yarn gasket for 10 joints=2.00kg
2.00 Kg 50.00 100.00
Fire wood 0.37 Qntl 385.00 142.45
Kerosene oil 0.76 Litre 30.00 22.80
b. Labour charges for jointing
Plumber Fitter(S) 1.50 Each 190.00 285.00
Helper to plumber or fitter 1.50 Each 170.00 255.00
Male worker 3 Each 150.00 450.00
(a+b) 5155.25
c. Add Contractor's Profit & Overhead charges 15% 5155.25 773.29
Total (a+b+c) 5928.54
Rate per each joint is 5,928.54 ÷ 10 = 592.85
say 592.90
[ iv ] 150 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=3.40kg per each joint=34kg
34.00 Kg 150.00 5100.00
Weight of spun yarn gasket for 10 joints=2.30kg
2.30 Kg 50.00 115.00
Fire wood 0.42 Qntl 385.00 161.70
Kerosene oil 0.76 Litre 30.00 22.80
b. Labour charges for jointing
Plumber Fitter(S) 1.50 Each 190.00 285.00
Helper to plumber or fitter 1.50 Each 170.00 255.00
Male worker 3 Each 150.00 450.00
(a+b) 6389.50
c. Add Contractor's Profit & Overhead charges 15% 6389.50 958.43
Total (a+b+c) 7347.93
Rate per each joint is 7,347.93 ÷ 10 = 734.79
say 734.80
9
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ vi ] 250 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=6.10kg per each joint=61kg
61.00 Kg 150.00 9150.00
Weight of spun yarn gasket for 10 joints=3.50kg
3.50 Kg 50.00 175.00
Fire wood 0.65 Qntl 385.00 250.25
Kerosene oil 1.14 Litre 30.00 34.20
b. Labour charges for jointing
Plumber Fitter(S) 2.50 Each 190.00 475.00
Helper to plumber or fitter 2.50 Each 170.00 425.00
Male worker 5 Each 150.00 750.00
(a+b) 11259.45
c. Add Contractor's Profit & Overhead charges 15% 11259.45 1688.92
Total (a+b+c) 12948.37
Rate per each joint is 12,948.37 ÷ 10 = 1294.84
say 1294.80
10
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ix ] 400 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=9.50 kg per each joint=95kg
95.00 Kg 150.00 14250.00
Weight of spun yarn gasket for 10 joints=7.50kg
7.50 Kg 50.00 375.00
Fire wood 1.12 Qntl 385.00 431.20
Kerosene oil 1.70 Litre 30.00 51.00
b. Labour charges for jointing
Plumber Fitter(S) 4 Each 190.00 760.00
Helper to plumber or fitter 4 Each 170.00 680.00
Male worker 8 Each 150.00 1200.00
(a+b) 17747.20
c. Add Contractor's Profit & Overhead charges 15% 17747.20 2662.08
Total (a+b+c) 20409.28
Rate per each joint is 20,409.28 ÷ 10 = 2040.93
say 2040.90
[ xi ] 500 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=15.00 kg per each joint=150kg
150.00 Kg 150.00 22500.00
Weight of spun yarn gasket for 10 joints=10.00kg
10.00 Kg 50.00 500.00
Fire wood 1.31 Qntl 385.00 504.35
Kerosene oil 2.27 Litre 30.00 68.10
b. Labour charges for jointing
Plumber Fitter(S) 4.75 Each 190.00 902.50
Helper to plumber or fitter 4.75 Each 170.00 807.50
Male worker 9.50 Each 150.00 1425.00
(a+b) 26707.45
c. Add Contractor's Profit & Overhead charges 15% 26707.45 4006.12
Total (a+b+c) 30713.57
Rate per each joint is 30,713.57 ÷ 10 = 3071.36
say 3071.40
11
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xii ] 600 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=19.00 kg per each joint=190kg
190.00 Kg 150.00 28500.00
Weight of spun yarn gasket for 10 joints=12.00kg
12.00 Kg 50.00 600.00
Fire wood 1.68 Qntl 385.00 646.80
Kerosene oil 2.84 Litre 30.00 85.20
b. Labour charges for jointing
Plumber Fitter(S) 6.50 Each 190.00 1235.00
Helper to plumber or fitter 6.50 Each 170.00 1105.00
Male worker 13 Each 150.00 1950.00
(a+b) 34122.00
c. Add Contractor's Profit & Overhead charges 15% 34122.00 5118.30
Total (a+b+c) 39240.30
Rate per each joint is 39,240.30 ÷ 10 = 3924.03
say 3924.00
12
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xv ] 800 mm diameter
Details for 10 joints
a. Materials
Weight of lead required for 10 joints=31.50 kg per each joint=315kg
315.00 Kg 150.00 47250.00
Weight of spun yarn gasket for 10 joints=15.30kg
15.30 Kg 50.00 765.00
Fire wood 2.33 Qntl 385.00 897.05
Kerosene oil 3.41 Litre 30.00 102.30
b. Labour charges for jointing
Plumber Fitter(S) 8.50 Each 190.00 1615.00
Helper to plumber or fitter 8.50 Each 170.00 1445.00
Male worker 17.00 Each 150.00 2550.00
(a+b) 54624.35
c. Add Contractor's Profit & Overhead charges 15% 54624.35 8193.65
Total (a+b+c) 62818.00
Rate per each joint is 62,818.00 ÷ 10 = 6281.80
say 6281.80
13
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.1.25 Providing flanged joints conforming to IS:3114-1994 to flanged Cast Iron pipes and fittings of
the following nominal diameters including testing of joints, cost of bolts and nuts and rubber
insertions as per specification complete
[ i ] 80 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) (IS 638 : 1979) 10 nos 0.04 sqm per each
(weight per square metre shall be not less than 112 g/mm thickness.)
10 Each 11.00 110.00
Nuts & bolts 16mm x 60 mm long @ 0.2874 kg per each 40nos 11.50 kg
11.50 Kg 70.00 805.00
b. Labour for jointing
Plumber Fitter(S) 0.15 Each 190.00 28.50
Helper to plumber or fitter 0.15 Each 170.00 25.50
Male worker 0.80 Each 150.00 120.00
(a+b) 1089.00
c. Add Contractor's Profit & Overhead charges 15% 1089.00 163.35
Total (a+b+c) 1252.35
Rate per each joint is 1,252.35 ÷ 10 = 125.24
say 125.20
[ ii ] 100 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.05 sqm per each
10 Each 14.00 140.00
Nuts & bolts 16mm x60 mm long @ 0.2874 kg per each 80nos 23.00 kg
23.00 Kg 70.00 1610.00
b. Labour for jointing
Plumber Fitter(S) 0.25 Each 190.00 47.50
Helper to plumber or fitter 0.25 Each 170.00 42.50
Male worker 1.00 Each 150.00 150.00
(a+b) 1990.00
c. Add Contractor's Profit & Overhead charges 15% 1990.00 298.50
Total (a+b+c) 2288.50
Rate per each joint is 2,288.50 ÷ 10 = 228.85
say 228.90
14
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 150 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.08 sqm per each
10 Each 17.00 170.00
Nuts & bolts 20mm x x65 mm long @ 0.4643 kg per each 80nos 37.14 kg
37.14 Kg 70.00 2599.80
b. Labour for jointing
Plumber Fitter(S) 0.30 Each 190.00 57.00
Helper to plumber or fitter 0.30 Each 170.00 51.00
Male worker 1.10 Each 150.00 165.00
(a+b) 3042.80
c. Add Contractor's Profit & Overhead charges 15% 3042.80 456.42
Total (a+b+c) 3499.22
Rate per each joint is 3,499.22 ÷ 10 = 349.92
say 349.90
[ vi ] 250 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.156 sqm per each
10 Each 32.00 320.00
Nuts & bolts 20mm x75 mm long @ 0.4892 kg per each 120nos 59.00 kg
59.00 Kg 70.00 4130.00
b. Labour for jointing
Plumber Fitter(S) 0.40 Each 190.00 76.00
Helper to plumber or fitter 0.40 Each 170.00 68.00
Male worker 1.30 Each 150.00 195.00
(a+b) 4789.00
c. Add Contractor's Profit & Overhead charges 15% 4789.00 718.35
Total (a+b+c) 5507.35
Rate per each joint is 5,507.35 ÷ 10 = 550.74
say 550.70
[ ix ] 400 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.32 sqm per each
10 Each 67.00 670.00
Nuts & bolts 24mm x 85 mm long @ 0.7348 kg per each 160nos 118.00 kg
118.00 Kg 70.00 8260.00
b. Labour for jointing
Plumber Fitter(S) 0.50 Each 190.00 95.00
Helper to plumber or fitter 0.50 Each 170.00 85.00
Male worker 1.50 Each 150.00 225.00
(a+b) 9335.00
c. Add Contractor's Profit & Overhead charges 15% 9335.00 1400.25
Total (a+b+c) 10735.25
Rate per each joint is 10,735.25 ÷ 10 = 1073.53
say 1073.50
16
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 11601.00 1740.15
Total (a+b+c) 13341.15
Rate per each joint is 13,341.15 ÷ 10 = 1334.12
say 1334.10
[ xi ] 500 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.45 sqm per each
10 Each 106.00 1060.00
Nuts & bolts 24mm x 90 mm long @ 0.7502 kg per each 200nos 150.00 kg
150.00 Kg 70.00 10500.00
b. Labour for jointing
Plumber Fitter(S) 0.65 Each 190.00 123.50
Helper to plumber or fitter 0.65 Each 170.00 110.50
Male worker 1.80 Each 150.00 270.00
(a+b) 12064.00
c. Add Contractor's Profit & Overhead charges 15% 12064.00 1809.60
Total (a+b+c) 13873.60
Rate per each joint is 13,873.60 ÷ 10 = 1387.36
say 1387.40
2.1.26 Providing push-on-joints conforming to IS:3114-1994 to Centrifugally (Spun) Cast Iron Pipes or
Ductile Iron Pipes using Rubber Gaskets Conforming to I.S 5382 of S.B.R quality including testing
of joints as per specification complete .
[ i ] 80mm diameter
Details of cost for 10 joints
a. Materials
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 80 mm dia
10 Each 20.00 200.00
b. Labour charges
Plumber Fitter(S) =5/6 0.833 Each 190 158.33
Helper to plumber or fitter=2/3 0.667 Each 170 113.33
Male worker=5/3 1.667 Each 150 250.00
(a+b) 721.66
c. Add Contractor's Profit & Overhead charges 15% 721.66 108.25
Total (a+b+c) 829.91
Rate per each joint is 829.91 ÷ 10 = 82.99
say 83.00
17
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] 100mm diameter
Details of cost for 10 joints
a. Materials
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 100 mm dia
10 Each 26.00 260.00
b. Labour charges
Plumber Fitter(S) =5/6 0.833 Each 190 158.33
Helper to plumber or fitter=2/3 0.667 Each 170 113.33
Male worker=5/3 1.667 Each 150 250.00
(a+b) 781.66
c. Add Contractor's Profit & Overhead charges 15% 781.66 117.25
Total (a+b+c) 898.91
Rate per each joint is 898.91 ÷ 10 = 89.89
say 89.90
[ iv ] 200mm diameter
Details of cost for 10 joints
a. Materials
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 200 mm dia
10 Each 62.00 620.00
b. Labour charges
Plumber Fitter(S)=4/3 1.33 Each 190.00 253.33
Helper to plumber or fitter=1 1.00 Each 170.00 170.00
Male worker=3 3.00 Each 150.00 450.00
(a+b) 1493.33
c. Add Contractor's Profit & Overhead charges 15% 1493.33 224.00
Total (a+b+c) 1717.33
Rate per each joint is 1,717.33 ÷ 10 = 171.73
say 171.70
18
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 1603.33 240.50
Total (a+b+c) 1843.83
Rate per each joint is 1,843.83 ÷ 10 = 184.38
say 184.40
[ vi ] 300mm diameter
Details of cost for 10 joints
a. Materials
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 300 mm dia
10 Each 103.00 1030.00
b. Labour charges
Plumber Fitter(S)=4/3 1.33 Each 190.00 253.33
Helper to plumber or fitter=1 1.00 Each 170.00 170.00
Male worker=10/3 3.33 Each 150.00 500.00
(a+b) 1953.33
c. Add Contractor's Profit & Overhead charges 15% 1953.33 293.00
Total (a+b+c) 2246.33
Rate per each joint is 2,246.33 ÷ 10 = 224.63
say 224.60
[ ix ] 450mm diameter
Details of cost for 10 joints
a. Materials
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 450 mm dia
10 Each 260.00 2600.00
19
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber Fitter(S)=2 2.00 Each 190.00 380.00
Helper to plumber or fitter=2 2.00 Each 170.00 340.00
Male worker=5 5.00 Each 150.00 750.00
(a+b) 4070.00
c. Add Contractor's Profit & Overhead charges 15% 4070.00 610.50
Total (a+b+c) 4680.50
Rate per each joint is 4,680.50 ÷ 10 = 468.05
say 468.10
[ xi ] 600mm diameter
Details of cost for 10 joints
a. Materials
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 600 mm dia
10 Each 352.00 3520.00
b. Labour charges
Plumber Fitter(S)=8/3 2.67 Each 190.00 506.67
Helper to plumber or fitter=8/3 2.67 Each 170.00 453.33
Male worker=23/3 7.67 Each 150.00 1150.00
(a+b) 5630.00
c. Add Contractor's Profit & Overhead charges 15% 5630.00 844.50
Total (a+b+c) 6474.50
Rate per each joint is 6,474.50 ÷ 10 = 647.45
say 647.50
2.1.27 Providing cement joints conforming to IS:3114-1994 using cement mortar (1 cement : 1 coarse
sand) to Spun Iron or Cast Iron pipes and fittings of the following nominal diameter including
testing of the joints as per specification all complete.
[ i ] 80mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.007 cum 0.007 Cum 46.00 0.32
Cement 0.10 Qntl 714.00 71.40
Spun yarn 0.72 Kg 50.00 36.00
b. Labour charges
Plumber Fitter(S) = (1/4 + 3/4) = 1 no 1.00 Each 190.00 190.00
Helper to plumber or fitter = (1 + 0) = 1 no 1.00 Each 170.00 170.00
Male worker = (1 + 1) = 2 nos 2.00 Each 150.00 300.00
(a+b) 767.72
20
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 767.72 115.16
Total (a+b+c) 882.88
Rate per each joint is 882.88 ÷ 10 = 88.29
say 88.30
[ ii ] 100mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.009 cum 0.009 Cum 46.00 0.41
Cement 0.129 Qntl 714.00 92.11
Spun yarn 1.25 Kg 50.00 62.50
b. Labour charges
Plumber Fitter(S) = (0.60 + 0.50) = 1.10 no 1.10 Each 190.00 209.00
Helper to plumber or fitter = (1.16 + 0) = 1.16 no
1.16 Each 170.00 197.20
Male worker = (1.16 + 1) = 2.16 nos 2.16 Each 150.00 324.00
(a+b) 885.22
c. Add Contractor's Profit & Overhead charges 15% 885.22 132.78
Total (a+b+c) 1018.00
Rate per each joint is 1,018.00 ÷ 10 = 101.80
say 101.80
[ iv ] 150mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.013 cum 0.013 Cum 46.00 0.60
Cement 0.186 Qntl 714.00 132.80
Spun yarn 1.62 Kg 50.00 81.00
b. Labour charges
Plumber Fitter(S) = (0.83 + 1) = 1.83 nos 1.83 Each 190.00 347.70
Helper to plumber or fitter = (1.67 + 0) = 1.67 nos
1.67 Each 170.00 283.90
Male worker = (1.57 + 1.75) = 3.32 nos 3.32 Each 150.00 498.00
(a+b) 1344.00
c. Add Contractor's Profit & Overhead charges 15% 1344.00 201.60
Total (a+b+c) 1545.60
Rate per each joint is 1,545.60 ÷ 10 = 154.56
say 154.60
21
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ v ] 200mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.018 cum 0.018 Cum 46.00 0.83
Cement 0.257 Qntl 714.00 183.50
Spun yarn 1.98 Kg 50.00 99.00
b. Labour charges
Plumber Fitter(S) = (1.66 + 1) = 2.66 nos 2.66 Each 190.00 505.40
Helper to plumber or fitter = (2.33 + 0) = 2.33 nos
2.33 Each 170.00 396.10
Male worker = (2.33 + 2.00) = 4.33 nos 4.33 Each 150.00 649.50
(a+b) 1834.33
c. Add Contractor's Profit & Overhead charges 15% 1834.33 275.15
Total (a+b+c) 2109.48
Rate per each joint is 2,109.48 ÷ 10 = 210.95
say 210.90
[ vi ] 250mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.024 cum 0.024 Cum 46.00 1.10
Cement 0.343 Qntl 714.00 244.90
Spun yarn 2.24 Kg 50.00 112.00
b. Labour charges
Plumber Fitter(S) = (1.50 + 1) = 2.50 nos 2.50 Each 190.00 475.00
Helper to plumber or fitter = (3.00 + 0) = 3.00 nos
3.00 Each 170.00 510.00
Male worker = (3.00 + 2.00) = 5.00 nos 5.00 Each 150.00 750.00
(a+b) 2093.00
c. Add Contractor's Profit & Overhead charges 15% 2093.00 313.95
Total (a+b+c) 2406.95
Rate per each joint is 2,406.95 ÷ 10 = 240.70
say 240.70
[ ix ] 400mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.044 cum 0.044 Cum 46.00 2.02
Cement 0.629 Qntl 714.00 449.11
Spun yarn 5.04 Kg 50.00 252.00
b. Labour charges
Plumber Fitter(S) = (2.83 + 1)= 3.83 nos 3.83 Each 190.00 727.70
Helper to plumber or fitter = (5.67 + 0)= 5.67 nos
5.67 Each 170.00 963.90
Male worker = (5.67 + 2.50)= 8.17 nos 8.17 Each 150.00 1225.50
(a+b) 3620.23
c. Add Contractor's Profit & Overhead charges 15% 3620.23 543.03
Total (a+b+c) 4163.26
Rate per each joint is 4,163.26 ÷ 10 = 416.33
say 416.30
[ xi ] 500mm diameter
Data for making and testing of 10 joints
a. Materials
Sand = 0.062 cum 0.062 Cum 46.00 2.85
Cement 0.887 Qntl 714.00 633.32
Spun yarn 6.91 Kg 50.00 345.50
b. Labour charges
Plumber Fitter(S) = (3.50 + 1.50=5.00 nos) 5.00 Each 190.00 950.00
Helper to plumber or fitter = (7.00 + 0)-7.00 nos
7.00 Each 170.00 1190.00
Male worker = (7.00 + 3.00)=10.00 nos 10.00 Each 150.00 1500.00
(a+b) 4621.67
23
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 4621.67 693.25
Total (a+b+c) 5314.92
Rate per each joint is 5,314.92 ÷ 10 = 531.49
say 531.50
2.1.28 Providing, fixing of CI mechanical joint socket conforming to IS:13382/92 to flanged ends of
Cast Iron Pipes or Ductile Iron Pipes including testing of joints as per specification complete .
[ i ] 100mm dia C.I mechanical joint socket
Details of cost for 10 joints
a. Materials
C.I mechanical joint socket 10 Each 2113.18 21131.80
Rubber insertion 3mm thick x 10 nos(0.05sqm each)
10 Each 14.00 140.00
16mmx60mm long nut and bolt @0.2874kg per each=80nos(23.00kg)
23.00 Kg 70.00 1610.00
b. Labour charges
Weight of MJ socket 1.90 Qntl 88.39 167.94
Providing flanged joints 10.00 Each 24.00 240.00
(a+b) 23289.74
c. Add Contractor's Profit & Overhead charges 15% 23289.74 3493.46
Total (a+b+c) 26783.20
Rate per each joint is 26,783.20 ÷ 10 = 2678.32
say 2678.30
25
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ vi ] 350mm dia C.I mechanical joint socket
Details of cost for 10 joints
a. Materials
C.I mechanical joint socket 10 Each 11941.96 119419.60
Rubber insertion 3mm thick x 10 nos(0.26sqm each)
10 Each 45.00 450.00
20mmx80mm long nut and bolt @0.4978kg per each=160nos(80.00kg)
80.00 Kg 70.00 5600.00
b. Labour charges
Weight of MJ socket 9.50 Qntl 88.39 839.71
Providing flanged joints 10.00 Each 40.50 405.00
(a+b) 126714.31
c. Add Contractor's Profit & Overhead charges 15% 126714.31 19007.15
Total (a+b+c) 145721.46
Rate per each joint is 145,721.46 ÷ 10 = 14572.15
say 14572.10
27
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iii ] 200mm dia C.I mechanical joint collar
Details of cost for 10 joints
a. Materials
C.I mechanical joint collar 10 Each 6032.46 60324.60
b. Labour charges
Weight of MJ collar 5.40 Qntl 88.39 477.31
(a+b) 60801.91
c. Add Contractor's Profit & Overhead charges 15% 60801.91 9120.29
Total (a+b+c) 69922.20
Rate per each joint is 69,922.20 ÷ 10 = 6992.22
say 6992.20
28
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 193657.57 29048.64
Total (a+b+c) 222706.21
Rate per each joint is 222,706.21 ÷ 10 = 22270.62
say 22270.60
29
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.2 MILD STEEL PIPES
2.2.1 Laying in trenches MS pipes of all Classes conforming to IS:3589 - 2001 & IS:3601 - 2006 of the
following outside diameter as per specification complete. (Earthwork in trenches, jointing of pipes,
specials and fittings to be measured separately)
88.9 mm outside dia
a. Materials
88.9 mm OD MS ERW pipe 6.30 mm thick 1.00 Mtr 512.00 512.00
b. Labour for laying
Rate per 100 kg or 1 Qntl vide item No.2.1.1 50.72
For 1m of 88.90mm OD MS ERW pipe 6.30 mm thick
12.80 100kg 50.72 6.49
(a + b) 518.49
c. Add Contractor's Profit & Overhead charges 15% 518.49 77.77
Total (a+b+c) Total 596.26
say 596.30
Outside Thickness Weight in Rate per
Sl No. dia in Amount
in mm kg/Mtr Mtr
mm
1 88.9 2.9 6.15 246.00 286.50
3.2 6.76 270.40 314.90
4.0 8.38 335.20 390.40
5.0 10.30 412.00 479.80
5.4 11.10 444.00 517.10
5.6 11.50 460.00 535.70
6.3 12.80 512.00 596.30
8.0 16.00 640.00 745.30
2 101.6 3.6 8.70 348.00 405.30
4.0 9.63 385.20 448.60
5.0 11.90 476.00 554.30
3 114.3 3.2 8.77 350.80 408.50
3.6 9.83 393.20 457.90
4.5 12.20 488.00 568.30
5.4 14.50 580.00 675.50
6.3 16.80 672.00 782.60
8.0 21.00 840.00 978.20
8.8 22.90 916.00 1066.80
4 127 4.5 13.60 544.00 633.50
5.0 15.00 600.00 698.70
5.4 16.20 648.00 754.60
5 139.7 3.6 12.10 484.00 563.70
4.0 13.40 536.00 624.20
4.5 15.00 600.00 698.70
5.0 16.60 664.00 773.30
5.4 17.90 716.00 833.80
6.3 20.70 828.00 964.30
8.0 26.00 1040.00 1211.20
10.0 32.00 1280.00 1490.70
6 152.4 4.5 16.40 656.00 764.00
5.0 18.20 728.00 847.80
5.4 19.60 784.00 913.00
7 165.1 4.5 17.80 712.00 829.20
5.0 19.70 788.00 917.70
5.4 21.20 848.00 987.60
6.3 24.80 992.00 1155.30
30
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
8 168.3 2.6 10.60 424.00 493.80
3.2 12.00 480.00 559.00
4.0 18.20 728.00 847.80
4.5 18.20 728.00 847.80
6.3 25.20 1008.00 1173.90
7.1 28.20 1128.00 1313.60
8.0 31.60 1264.00 1472.00
9 219.1 2.6 13.90 556.00 647.50
3.6 19.10 764.00 889.70
4.5 23.80 952.00 1108.70
6.3 33.10 1324.00 1541.90
10 273 3.6 23.90 956.00 1113.30
4.0 26.50 1060.00 1234.50
5.0 33.00 1320.00 1537.20
6.3 41.10 1644.00 1914.60
11 323.9 4.0 31.80 1272.00 1481.30
4.5 35.40 1416.00 1649.00
5.6 44.00 1760.00 2049.70
7.1 55.50 2220.00 2585.40
12 355.6 4.0 34.70 1388.00 1616.40
5.0 43.20 1728.00 2012.40
5.6 48.30 1932.00 2250.00
8.0 68.60 2744.00 3195.60
13 406.4 4.0 39.70 1588.00 1849.40
5.0 49.50 1980.00 2305.90
6.3 62.20 2488.00 2897.50
8.8 86.30 3452.00 4020.10
14 457 4.0 44.70 1788.00 2082.30
5.0 55.70 2228.00 2594.70
6.3 70.00 2800.00 3260.80
10.0 110.00 4400.00 5124.20
15 508 5.0 62.00 2480.00 2888.20
5.6 69.40 2776.00 3232.90
6.3 77.90 3116.00 3628.80
11.0 135.00 5400.00 6288.70
16 610 5.8 83.50 3340.00 3889.70
6.3 93.80 3752.00 4369.50
12.5 184.00 7360.00 8571.30
17 711 6.3 109.00 4360.00 5077.60
7.1 123.00 4920.00 5729.70
14.2 244.00 9760.00 11366.30
18 813 7.1 141.00 5781.00 6730.40
8.0 159.00 6519.00 7589.60
18.0 314.00 12874.00 14988.20
19 914 8.0 179.00 7339.00 8544.30
8.8 196.00 8036.00 9355.70
10.0 223.00 9143.00 10644.50
17.5 387.00 15867.00 18472.80
20 1016 8.8 219.00 8979.00 10453.60
10.0 248.00 10168.00 11837.90
20.0 491.00 20131.00 23437.00
21 1067 8.8 230.00 9430.00 10978.70
10.0 251.00 10291.00 11981.10
11.0 286.00 11726.00 13651.70
22 1118 8.8 241.00 9881.00 11503.70
10.0 273.00 11193.00 13031.20
11.0 300.00 12300.00 14320.00
31
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
23 1219 10.0 298.00 12218.00 14224.50
11.0 328.00 13448.00 15656.50
12.5 372.00 15252.00 17756.80
24 1422 12.5 435.00 17835.00 20764.00
14.2 493.00 20213.00 23532.50
25 1626 14.2 564.00 23124.00 26921.60
16.0 635.00 26035.00 30310.60
26 1829 14.2 634.00 25994.00 30262.90
16.0 715.00 29315.00 34129.30
17.5 782.00 32062.00 37327.40
27 2032 16.0 795.00 32595.00 37948.00
17.5 869.00 35629.00 41480.20
20.0 992.00 40672.00 47351.40
28 2235 17.5 957.00 39237.00 45680.70
20.0 1093.00 44813.00 52172.50
22.2 1211.00 49651.00 57805.00
29 2540 20.0 1243.00 50963.00 59332.50
22.2 1379.00 56539.00 65824.20
25.0 1551.00 63591.00 74034.30
2.2.2 Flame cutting and facing of MS plate up to 8mm thick as per specification complete
Data for 1.0m
a. Material:
Oxygen 4.28 kg 5.35 22.90
Acetylene gas 2.14 kg 55.55 118.88
b. Labour:
Fitter (special) 0.10 Each 205.00 20.50
Welder(special) 0.16 Each 205.00 32.80
Helper to gas cutter 0.32 Each 170.00 54.40
Semi skilled mullia 0.48 Each 170.00 81.60
(a + b) 331.08
c. Add Contractor's Profit & Overhead charges 15% 331.08 49.66
Total (a+b+c) Rate per 1.0m. 380.74
say 380.70
2.2.3 Flame cutting and facing of MS plate from 8mm to 10mm thick as per specification complete
Data for 1.0m
a. Material:
Oxygen 6.420 kg 5.35 34.35
Acetylene gas 3.21 kg 55.55 178.32
b. Labour:
Fitter (special) 0.16 Each 205.00 32.80
Welder(special) 0.32 Each 205.00 65.60
Helper to gas cutter 0.32 Each 170.00 54.40
Semi skilled mullia 0.48 Each 170.00 81.60
(a + b) 447.07
c. Add Contractor's Profit & Overhead charges 15% 447.07 67.06
Total (a+b+c) Rate per 1.0m. 514.13
say 514.10
2.2.4 Flame cutting and facing of MS plate from 12mm to 25mm thick as per specification complete
Data for 1.0m
a. Material:
Oxygen 11.413 kg 5.35 61.06
Acetylene gas 5.707 kg 55.55 317.02
32
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour:
Fitter (specials) 0.16 Each 205.00 32.80
Welder(special) 0.40 Each 205.00 82.00
Helper to gas cutter 0.32 Each 170.00 54.40
semi skilled mullia 0.48 Each 170.00 81.60
(a + b) 628.88
c. Add Contractor's Profit & Overhead charges 15% 628.88 94.33
Total (a+b+c) Rate per 1.0m. 723.21
say 723.20
2.2.5 Providing joints by welding with two welding beads/pass, conforming to IS:816-1998
(Single 60° Butt weld) to MS pipes and fittings at site by using welding generator including testing
of joints, as per specification complete
Data for 1.0 m long weld length
a. Machineries
Hire charges for 33 KVA generator set 1.50 Hour 240.00 360.00
1.0 m welding = 80 minutes
Idle = 10 minutes
90 minutes = 1 hr 30 min
Welding transformer 1.50 Hour 81.00 121.50
b. Materials
Electrode No-10 (3.15mm dia x 350mm long) for Butt weld of 1.0m long = 26pcs (Details at 'P')
0.325 Pkt @ 80pc per pkt (overchord-s) 0.325 Pkt 420.00 136.50
c. Labour:
1st class welder 0.25 Each 205.00 51.25
Fitter 0.25 Each 205.00 51.25
Semi skilled mullia 0.40 Each 170.00 68.00
(a+b+c) 788.50
d. Add Contractor's Profit & Overhead charges 15% 788.50 118.28
Total (a+b+c+d) Rate per 1.0m. 906.78
say 906.80
2.2.6 Providing joints by welding with two welding beads/pass, conforming to IS:816-1998 (Fillet
weld) to MS pipes and fittings at site by using welding generator including testing of joints, as per
specification complete
Data for 1.0 m long weld length
a. Machineries
Hire charges for 33 KVA generator set 1.50 Hour 240.00 360.00
1.0 m welding = 80 minutes
Idle = 10 minutes
90 minutes = 1 hr 30 min
Welding transformer 1.50 Hour 81.00 121.50
b. Materials
Electrode No-10 (3.15mm dia x 350mm long)
for Fillet weld of 1.0m long = 48pcs (Details at
'Q')
0.6 Pkt @ 80pc per pkt (overchord-s) 0.60 Pkt 420.00 252.00
c. Labour:
1st class welder 0.25 Each 205.00 51.25
Fitter 0.25 Each 205.00 51.25
Semi skilled mullia 0.40 Each 170.00 68.00
(a+b+c) 904.00
d. Add Contractor's Profit & Overhead charges 15% 904.00 135.60
Total (a+b+c+d) Rate per 1.0m. 1039.60
say 1039.60
33
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.2.7 Providing joints by welding with two welding beads/pass, conforming to IS:816-1998
(Single 60° Butt weld) to MS pipes and fittings at Workshop by using welding generator including
testing of joints, as per specification complete
Data for 1.0m
a. Energy Charges (Details at 'R') 518.92
b. Materials
Electrode No-10 (3.15mm dia x 350mm long)
for Butt weld of 1.0m long = 26pcs (Details at
'P')
0.325 Pkt @ 80pc per pkt (overchord-s) 0.325 Pkt 420.00 136.50
c. Labour:
1st class welder 0.20 Each 205.00 41.00
Fitter 0.20 Each 205.00 41.00
Semi skilled mullia 0.30 Each 170.00 51.00
(a+b+c) 788.42
Add Contractor's Profit & Overhead charges 15% 788.42 118.26
Total (a+b+c+d) Rate per 1.0m. 906.68
say 906.70
2.2.8 Providing joints by welding with two welding beads/pass, conforming to IS:816-1998 (Fillet
weld) to MS pipes and fittings at Workshop by using welding generator including testing of joints,
as per specification complete
Data for 1.0m
a. Energy Charges (Details at 'R') 518.92
b. Materials
Electrode No-10 (3.15mm dia x 350mm long)
for Fillet weld of 1.0m long = 48pcs (Details at
'Q')
0.60 Pkt @ 80pc per pkt (overchord-s) 0.60 Pkt 420.00 252.00
c. Labour:
1st class welder 0.20 Each 205.00 41.00
Fitter 0.20 Each 205.00 41.00
Semi skilled mullia 0.30 Each 170.00 51.00
(a+b+c) 903.92
Add Contractor's Profit & Overhead charges 15% 903.92 135.59
Total (a+b+c+d) Rate per 1.0m. 1039.51
say 1039.50
P. For Single 60° butt weld,considering 5/16 inch (7.94mm) thick pipe/plate
Electrode Consumption
Using electrode of size No. 10 x 350 mm long =3.15 mm dia x 350 mm long
Weight of welds/ foot run (for 5/16 inch =7.94mm thick) =(Vide Table-213) 0.255 lb/ft
of 3.15 x 350mm size 0.116 kg/ft
0.381 kg/m
Deposit of weld by 3.15 mm dia x 350 mm long electrode =(Vide Table-212)
17.00 gm/pc
Or 17 gm of weld is deposited from the rod of 1.00 pc
so, 381 gm will be deposited from = 1/17 x381 = 22.41 pc
Take 40 - 50 mm long stub end as wastage on every pc of 350mm long electrode.
So, wastage (taking average 45mm length)= 45/350 12.86 %
Therefore, 22.41 pcs will require(100-12.86=87.14%)
22.41/87.14%= 25.72 pcs
say 26.00 pcs
For 1.0m long single 60° Butt weld 26 pcs
34
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Q. For Fillet weld, having fillet-leg length of 1/2 inch (12mm)
Electrode Consumption
Using electrode of size No. 10 x 350 mm long =3.15 mm dia x 350 mm long
Weight of welds/ foot run for 1/2 inch (12mm)(Vide Table-211) 0.474 lb/ft
of 3.15 x 350mm size 0.215 kg/ft
0.705 kg/m
Deposit of weld by 3.15 mm dia x 350 mm long electrode =(Vide Table-212)
17.00 gm/pc
Or 17 gm of weld is deposited from the rod of 1.00 pc
So, 705 gm will be deposited from = 1/17 x705 = 41.47 pc
Take 40 - 50 mm long stub end as wastage on every pc of 350mm long electrode.
So, wastage (taking average 45mm length)= 45/350 12.86 %
Therefore 41.47 pcs use will require(100-12.86=87.14%)
41.47/87.14%= 47.59 pcs
say 48.00 pcs
For 1.0m long Fillet weld (12mm long fillet-leg) will require electrode of size 3.15mm x 350mm=
48 pcs
35
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.3 UNPLASTICISED PVC PIPES & SPECIALS
2.3.1 Laying in trenches unplasticised PVC pipes conforming to IS:4985-2000 and specials of the
following outside diameter for all classes including jointing with supply of approved solvent cement
by non-heat application method including testing as per specification complete. (Earth work in
trenches to be measured and paid for separately)
[ i ] 75mm dia rigid UPVC pipe Class-3 (0.60 mpa)
Data for 10 metres of unplasticised PVC pipes
a. Materials
75mm dia rigid UPVC pipe Class-3 (0.60 mpa) 10.00 Mtr 87.11 871.10
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker 0.24 Each 150.00 36.00
c. Labour for jointing and testing
Plumber Fitter(S) 0.22 Each 190.00 41.80
Helper to plumber or fitter 0.83 Each 170.00 141.10
Male worker (unskilled) 0.12 Each 150.00 18.00
d. Jointing materials
Cost of solvent cement=30 gms or 0.03kg 0.03 Kg 171.00 5.13
(a+b+c+d) 1135.93
e. Add Contractor's Profit & Overhead charges 15.00% 1135.93 170.39
Total (a+b+c+d+e) 1306.32
Rate per metre is 1,306.32 ÷ 10 = 130.63
say 130.60
36
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
d. Jointing materials
Cost of solvent cement=56 gms or 0.056kg 0.056 Kg 171.00 9.58
(a+b+c+d) 2204.28
e. Add Contractor's Profit & Overhead charges 15% 2204.28 330.64
Total (a+b+c+d+e) 2534.92
Rate per metre is 2,534.92 ÷ 10 = 253.49
say 253.50
37
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
d. Jointing materials
Cost of solvent cement=133 gms or 0.133kg 0.133 Kg 171.00 22.74
(a+b+c+d) 4383.44
e. Add Contractor's Profit & Overhead charges 15% 4383.44 657.52
Total (a+b+c+d+e) 5040.96
Rate per metre is 5,040.96 ÷ 10 = 504.10
say 504.10
38
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
d. Jointing materials
Cost of solvent cement=250 gms or 0.25kg 0.25 Kg 171.00 42.75
(a+b+c+d) 10396.75
e. Add Contractor's Profit & Overhead charges 15% 10396.75 1559.51
Total (a+b+c+d+e) 11956.26
Rate per metre is 11,956.26 ÷ 10 = 1195.63
say 1195.60
2.3.2 Laying in trenches unplasticised PVC pipes IS:4985-2000 and specials of the following outside
diameter for all classes including jointing with supply of approved solvent cement by heat
application method including testing as per specification complete. (Earth work in trenches to be
measured and paid for separately)
[ i ] 75mm dia rigid UPVC pipe Class-3 (0.60 mpa)
Data for 10 metres of unplasticised PVC pipes
a. Materials
75mm dia rigid UPVC pipe Class-3 (0.60 mpa) 10.00 Mtr 87.11 871.10
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker 0.24 Each 150.00 36.00
39
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Labour for jointing and testing
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 1.25 Each 170.00 212.50
Male worker (unskilled) 0.18 Each 150.00 27.00
d. Jointing materials
Cost of solvent cement=30 gms or 0.03kg 0.03 Kg 171.00 5.13
(a+b+c+d) 1237.23
e. Add Contractor's Profit & Overhead charges 15% 1237.23 185.58
Total (a+b+c+d+e) 1422.81
Rate per metre is 1,422.81 ÷ 10 = 142.28
say 142.30
2.3.3[a] Fixing metal or pvc fabricated saddle pieces conforming to IS:10299-1982 using suitable
rubber 'O' rings, bolts and nuts etc to pvc pipes of outside diameter 80mm to 315mm as per
specification complete. (Excluding cost of materials)
80mm to 315mm diameter
Details for 1 piece of rubber'O' ring
a. Labour charges
Plumber/ Fitter(S) 0.25 Each 190.00 47.50
Helper to plumber or fitter 0.50 Each 170.00 85.00
Total 132.50
b. Add Contractor's Profit & Overhead charges 15% 132.50 19.88
Total (a+b) Cost for each 152.38
say 152.40
2.3.3[b] Fixing half-round moulded unplasticised PVC sections in two halves by means of solvent
cement as per specification complete. (Excluding cost of materials)
Rate of fixing is same as per item No 2.3.3 [a] pvc fabricated saddle pieces
Rate per each 152.40
2.3.4 Providing flanged joints (Full-faced Flanges) conforming to IS:3114-1994 for jointing pvc
pipes and other conventional pipes and fittings of the following nominal diameters including testing
of joints, cost of bolts and nuts and rubber insertion as per specification complete.
[ i ] Range 75mm to 90mm
Data for 10 joints
43
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
a. Materials to be used
Rubber insertion 3mm thick x 10 nos (0.04 sqm each)
10 Each 11.00 110.00
16mm x 60mm long nut and bolt @ 0.2874kg per each=40nos (11.50kg)
11.50 Kg 70.00 805.00
b. Labour for jointing
Plumber Fitter(S) 0.15 Each 190.00 28.50
Helper to plumber or fitter 0.15 Each 170.00 25.50
Male worker(unskilled) 0.80 Each 150.00 120.00
(a+b) 1089.00
c. Add Contractor's Profit & Overhead charges 15% 1089.00 163.35
Total (a+b+c) 1252.35
Rate per each joint is 1,252.35 ÷ 10 = 125.24
say 125.20
[ ii ] 100mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3mm thick x 10 nos(0.05sqm each)
10 Each 14.00 140.00
16mmx60mm long nut and bolt @0.2874kg per each=80nos(23.00kg)
23.00 Kg 70.00 1610.00
b. Labour for jointing
Plumber Fitter(S) 0.25 Each 190.00 47.50
Helper to plumber or fitter 0.25 Each 170.00 42.50
Male worker(unskilled) 1.00 Each 150.00 150.00
(a+b) 1990.00
c. Add Contractor's Profit & Overhead charges 15% 1990.00 298.50
Total (a+b+c) 2288.50
Rate per each joint is 2,288.50 ÷ 10 = 228.85
say 228.90
[ iv ] 150 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.08 sqm per each
10 Each 17.00 170.00
Nuts & bolts 20mm xx65 mm long @ 0.4643 kg per each 80nos 37.14 kg
37.14 Kg 70.00 2599.80
44
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for jointing
Plumber Fitter(S) 0.30 Each 190.00 57.00
Helper to plumber or fitter 0.30 Each 170.00 51.00
Male worker 1.10 Each 150.00 165.00
(a+b) 3042.80
c. Add Contractor's Profit & Overhead charges 15% 3042.80 456.42
Total (a+b+c) 3499.22
Rate per each joint is 3,499.22 ÷ 10 = 349.92
say 349.90
[ vi ] 250 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.156 sqm per each
10 Each 32.00 320.00
Nuts & bolts 20mm x75 mm long @ 0.4892 kg per each 120nos 58.70 kg
58.70 Kg 70.00 4109.00
b. Labour for jointing
Plumber Fitter(S) 0.40 Each 190.00 76.00
Helper to plumber or fitter 0.40 Each 170.00 68.00
Male worker 1.30 Each 150.00 195.00
(a+b) 4768.00
c. Add Contractor's Profit & Overhead charges 15% 4768.00 715.20
Total (a+b+c) 5483.20
Rate per each joint is 5,483.20 ÷ 10 = 548.32
say 548.30
45
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Male worker 1.30 Each 150.00 195.00
(a+b) 4848.00
c. Add Contractor's Profit & Overhead charges 15% 4848.00 727.20
Total (a+b+c) 5575.20
Rate per each joint is 5,575.20 ÷ 10 = 557.52
say 557.50
2.3.5 Providing flanged joints (stub flanges) conforming to IS:3114-1994 for jointing pvc pipes and
other fittings of the following nominal diameter including testing of joints, cost of bolts and nuts
and rubber insertion as per specification complete.
[ i ] 75mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3mm thick x 10 nos(0.04 sqm each)
10 Each 11.00 110.00
16mmx60mm long nut and bolt @0.2874kg per each=40nos(11.50kg)
11.50 Kg 70.00 805.00
b. Labour for jointing
Plumber Fitter(S) 0.15 Each 190.00 28.50
Helper to plumber or fitter 0.15 Each 170.00 25.50
Male worker(unskilled) 0.80 Each 150.00 120.00
(a+b) 1089.00
c. Add Contractor's Profit & Overhead charges 15% 1089.00 163.35
Total (a+b+c) 1252.35
Rate per each joint is 1,252.35 ÷ 10 = 125.24
say 125.20
[ ii ] 90mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3mm thick x 10 nos(0.04sqm each)
10 Each 11.00 110.00
16mmx60mm long nut and bolt @0.2874kg per each=40nos(11.50kg)
11.50 Kg 70.00 805.00
b. Labour for jointing
Plumber Fitter(S) 0.15 Each 190.00 28.50
Helper to plumber or fitter 0.15 Each 170.00 25.50
Male worker(unskilled) 0.80 Each 150.00 120.00
(a+b) 1089.00
c. Add Contractor's Profit & Overhead charges 15% 1089.00 163.35
Total (a+b+c) 1252.35
Rate per each joint is 1,252.35 ÷ 10 = 125.24
say 125.20
46
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 1989.30 298.40
Total (a+b+c) 2287.70
Rate per each joint is 2,287.70 ÷ 10 = 228.77
say 228.80
[ iv ] 125 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.06 sqm per each
10 Each 15.00 150.00
Nuts & bolts 16mm x60 mm long @ 0.2953 kg per each 80nos 23.62 kg
23.62 Kg 70.00 1653.40
b. Labour for jointing
Plumber Fitter(S) 0.25 Each 190.00 47.50
Helper to plumber or fitter 0.25 Each 170.00 42.50
Male worker 1.00 Each 150.00 150.00
(a+b) 2043.40
c. Add Contractor's Profit & Overhead charges 15% 2043.40 306.51
Total (a+b+c) 2349.91
Rate per each joint is 2,349.91 ÷ 10 = 234.99
say 235.00
[ vi ] 160 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.08 sqm per each
10 Each 17.00 170.00
Nuts & bolts 20mm x x65 mm long @ 0.4643 kg per each 80nos 37.14 kg
37.14 Kg 70.00 2599.80
b. Labour for jointing
Plumber Fitter(S) 0.30 Each 190.00 57.00
Helper to plumber or fitter 0.30 Each 170.00 51.00
Male worker 1.10 Each 150.00 165.00
(a+b) 3042.80
c. Add Contractor's Profit & Overhead charges 15% 3042.80 456.42
Total (a+b+c) 3499.22
Rate per each joint is 3,499.22 ÷ 10 = 349.92
say 349.90
47
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ vii ] 180 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.08 sqm per each
10 Each 17.00 170.00
Nuts & bolts 20mm x x65 mm long @ 0.4643 kg per each 80nos 37.14 kg
37.14 Kg 70.00 2599.80
b. Labour for jointing
Plumber Fitter(S) 0.30 Each 190.00 57.00
Helper to plumber or fitter 0.30 Each 170.00 51.00
Male worker 1.10 Each 150.00 165.00
(a+b) 3042.80
c. Add Contractor's Profit & Overhead charges 15% 3042.80 456.42
Total (a+b+c) 3499.22
Rate per each joint is 3,499.22 ÷ 10 = 349.92
say 349.90
[ ix ] 225 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.116 sqm per each
10 Each 22.00 220.00
Nuts & bolts 20mm x x70 mm long @ 0.4750 kg per each 80nos 38.00 kg
38.00 Kg 70.00 2660.00
b. Labour for jointing
Plumber Fitter(S) 0.30 Each 190.00 57.00
Helper to plumber or fitter 0.30 Each 170.00 51.00
Male worker 1.10 Each 150.00 165.00
(a+b) 3153.00
c. Add Contractor's Profit & Overhead charges 15% 3153.00 472.95
Total (a+b+c) 3625.95
Rate per each joint is 3,625.95 ÷ 10 = 362.60
say 362.60
[ xi ] 280 mm diameter
Data for 10 joints
a. Materials to be used
Rubber insertion 3 mm thick (IS:638-1979) 10 nos 0.156 sqm per each
10 Each 32.00 320.00
Nuts & bolts 20mm x75 mm long @ 0.4892 kg per each 120nos 58.70 kg
58.70 Kg 70.00 4109.00
b. Labour for jointing
Plumber Fitter(S) 0.40 Each 190.00 76.00
Helper to plumber or fitter 0.40 Each 170.00 68.00
Male worker 1.30 Each 150.00 195.00
(a+b) 4768.00
c. Add Contractor's Profit & Overhead charges 15% 4768.00 715.20
Total (a+b+c) 5483.20
Rate per each joint is 5,483.20 ÷ 10 = 548.32
say 548.30
49
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.4 POLYETHYLENE (PE) PIPES AND SPECIALS
2.4.1 Laying in trenches High Density Polyethylene Pipes conforming to IS 4984 - 1995 and Specials of
following outside diameter and Class-1 to Class-3 and jointing by Fusion welding method including
testing as per specification complete. (Earth work in trenches to be measured and paid for
separately)
[ i ] 75mm dia High Density Polyethylene Pipes PN 6.0
Data for 10 metres of High Density Polyethylene Pipes
a. Materials
75mm dia High Density Polyethylene Pipes PN 6.0
10.00 Mtr 126.97 1269.70
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker (unskilled) 0.24 Each 150.00 36.00
Labour for jointing and testing
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 1.25 Each 170.00 212.50
Male worker (unskilled) 0.18 Each 150.00 27.00
Total 1630.70
c. Add Contractor's Profit & Overhead charges 15% 1630.70 244.61
Total (a+b+c) 1875.31
Rate per metre is 1,875.31 ÷ 10 = 187.53
say 187.50
50
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 3257.30 488.60
Total (a+b+c) 3745.90
Rate per metre is 3,745.90 ÷ 10 = 374.59
say 374.60
52
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ x ] 280mm dia High Density Polyethylene Pipes PN 6.0
Data for 10 metres of High Density Polyethylene Pipes
a. Materials
280mm dia High Density Polyethylene Pipes PN 6.0
10.00 Mtr 1729.71 17297.10
b. Labour for laying
Plumber Fitter(S) 0.45 Each 190.00 85.50
Male worker (unskilled) 0.90 Each 150.00 135.00
Labour for jointing and testing
Plumber Fitter(S) 1.88 Each 190.00 357.20
Helper to plumber or fitter 5.37 Each 170.00 912.90
Male worker (unskilled) 0.72 Each 150.00 108.00
(a+b) 18895.70
c. Add Contractor's Profit & Overhead charges 15% 18895.70 2834.36
Total (a+b+c) 21730.06
Rate per metre is 21,730.06 ÷ 10 = 2173.01
say 2173.00
53
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xiii ] 400mm dia
Data for 10 metres of High Density Polyethylene pipes
a. Materials
400mm dia High Density Polyethylene Pipes PN 6.0
10.00 Mtr 3774.71 37747.10
b. Labour for laying
Plumber Fitter(S) 0.635 Each 190.00 120.65
Male worker (unskilled) 1.27 Each 150.00 190.50
Labour for jointing and testing
Plumber Fitter(S) 2.387 Each 190.00 453.53
Helper to plumber or fitter 7.62 Each 170.00 1295.40
Male worker (unskilled) 0.952 Each 150.00 142.80
(a+b) 39949.98
c. Add Contractor's Profit & Overhead charges 15% 39949.98 5992.50
Total (a+b+c) 45942.48
Rate per metre is 45,942.48 ÷ 10 = 4594.25
say 4594.30
[ xv ] 500mm dia
Data for 10 metres of High Density Polyethylene pipes
a. Materials
500mm dia High Density Polyethylene Pipes PN 6.0
10.00 Mtr 5884.43 58844.30
b. Labour for laying
Plumber Fitter(S) 0.793 Each 190.00 150.67
Male worker (unskilled) 1.587 Each 150.00 238.05
Labour for jointing and testing
Plumber Fitter(S) 2.983 Each 190.00 566.77
Helper to plumber or fitter 9.522 Each 170.00 1618.74
Male worker (unskilled) 1.19 Each 150.00 178.50
(a+b) 61597.03
c. Add Contractor's Profit & Overhead charges 15% 61597.03 9239.55
Total (a+b+c) 70836.58
Rate per metre is 70,836.58 ÷ 10 = 7083.66
say 7083.70
54
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xvi ] 560mm dia
Data for 10 metres of High Density Polyethylene pipes
a. Materials
560mm dia High Density Polyethylene Pipes PN 6.0
10.00 Mtr 7438.67 74386.70
b. Labour for laying
Plumber Fitter(S) 0.883 Each 190.00 167.77
Male worker (unskilled) 1.777 Each 150.00 266.55
Labour for jointing and testing
Plumber Fitter(S) 3.34 Each 190.00 634.60
Helper to plumber or fitter 10.662 Each 170.00 1812.54
Male worker (unskilled) 1.332 Each 150.00 199.80
(a+b) 77467.96
c. Add Contractor's Profit & Overhead charges 15% 77467.96 11620.19
Total (a+b+c) 89088.15
Rate per metre is 89,088.15 ÷ 10 = 8908.82
say 8908.80
2.4.2 Laying in trenches High Density Polyethylene Pipes conforming to IS 4984 - 1995 and specials of
following outside diameter and Class-4 to Class-5 and jointing by Fusion welding method including
testing as per specification complete. (Earth work in trenches to be measured and paid for
separately)
[ i ] 75mm dia High Density Polyethylene Pipes PN 8.0
Data for 10 metres of High Density Polyethylene Pipes
a. Materials
75mm dia High Density Polyethylene Pipes PN 8.0
10.00 Mtr 160.14 1601.40
b. Labour for laying
Plumber Fitter(S) 0.30 Each 190.00 57.00
Male worker 0.60 Each 150.00 90.00
c. Labour for jointing and testing
Plumber Fitter(S) 0.825 Each 190.00 156.75
Helper to plumber or fitter 3.125 Each 170.00 531.25
Male worker 0.45 Each 150.00 67.50
(a+b+c) 2503.90
d. Add Contractor's Profit & Overhead charges 15% 2503.90 375.59
Total (a+b+c+d) 2879.49
Rate per metre is 2,879.49 ÷ 10 = 287.95
say 288.00
55
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
56
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ v ] 140mm dia High Density Polyethylene Pipes PN 8.0
Data for 10 metres of High Density Polyethylene Pipes
a. Materials
140mm dia High Density Polyethylene Pipes PN 8.0
10.00 Mtr 548.43 5484.30
b. Labour for laying
Plumber Fitter(S) 0.55 Each 190.00 104.50
Male worker 1.10 Each 150.00 165.00
c. Labour for jointing and testing
Plumber Fitter(S) 1.65 Each 190.00 313.50
Helper to plumber or fitter 6.00 Each 170.00 1020.00
Male worker 0.825 Each 150.00 123.75
(a+b+c) 7211.05
d. Add Contractor's Profit & Overhead charges 15% 7211.05 1081.66
Total (a+b+c+d) 8292.71
Rate per metre is 8,292.71 ÷ 10 = 829.27
say 829.30
57
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ viii ] 225mm dia High Density Polyethylene Pipes PN 8.0
Data for 10 metres of High Density Polyethylene Pipes
a. Materials
225mm dia High Density Polyethylene Pipes PN 8.0
10.00 Mtr 1362.74 13627.40
b. Labour for laying
Plumber Fitter(S) 0.90 Each 190.00 171.00
Male worker 1.80 Each 150.00 270.00
c. Labour for jointing and testing
Plumber Fitter(S) 2.85 Each 190.00 541.50
Helper to plumber or fitter 10.95 Each 170.00 1861.50
Male worker 1.35 Each 150.00 202.50
(a+b+c) 16673.90
d. Add Contractor's Profit & Overhead charges 15% 16673.90 2501.09
Total (a+b+c+d) 19174.99
Rate per metre is 19,174.99 ÷ 10 = 1917.50
say 1917.50
58
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xi ] 315mm dia High Density Polyethylene Pipes PN 8.0
Data for 10 metres of High Density Polyethylene Pipes
a. Materials
315mm dia High Density Polyethylene Pipes PN 8.0
10.00 Mtr 2801.77 28017.70
b. Labour for laying
Plumber Fitter(S) 1.25 Each 190.00 237.50
Male worker 2.50 Each 150.00 375.00
c. Labour for jointing and testing
Plumber Fitter(S) 4.70 Each 190.00 893.00
Helper to plumber or fitter 15.00 Each 170.00 2550.00
Male worker 1.875 Each 150.00 281.25
(a+b+c) 32354.45
d. Add Contractor's Profit & Overhead charges 15% 32354.45 4853.17
Total (a+b+c+d) 37207.62
Rate per metre is 37,207.62 ÷ 10 = 3720.76
say 3720.80
59
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xiv ] 450 mm dia High Density Polyethylene Pipes PN 8.0
Data for 10 metres of High Density Polyethylene pipes
a. Materials
450mm dia High Density Polyethylene Pipes PN 8.0
10.00 Mtr 6037.49 60374.90
b. Labour for laying
Plumber Fitter(S) 1.785 Each 190.00 339.15
Male worker 3.57 Each 150.00 535.50
c. Labour for jointing and testing
Plumber Fitter(S) 6.71 Each 190.00 1274.90
Helper to plumber or fitter 21.42 Each 170.00 3641.40
Male worker 2.68 Each 150.00 402.00
(a+b+c) 66567.85
d. Add Contractor's Profit & Overhead charges 15% 3641.40 546.21
Total (a+b+c+d) 67114.06
Rate per metre is 67,114.06 ÷ 10 = 6711.41
say 6711.40
60
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xvii ] 630mm dia High Density Polyethylene Pipes PN 8.0
Data for 10 metres of High Density Polyethylene pipes
a. Materials
630mm dia High Density Polyethylene Pipes PN 8.0
10.00 Mtr 11789.93 117899.30
b. Labour for laying
Plumber Fitter(S) 2.50 Each 190.00 475.00
Male worker 5.00 Each 150.00 750.00
c. Labour for jointing and testing
Plumber Fitter(S) 8.35 Each 190.00 1586.50
Helper to plumber or fitter 30.80 Each 170.00 5236.00
Male worker 3.75 Each 150.00 562.50
(a+b+c) 126509.30
d. Add Contractor's Profit & Overhead charges 15% 126509.30 18976.40
Total (a+b+c+d) 145485.70
Rate per metre is 145,485.70 ÷ 10 = 14548.57
say 14548.60
61
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.5 ASBESTOS CEMENT PRESSURE PIPES AND SPECIALS
2.5.1 Laying in trenches Asbestos cement pressure pipes conforming to IS:1592-2003, Class-5,
10 & 15 of the folowing nominal diameter as per specification complete. (Earth work in trenches
and jointing of pipes, specials and fittings to be measured and paid for separately)
80mm dia
Details for 10.00 metre
a. Materials
80mm dia A.C pressure pipes, Class-5 10.00 Mtr 252.00 2520.00
b. Labour required for laying
514 Kg = 5.14 Qtl
Plumber (Fitter) 2nd class 0.17 Each 190.00 32.30
Helper to plumber or fitter (unskilled) 0.17 Each 150.00 25.50
Male worker 1.33 Each 150.00 199.50
257.30
For 100 Kgs = 257.30 ÷ 5.14 = 50.06
Weight of 80mm AC pipe @ 6.225 kg per mtr
For 10 mtrs weight = 62.25 kg
Labour for 10 mtrs @ 50.06 per Qntl 31.16
(a + b) 2551.16
c. Add Contractor's Profit & Overhead charges 15% 2551.16 382.67
Total (a+b+c) 2933.83
Labour per metre is 2,933.83 ÷ 10 = 293.38
say 293.40
Dia in Class-10
Sl No. Weight in Rate per Amount
mm
Qntl. Mtr
1 80 6.225 252.00 293.40
2 100 7.800 316.00 367.90
3 125 9.800 397.00 462.20
4 150 12.500 507.00 590.20
5 200 19.100 778.00 905.70
6 250 24.400 1004.00 1168.60
7 300 32.200 1305.00 1519.30
62
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Dia in Class-15
Sl No. Weight in Rate per Amount
mm
Qntl. Mtr
1 80 6.225 252.00 293.40
2 100 8.175 331.00 385.40
3 125 10.725 434.00 505.30
4 150 15.175 615.00 716.00
5 200 25.300 1030.00 1199.10
6 250 32.000 1317.00 1533.00
7 300 44.925 1821.00 2120.00
2.5.2 Laying in trenches plain ended Cast Iron bends for Asbestos Cement Pressure pipes, of
the following classess and nominal diameter as per specification complete.
I. Class - 5
80mm nominal diameter
i. Laying of 90° bend
a. Materials
80mm dia Cast Iron specials such as Bends, Tees etc
1.00 Qntl 4127.24 4127.24
b. Labour for laying Tees
For average take details for 10 numbers Tees of 200mm x 150mm size Weight of
Tees = 74 kg x 10 = 740 kgs or 7.40 quintals
Plumber (Fitter) 2nd class 0.93 Each 190.00 176.70
Helper to plumber or fitter 0.62 Each 170.00 105.40
Male worker (unskilled) 2.48 Each 150.00 372.00
654.10
Rate per each quintal is 654.10 ÷ 7.40 = 88.39
(a + b) 4215.63
c. Add Contractor's Profit & Overhead charges 15.00% 4215.63 632.34
Total (a+b+c) 4847.97
say 4848.00
Weight of 90° bend = 7.20 kg 7.20 100 kg 4848.00 349.06
Rate per each 349.10
Plain ended Cast Iron bends for Asbestos Cement Pressure pipes
Dia in Class-5 (90° bend)
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.072 297.16 349.10
2 100 0.100 406.09 477.20
3 125 0.140 553.14 650.30
4 150 0.190 731.38 860.40
5 200 0.305 1172.21 1379.00
63
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Dia in Class-5 (22.50° bend)
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.053 218.74 251.60
2 100 0.070 284.26 326.90
3 125 0.096 379.29 436.20
4 150 0.123 473.47 544.50
5 200 0.180 691.80 795.60
Plain ended Cast Iron bends for Asbestos Cement Pressure pipes
Dia in Class-10 (90° bend)
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.072 297.16 349.10
2 100 0.100 406.09 477.20
3 125 0.140 553.14 650.30
4 150 0.190 731.38 860.40
5 200 0.324 1245.23 1464.90
Plain ended Cast Iron bends for Asbestos Cement Pressure pipes
Dia in Class-15 (90° bend)
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.072 297.16 349.10
2 100 0.102 414.21 486.70
3 125 0.148 584.74 687.50
4 150 0.200 769.88 905.70
5 200 0.353 1356.69 1596.10
64
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Dia in Class-15 (22.50° bend)
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.053 218.74 251.60
2 100 0.070 284.26 326.90
3 125 0.102 403.00 463.50
4 150 0.135 519.67 597.60
5 200 0.228 876.27 1007.70
2.5.3 Laying plain end Cast Iron plug for Asbestos Cement Pressure pipes, of the following classes
and nominal diameter as per specification complete.
Plain ended Cast Iron plug for Asbestos Cement Pressure pipes
Dia in Class-5
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.035 144.45 169.70
2 100 0.048 194.92 229.00
3 125 0.066 260.76 306.60
4 150 0.090 346.44 407.60
5 200 0.140 538.06 633.00
Dia in Class-10
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.035 144.45 166.10
2 100 0.048 194.92 224.20
3 125 0.066 260.76 299.90
4 150 0.090 346.44 398.40
5 200 0.154 591.87 680.70
Dia in Class-15
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.035 144.45 166.10
2 100 0.048 194.92 224.20
3 125 0.070 276.57 318.10
4 150 0.096 369.54 425.00
5 200 0.174 668.74 769.10
2.5.4 Laying in trenches plain ended Cast Iron reducer for Asbestos cement pressure pipes, of
the following classes and nominal diameter as per specification complete.
Plain ended Cast Iron Reducer for Asbestos Cement Pressure pipes
Size in Class-5
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 100x80 0.083 337.05 396.00
2 125x80 0.096 379.29 445.90
3 125x100 0.103 406.95 478.50
4 150x80 0.110 423.43 498.10
5 150x100 0.126 485.02 570.60
6 150x125 0.134 515.82 606.80
7 200x100 0.150 576.50 678.20
8 200x125 0.160 614.93 723.40
9 200x150 0.180 691.80 813.90
65
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Size in Class-10
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 100x80 0.083 337.05 387.60
2 125x80 0.096 379.29 436.20
3 125x100 0.103 406.95 468.00
4 150x80 0.110 423.43 486.90
5 150x100 0.126 485.02 557.80
6 150x125 0.134 515.82 593.20
7 200x100 0.160 614.93 707.20
8 200x125 0.173 664.89 764.60
9 200x150 0.188 722.54 830.90
Size in Class-15
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 100x80 0.083 337.05 387.60
2 125x80 0.100 395.10 454.40
3 125x100 0.106 418.80 481.60
4 150x80 0.116 446.53 513.50
5 150x100 0.127 488.87 562.20
6 150x125 0.143 550.46 633.00
7 200x100 0.174 668.74 769.10
8 200x125 0.190 730.23 839.80
9 200x150 0.208 799.41 919.30
2.5.5 Laying in trenches Cast Iron plain end crosses for Asbestos cement pressure pipes of the
following classes and nominal diameter as per specification complete.
Plain ended Cast Iron Crosses for Asbestos Cement Pressure pipes
Size in Class-5
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80x 0.126 520.03 610.80
80x80
2 100x100 0.173 702.53 825.50
x100x100
2 125x125 0.234 924.53 1087.00
x125x125
3 150x150 0.320 1231.80 1449.10
x150x150
4 200x200 0.526 2021.58 2378.30
x200x200
Size in Class-10
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80x 0.126 520.03 598.00
80x80
2 100x100 0.173 702.53 807.90
x100x100
2 125x125 0.234 924.53 1063.20
x125x125
3 150x150 0.320 1231.80 1416.60
x150x150
4 200x200 0.564 2167.63 2492.80
x200x200
66
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Size in Class-15
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80x 0.126 520.03 598.00
80x80
2 100x100 0.173 702.53 807.90
x100x100
2 125x125 0.246 971.94 1117.70
x125x125
3 150x150 0.343 1320.34 1518.40
x150x150
4 200x200 0.622 2390.54 2749.10
x200x200
2.5.6 Laying in trenches Cast Iron plain end flanged spigots for Asbestos Cement pressure
pipes of the following classes and nominal diameter as per specification complete.
Plain ended Cast Iron plain end flanged spigots for Asbestos Cement Pressure pipes
Dia in Class-5
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.074 305.42 358.80
2 100 0.090 365.48 429.50
3 125 0.113 446.46 524.90
4 150 0.143 550.46 647.60
5 200 0.197 757.13 890.70
Dia in Class-10
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.074 305.42 351.20
2 100 0.090 365.48 420.30
3 125 0.113 446.46 513.40
4 150 0.143 550.46 633.00
5 200 0.206 791.72 910.50
Dia in Class-15
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.074 305.42 351.20
2 100 0.090 365.48 420.30
3 125 0.117 462.26 531.60
4 150 0.148 569.71 655.20
5 200 0.221 849.37 976.80
67
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.5.7 Laying in trenches Cast Iron plain end Tees for Asbestos Cement pressure pipes of the
following classes and nominal diameter as per specification complete.
Plain ended Cast Iron plain end Tee for Asbestos Cement Pressure pipes
Class-5
Size in
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80 0.092 379.71 446.00
2 100x80 0.120 487.30 572.60
3 100x100 0.130 527.91 620.30
4 125x80 0.167 659.81 775.80
5 125x100 0.177 699.32 822.20
6 125x125 0.190 750.68 882.60
7 150x80 0.202 777.57 914.70
8 150x100 0.230 885.36 1041.50
9 150x125 0.247 950.80 1118.50
10 150x150 0.260 1000.84 1177.40
11 200x80 0.354 1360.53 1600.60
12 200x100 0.362 1391.28 1636.80
13 200x125 0.378 1452.77 1709.10
14 200x150 0.394 1514.26 1781.40
15 200x200 0.430 1652.62 1944.20
Size in Class-10
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80 0.092 379.71 436.70
2 100x80 0.120 487.30 560.40
3 100x100 0.130 527.91 607.10
4 125x80 0.167 659.81 758.80
5 125x100 0.177 699.32 804.20
6 125x125 0.190 750.68 863.30
7 150x80 0.202 777.57 894.20
8 150x100 0.230 885.36 1018.20
9 150x125 0.247 950.80 1093.40
10 150x150 0.260 1000.84 1151.00
11 200x80 0.360 1383.59 1591.10
12 200x100 0.380 1460.46 1679.50
13 200x125 0.397 1525.79 1754.70
14 200x150 0.413 1587.29 1825.40
15 200x200 0.460 1767.92 2033.10
68
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Size in Class-15
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80 0.092 379.71 436.70
2 100x80 0.120 487.30 560.40
3 100x100 0.130 527.91 607.10
4 125x80 0.174 687.47 790.60
5 125x100 0.183 723.03 831.50
6 125x125 0.200 790.19 908.70
7 150x80 0.236 908.45 1044.70
8 150x100 0.242 931.55 1071.30
9 150x125 0.258 993.14 1142.10
10 150x150 0.277 1066.28 1226.20
11 200x80 0.402 1545.01 1776.80
12 200x100 0.410 1575.76 1812.10
13 200x125 0.428 1644.94 1891.70
14 200x150 0.448 1721.80 1980.10
15 200x200 0.503 1933.18 2223.20
2.5.8 Laying in trenches Cast Iron plain end 'Wye' for Asbestos Cement pressure pipes of the
following classes and nominal diameter as per specification complete.
Plain ended Cast Iron plain end Wye for Asbestos Cement Pressure pipes
Class-5
Size in
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80 0.147 606.70 712.60
2 100x80 0.190 771.56 906.60
3 100x100 0.207 840.60 987.70
4 125x80 0.240 948.23 1114.90
5 125x100 0.258 1019.35 1198.50
6 125x125 0.280 1106.27 1300.70
7 150x80 0.310 1193.31 1403.80
8 150x100 0.326 1254.90 1476.30
9 150x125 0.350 1347.28 1584.90
10 150x150 0.375 1443.52 1698.20
11 200x80 0.470 1806.36 2125.10
12 200x100 0.490 1883.22 2215.50
13 200x125 0.516 1983.15 2333.10
14 200x150 0.545 2094.60 2464.20
15 200x200 0.606 2329.05 2740.00
69
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Size in Class-10
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80 0.147 606.70 697.70
2 100x80 0.190 771.56 887.30
3 100x100 0.207 840.60 966.70
4 125x80 0.240 948.23 1090.50
5 125x100 0.258 1019.35 1172.30
6 125x125 0.280 1106.27 1272.20
7 150x80 0.310 1193.31 1372.30
8 150x100 0.326 1254.90 1443.10
9 150x125 0.350 1347.28 1549.40
10 150x150 0.375 1443.52 1660.00
11 200x80 0.490 1883.22 2165.70
12 200x100 0.510 1960.09 2254.10
13 200x125 0.535 2056.17 2364.60
14 200x150 0.564 2167.63 2492.80
15 200x200 0.634 2436.66 2802.20
Size in Class-15
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80x80 0.147 606.70 697.70
2 100x80 0.190 771.56 887.30
3 100x100 0.207 840.60 966.70
4 125x80 0.248 979.84 1126.80
5 125x100 0.264 1043.06 1199.50
6 125x125 0.290 1145.78 1317.60
7 150x80 0.320 1231.80 1416.60
8 150x100 0.337 1297.24 1491.80
9 150x125 0.363 1397.32 1606.90
10 150x150 0.392 1508.96 1735.30
11 200x80 0.520 1998.52 2298.30
12 200x100 0.540 2075.39 2386.70
13 200x125 0.567 2179.16 2506.00
14 200x150 0.600 2305.99 2651.90
15 200x200 0.678 2605.76 2996.60
2.5.9 Fixing Cast Iron detachable joints comprising collar, rubber rings, flanges, bolts and
nuts to Asbestos Cement pressure pipes or plain ended Cast Iron special of the following
nominal diameter as per specification complete including testing (excluding cost of CID collar,
rubber rings, flanges and nuts)
[A] 80mm dia
Details for 10 joints
a. Materials
Weight of 80mm dia detachable joints complete = 4.08 kg
for 10 nos = 10 x 4.08 = 40.80 kg 0.408 Qntl 4127.24 1683.92
b. Labour for fitting
Plumber (Fitter) 2nd class 0.30 Each 190.00 57.00
Helper to plumber or fitter 0.30 Each 170.00 51.00
Male worker (unskilled) 1.60 Each 150.00 240.00
(a + b) 2031.92
c. Add Contractor's Profit & Overhead charges 15% 2031.92 304.79
Total (a+b+c) 2336.71
Rate per each is Rs.2,336.71 ÷ 10 = 233.67
say 233.70
70
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[B] 100mm dia
Details for 10 joints
a. Materials
Weight of 100mm dia detachable joints complete = 5.90 kg
for 10 nos = 10 x 5.90 = 59.00 kg 0.590 Qntl 4060.87 2395.91
b. Labour for fitting
Plumber (Fitter) 2nd class 0.50 Each 190.00 95.00
Helper to plumber or fitter 0.50 Each 170.00 85.00
Male worker (unskilled) 2.00 Each 150.00 300.00
(a + b) 2875.91
c. Add Contractor's Profit & Overhead charges 15% 2875.91 431.39
Total (a+b+c) 3307.30
Rate per each is Rs.3,307.30 ÷ 10 = 330.73
say 330.70
71
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 6299.44 944.92
Total (a+b+c) 7244.36
Rate per each is 7,244.36 ÷ 10 = 724.44
say 724.40
2.5.10 Fixing Asbestos Cement Coupling Joints comprising of collar, rubber rings to AC pressure
pipes of the following nominal diameter including testing as per specification complete (Excluding
cost of AC coupling and rubber rings)
[A] 100mm dia [Rate same as Sl No 2.1.26 (i)] 89.90
[B] 150mm dia [Rate same as Sl No 2.1.26 (ii)] 125.30
[C] 200mm dia [Rate same as Sl No 2.1.26 (iii)] 171.70
[D] 250mm dia [Rate same as Sl No 2.1.26 (iv)] 184.40
[E] 300mm dia [Rate same as Sl No 2.1.26 (v)] 224.60
2.5.11 Fixing Cast Iron Saddle Piece conforming to IS:10299-1982 consisting of strips suitable rubber
packing to be used between straps and pipes, bolts and nuts to Asbestos Cement pressure pipes of
the following nominal diameter as per specification complete (excluding cost of CI saddle piece,
suitable rubber packing, bolts and nuts)
For 80mm to 300mm dia
Details for one joint
a. Labour for laying
Plumber (Fitter) 2nd class 0.25 Each 190.00 47.50
Helper to plumber or fitter 0.50 Each 170.00 85.00
132.50
b. Add Contractor's Profit & Overhead charges 15.00% 132.50 19.88
Total (a+b) 152.38
say 152.40
72
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.6 APPURTENANCES
2.6.1 Fixing Cast Iron Sluice Valve with double flanged ends for water works purposes conforming
to IS 14846 - 2000 for the following rating and nominal diameters as per specification complete
[A] RATING - PN (Nominal Pressure) - 1.0 (IS : 14846 - 2000)
[i] 80 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 2100.00 21000.00
Rubber insertion 3mm thick 20 nos (0.04 sqm each)
20 Each 11.00 220.00
Nuts & Bolts 16mm x 60mm long @ 0.2874 kg
per each 80 nos = 23.00 kg 23.00 Kg 70.00 1610.00
Weight of 10 Sluice Valves = 10x31.3 kg=313 kg=3.13 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
3.13 Qntl 88.39 276.66
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (i) 20 Each 17.40 348.00
(a + b) 23454.66
c. Add Contractor's Profit & Overhead charges 15% of 23454.66 3518.20
Total (a+b+c) 26972.86
Rate per each is 26,972.86 ÷ 10 = 2697.29
say 2697.30
[ ii ] 100 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 2800.00 28000.00
Rubber insertion 3mm thick =20 nos (0.05 sqm each)
20 Each 14.00 280.00
Nuts & Bolts 16mmx60mm long @ 0.2874 kg
per each 160 nos 46.00 kg 46.00 Kg 70.00 3220.00
Weight of 10 Sluice Valves = 10x44.3 kg=443 kg=4.43 quintals
Labour for jointing
b. Rate same as item No 2.1.9 for laying Cast iron bends
4.43 Qntl 88.39 391.57
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (ii) 20 Each 24.00 480.00
(a + b) 32371.57
c. Add Contractor's Profit & Overhead charges 15% of 32371.57 4855.74
Total (a+b+c) 37227.31
Rate per each is 37,227.31 ÷ 10 = 3722.73
say 3722.70
73
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
5.63 Qntl 88.39 497.64
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (iii) 20 Each 24.00 480.00
(a + b) 39585.14
c. Add Contractor's Profit & Overhead charges 15% of 39585.14 5937.77
Total (a+b+c) 45522.91
Rate per each is 45,522.91 ÷ 10 = 4552.29
say 4552.30
[ iv ] 150 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 4200.00 42000.00
Rubber insertion 3mm thick= 20 nos (0.08 sqm each)
20 Each 17.00 340.00
Nuts & Bolts 20mmx65mm long =160 nos @ 0.4643 kg
per each =74.28 kg 74.28 Kg 70.00 5199.60
Weight of 10 Sluice Valves = 10x71.3 kg=713 kg=7.13 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
7.13 Qntl 88.39 630.22
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (iv) 20 Each 27.30 546.00
(a + b) 48715.82
c. Add Contractor's Profit & Overhead charges 15% of 48715.82 7307.37
Total (a+b+c) 56023.19
Rate per each is 56,023.19 ÷ 10 = 5602.32
say 5602.30
[ vi ] 250 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 11500.00 115000.00
Rubber insertion 3mm thick= 20 nos (0.156 sqm each)
20 Each 32.00 640.00
74
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Nuts & Bolts 20mmx75mm long =240 nos @ 0.4892 kg
per each =118.00 kg 118.00 Kg 70.00 8260.00
Weight of 10 Sluice Valves = 10x176.9 kg=1769 kg=17.69 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
17.69 Qntl 88.39 1563.62
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (vi) 20 Each 33.90 678.00
(a + b) 126141.62
c. Add Contractor's Profit & Overhead charges 15% of 126141.62 18921.24
Total (a+b+c) 145062.86
Rate per each is 145,062.86 ÷ 10 = 14506.29
say 14506.30
75
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] 400 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 27000.00 270000.00
Rubber insertion 3mm thick 20 nos (0.32 sqm each)
20 Each 67.00 1340.00
Nuts & Bolts 24mmx85mm long =320 nos @ 0.7348 kg
per each = 236.00 kg 236.00 Kg 70.00 16520.00
Weight of 10 Sluice Valves = 10x1.8x234 kg=4212 kg=42.12 quintals
(Weight of one 90° bend)
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
42.12 Qntl 88.39 3722.99
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (ix) 20 Each 40.50 810.00
(a + b) 292392.99
c. Add Contractor's Profit & Overhead charges 15% of 292392.99 43858.95
Total (a+b+c) 336251.94
Rate per each is 336,251.94 ÷ 10 = 33625.19
say 33625.20
[i] 80 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 2150.00 21500.00
Rubber insertion 3mm thick 20 nos (0.04 sqm each)
20 Each 11.00 220.00
Nuts & Bolts 16mmx60mm long @ 0.2874 kg
per each 80 nos 23.00 kg 23.00 Kg 70.00 1610.00
Weight of 10 Sluice Valves = 10x37.30 kg=373 kg=3.73 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
3.73 Qntl 88.39 329.69
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (i) 20 Each 17.40 348.00
(a + b) 24007.69
c. Add Contractor's Profit & Overhead charges 15% of 24007.69 3601.15
Total (a+b+c) 27608.84
Rate per each is 27,608.84 ÷ 10 = 2760.88
say 2760.90
[ ii ] 100 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 2880.00 28800.00
Rubber insertion 3mm thick =20 nos (0.05 sqm each)
20 Each 14.00 280.00
Nuts & Bolts 16mmx60mm long @ 0.2874 kg
per each 160 nos 46.00 kg 46.00 Kg 70.00 3220.00
Weight of 10 Sluice Valves = 10x56.3 kg=563 kg=5.63 quintals
77
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
5.63 Qntl 88.39 497.64
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (ii) 20 Each 24.00 480.00
(a + b) 33277.64
c. Add Contractor's Profit & Overhead charges 15% of 33277.64 4991.65
Total (a+b+c) 38269.29
Rate per each is 38,269.29 ÷ 10 = 3826.93
say 3826.90
[ iv ] 150 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 4310.00 43100.00
Rubber insertion 3mm thick= 20 nos (0.08 sqm each)
20 Each 17.00 340.00
Nuts & Bolts 20mmx65mm long =160 nos @ 0.4643 kg
per each =74.28 kg 74.28 Kg 70.00 5199.60
Weight of 10 Sluice Valves = 10x86.3 kg=863 kg=8.63 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
8.63 Qntl 88.39 762.81
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (iv) 20 Each 27.30 546.00
(a + b) 49948.41
c. Add Contractor's Profit & Overhead charges 15% of 49948.41 7492.26
Total (a+b+c) 57440.67
Rate per each is 57,440.67 ÷ 10 = 5744.07
say 5744.10
[ vi ] 250 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 11990.00 119900.00
Rubber insertion 3mm thick= 20 nos (0.156 sqm each)
20 Each 32.00 640.00
Nuts & Bolts 20mmx75mm long =240 nos @ 0.4892 kg
per each =118.00 kg 118.00 Kg 70.00 8260.00
Weight of 10 Sluice Valves = 10x226.9 kg=2269 kg=22.69 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
22.69 Qntl 88.39 2005.57
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (vi) 20 Each 33.90 678.00
(a + b) 131483.57
c. Add Contractor's Profit & Overhead charges 15% of 131483.57 19722.54
Total (a+b+c) 151206.11
Rate per each is 151,206.11 ÷ 10 = 15120.61
say 15120.60
79
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ i ] 350 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 23995.00 239950.00
Rubber insertion 3mm thick 20 nos (0.26 sqm each)
20 Each 40.00 800.00
Nuts & Bolts 20mmx80mm long =320 nos @ 0.4978 kg
per each = 160.00 kg 160.00 Kg 70.00 11200.00
Weight of 10 Sluice Valves = 10x2.2x181 kg=3982 kg=39.82 quintals
(Weight of one 90° bend)
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
39.82 Qntl 88.39 3519.69
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (viii) 20 Each 40.50 810.00
(a + b) 256279.69
c. Add Contractor's Profit & Overhead charges 15% of 256279.69 38441.95
Total (a+b+c) 294721.64
Rate per each is 294,721.64 ÷ 10 = 29472.16
say 29472.20
[ ii ] 400 mm diameter
Data for 10 numbers of Cast Iron Sluice Valves
a. Materials to be used
Cast Iron Sluice Valve with cap 10 Each 32990.00 329900.00
Rubber insertion 3mm thick 20 nos (0.32 sqm each)
20 Each 67.00 1340.00
Nuts & Bolts 24mmx85mm long =320 nos @ 0.7348 kg
per each = 236.00 kg 236.00 Kg 70.00 16520.00
Weight of 10 Sluice Valves = 10x2.2x234 kg=5148 kg=51.48 quintals
(Weight of one 90° bend)
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
51.48 Qntl 88.39 4550.32
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (ix) 20 Each 40.50 810.00
(a + b) 353120.32
c. Add Contractor's Profit & Overhead charges 15% of 353120.32 52968.05
Total (a+b+c) 406088.37
Rate per each is 406,088.37 ÷ 10 = 40608.84
say 40608.80
80
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (x) 20 Each 47.10 942.00
(a + b) 448791.28
c. Add Contractor's Profit & Overhead charges 15% of 448791.28 67318.69
Total (a+b+c) 516109.97
Rate per each is 516,109.97 ÷ 10 = 51611.00
say 51611.00
81
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.6.2 Fixing swing check type Reflux Valves (Non-return valves) with double flanged ends conforming to
IS : 5312 (Part-I) - 2004 for water works purposes for the following rating and nominal diameters
as per specification complete
[i] 80 mm diameter
Data for 10 numbers of Cast Iron Reflux Valves
a. Materials to be used
Swing check type Reflux Valves (Non-return valves) with double flanged ends
10 Each 2030.00 20300.00
Rubber insertion 3mm thick 20 nos (0.04 sqm each)
20 Each 11.00 220.00
Nuts & Bolts 16mmx60mm long @ 0.2874 kg
per each 80 nos 23.00 kg 23.00 Kg 70.00 1610.00
Weight of 10 Reflux Valves = 10x37.30 kg=373 kg=3.73 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
3.73 Qntl 88.39 329.69
Providing flanged joints to Reflux Valves
Rate same as item No 2.1.25 (i) 20 Each 17.40 348.00
(a + b) 22807.69
c. Add Contractor's Profit & Overhead charges 15% of 22807.69 3421.15
Total (a+b+c) 26228.84
Rate per each is 26,228.84 ÷ 10 = 2622.88
say 2622.90
[ ii ] 100 mm diameter
Data for 10 numbers of Cast Iron Reflux Valves
a. Materials to be used
Swing check type Reflux Valves (Non-return valves) with double flanged ends
10 Each 2900.00 29000.00
Rubber insertion 3mm thick =20 nos (0.05 sqm each)
20 Each 14.00 280.00
Nuts & Bolts 16mmx60mm long @ 0.2874 kg
per each 160 nos 46.00 kg 46.00 Kg 70.00 3220.00
Weight of 10 Reflux Valves = 10x56.3 kg=563 kg=5.63 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
5.63 Qntl 88.39 497.64
Providing flanged joints to Reflux Valves
Rate same as item No 2.1.25 (ii) 20 Each 24.00 480.00
(a + b) 33477.64
c. Add Contractor's Profit & Overhead charges 15% of 33477.64 5021.65
Total (a+b+c) 38499.29
Rate per each is 38,499.29 ÷ 10 = 3849.93
say 3849.90
82
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Nuts & Bolts 16mmx60mm long @ 0.2953 kg
per each 160 nos =47.25 kg 47.25 Kg 70.00 3307.50
Weight of 10 Reflux Valves = 10x68.3 kg=683 kg=6.83 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
6.83 Qntl 88.39 603.70
Providing flanged joints to Reflux Valves
Rate same as item No 2.1.25 (iii) 20 Each 24.00 480.00
(a + b) 58691.20
c. Add Contractor's Profit & Overhead charges 15% of 58691.20 8803.68
Total (a+b+c) 67494.88
Rate per each is 67,494.88 ÷ 10 = 6749.49
say 6749.50
[ ii ] 200 mm diameter
Data for 10 numbers of Cast Iron Reflux Valves
a. Materials to be used
Swing check type Reflux Valves (Non-return valves) with double flanged ends
10 Each 10500.00 105000.00
Rubber insertion 3mm thick= 20 nos (0.116 sqm each)
20 Each 22.00 440.00
Nuts & Bolts 20mmx70mm long =160 nos @ 0.4750 kg
per each =76.00 kg 76.00 Kg 70.00 5320.00
Weight of 10 Reflux Valves = 10x121.5 kg=1215 kg=12.15 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
12.15 Qntl 88.39 1073.94
Providing flanged joints to Reflux Valves
Rate same as item No 2.1.25 (v) 20 Each 27.30 546.00
(a + b) 112379.94
c. Add Contractor's Profit & Overhead charges 15% of 112379.94 16856.99
Total (a+b+c) 129236.93
Rate per each is 129,236.93 ÷ 10 = 12923.69
say 12923.70
83
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 300 mm diameter
Data for 10 numbers of Cast Iron Reflux Valves
a. Materials to be used
Swing check type Reflux Valves (Non-return valves) with double flanged ends
10 Each 20800.00 208000.00
Rubber insertion 3mm thick= 20 nos (0.20 sqm each)
20 Each 40.00 800.00
Nuts & Bolts 20mmx75mm long =240 nos @ 0.4892 kg
per each =118.00 kg 118.00 Kg 70.00 8260.00
Weight of 10 Reflux Valves = 10x242.4 kg=2424 kg=24.24 quintals
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
24.24 Qntl 88.39 2142.57
Providing flanged joints to Reflux Valves
Rate same as item No 2.1.25 (vii) 20 Each 33.90 678.00
(a + b) 219880.57
c. Add Contractor's Profit & Overhead charges 15% of 219880.57 32982.09
Total (a+b+c) 252862.66
Rate per each is 252,862.66 ÷ 10 = 25286.27
say 25286.30
84
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
28.96 Qntl 88.39 2559.77
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (viii) 20 Each 40.50 810.00
(a + b) 264369.77
c. Add Contractor's Profit & Overhead charges 15% of 264369.77 39655.47
Total (a+b+c) 304025.24
Rate per each is 304,025.24 ÷ 10 = 30402.52
say 30402.50
[ ii ] 400 mm diameter
Data for 10 numbers of Cast Iron Reflux Valves
a. Materials to be used
Swing check type Reflux Valves (Non-return valves) with double flanged ends
10 Each 32200.00 322000.00
Rubber insertion 3mm thick 20 nos (0.32 sqm each)
20 Each 67.00 1340.00
Nuts & Bolts 24mmx85mm long =320 nos @ 0.7348 kg
per each = 236.00 kg 236.00 Kg 70.00 16520.00
Weight of 10 Sluice Valves = 10x1.6x234 kg=3744 kg=37.44 quintals
(Weight of one 90° bend)
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
37.44 Qntl 88.39 3309.32
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (ix) 20 Each 40.50 810.00
(a + b) 343979.32
c. Add Contractor's Profit & Overhead charges 15% of 343979.32 51596.90
Total (a+b+c) 395576.22
Rate per each is 395,576.22 ÷ 10 = 39557.62
say 39557.60
85
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 500 mm diameter
Data for 10 numbers of Cast Iron Reflux Valves
a. Materials to be used
Swing check type Reflux Valves (Non-return valves) with double flanged ends
10 Each 50900.00 509000.00
Rubber insertion 3mm thick 20 nos (0.45 sqm each)
20 Each 106.00 2120.00
Nuts & Bolts 24mmx90mm long =400 nos @ 0.7502 kg
per each = 300.00 kg 300.00 Kg 70.00 21000.00
Weight of 10 Sluice Valves = 10x1.6x370 kg=5920 kg=59.20 quintals
(Weight of one 90° bend)
b. Labour for jointing
Rate same as item No 2.1.9 for laying Cast iron bends
59.20 Qntl 88.39 5232.69
Providing flanged joints to Sluice Valves
Rate same as item No 2.1.25 (xi) 20 Each 50.40 1008.00
(a + b) 538360.69
c. Add Contractor's Profit & Overhead charges 15% of 538360.69 80754.10
Total (a+b+c) 619114.79
Rate per each is 619,114.79 ÷ 10 = 61911.48
say 61911.50
2.6.3 Fixing single Air Relief Valve conforming to IS 14845 : 2000 for water works purposes for the
following diameters including drilling the water main (Cast Iron pipes with metal straps) as per
specification complete
86
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for drilling and fixing the air valve
Plumber Fitter(S) 0.25 Each 190.00 47.50
Helper to plumber or fitter 0.50 Each 170.00 85.00
Male worker (unskilled) 0.50 Each 150.00 75.00
Add Jointing materials etc 17% of 207.50 35.28
(a+b) 1542.78
c. Add Contractor's Profit & Overhead charges 15% of 1542.78 231.42
Total (a+b+c) Rate per each 1774.20
say 1774.20
[ ii ] 20mm dia Single Air Valve with metal strap for pipe (Cost of material only)
1 Each 1600.00 1600.00
[ iii ] 25mm dia Single Air Valve with metal strap for pipe (Cost of material only)
1 Each 1800.00 1800.00
2.6.4 Fixing Double Air Relief Valve conforming to IS 14845 : 2000 for water works purposes for the
following diameters including drilling the water main (Cast iron pipes with metal straps) as per
specification complete
87
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.6.5 Fixing of water meters (Domestic Type) conforming to IS :779-1994 and Stop Cock in GI Mild
Steel pipe / PVC pipe / PE pipe of the following nominal diameter as per specification complete
[i] 15 mm diameter
a. Materials
15 mm diameter water meter 1 Each 655.00 655.00
15 mm dia brass stop cock 1 Each 165.00 165.00
15mm Jam nut 1 Each 6.00 6.00
b. Labour charges
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.33 Each 170.00 56.10
Add Jointing materials etc 2% of 118.80 2.38
(a+b) 947.18
c. Add Contractor's Profit & Overhead charges 15% of 947.18 142.08
Total (a+b+c) Rate per each 1089.26
say 1089.30
[ ii ] 20 mm diameter
a. Materials
20 mm diameter water meter 1 Each 837.00 837.00
20 mm dia brass stop cock 1 Each 215.00 215.00
20mm Jam nut 1 Each 7.00 7.00
b. Labour charges
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.33 Each 170.00 56.10
Add Jointing materials etc 2% of 118.80 2.38
(a+b) 1180.18
c. Add Contractor's Profit & Overhead charges 15% of 1180.18 177.03
Total (a+b+c) Rate per each 1357.21
say 1357.20
[ iii ] 25 mm diameter
a. Materials
25 mm diameter water meter 1 Each 1300.00 1300.00
25 mm dia brass stop cock 1 Each 270.00 270.00
25mm Jam nut 1 Each 8.00 8.00
b. Labour charges
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.33 Each 170.00 56.10
Add Jointing materials etc 2% of 118.80 2.38
(a+b) 1699.18
c. Add Contractor's Profit & Overhead charges 15% of 1699.18 254.88
Total (a+b+c) Rate per each 1954.06
say 1954.10
[ iv ] 32 mm diameter
a. Materials
32 mm diameter water meter 1 Each 1500.00 1500.00
32 mm dia brass stop cock 1 Each 420.00 420.00
32mm Jam nut 1 Each 10.00 10.00
88
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.33 Each 170.00 56.10
Add Jointing materials etc 2% of 118.80 2.38
(a+b) 2051.18
c. Add Contractor's Profit & Overhead charges 15% of 2051.18 307.68
Total (a+b+c) Rate per each 2358.86
say 2358.90
[v] 40 mm diameter
a. Materials
40 mm diameter water meter 1 Each 1700.00 1700.00
40 mm dia brass stop cock 1 Each 570.00 570.00
40mm Jam nut 1 Each 12.00 12.00
b. Labour charges
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.33 Each 170.00 56.10
Add Jointing materials etc 2% of 118.80 2.38
(a+b) 2403.18
c. Add Contractor's Profit & Overhead charges 15% of 2403.18 360.48
Rate per each 2763.66
Total (a+b+c) Rate per each 2763.70
[ vi ] 50 mm diameter
a. Materials
50 mm diameter water meter 1 Each 1800.00 1800.00
50 mm dia brass stop cock 1 Each 790.00 790.00
50mm Jam nut 1 Each 14.00 14.00
b. Labour charges
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.33 Each 170.00 56.10
Add Jointing materials etc 2% of 118.80 2.38
(a+b) 2725.18
c. Add Contractor's Profit & Overhead charges 15% of 2725.18 408.78
Total (a+b+c) Rate per each 3133.96
say 3134.00
2.6.6 Fixing of Water Meters (Bulk Type) conforming to IS:2373-1981 Vane Wheel type meter or
Helical type meter or water meter Dry Dial type or water meter Wet Dial type with double flanged
ends for the following nominal diameter as per specification complete
[i] 50 mm diameter
Data for 10 numbers of water meters (Bulk type)
a. Materials
50 mm water meter (Bulk type) 10 Each 1800.00 18000.00
Rubber insertion 3 mm thick (IS:638-1979) = 20 nos = (20 x 0.027) sqm per each
20 Each 10.00 200.00
Nuts & Bolts 16 mm x 60 mm long = 80 nos
@ 0.2874 per each = 23 kg 23.00 Kg 70.00 1610.00
Weight of 10 Water Meters = 19.56 kg x 10 = 195 kg or 1.96 Qtl
(considering the weight of a 50mm water meter is 5/8 weight of
80mm dia CI sluice valve, Rating PN-1)
89
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for fixing
Rate same as item No 2.1.9 for laying Cast iron bends
1.96 Qntl 88.39 173.24
Providing flanged joints to Water meter
Rate same as item No 2.1.25 (i) 20 Each 17.40 348.00
(a+b) 20331.24
c. Add Contractor's Profit & Overhead charges 15% 20331.24 3049.69
Total (a+b+c) 23380.93
Rate per each joint is 23,380.93 ÷ 10 = 2338.09
say 2338.10
[ ii ] 80 mm diameter
Data for 10 numbers of water meters (Bulk type)
a. Materials
80 mm water meter (Bulk type) 10 Each 2030.00 20300.00
Rubber insertion 3 mm thick (IS:638-1979) = 20 nos = (20 x 0.04) sqm per each
20 Each 11.00 220.00
Nuts & Bolts 16 mm x 60 mm long = 80 nos
@ 0.2874 per each = 23 kg 23.00 Kg 70.00 1610.00
Weight of 10 Water Meters = 31.30 kg x 10 = 313 kg or 3.13 Qtl
(considering the weight of a 80mm water meter is equal to weight of
a 80mm dia CI sluice valve, Rating PN-1)
b. Labour for fixing
Rate same as item No 2.1.9 for laying Cast iron bends
3.13 Qntl 88.39 276.66
Providing flanged joints to Water meter
Rate same as item No 2.1.25 (i) 20 Each 17.40 348.00
(a+b) 22754.66
c. Add Contractor's Profit & Overhead charges 15% 22754.66 3413.20
Total (a+b+c) 26167.86
Rate per each joint is 26,167.86 ÷ 10 = 2616.79
say 2616.80
90
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 150 mm diameter
Data for 10 numbers of water meters (Bulk type)
a. Materials
150 mm water meter (Bulk type) 10 Each 4560.00 45600.00
Rubber insertion 3 mm thick (IS:638-1979) = 20 nos = (20 x 0.08) sqm per each
20 Each 17.00 340.00
Nuts & Bolts 20 mm x 65 mm long = 160 nos
@ 0.4643 per each = 74.28 kg 74.28 Kg 70.00 5199.60
Weight of 10 Water Meters = 71.30 kg x 10 = 713 kg or 7.13 Qtl
(considering the weight of a 150mm water meter is equal to weight of
a 150mm dia CI Sluice Valve, Rating PN-1)
b. Labour for fixing
Rate same as item No 2.1.9 for laying Cast iron bends
7.13 Qntl 88.39 630.22
Providing flanged joints to Water meter
Rate same as item No 2.1.25 (iv) 20 Each 27.30 546.00
(a+b) 52315.82
c. Add Contractor's Profit & Overhead charges 15% 52315.82 7847.37
Total (a+b+c) 60163.19
Rate per each joint is 60,163.19 ÷ 10 = 6016.32
say 6016.30
[ vi ] 250 mm diameter
Data for 10 numbers of water meters (Bulk type)
a. Materials
250 mm water meter (Bulk type) 10 Each 11320.00 113200.00
Rubber insertion 3 mm thick (IS:638-1979) = 20 nos = (20 x 0.156) sqm per each
20 Each 32.00 640.00
Nuts & Bolts 20 mm x 75 mm long = 240 nos
@ 0.4892 per each = 118.00 kg 118.00 Kg 70.00 8260.00
Weight of 10 Water Meters = 176.90 kg x 10 = 1769 kg or 17.69 Qtl
(considering the weight of a 250mm water meter is equal to weight of
a 250mm dia CI Sluice Valve, Rating PN-1)
91
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for fixing
Rate same as item No 2.1.9 for laying Cast iron bends
17.69 Qntl 88.39 1563.62
Providing flanged joints to Water meter
Rate same as item No 2.1.25 (vi) 20 Each 33.90 678.00
(a+b) 124341.62
c. Add Contractor's Profit & Overhead charges 15% 124341.62 18651.24
Total (a+b+c) 142992.86
Rate per each joint is 142,992.86 ÷ 10 = 14299.29
say 14299.30
92
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ix ] 400 mm diameter
Data for 10 numbers of water meters (Bulk type)
a. Materials
400 mm water meter (Bulk type) 10 Each 20970.00 209700.00
Rubber insertion 3 mm thick (IS:638-1979) = 20 nos = (20 x 0.38) sqm per each
20 Each 67.00 1340.00
Nuts & Bolts 24 mm x 85 mm long = 320 nos
@ 0.7348 per each = 236.00 kg 236.00 Kg 70.00 16520.00
Weight of 10 Water Meters = 327.60 kg x 10 = 3276 kg or 32.76 Qtl
(considering the weight of a 400mm water meter is equal to weight of
a 400mm dia CI Sluice Valve, Rating PN-0.4)
b. Labour for fixing
Rate same as item No 2.2.14 for laying CI bends 32.76 Qntl 88.39 2895.66
Providing flanged joints to Water meter
Rate same as item No 2.1.25 (ix) 20 Each 40.50 810.00
(a+b) 231265.66
c. Add Contractor's Profit & Overhead charges 15% 231265.66 34689.85
Total (a+b+c) 265955.51
Rate per each joint is 265,955.51 ÷ 10 = 26595.55
say 26595.60
2.6.7 Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts,bolts, rubber
insertions etc. complete conforming to IS: 2373-1981
[ i ] 80 mm dia
Details of cost for one no. dirt box strainer
a. Materials
Dirt box strainer 80 mm 1 Each 2620.00 2620.00
Carriage of dirt box strainer LS 38.74
b. Labour for laying dirt box stainer LS 58.11
Providing flanged joints to double acting air
valves with bolts, nuts and rubber insertions etc
Rate same as item No 2.1.25 (i) 2 Each 108.90 217.80
(a+b) 2934.65
c. Add Contractor's Profit & Overhead charges 15% 2934.65 440.20
Total (a+b+c) 3374.85
say 3374.90
93
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] 100 mm dia
Details of cost for one no. dirt box strainer
a. Materials
Dirt box strainer 100 mm 1 Each 4180.00 4180.00
Carriage of dirt box strainer LS 38.74
b. Labour for laying dirt box stainer LS 77.48
Providing flanged joints to double acting air
valves with bolts, nuts and rubber insertions etc
Rate same as item No 2.1.25 (ii) 2 Each 199.00 398.00
(a+b) 4694.22
c. Add Contractor's Profit & Overhead charges 15% 4694.22 704.13
Total (a+b+c) 5398.35
say 5398.40
[ iv ] 200 mm dia
Details of cost for one no. dirt box strainer
a. Materials
Dirt box strainer 200 mm 1 Each 7550.00 7550.00
Carriage of dirt box strainer LS 77.48
b. Labour for laying dirt box stainer LS 154.96
Providing flanged joints to double acting air
valves with bolts, nuts and rubber insertions etc
Rate same as item No 2.1.25 (iv) 2 Each 315.30 630.60
(a+b) 8413.04
c. Add Contractor's Profit & Overhead charges 15% 8413.04 1261.96
Total (a+b+c) 9675.00
say 9675.00
2.6.8 Fixing of spindle Fire Hydrant sluice valve type with 65mm outlet conforming to IS:909-1992
complete with components as per specification complete
Data for 10 numbers of Spindle Fire Hydrants
a. Materials
65 mm Gun metal Outlet Fire Hydrants with components
10 Each 4800.00 48000.00
Rubber insertion 3 mm thick (IS:638-1979) = 10 nos = (10 x 0.04) sqm per each
10 Each 11.00 110.00
Nuts & Bolts 16 mm x 60 mm long = 40 nos
@ 0.2874 per each = 11.50 kg 11.50 Kg 70.00 805.00
94
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber Fitter(S) 1.50 Each 190.00 285.00
Helper to plumber or fitter 1.00 Each 170.00 170.00
Male worker (unskilled) 4.00 Each 150.00 600.00
(a+b) 49970.00
c. Add Contractor's Profit & Overhead charges 15% 49970.00 7495.50
Total (a+b+c) 57465.50
Rate per each is 57,465.50 ÷ 10 = 5746.55
say 5746.60
2.6.9 Fixing Pressure Release Valve with components conforming to IS:14150-2005 as per
specification complete
[ i ] 80 mm diameter
Data for 10 numbers of Pressure Release Valve with components
a. Materials
80 mm Bronze Pressure Release Valve with components
10 Each 14154.00 141540.00
Rubber insertion 3 mm thick (IS:638-1979) = 10 nos = (10 x 0.04) sqm per each
10 Each 11.00 110.00
Nuts & Bolts 16 mm x 60 mm long = 40 nos
@ 0.2874 per each = 11.50 kg 11.50 Kg 70.00 805.00
b. Labour charges
Plumber Fitter(S) 1.50 Each 190.00 285.00
Helper to plumber or fitter 1.00 Each 170.00 170.00
Male worker (unskilled) 4.00 Each 150.00 600.00
(a+b) 143510.00
c. Add Contractor's Profit & Overhead charges 15% 143510.00 21526.50
Total (a+b+c) 165036.50
Rate per each is 165,036.50 ÷ 10 = 16503.65
say 16503.70
95
Section – 3
3.1.1 Providing and fixing to wall or ceiling and floor galvanized mild steel tubes (medium
grade) conforming to IS: 1239/2004, Part-1 of the following nominal bore, tube fittings and
clamps including making good the wall, ceiling and floor, testing all complete as per specification.
In ground floor
[i] 15mm diameter
Details of cost for 10 metres
a. Materials
15mm G.I pipes 10.00 metre 62.44 624.40
Add for fittings (heavy quality) and wastages = 1.5 15%
metres 624.40 93.66
White lead, hemp oil etc 1% of item (a) 1% 624.40 6.24
White lead, hemp oil, clamps, pegs, sand and cement etc 2% of item (a)
2% 624.40 12.49
b. Labour charges
Plumber Fitter(S) 0.67 Each 190.00 127.30
Male worker 0.67 Each 150.00 100.50
(a+b) 964.59
c. Add Contractor's Profit & Overhead charges 15% 964.59 144.69
Total (a+b+c) 1109.28
Rate per metre is 1,109.28 ÷ 10 = 110.93
say 110.90
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm G.I pipes 10.00 metre 79.75 797.50
Add for fittings (heavy quality) and wastages = 1.5 15%
metres 797.50 119.63
White lead,hemp oil etc 1% 797.50 7.98
White lead,hemp oil,clamps,pegs,sand and cement etc
2% 797.50 15.95
b. Labour charges
Plumber Fitter(S) 0.75 Each 190.00 142.50
Male worker 0.67 Each 150.00 100.50
(a+b) 1184.06
c. Add Contractor's Profit & Overhead charges 15% 1184.06 177.61
Total (a+b+c) 1361.67
Rate per metre is 1,361.67 ÷ 10 = 136.17
say 136.20
96
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 1680.46 252.07
Total (a+b+c) 1932.53
Rate per metre is 1,932.53 ÷ 10 = 193.25
say 193.30
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm G.I pipes 10.00 metre 155.06 1550.60
Add for fittings (heavy quality) and wastages = 1.5 15%
metres 1550.60 232.59
White lead,hemp oil etc 1% 1550.60 15.51
White lead,hemp oil,clamps,pegs,sand and cement etc
2% 1550.60 31.01
b. Labour charges
Plumber Fitter(S) 0.83 Each 190.00 157.70
Male worker 1.00 Each 150.00 150.00
(a+b) 2137.41
c. Add Contractor's Profit & Overhead charges 15% 2137.41 320.61
Total (a+b+c) 2458.02
Rate per metre is 2,458.02 ÷ 10 = 245.80
say 245.80
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm G.I pipes 10.00 metre 244.90 2449.00
Add for fittings (heavy quality) and wastages = 1.5 15%
metres 2449.00 367.35
White lead,hemp oil etc 1% 2449.00 24.49
White lead,hemp oil,clamps,pegs,sand,cement etc
2% 2449.00 48.98
b. Labour charges
Plumber Fitter(S) 1.17 Each 190.00 222.30
Male worker 1.67 Each 150.00 250.50
(a+b) 3362.62
c. Add Contractor's Profit & Overhead charges 15% 3362.62 504.39
Total (a+b+c) 3867.01
Rate per metre is 3,867.01 ÷ 10 = 386.70
say 386.70
97
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.2 Fixing Brass Bell Plug of the following nominal size as per specification complete
[ i ] 32 mm diameter
Details of cost for one number
a. Materials
Brass Bell Plug with rivets or 'J' hooks 1 Each 80.00 80.00
b. Labour charges
Plumber Fitter(S) 0.125 Each 190.00 23.75
(a+b) 103.75
c. Add Contractor's Profit & Overhead charges 15% 103.75 15.56
Total (a+b+c) 119.31
say 119.30
[ ii ] 50mm Brass Bell Plug with rivets or 'J' hooks
1 Each 100.00 100.00
[ iii ] 80mm Brass Bell Plug with rivets or 'J' hooks
1 Each 120.00 120.00
[ iv ] 100mm Brass Bell Plug with rivets or 'J' hooks
1 Each 140.00 140.00
3.1.3 Providing and fixing to wall or ceiling and floor rigid UPVC pipes class IV (8 kgf/cm²)/class III
(6kgf/cm²) conforming to IS:4985/2000 and pipe fittings of the following nominal bore with clamps
including making good the wall, ceiling and floor all complete as per specification
A. In ground floor
[ i ] 16mm diameter
Details of cost for 10 metres
a. Materials
16mm UPVC pipes class IV 10.00 metre 9.56 95.60
Add 15% for fittings and wastages = 1.5 metres
15% 95.60 14.34
Wooden plug, clamps, cement etc 3% of item (a)
3% 95.60 2.87
b. Labour charges
Plumber Fitter(S) 0.67 Each 190.00 127.30
Male worker 0.67 Each 150.00 100.50
(a+b) 340.61
c. Add Contractor's Profit & Overhead charges 15% 340.61 51.09
Total (a+b+c) 391.70
Rate per metre is 391.70 ÷ 10 = 39.17
say 39.20
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm UPVC pipes class IV 10.00 metre 11.78 117.80
Add for fittings and wastages 15% 117.80 17.67
Wooden plug, clamps, cement etc 3% of item (a)
3% 117.80 3.53
b. Labour charges
Plumber Fitter(S) 0.75 Each 190.00 142.50
Male worker 0.67 Each 150.00 100.50
(a+b) 382.00
c. Add Contractor's Profit & Overhead charges 15% 382.00 57.30
Total (a+b+c) 439.30
Rate per metre is 439.30 ÷ 10 = 43.93
43.90
98
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iii ] 25mm diameter
Details of cost for 10 metres
a. Materials
25mm UPVC pipes class IV 10.00 metre 14.56 145.60
Add for fittings and wastages 15% 145.60 21.84
Wooden plug, clamps, cement etc 3% of item (a)
3% 145.60 4.37
b. Labour charges
Plumber Fitter(S) 0.83 Each 190.00 157.70
Male worker 0.67 Each 150.00 100.50
(a+b) 430.01
c. Add Contractor's Profit & Overhead charges 15% 430.01 64.50
Total (a+b+c) 494.51
Rate per metre is 494.51 ÷ 10 = 49.45
49.50
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm UPVC pipes class IV 10.00 metre 21.89 218.90
Add for fittings and wastages 15% 218.90 32.84
Wooden plug, clamps, cement etc 3% of item (a)
3% 218.90 6.57
b. Labour charges
Plumber Fitter(S) 0.83 Each 190.00 157.70
Male worker 1.00 Each 150.00 150.00
(a+b) 566.01
c. Add Contractor's Profit & Overhead charges 15% 566.01 84.90
Total (a+b+c) 650.91
Rate per metre is 650.91 ÷ 10 = 65.09
65.10
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm UPVC pipes class IV 10.00 metre 51.30 513.00
Add for fittings and wastages 15% 513.00 76.95
Wooden plug, clamps, cement etc 3% of item (a)
3% 513.00 15.39
99
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber Fitter(S) 1.17 Each 190.00 222.30
Male worker 1.67 Each 150.00 250.50
(a+b) 1078.14
c. Add Contractor's Profit & Overhead charges 15% 1078.14 161.72
Total (a+b+c) 1239.86
Rate per metre is 1,239.86 ÷ 10 = 123.99
say 124.00
3.1.4 Providing and fixing to wall or ceiling and floor pvc pipes class conforming to ASTM-D-
1785/89 (Sch-80) and pipe fittings of the following nominal bore with clamps including making
good the wall, ceiling and floor all complete as per specification complete.
In ground floor
[i] 15mm diameter
Details of cost for 10 metres
a. Materials
15mm PVC sch-80 pipes 10.00 metre 27.94 279.40
Add for fittings and wastages 15% 279.40 41.91
Wooden plug,clamps, cement etc 3% 279.40 8.38
b. Labour charges
Plumber Fitter(S) 0.67 Each 190.00 127.30
Male worker 0.67 Each 150.00 100.50
(a+b) 557.49
c. Add Contractor's Profit & Overhead charges 15% 557.49 83.62
Total (a+b+c) 641.11
Rate per metre is 641.11 ÷ 10 = 64.11
say 64.10
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm PVC sch-80 pipes 10.00 metre 37.83 378.30
Add for fittings and wastages 15% 378.30 56.75
Wooden plug,clamps, cement etc 3% 378.30 11.35
b. Labour charges
Plumber Fitter(S) 0.75 Each 190.00 142.50
Male worker 0.67 Each 150.00 100.50
(a+b) 689.40
c. Add Contractor's Profit & Overhead charges 15% 689.40 103.41
Total (a+b+c) 792.81
Rate per metre is 792.81 ÷ 10 = 79.28
79.30
100
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 913.46 137.02
Total (a+b+c) 1050.48
Rate per metre is 1,050.48 ÷ 10 = 105.05
say 105.10
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm PVC sch-80 pipes 10.00 metre 76.82 768.20
Add for fittings and wastages 15% 768.20 115.23
Wooden plug,clamps, cement etc 3% 768.20 23.05
b. Labour charges
Plumber Fitter(S) 0.83 Each 190.00 157.70
Male worker 1.00 Each 150.00 150.00
(a+b) 1214.18
c. Add Contractor's Profit & Overhead charges 15% 1214.18 182.13
Total (a+b+c) 1396.31
Rate per metre is 1,396.31 ÷ 10 = 139.63
say 139.60
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm PVC sch-80 pipes 10.00 metre 129.02 1290.20
Add for fittings and wastages 15% 1290.20 193.53
Wooden plug,clamps, cement etc 3% 1290.20 38.71
b. Labour charges
Plumber Fitter(S) 1.17 Each 190.00 222.30
Male worker 1.67 Each 150.00 250.50
(a+b) 1995.24
c. Add Contractor's Profit & Overhead charges 15% 1995.24 299.29
Total (a+b+c) 2294.53
Rate per metre is 2,294.53 ÷ 10 = 229.45
say 229.50
101
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.5 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes conforming to IS:15778,
having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded
fittings including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes &
fittings with one step CPVC solvent cement and testing of joints complete as per direction of
Engineer-in-Charge
102
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 32 mm nominal outer dia pipes
Details of cost for 10 metre
a. MATERIAL:
Chlorinated Polyvinyl - chloride (CPVC) pipe 32 mm outer dia
10.00 Mtr 120.00 1200.00
Add 30% for fittings and wastage etc. 360.00
Cement, sand and grit etc LS 6.20
b. LABOUR:
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.98 Each 170.00 166.60
Male worker (unskilled) 0.98 Each 150.00 147.00
(a+b) 1942.50
c. Add Contractor's Profit & Overhead charges 15% 1942.50 291.38
Total (a+b+c) 2233.88
Rate per metre is 2,233.88 ÷ 10 = 223.39
say 223.40
103
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.6 Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite
Pressure Pipes conforming to IS - 15450, U.V. stabilized with carban black having thermal
stability for hot & cold water supply, capable to withstand temperature up to 80°C including all
special fittings of composite material (engineering plastic blend and brass inserts wherever
required) e.g. elbows, tees, reducers, couplers & connectors etc., with clamps at 1.00 meter
spacing. This includes testing of joints complete of joints complete as per direction of the Engineer-
in-Charge
104
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 32 mm outer dia pipes
Details of cost for 10 metre
a. MATERIAL:
32 mm PE-AL-PE Composite pressure pipe 10.00 Mtr 193.00 1930.00
Add 30% for fittings and wastage etc. 579.00
Cement, sand and grit etc LS 6.20
b. LABOUR:
Plumber Fitter(S) 0.33 Each 190.00 62.70
Helper to plumber or fitter 0.98 Each 170.00 166.60
Male worker (unskilled) 0.98 Each 150.00 147.00
(a+b) 2891.50
c. Add Contractor's Profit & Overhead charges 15% 2891.50 433.73
Total (a+b+c) 3325.23
Rate per metre is 3,325.23 ÷ 10 = 332.52
say 332.50
105
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.7 Providing and fixing of 3 layer PP-R (Poly propylene Random copolymer) pipes conforming
to IS:15801, SDR 7.4, U V stabilized & anti - microbial fusion welded, having thermal stability for
hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings,
i/c fixing the pipe with clamps at 1.00 m spacing. This includes testing of joints complete as per
direction of Engineer-in-Charge.
106
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
107
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.8 Fixing Rotational moulded polyethylene cylindrical vertical water storage tanks
conforming to IS : 12701--1996 including cutting holes through the tank and fixing mild steel tubes
and fittings and providing extra sockets and jam nuts, fixing ball valve etc, including hoisting upto
a height of 5 metres above ground level and placing the tank to the required position etc all
complete as per specification and direction of the Engineer in charge
[i] 2000 litre capacity Double Layer Cylinderical Vertical water storage tanks
Details of cost for one Tank
On the roof of ground floor
a. Materials:
2000 litre capacity Double Layer Cylinderical Vertical water storage tanks
2000 Litre 4.40 8800.00
Lead , paint and yarn LS 6.60
b. Labour charges
Plumber fitter (S) 0.50 Each 190.00 95.00
Helper to plumber/ fitter 0.75 Each 170.00 127.50
Male Worker 5.00 Each 150.00 750.00
(a+b) 9779.10
c. Add Contractor's Profit & Overhead charges 15% of 9779.10 1466.87
Total (a+b+c) 11245.97
say 11246.00
[ ii ] 1000 litre capacity Double Layer Cylinderical Vertical water storage tanks
On the roof of ground floor
Details of cost for one Tank
a. Materials:
1000 litre capacity Double Layer Cylinderical Vertical water storage tanks
1000 Litre 4.40 4400.00
Lead , paint and yarn LS 6.60
b. Labour charges
Plumber fitter (S) 0.50 Each 190.00 95.00
Helper to plumber/ fitter 0.75 Each 170.00 127.50
Male Worker 4.00 Each 150.00 600.00
(a+b) 5229.10
c. Add Contractor's Profit & Overhead charges 15% of 5229.10 784.37
Total (a+b+c) 6013.47
say 6013.50
3.1.9 Extra over item No 3.1.8 for hoisting Rotational moulded polyethylene cylindrical vertical
water storage tanks of the following size for every additional height of 5 metres or part thereof
108
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.10 Cutting holes through existing brick work including making good the same in cement
mortar (1:4) for taking GI/PVC pipes and fittings etc all complete as per specification.
3.1.11 Cutting hole in R.C.C floors and roofs upto 19 cm thick for passing G.I / P.V.C pipes and
fittings etc and repairing the holes after insertion of pipes etc with cement concrete
(1:2:4) including finishing complete so as to make it leak proof.
109
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.1.12 Cutting grooves in pucca floors and walls for taking GI/PVC pipes and making good
the damages as per specification complete.
[ i ] In ground floor
Details of cost for 30 metres
a. Materials
Cement concrete (I:3:6) with metal [Excluding CP&OHC]
0.56 cum 2931.06 1641.39
12mm cement plaster (1:3) [Excluding CP&OHC] 4.57 sqm 96.34 440.27
Cement punning [Excluding CP&OHC] 4.57 sqm 17.73 81.03
b. Labour charges for cutting
Plumber fitter 0.50 Each 190.00 95.00
Helper to plumber 1.00 Each 170.00 170.00
c. Labour charges for redoing
Mason special 1.00 Each 205.00 205.00
Male worker 1.00 Each 150.00 150.00
(a+b+c) 2782.69
d. Add Contractor's Profit & Overhead charges 15% 2782.69 417.40
Total (a+b+c+d) 3200.09
Cost per 1 metre = 3,200.09 ÷ 30 = 106.67
say 106.70
110
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.2 HOUSE SERVICE PIPES
3.2.1 Providing and laying in trenches galvanized mild steel tubes (light grade) conforming to
IS:1239/2004, Part-1 of the following nominal bore and tube fittings including testing as per
specification complete. (Earth work in trenches to be measured and paid for separately)
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm G.I pipes 10.00 metre 72.04 720.4
Tube fittings and wastages 2% 720.4 14.41
White lead,hemp oil etc 1% 720.4 7.2
b. Labour for laying
Plumber Fitter(S) 0.08 Each 190 15.2
Male worker 0.16 Each 150 24
(a+b) 781.21
c. Add Contractor's Profit & Overhead charges 15% 781.21 117.18
Total (a+b+c) 898.39
Rate per metre is 898.39 ÷ 10 = 89.84
say 89.8
111
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm G.I pipes 10.00 metre 128.02 1280.2
Tube fittings and wastages 2% 1280.2 25.6
White lead,hemp oil etc 1% 1280.2 12.8
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190 22.8
Male worker 0.25 Each 150 37.5
(a+b) 1378.9
c. Add Contractor's Profit & Overhead charges 15% 1378.9 206.84
1585.74
Rate per metre is 1,585.74 ÷ 10 = 158.57
Total (a+b+c) say 158.6
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm G.I pipes 10.00 metre 193.89 1938.90
Tube fittings and wastages 2% 1938.90 38.78
White lead,hemp oil etc 1% 1938.90 19.39
b. Labour for laying
Plumber Fitter(S) 0.16 Each 190.00 30.40
Male worker 0.33 Each 150.00 49.50
(a+b) 2076.97
c. Add Contractor's Profit & Overhead charges 15% 2076.97 311.55
2388.52
Rate per metre is 2,388.52 ÷ 10 = 238.85
Total (a+b+c) say 238.90
112
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 3053.36 458.00
Total (a+b+c) 3511.36
Rate per metre is 3,511.36 ÷ 10 = 351.14
say 351.10
3.2.2 Providing and laying in trenches galvanized mild steel tubes (medium grade) conforming to
IS:1239/2004, Part-1 of the following nominal bore and tube fittings including testing as per
specification complete. (Earth work in trenches to be measured and paid for separately)
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm G.I pipes 10.00 metre 79.75 797.50
Tube fittings and wastages 2% 797.50 15.95
White lead,hemp oil etc 1% 797.50 7.98
b. Labour for laying
Plumber Fitter(S) 0.08 Each 190.00 15.20
Male worker 0.16 Each 150.00 24.00
(a+b) 860.63
c. Add Contractor's Profit & Overhead charges 15% 860.63 129.09
Total (a+b+c) 989.72
Rate per metre is 989.72 ÷ 10 = 98.97
say 99.00
113
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iii ] 25mm diameter
Details of cost for 10 metres
a. Materials
25mm G.I pipes 10.00 metre 120.53 1205.30
Tube fittings and wastages 2% 1205.30 24.11
White lead,hemp oil etc 1% 1205.30 12.05
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker 0.25 Each 150.00 37.50
(a+b) 1301.76
c. Add Contractor's Profit & Overhead charges 15% 1301.76 195.26
Total (a+b+c) 1497.02
Rate per metre is 1,497.02 ÷ 10 = 149.70
say 149.70
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm G.I pipes 10.00 metre 155.06 1550.60
Tube fittings and wastages 2% 1550.60 31.01
White lead,hemp oil etc 1% 1550.60 15.51
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker 0.25 Each 150.00 37.50
(a+b) 1657.42
c. Add Contractor's Profit & Overhead charges 15% 1657.42 248.61
1906.03
Rate per metre is 1,906.03 ÷ 10 = 190.60
Total (a+b+c) say 190.60
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm G.I pipes 10.00 metre 244.90 2449.00
Tube fittings and wastages 2% 2449.00 48.98
White lead,hemp oil etc 1% 2449.00 24.49
b. Labour for laying
Plumber Fitter(S) 0.16 Each 190.00 30.40
Male worker 0.33 Each 150.00 49.50
(a+b) 2602.37
114
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 2602.37 390.36
Total (a+b+c) 2992.73
Rate per metre is 2,992.73 ÷ 10 = 299.27
say 299.30
3.2.3 Providing and laying in trenches galvanized mild steel tubes (heavy grade) conforming to
IS:1239/2004, Part-1 of the following nominal bore and tube fittings including testing as per
specification complete. (Earth work in trenches to be measured and paid for separately)
115
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm G.I pipes 10.00 metre 94.36 943.60
Tube fittings and wastages 2% 943.60 18.87
White lead,hemp oil etc 1% 943.60 9.44
b. Labour for laying
Plumber Fitter(S) 0.08 Each 190.00 15.20
Male worker 0.16 Each 150.00 24.00
(a+b) 1011.11
c. Add Contractor's Profit & Overhead charges 15% 1011.11 151.67
Total (a+b+c) 1162.78
Rate per metre is 1,162.78 ÷ 10 = 116.28
say 116.30
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm G.I pipes 10.00 metre 185.11 1851.10
Tube fittings and wastages 2% 1851.10 37.02
White lead,hemp oil etc 1% 1851.10 18.51
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker 0.25 Each 150.00 37.50
(a+b) 1966.93
c. Add Contractor's Profit & Overhead charges 15% 1966.93 295.04
Total (a+b+c) 2261.97
Rate per metre is 2,261.97 ÷ 10 = 226.20
say 226.20
116
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 2248.77 337.32
Total (a+b+c) 2586.09
Rate per metre is 2,586.09 ÷ 10 = 258.61
say 258.60
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm G.I pipes 10.00 metre 296.25 2962.50
Tube fittings and wastages 2% 2962.50 59.25
White lead,hemp oil etc 1% 2962.50 29.63
b. Labour for laying
Plumber Fitter(S) 0.16 Each 190.00 30.40
Male worker 0.33 Each 150.00 49.50
(a+b) 3131.28
c. Add Contractor's Profit & Overhead charges 15% 3131.28 469.69
Total (a+b+c) 3600.97
Rate per metre is 3,600.97 ÷ 10 = 360.10
say 360.10
117
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.2.4 Providing and laying in trenches unplasticised PVC pipes conforming to IS: 4985/2000 of Class IV
(10 kgf/cm²) of the following nominal bore and pipe fittings including testing as per specification
complete. (Earth work in trenches to be measured and paid for separately)
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm dia Class-IV PVC pipes 10.00 metre 11.78 117.80
Pipe fittings and wastages 2% 117.80 2.36
b. Labour for laying
Plumber Fitter(S) 0.08 Each 190.00 15.20
Male worker 0.16 Each 150.00 24.00
(a+b) 159.36
c. Add Contractor's Profit & Overhead charges 15% 159.36 23.90
Total (a+b+c) 183.26
Rate per metre is 183.26 ÷ 10 = 18.33
say 18.30
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm dia Class-IV PVC pipes 10.00 metre 21.89 218.90
Pipe fittings and wastages 2% 218.90 4.38
b. Labour for laying
Plumber Fitter(S) 0.12 Each 190.00 22.80
Male worker 0.25 Each 150.00 37.50
(a+b) 283.58
118
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 283.58 42.54
Total (a+b+c) 326.12
Rate per metre is 326.12 ÷ 10 = 32.61
say 32.60
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia Class-IV PVC pipes 10.00 metre 51.30 513.00
Pipe fittings and wastages 2% 513.00 10.26
b. Labour for laying
Plumber Fitter(S) 0.16 Each 190.00 30.40
Male worker 0.33 Each 150.00 49.50
(a+b) 603.16
c. Add Contractor's Profit & Overhead charges 15% 603.16 90.47
Total (a+b+c) 693.63
Rate per metre is 693.63 ÷ 10 = 69.36
say 69.40
119
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 1286.76 193.01
Total (a+b+c) 1479.77
Rate per metre is 1,479.77 ÷ 10 = 147.98
say 148.00
3.2.5 Providing and laying in trenches unplasticised PVC pipes conforming to IS: 4985/2000 of Class III
(6 kgf/cm²) of the following nominal bore and pipe fittings including testing as per specification
complete. (Earth work in trenches to be measured and paid for separately)
[ ii ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm PVC Class-III pipes 10.00 metre 38.78 387.80
Pipe fittings and wastages 2% 387.80 7.76
b. Labour for laying
Plumber Fitter(S) 0.16 Each 190.00 30.40
Male worker 0.33 Each 150.00 49.50
(a+b) 475.46
c. Add Contractor's Profit & Overhead charges 15% 475.46 71.32
Total (a+b+c) 546.78
Rate per metre is 546.78 ÷ 10 = 54.68
say 54.70
[ iv ] 75mm diameter
Details of cost for 10 metres
a. Materials
75mm PVC Class-III pipes 10.00 metre 87.11 871.10
Pipe fittings and wastages 2% 871.10 17.42
120
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for laying
Plumber Fitter(S) 0.25 Each 190.00 47.50
Male worker 0.66 Each 150.00 99.00
(a+b) 1035.02
c. Add Contractor's Profit & Overhead charges 15% 1035.02 155.25
Total (a+b+c) 1190.27
Rate per metre is 1,190.27 ÷ 10 = 119.03
say 119.00
3.2.6 Providing and laying in trenches unplasticised PVC pipes conforming to IS: 4985/2000 of class II
(4kgf/cm²) of the following nominal bore and pipe fittings including testing as per specification
complete. (Earth work in trenches to be measured and paid for separately)
[ ii ] 75mm dia
Details of cost for 10 metres
a. Materials
75mm PVC Class-II pipes 10.00 metre 61.88 618.80
Pipe fittings and wastages 2% 618.80 12.38
b. Labour for laying
Plumber Fitter(S) 0.25 Each 190.00 47.50
Male worker 0.66 Each 150.00 99.00
(a+b) 777.68
c. Add Contractor's Profit & Overhead charges 15% 777.68 116.65
Total (a+b+c) 894.33
Rate per metre is 894.33 ÷ 10 = 89.43
say 89.40
3.2.7 Providing and laying in trenches PVC pipes conforming to ASTM-D-1785/89 (Schedule-80) of the
following nominal bore and pipe fittings including testing as per specification complete. (Earth work
in trenches to be measured and paid for separately)
121
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 324.19 48.63
Total (a+b+c) 372.82
Rate per metre is 372.82 ÷ 10 = 37.28
say 37.30
[ ii ] 20mm diameter
Details of cost for 10 metres
a. Materials
20mm PVC sch-80 pipes 10.00 metre 37.83 378.30
Pipe fittings and wastages 2% 378.30 7.57
b. Labour for laying
Plumber Fitter (S) 0.08 Each 190.00 15.20
Male worker 0.16 Each 150.00 24.00
(a+b) 425.07
c. Add Contractor's Profit & Overhead charges 15% 425.07 63.76
Total (a+b+c) 488.83
Rate per metre is 488.83 ÷ 10 = 48.88
say 48.90
[ iv ] 32mm diameter
Details of cost for 10 metres
a. Materials
32mm PVC sch-80 pipes 10.00 metre 76.82 768.20
Pipe fittings and wastages 2% 768.20 15.36
b. Labour for laying
Plumber Fitter (S) 0.12 Each 190.00 22.80
Male worker 0.25 Each 150.00 37.50
(a+b) 843.86
c. Add Contractor's Profit & Overhead charges 15% 843.86 126.58
Total (a+b+c) 970.44
Rate per metre is 970.44 ÷ 10 = 97.04
say 97.00
122
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 1029.32 154.40
Total (a+b+c) 1183.72
Rate per metre is 1,183.72 ÷ 10 = 118.37
say 118.40
[ vi ] 50mm diameter
Details of cost for 10 metres
a. Materials
50mm PVC sch-80 pipes 10.00 metre 129.02 1290.20
Pipe fittings and wastages 2% 1290.20 25.80
b. Labour for laying
Plumber Fitter (S) 0.16 Each 190.00 30.40
Male worker 0.33 Each 150.00 49.50
(a+b) 1395.90
c. Add Contractor's Profit & Overhead charges 15% 1395.90 209.39
Total (a+b+c) 1605.29
Rate per metre is 1,605.29 ÷ 10 = 160.53
say 160.50
3.2.8 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes conforming to IS 15778,
having thermal stability for hot & cold water supply including all CPVC plain & brass threaded
fittings. This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching,
refilling & testing of joints complete as per direction of Engineer- in-Charge
124
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ vi ] 50 mm nominal outer dia pipes
Details of cost for 10 metre
a. MATERIAL:
Chlorinated Polyvinyl - chloride (CPVC) pipe 50 mm outer dia
10.00 Mtr 280.00 2800.00
Add 30% for fittings and wastage etc. 840.00
b. LABOUR:
Plumber Fitter(S) 0.16 Each 190.00 30.40
Male worker (unskilled) 0.33 Each 150.00 49.50
Trenching & refilling etc
Male worker (unskilled) 1.32 Each 150.00 198.00
(a+b) 3917.90
c. Add Contractor's Profit & Overhead charges 15% 3917.90 587.69
Total (a+b+c) 4505.59
Rate per metre is 4,505.59 ÷ 10 = 450.56
say 450.60
126
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
LABOUR:
Plumber Fitter(S) 0.08 Each 190.00 15.20
Male worker (unskilled) 0.16 Each 150.00 24.00
Trenching & refilling etc
Male worker (unskilled) 1.32 Each 150.00 198.00
(a+b) 1680.20
c. Add Contractor's Profit & Overhead charges 15% 1680.20 252.03
Total (a+b+c) 1932.23
Rate per metre is 1,932.23 ÷ 10 = 193.22
say 193.20
127
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 4307.90 646.19
Total (a+b+c) 4954.09
Rate per metre is 4,954.09 ÷ 10 = 495.41
say 495.40
3.2.10 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to
IS:15801 U V stabilized & anti - microbial fusion welded, having thermal stability for hot & cold
water supply, including all PP-R plain & brass threaded polypropylene random fittings, including
trenching ,refilling & testing of joints complete as per direction of Engineer-in-Charge
128
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% 887.20 133.08
Total (a+b+c) 1020.28
Rate per metre is 1,020.28 ÷ 10 = 102.03
say 102.00
129
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
130
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ix ] PN - 16 Pipe, 90 mm OD (SDR -7.4)
Details of cost for 10 metre
a. MATERIAL:
Poly propylene- Random - Co - Polymer (PPR)
pipes SDR 7.4 - 90 mm Outer dia 10.00 Mtr 1020.00 10200.00
Add 30% for fittings and wastage etc. 3060.00
b. LABOUR:
Plumber Fitter(S) 0.37 Each 190.00 70.30
Male worker (unskilled) 0.97 Each 150.00 145.50
Trenching & refilling etc
Male worker (unskilled) 1.60 Each 150.00 240.00
(a+b) 13715.80
c. Add Contractor's Profit & Overhead charges 15% 13715.80 2057.37
Total (a+b+c) 15773.17
Rate per metre is 15,773.17 ÷ 10 = 1577.32
say 1577.30
131
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.2.11 Making connection of galvanised mild steel distribution branch with galvanised mild steel
main 25 mm to 40 mm nominal bore by providing and fixing tee including cutting and
threading the pipes complete
3.2.12 Making connection of galvanised mild steel distribution branch with galvanised mild steel
main 50 mm to 80 mm nominal bore by providing and fixing tee including cutting and
threading the pipes complete
132
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.2.13 Fixing ferrule conforming to IS:2692-1978 of the following nominal bore including drilling the
water main (Cast Iron pipes or pipes with the metal straps) as per Specification complete.
Materials
20mm dia G.M ferrule cock as per IS:2692-
1 Each 726.00 726.00
1978
25mm dia G.M ferrule cock as per IS:2692-
1 Each 1327.00 1327.00
1979
[ ii ] 32mm to 50mm bore
Details for one ferrule
a. Materials
32mm dia G.M ferrule cock as per IS:2692-1978 1 Each 1500.00 1500.00
b. Labour for laying
Plumber fitter (S) 0.50 Each 190.00 95.00
Helper to plumber/ fitter 1.00 Each 170.00 170.00
Male Worker 1.00 Each 150.00 150.00
Jointing materials 17% of 415.00 70.55
(a+b) 1985.55
c. Add Contractor's Profit & Overhead charges 15% of 1985.55 297.83
Total (a+b+c) Rate per each 2283.38
say 2283.40
Materials
40mm dia G.M ferrule cock as per IS:2692-1978
1 Each 2000.00 2000.00
50mm dia G.M ferrule cock as per IS:2692-1978
1 Each 2500.00 2500.00
3.2.14 Fixing of Brass Screw-down Bib Cocks (Taps) polished bright conforming to IS:781-1995 of
the following nominal sizes as per specification complete.
[i] 15mm diameter
Details for 10nos of Brass Screw Down Bib Cocks
a. Materials
15mm dia Brass Screw-down Bib Cock = 10 nos
10 Each 165.00 1650.00
b. Labour for laying
Plumber fitter (S) 0.33 Each 190.00 62.70
Helper to plumber/ fitter 0.33 Each 170.00 56.10
Jointing materials 2% of 118.80 2.38
(a+b) 1771.18
c. Add Contractor's Profit & Overhead charges 15% of 1771.18 265.68
Total (a+b+c) 2036.86
Rate per each is 2,036.86 ÷ 10 = 203.69
say 203.70
133
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.2.15 Fixing of Brass Push Cock of following nominal sizes as per specification complete.
Materials
[ ii ] 20mm dia Brass Push Cock 1 Each 210.00 210.00
3.2.16 Fixing of Brass Screw-down Stop Cocks conforming to IS:781-1995 of the following nominal
sizes as per specification complete.
3.2.17 Fixing of Brass or Gun Metal Full Way Valve conforming to IS:781-1995 of the following
nominal sizes with wheel as per specification complete.
[ iv ] 32mm diameter
Details for 10 nos of Brass or Gun Metal Full Way Valves
a. Materials
32mm dia Brass or Gun Metal Full Way Valve = 10 nos
10 Each 820.00 8200.00
b. Labour for laying
Plumber fitter (S) 0.75 Each 190.00 142.50
Helper to plumber/ fitter 0.75 Each 170.00 127.50
Jointing materials 2% of 270.00 5.40
(a+b) 8475.40
c. Add Contractor's Profit & Overhead charges 15% of 8475.40 1271.31
Total (a+b+c) 9746.71
Rate per each is 9,746.71 ÷ 10 = 974.67
say 974.70
135
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ vii ] 65mm diameter
Details for 10 nos of Brass or Gun Metal Full Way Valves
a. Materials
65mm dia Brass or Gun Metal Full Way Valve = 10 nos
10 Each 2750.00 27500.00
b. Labour for laying
Plumber fitter (S) 1.00 Each 190.00 190.00
Helper to plumber/ fitter 1.00 Each 170.00 170.00
Jointing materials 2% of 360.00 7.20
(a+b) 27867.20
c. Add Contractor's Profit & Overhead charges 15% of 27867.20 4180.08
Total (a+b+c) 32047.28
Rate per each is 32,047.28 ÷ 10 = 3204.73
say 3204.70
3.2.18 Fixing of Brass Ball Valve (Horizontal plunger type) conforming to IS 1703-1977 as per
specification complete
[ A ] High pressure/Low pressure with copper or PVC floats of the following nominal bore
[ ii ] 20mm dia nominal bore brass Ball Valve teflon brass ball & spindle
1 Each 360.00 360.00
[ iii ] 25mm dia nominal bore brass Ball Valve teflon brass ball & spindle
1 Each 480.00 480.00
[ iv ] 32mm dia nominal bore
Details for 1 No of Copper or PVC Ball Valve (Horizontal plunger type)
a. Materials
32mm dia nominal bore brass Ball Valve teflon brass ball & spindle
(Horizontal plunger type) = 1 No 1 Each 820.00 820.00
b. Labour for laying
Plumber fitter (S) 0.25 Each 190.00 47.50
Helper to plumber/fitter 0.25 Each 170.00 42.50
Jointing materials 2% of 90.00 1.80
(a+b) 911.80
c. Add Contractor's Profit & Overhead charges 15% of 911.80 136.77
Total (a+b+c) Rate per each number 1048.57
say 1048.60
136
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[v] 40mm dia nominal bore brass Ball Valve teflon brass ball & spindle
1 Each 1040.00 1040.00
[ vi ] 50mm dia nominal bore brass Ball Valve teflon brass ball & spindle
1 Each 1620.00 1620.00
3.2.19 Fixing of Gun Metal Check or Non-return Valve Class - I conforming to IS : 5312 (Part-I) -
2004 of the following nominal bore as per specification complete
137
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.3 PLUMBING SOIL WASTE, VENTILATING PIPES & FITTINGS
3.3.1 Fixing Sand Cast Iron soil waste ventilating pipes and fittings conforming to IS: 1729–2002
or its latest revision/Centrifugally cast (spun) iron socket & spigot (S&S) pipe as per IS: 3989, to
walls with nails, bobbins and wooden plugs as per specification or laying in trenches including
earthwork in excavation in all kinds of soil and refilling of trenches as per specification. (Jointing to
be measured and paid for separately)
B Centrifugally cast (spun) iron socket & spigot (S&S) pipe as per IS: 3989
Details of cost for 16.92 metres [(1.75mx10)-
(9x0.065m) = 16.915 m say 16.92 m]
a. Materials
C.C.I. (spun) socketed soil, waste and vent pipe
1.80 metres long: 75 mm dia 10.50 Each 985.00 10342.50
Scaffolding LS 120.29
Carriage of materials LS 60.17
b. Labour charges
Plumber fitter 0.35 Each 190.00 66.50
Helper to plumber 0.17 Each 170.00 28.90
Male worker 0.70 Each 150.00 105.00
(a+b) 10723.36
c. Add Contractor's Profit & Overhead charges 15% of 10723.36 1608.50
Total (a+b+c) 12331.86
Rate per metre = 12,331.86 ÷ 16.92 = 728.83
say 728.80
[ ii ] 100mm diameter
A Sand cast iron S&S pipe as per IS: 1729
Details of cost for 17.37 metres [(1.8mx10)-
(9x0.07m) = 17.37 m]
a. Materials
S.C.I. soil, waste and vent single socketed pipe
10.50 Each 990.00 10395.00
1.80 metres long: 100 mm dia
Scaffolding LS 120.29
Carriage of materials LS 80.19
138
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber fitter 0.42 Each 190.00 79.80
Helper to plumber 0.21 Each 170.00 35.70
Male worker 0.83 Each 150.00 124.50
(a+b) 10835.48
c. Add Contractor's Profit & Overhead charges 15% of 10835.48 1625.32
Total (a+b+c) 12460.80
Rate per metre = 12,460.80 ÷ 17.37 = 717.37
say 717.40
B Centrifugally cast (spun) iron socket & spigot (S&S) pipe as per IS: 3989
Details of cost for 16.87 metres [(1.75mx10)-
(9x0.07m) = 16.87m]
a. Materials
C.C.I. (spun) socketed soil, waste and vent pipe
1.80 metres long: 100 mm dia 10.50 Each 1130.00 11865.00
Scaffolding LS 120.29
Carriage of materials LS 80.19
b. Labour charges
Plumber fitter 0.42 Each 190.00 79.80
Helper to plumber 0.21 Each 170.00 35.70
Male worker 0.83 Each 150.00 124.50
(a+b) 12305.48
c. Add Contractor's Profit & Overhead charges 15% of 12305.48 1845.82
Total (a+b+c) 14151.30
Rate per metre = 14,151.30 ÷ 16.87 = 838.84
say 838.80
3.3.2 Providing and fixing on wall face unplasticised Rigid PVC soil, waste and rain water pipes
conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS: 5382, leaving
10 mm gap for thermal expansion, (i) Single socketed pipes
139
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] 110mm diameter
Data for 10metres of U-PVC SWR pipes
a. Materials
110mm dia UPVC single socketed pipe (working
pressure 4 kg / cm²) 6.00 pair 129.00 774.00
110mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 1 Each 20.00 20.00
Adhesive etc LS 12.01
Scaffolding LS 27.70
b. Labour charges
Plumber fitter 0.23 Each 190.00 43.70
Helper to plumber 0.11 Each 170.00 18.70
Male worker 0.45 Each 150.00 67.50
(a+b) 963.61
c. Add Contractor's Profit & Overhead charges 15% of 963.61 144.54
Total (a+b+c) 1108.15
Rate per metre = 1,108.15 ÷ 6.00 = 184.69
say 184.70
3.3.3 Providing and fixing on wall face unplasticised-PVC moulded fittings / accessories for unplasticised
Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring
conforming to IS : 5382, leaving 10 mm gap for thermal expansion
Coupler
[i] 75mm
Details of cost for 1coupler
a. Materials
UPVC coupler for UPVC drainage pipes 75mm
1 Each 34.00 34.00
75mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 2 Each 16.00 32.00
Adhesive etc LS 4.07
b. Carriage and fixing charges LS 13.95
(a+b) 84.02
c. Add Contractor's Profit & Overhead charges 15% of 84.02 12.60
Cost per each 96.62
Total (a+b+c) say 96.60
110mm
Details of cost for 1coupler
a. Materials
UPVC coupler for UPVC drainage pipes 110mm
1 Each 52.00 52.00
110mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 2 Each 20.00 40.00
Adhesive etc LS 4.07
b. Carriage and fixing charges LS 16.08
(a+b) 112.15
c. Add Contractor's Profit & Overhead charges 15% of 112.15 16.82
Total (a+b+c) Cost per each 128.97
say 129.00
140
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Single pushfit Coupler
[ iii ] 75mm
Details of cost for 1coupler
a. Materials
UPVC pushfit coupler (single) 75 mm thick 1 Each 50.00 50.00
75mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 2 Each 16.00 32.00
Adhesive etc LS 4.07
b. Carriage and fixing charges LS 13.95
100.02
c. Add Contractor's Profit & Overhead charges 15% of 100.02 15.00
Total (a+b+c) Cost per each 115.02
say 115.00
[ iv ] 110mm
Details of cost for 1coupler
a. Materials
UPVC pushfit coupler (single) 110 mm thick 1 Each 81.00 81.00
110mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 2 Each 20.00 40.00
Adhesive etc LS 4.07
b. Carriage and fixing charges LS 16.08
(a+b) 141.15
c. Add Contractor's Profit & Overhead charges 15% of 141.15 21.17
Total (a+b+c) Cost per each 162.32
say 162.30
[ v ] 75x75x75 mm
Details of cost for 1 tee
a. Materials
UPVC single equal Tee (with door) 75x75x75 mm 1 Each 115.00 115.00
75mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 3 Each 16.00 48.00
b. Adhesive, Carriage of material rubber washer etc. including
LS fixing charges 16.03
(a+b) 179.03
c. Add Contractor's Profit & Overhead charges 15% of 179.03 26.85
Total (a+b+c) Cost per each 205.88
say 205.90
[ vi ] 110x110x110 mm
Details of cost for 1 tee
a. Materials
UPVC single equal Tee (with door) 110x110x110 mm 1 Each 180.00 180.00
110mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 3 Each 20.00 60.00
b. Adhesive, Carriage of material rubber washer etc. including
LS fixing charges 20.07
(a+b) 260.07
c. Add Contractor's Profit & Overhead charges 15% of 260.07 39.01
Total (a+b+c) Cost per each 299.08
say 299.10
141
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Single tee without door
[ vii ] 75x75x75 mm
Details of cost for 1 tee
a. Materials
UPVC single equal Tee (without door) 75x75x75 mm 1 Each 95.00 95.00
75mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 3 Each 16.00 48.00
b. Adhesive, Carriage of material rubber washer etc. including
LS fixing charges 16.03
(a+b) 159.03
c. Add Contractor's Profit & Overhead charges 15% of 159.03 23.85
Total (a+b+c) Cost per each 182.88
say 182.90
[ viii ] 110x110x110 mm
Details of cost for 1 tee
a. Materials
UPVC single equal Tee (without door) 110x110x110 mm 1 Each 128.00 128.00
110mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 3 Each 20.00 60.00
b. Adhesive, Carriage of material rubber washer etc. including
LS fixing charges 20.07
208.07
c. Add Contractor's Profit & Overhead charges 15% of 208.07 31.21
Total (a+b+c) Cost per each 239.28
say 239.30
Bend 87.5°
142
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Shoe (Plain)
[ xi ] 75 mm dia Shoe
Details of cost for 1 shoe
a. Materials
UPVC plain shoe 75 mm bend 1 Each 107.00 107.00
75mm dia UPVC pipe (working pressure 4 kg /
cm²) Rubber (Seal) Ring 1 Each 16.00 16.00
Adhesive etc LS 4.07
b. Carriage and fixing charges LS 13.95
(a+b) 141.02
c. Add Contractor's Profit & Overhead charges 15% of 141.02 21.15
Total (a+b+c) Cost per each 162.17
say 162.20
3.3.4 Providing cement joints conforming to IS:3114-1994 to sand cast iron/centrifugally cast (spun) iron
spigot and socket, soil waste ventilating pipes and fittings with spun yarn soaked in cement slurry
or bitumen and cement mortar (1:1) as per specification.
In Ground Floor
[i] 75mm diameter
Details of cost for 17 joints
a. Materials
Spun Yarn 1.09 Kg 50.00 54.50
Cement 0.08 Qntl 714.00 57.12
Sand, Bitumen etc LS 3.30
b. Labour charges
Plumber fitter 0.25 Each 190.00 47.50
Helper to plumber 0.25 Each 170.00 42.50
Male worker 0.16 Each 150.00 24.00
Curing & scaffolding etc 10% of 114.00 11.40
(a+b) 240.32
c. Add Contractor's Profit & Overhead charges 15% of 240.32 36.05
Total (a+b+c) 276.37
Rate per joint = 276.37 ÷ 17 = 16.26
say 16.30
[ ii ] 100mm diameter
Details of cost for 17 joints
a. Materials
Spun Yarn 2.18 Kg 50.00 109.00
Cement 0.12 Qntl 714.00 85.68
Sand, Bitumen etc LS 6.60
143
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber fitter 0.50 Each 190.00 95.00
Helper to plumber 0.50 Each 170.00 85.00
Male worker 0.50 Each 150.00 75.00
Curing & scaffolding etc 10% of 255.00 25.50
(a+b) 481.78
c. Add Contractor's Profit & Overhead charges 15% of 481.78 72.27
Total (a+b+c) 554.05
Rate per joint = 554.05 ÷ 17 = 32.59
say 32.60
3.3.5 Providing lead caulked joints conforming to IS:3114-1994 to Sand Cast Iron/centrifugally
cast (spun) iron spigot and socket, soil, waste, ventilating pipes and fittings including
testing the joints as per specification.
In Ground Floor
[i] 50mm diameter
Details of cost for one joint
a. Materials
Pig lead 0.77 Kg 150.00 115.50
spun yarn 0.06 Kg 50.00 3.00
Kerosene oil, fuel and other sundries LS 10.07
Carriage of materials LS 2.13
b. Labour charges
Plumber fitter 0.04 Each 190.00 7.60
Helper to plumber 0.05 Each 170.00 8.50
Male worker 0.05 Each 150.00 7.50
Scaffolding etc 10% of 23.60 2.36
(a+b) 156.66
c. Add Contractor's Profit & Overhead charges 15% of 156.66 23.50
Total (a+b+c) 180.16
say 180.20
[ ii ] 75mm diameter
Details of cost for one joint
a. Materials
Pig lead 0.88 Kg 150.00 132.00
spun yarn 0.09 Kg 50.00 4.50
Kerosene oil, fuel and other sundries LS 16.08
Carriage of materials LS 2.13
b. Labour charges
Plumber fitter 0.05 Each 190.00 9.50
Helper to plumber 0.05 Each 170.00 8.50
Male worker 0.09 Each 150.00 13.50
Scaffolding etc 10% of 31.50 3.15
(a+b) 189.36
c. Add Contractor's Profit & Overhead charges 15% of 189.36 28.40
Total (a+b+c) 217.76
say 217.80
3.3.6 Cutting holes through the brick or laterite masonry wall for taking Sand Cast Iron
(SCI) /centrifugally cast (spun) iron pipes and mending good the damages.
145
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.3.8 Cutting of R.C.C chajja for taking S.C.I/PVC/C.C.I pipes including mending good the
damages etc all complete.
3.3.9 Cutting by chiselling in brick masonry wall for fixing sand cast iron pipes of following
nominal size and fittings including making good the same with brick work in cement mortar (1:3)
including plastering all complete as per specification.
[ ii ] 100mm diameter
Details of cost for 1.828 metre
a. Materials
K.B. Bricks having crushing strength not less 21 1000 4950.00 103.95
than 75kg/cm²
Cement 0.13 Qntl 714.00 92.82
Sand 1.98
b. Labour for redoing
Mason 0.25 Each 190.00 47.50
Man Mulia 0.50 Each 150.00 75.00
(a+b) 321.25
c. Add Contractor's Profit & Overhead charges 15% of 321.25 48.19
Total (a+b+c) 369.44
Rate per metre = 369.44 ÷ 1.828 = 202.10
say 202.10
146
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4 SANITARY INSTALLATIONS
3.4.1 Fixing water closet, squatting pan (Indian type W.C pan) conforming to IS 2556 : Part 3-
2004 duly embedded in cement concrete (1:4:8) using hard granite metal 4cm nominal size all
complete as per specification
[i] White Glazed vitreous china Squatting Pan - Long pattern size 580 mm
Details of cost for one number
a. Materials
580mm size vitreous china water closet squatting pan (Indian type)
squatting pan 1 Each 340.00 340.00
Cement for 0.12cum cement concrete 0.206 Qntl 714.00 147.08
Sand 0.058 Cum 46.00 2.67
Metal 0.115 Cum 682.00 78.43
b. Labour charges
Plumber fitter/Mason 0.50 Each 190.00 95.00
Male worker (unskilled) 0.50 Each 150.00 75.00
(a+b) 738.18
c. Add Contractor's Profit & Overhead charges 15% of 738.18 110.73
Total (a+b+c) Cost per each 848.91
say 848.90
[ ii ] 580 mm x 440mm size white glazed Vitreous China Orissa Pattern squatting pan 1525.00
[ iii ] 500 mm x 440mm size white glazed Vitreous China Orissa Pattern squatting pan 1250.00
[ iv ] 580 mm x 440mm size coloured glazed Vitreous China Orissa Pattern squatting pan 2365.00
[v] Salem Stainless steel AISI - 304 (18/8) Orrisa pattern W.C. pan 3630.00
3.4.2 Fixing in cement mortar (1:3) a pair of white vitreous china 250mm x 130mm x 30mm foot
rest for squatting pan water closet as per specification
Fixing 100mm size ‘P’ or ‘S’ trap (with horn or without horn) for water closet squatting pan
including jointing the trap with pan in cement mortar (1:1) as per specification.
147
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.4 Fixing Wash Down Water Closet (European type W.C pan) with integral ‘S’ or ‘P’ trap
conforming to IS 2556 : Part 8-2004, to the floor with wooden plug and chromium plated screws
including jointing the trap with soil pipe in cement mortar (1:1) etc all complete as per
specification. (Seat and cover to be measured and paid for separately)
3.4.5 Fixing plastic seat and cover for wash down water closet with chromium plated brass hinges
and rubber buffers all complete as per specification.
148
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
(Considering 1 fitter and 1 beldar can fix 8 cisterns in one day)
Plumber fitter/Mason 0.125 Each 190.00 23.75
Male worker (unskilled) 0.125 Each 150.00 18.75
(a+b) 1245.25
c. Add Contractor's Profit & Overhead charges 15% of 1245.25 186.79
1432.04
Total (a+b+c) Cost per each say 1432.00
3.4.7 Providing and fixing controlled flush, low level cistern made of vitreous china conforming
to IS 774-2004 with all fittings complete.
149
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.8 Fixing bowl pattern urinal conforming to IS 2556 : Part 6-1996 including connecting the urinal of
430x260x350 mm or 340x410x265 mm sizes respectively with waste pipe by means of white lead
mixed with chopped hemp etc all complete as per specification.
[i] Vitreous China - Flat Back Urinal of 430mm x260mm x350mm size
Details of cost for one number
a. Materials
Vitreous China - Flat Back Urinal of 430mm x260mm x350mm size
1 Each 805.00 805.00
Carriage of materials L.S 14.14
b. Labour charges
Plumber fitter 0.38 Each 190.00 72.20
Male worker (unskilled) 0.38 Each 150.00 57.00
(a+b) 948.34
c. Add Contractor's Profit & Overhead charges 15% of 948.34 142.25
1090.59
Total (a+b+c) Cost per each say 1090.60
[ ii ] White vitreous china clay half stall urinal flat back 580x380x350 mm 2845.00
[ iii ]Angle back 450x375x350 mm with waste fittings as per IS : 2556 1440.00
[ iv ] White Vetrious China Waterless Urinal 13208.00
[v] White vitreous china battery based/AC infrared sensor operated urinal
of approx. size 610 x 390 x 370 mm 12592.75
[ vi ] 15mm dia CP urinal spreader 250.00
3.4.9 Fixing glazed earthenware squatting plate of size 600mm x 350mm conforming to IS:2556-
Part-6-1995 with integral longitudinal flushing pipe including embedding the plate in 25mm cement
mortar (1:8) laid over 150mm cement concrete (1:4:8) using 40mm hard granite metal all
complete as per specification.
3.4.10 Fixing PVC automatic flushing cistern including cutting holes and making good the same all
complete as per specification.
150
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Male worker (unskilled) 0.68 Each 150.00 102.00
(a+b) 761.20
c. Add Contractor's Profit & Overhead charges 15% of 761.20 114.18
875.38
Total (a+b+c) Cost per each say 875.40
[ ii ] P.V.C. automatic flushing cistern 10 litre 530.00
3.4.11 Fixing wash basins with hole for pillar taps conforming to IS 2556 : Part 4-2004 with Cast
Iron or M S brackets painted white including cutting holes in walls and making good the damages
etc all complete as per specification.
3.4.12 Fixing pedestal for wash basin complete recessed at the back for the reception of pipes and
fittings
151
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.13 Fixing wash kitchen sink conforming to IS 2556 : Part 5-1994 with Cast Iron or M S brackets
painted white including cutting holes in walls and making good the damages etc all complete as
per specification.
3.4.14 Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS 13983 with C.I
brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and
making good the walls wherever required
A Stainless steel kitchen sink - with drain
board 510x1040 mm bowl depth 250 mm
[ ii ] Stainless steel kitchen sink - with drain board 510x1040 mm bowl depth 225 mm 4900.00
[ iii ] Stainless steel kitchen sink - with drain board 510x1040 mm bowl depth 200 mm 4200.00
[ iv ] Stainless steel kitchen sink - with drain board 510x1040 mm bowl depth 178 mm 2900.00
152
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
B Stainless steel kitchen sink - without drain board 610x510
mm bowl depth 200 mm
Details of cost for one number
a. Materials
Stainless steel kitchen sink - without drain
board 610x510 mm bowl depth 200 mm 1 Each 2950.00 2950.00
C I or M S bracket 1 Pair 53.00 53.00
Cement, sand and grit etc L.S 20.14
Painting of brackets etc L.S 40.10
Carriage of materials L.S 20.14
b. Labour charges for fixing sink
Plumber fitter 0.22 Each 190.00 41.80
Mason 0.33 Each 190.00 62.70
Male worker (unskilled) 0.56 Each 150.00 84.00
(a+b) 3271.88
c. Add Contractor's Profit & Overhead charges 15% of 3271.88 490.78
Total (a+b+c) Cost per each 3762.66
say 3762.70
[ ii ] Stainless steel kitchen sink - without drain board 610x510 mm bowl depth 200 mm 2950.00
[ iii ] Stainless steel kitchen sink - without drain board 610x460 mm bowl depth 200 mm 2750.00
[ iv ] Stainless steel kitchen sink - with drain board 470x420 mm bowl depth 178 mm 2050.00
3.4.15 Providing and fixing draining board with C.I. brackets including painting of brackets,cutting and
making good the walls wherever required
White glazed fire clay draining board of size 600x450x25 mm
Details of cost for one number
a. Materials
White glazed fire clay draining board of size 600x450x25 mm
1 Each 525.00 525.00
C I or M S bracket 1 Pair 53.00 53.00
Cement, sand and grit etc L.S 19.95
Painting of brackets etc L.S 38.74
Carriage of materials L.S 11.62
b. Labour charges for fixing sink
Plumber fitter 0.06 Each 190.00 11.40
Mason 0.17 Each 190.00 32.30
Male worker (unskilled) 0.22 Each 150.00 33.00
(a+b) 725.01
c. Add Contractor's Profit & Overhead charges 15% of 725.01 108.75
Total (a+b+c) Cost per each 833.76
say 833.80
3.4.16 Fixing one piece construction sheet steel bath tub size 1700mm x 700mm x 440mm
white vitreous enamelled sheet steel inside and painted with enamelled paint of required
shade on outside including integral overflow and with detachable feet all complete as per
specification.
[i] Overall white vitreous enamelled sheet steel bath tub of 1700mmx700mmx440mm size
Details of cost for one number
a. Materials
White vitreous enamelled sheet steel bath tub with a pair of detachable feet
1 Each 11300.00 11300.00
153
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Plumber fitter 0.50 Each 190.00 95.00
Male worker (unskilled) 1.00 Each 150.00 150.00
(a+b) 11545.00
c. Add Contractor's Profit & Overhead charges 15% of 11545.00 1731.75
Total (a+b+c) Cost per each 13276.75
say 13276.80
3.4.17 Fixing Cast (Spun) Iron floor traps of the following nominal diameter of outlet of self cleaning
design with sand cast iron screwed down or hinged grating with or without vent arm complete
including cost of cutting and making good the walls and floors all complete as per specification.
154
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% of 618.21 92.73
Total (a+b+c) Cost per each 710.94
say 710.90
3.4.18 Fixing Chromium Plated brass chain 50cm long and rubber plug for sink or wash basin
complete as per specification
3.4.19 Fixing Chromium Plated brass trap of the following nominal diameter for wash basin and sink
as per specification
3.4.20 Fixing PVC waste pipe of following nominal diameter for wash basin or sink including brass check
nut complete as per specification
[ ii ] Semi Rigid PVC waste pipe for sink and wash basin 40 mm dia with length
not less than 700 mm with PVC waste fittings 27.00
[ iii ] Flexible (coil shaped) PVC waste pipe for sink and wash basin 32 mm dia with length
not less than 700 mm with PVC waste fittings 26.00
[ iv ] Flexible (coil shaped) PVC waste pipe for sink and wash basin 40 mm dia with length
not less than 700 mm with PVC waste fittings 28.00
3.4.21 Fixing pillar taps capstan head screw down high pressure lettered ‘Hot’ and ‘Cold’ with long
screws, shanks and back nuts of the following nominal bore as per specification
3.4.22 Fixing 15mm dia PVC inlet connection pipe and making connection with pillar cocks and
supply mains for wash basin complete as per specification
[ i i] Unplasticised P.V.C. connection pipe with brass union 30 cm long 20 mm bore 33.00
[i] Unplasticised P.V.C. connection pipe with brass union 45 cm long 15 mm bore 33.00
[i] Unplasticised P.V.C. connection pipe with brass union 45 cm long 20 mm bore 43.00
156
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.23 Fixing Chromium Plated brass waste of the following nominal diameter for wash basin and sink
as per specification
3.4.24 Fixing Chromium Plated Brass Shower rose with 15mm or 20mm inlet including polishing all
complete as per specification.
3.4.25 Fixing standard size Chromium Plated brass or glazed porcelain Toilet paper holder fixed
to woden plugs with Chromium Plated brass screws complete as per specification.
157
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.26 Fixing 600mm x 450mm bevelled edge mirror of superior glass mounted on 6mm thick A.C
sheet or plywood sheet and fixed to wooden plugs with chromium plated brass screws and
washers complete as per specification.
158
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] Oval shape 450x350 mm (outer dimensions)
Details of cost for one number
a. Materials
Oval shape 450x350 mm (outer dimensions) Mirror with Plastic moulded frame
1 Each 300.00 300.00
Hard board 6 mm thick 0.17 Sqm 170.00 28.90
25mm CP screws 4 100 nos 112.00 4.48
Rawl plug 50 mm (designation 10 nos) 4 Each 10.00 40.00
Cement,sand and chips & carriage of materials L.S 8.33
b. Labour charges
Carpenter 0.33 Each 190.00 62.70
Male worker 0.33 Each 150.00 49.50
(a+b) 493.91
c. Add Contractor's Profit & Overhead charges 15% of 493.91 74.09
Total (a+b+c) Cost per each 568.00
say 568.00
3.4.27 Fixing standard sized glass-shelf with Chromium Plated brass brackets and guard rails
complete, fixed to woden plugs with Chromium Plated brass screws as per specification.
159
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.28 Fixing standard sized Chromium Plated brass towel rail complete with Chromium Plated
brass brackets fixed to wooden plugs with Chromium Plated brass screws, complete as per
specification.
3.4.29 Fixing standard sized Chromium Plated brass towel ring fixed to wooden plugs with Chromium
Plated brass screws, complete as per specification.
3.4.30 Fixing (a) Liquid Soap Container – Glass container or Plastic container with Chromium
Plated brass lid and brackets fixed to wooden plugs with Chromium Plated brass screws or (b)
Chromium Plated brass soap dish complete with Chromium Plated brass brackets fixed to
wooden plugs with Chromium Plated brass screws or (c) white glazed tooth brush holder fixed
to wooden plugs with Chromium Plated brass screws as per specification.
160
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.4.31 Fixing glazed earthenware half round channel (plain or with stop end) with necessary cement
concrete and finishing with white cement etc all complete as per specification
161
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.5 PAINTING
3.5.2 Painting 2 coat with any approved paint on new wood work/iron work all complete as per
specification.
3.5.3 Coaltaring 1 coat with Coal tar paint all complete as per specification.
3.5.4 Painting two coats with white enamel paint over one coat of priming with red oxide zinc
chrome primer on the external surface of new galvanised mild steel tubes and fittings of
following nominal diameters to give an even shade including preparing the surface and clearing the
surface of all all dirts, dusts and foreign matter as per specification.
In ground floor
[ i ] 15mm to 20mm dia
a. Materials
Details of cost for 10 metres (Area=0.85 sqm)
3.5.5 Painting two coats with ready mixed bituminous black anticorrosive paint over a priming coat of
red oxide zinc chrome primer on the external surface of new sand cast iron soil, waste, vent
pipe and fittings of following nominal diameters to give an even shade including preparing the
surface and cleaning of all dirt, dust and other foreign matter all complete as per specification.
In ground floor
[i] 50mm diameter
Details of cost for 10 metres
(area = π x 0.06m x 10m =1.89 sqm)
a. Materials
Primer (red oxide zinc chrome)
@ 0.54 ltr per 10 sqm 0.10 Litre 118.00 11.80
Bituminous black anticorrosive paint interior
@ 1.00 ltr per 10 sqm 0.19 Litre 85.00 16.15
Add extra due to restricted surface area 5% of 27.95 1.40
b. Labour charges
Rate same as item No 3.5.1 and 3.5.2 [Excluding CP,OHC& sundries]
1.89 sqm 64.38 121.68
163
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
(a+b) 151.03
c. Add Contractor's Profit & Overhead charges 15% of 151.03 22.65
Total (a+b+c) 173.68
Cost per metre = 173.68 ÷ 10.00 = 17.37
say 17.40
[ ii ] 100mm diameter
Details of cost for 10 mtrs
(area = π x 0.11m x 10m =3.45 sqm)
a. Materials
Primer (red oxide zinc chrome)
@ 0.54 ltr per 10 sqm 0.19 Litre 118.00 22.42
Bituminous black anticorrosive paint interior
@ 1.00 ltr per 10 sqm 0.345 Litre 85.00 29.33
Add extra due to restricted surface area 5% of 51.75 2.59
b. Labour charges
Rate same as item No 3.5.1 and 3.5.2 [Excluding CP,OHC& sundries]
3.45 sqm 64.38 222.11
276.45
c. Add Contractor's Profit & Overhead charges 15% of 276.45 41.47
Total (a+b+c) 317.92
Cost per metre = 317.92 ÷ 10.00 = 31.79
say 31.80
3.5.6 Painting one coat to inside surface of H.C.I pipes and fittings of following nominal
diameters with coal tar paint to give an even shade including cleaning of all dirt, dust and other
foreign matter as per specification.
164
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.6 DRAINAGE
3.6.1 Providing and fixing square-mouth S.W. gully trap class SP-1 complete with C.I.grating brick
masonry chamber with water tight C.I. cover with frame of 300x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not less than 2.70 kg as per standard design
[i] 100mm x 100mm size Square Mouth Trap P type
Details of cost for one Gully Trap
a. P.H. Materials
100mm x 100mm size SW Gully Trap P type 1 Each 70.00 70.00
C.I grating 100mm x 100mm 1 Each 15.00 15.00
C.I. cover and frame 300x300 mm inside 1 Each 280.00 280.00
Carriage of materials LS 6.70
b. Civil material & Labour charges
Cement concrete (1:4:8) using 40mm size hard granite metal [Excluding CP&OHC]
Bed = 0.68 x 0.68 x 0.10m = 0.046
Around trap = 0.30 x 0.30 x 0.675 = 0.061
Deduct -
0.345/3x[0.09+0.01+(0.09x0.01)/2] = 0.015
3.14/4x(0.124)²x0.47 = 0.006 cum 0.006
0.086 Cum 2524.08 217.07
Brick work with K.B bricks of 250mm x 120mm x 80mm having crushing
strength not less than 75kg/cm² in cement mortar (1:6)[Excluding CP&OHC]
1.66x0.115x0.675 m = 0.129 cum 0.129 Cum 2940.44 379.32
Cement concrete 1:2:4 [Excluding CP&OHC, sundries]
1.66x0.115x0.04 m = 0.008 cum 0.008 Cum 4047.02 32.38
12mm thick cement plaster (1:3) finished with a floating coat of
neat cement [Excluding CP&OHC, sundries]
½ x 0.358 x (1.20+0.4) = 0.286 Sqm 114.07 32.62
(a+b) 1033.09
c. Add Contractor's Profit & Overhead charges 15% of 1033.09 154.96
1188.05
Total (a+b+c) Cost of one Gully Trap = say 1188.10
165
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
12mm thick cement plaster (1:3) finished with a floating coat of
neat cement [Excluding CP&OHC, sundries]
[1/2x0.337x(l.20+0.60)] = 0.303 sqm 0.303 Sqm 114.07 34.56
(a+b) 1073.98
Add Contractor's Profit & Overhead charges 15% of 1073.98 161.10
1235.08
Total (a+b+c) Cost of one Gully Trap = say 1235.10
3.6.2 Making connection of drain or sewer line with existing Manhole including breaking into and
making good the walls, floor with cement concrete (1:2:4), cement plastered on both sides with
cement mortar (1:3) finished with a floating coat of neat cement and making necessary channels
with cement concrete (1:2:4) for the drain all complete as per specification.
166
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Male worker unskilled 0.25 Each 150.00 37.50
Add for delay and sundries L.S 30.02
(a+b) 188.36
c. Add Contractor's Profit & Overhead charges 15% of 188.36 28.25
Total (a+b+c) 216.61
say 216.60
167
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.7 MISCELLANEOUS
3.7.1 Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out
the pipes, manually / by mechanical means including stacking of pipes within 50 metres lead as per
direction of Engineer-in-Charge
3.7.2 Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes,
manually / by mechanical means breaking lead caulked joints, melting of lead and making into
blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer-in-
Charge
[ i ] Up to 150 mm diameter
a. Materials
Fire wood 0.46 Qntl 385.00 177.10
Kerosene oil 0.38 Litre 30.00 11.40
b. Civil material & Labour charges
Details of cost for 40.26 metre or 11 nos joints
Earth work in excavation for dismantling pipes including refilling of excavated earth
1x40.26x0.55x0.75 m= 16.61cum
Deduct for pipes of average 100 mm dia
=lx40.26x(22/7)/4x(0.018)x(0.018) =0.44cum
Total =16.17cum
Earth work in excavation in foundation trenches
16.17 100 Cum 6977.25 1128.22
Refilling trenches with excavated materials 16.17 100 Cum 4651.50 752.15
c. Labour charges
Helper to plumber or fitter 0.63 Each 170.00 107.10
Male worker unskilled 4.5 Each 150.00 675.00
Carriage LS 80.19
(a+b+c) 2742.66
d. Add Contractor's Profit & Overhead charges 15% of 2742.66 411.40
Total (a+b+c+d) Cost for 40.26 metre 3154.06
Rate per metre = 3,154.06 ÷ 40.26 = 78.34
say 78.30
168
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] Above 150 mm dia upto 300 mm dia
a. Materials
Fire wood 1.03 Qntl 385.00 396.55
Kerosene oil 1.14 Litre 30.00 34.20
b. Civil material & Labour charges
Details of cost for 40.26 metre or 11 nos joints
Earth work in excavation for dismantling pipes including refilling of excavated earth
1x40.26x0.65x0.75 m =19.63cum
Deduct for pipes of average 250 mm dia
lx40.26x(22/7)/4x(0.274)x(0.274)=2.37cum
Total =17.26cum
Earth work in excavation in foundation trenches 17.26 Cum 6977.25 1204.27
Refilling trenches with excavated materials 17.26 Cum 4651.50 802.85
c. Labour charges
Helper to plumber or fitter 1.30 Each 170.00 221.00
Male worker unskilled 7.50 Each 150.00 1125.00
Carriage LS 120.29
(a+b+c) 3473.41
d. Add Contractor's Profit & Overhead charges 15% of 3473.41 521.01
Total (a+b+c+d) Cost for 40.26 metre 3994.42
Rate per metre = 3,994.42 ÷ 40.26 = 99.22
say 99.20
3.7.3 Dismantling G.I or Black Iron pipes and fittings laid over the ground including repairing the
damages
169
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Add Contractor's Profit & Overhead charges 15% of 233.33 35.00
Total (a+b) 268.33
Rate per metre = 268.33 ÷ 30 = 8.94
say 8.90
3.7.4 Cutting the G.I or Black Iron pipes and inserting a fitting.
[ i ] 15mm to 25mm diameter
Details of cost for one number
a. Labour charges
Plumber fitter (S) 0.17 Each 190.00 31.67
Helper to plumber/ fitter 0.17 Each 170.00 28.33
Painting & yarn L.S 1.58
61.58
b. Add Contractor's Profit & Overhead charges 15% of 61.58 9.24
Total (a+b) Cost per each number 70.82
say 70.80
[ ii ] 32mm to 50mm diameter
Details of cost for one number
a. Labour charges
Plumber fitter (S) 0.25 Each 190.00 47.50
Helper to plumber/ fitter 0.25 Each 170.00 42.50
Painting & yarn L.S 1.58
91.58
b. Add Contractor's Profit & Overhead charges 15% of 91.58 13.74
Total (a+b) Cost per each number 105.32
say 105.30
3.7.5 Cutting the pucca drain for taking GI pipes and making good the damages.
170
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.7.6 Dismantling HCI pipes and fittings.
[ i ] 50mm dia HCI pipes and fittings
Details for 30 metres
a. Labour charges
Plumber fitter 0.50 Each 190.00 95.00
Helper to plumber 0.50 Each 170.00 85.00
Man mulia (unskilled) 2.00 Each 150.00 300.00
Scaffolding charges 10% of 480.00 48.00
528.00
b. Add Contractor's Profit & Overhead charges 15% of 528.00 79.20
Total (a+b) 607.20
Rate per metre = 607.20 ÷ 30 = 20.24
say 20.20
3.7.9 Dismantling squatting type water closet and urinal plates etc and mending good the
damages to the floors etc.
Details of cost for one number
a. Labour charges
Plumber fitter 0.50 Each 190.00 95.00
Man mulia (unskilled) 1.00 Each 150.00 150.00
Mending damages to the walls L.S 35.20
280.20
171
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Add Contractor's Profit & Overhead charges 15% of 280.20 42.03
Total (a+b) 322.23
say 322.20
3.7.10 Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the
material within 50 metres lead
[ i ] 75 to 80 mm dia pipe
Details of cost for 10 metres
a. Labour charges
Man mulia (unskilled) 0.72 Each 150.00 108.00
b. Add Contractor's Profit & Overhead charges 15% of 108.00 16.20
Total (a+b) 124.20
Rate per metre = 124.20 ÷ 10 = 12.42
say 12.40
3.7.11 Dismantling asbestos cement pressure pipes including excavation and refilling trenches after
taking out the pipes manually / by mechanical means and stacking the pipes within 50 metres lead
as per direction of Engineer-in-Charge
172
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] Above 150 mm diameter
Details of cost for 10 metre or 11 nos joints
Earth work in excavation for dismantling
pipes including refilling of excavated earth
10.00x0.65x0.75 m =4.88cum
Deduct for pipes of average 250 mm dia
= lxl0x(22/7)/4x(0.274)x(0.274)=0.590cum
Total =4.29cum
a. Labour charges
Man mulia (unskilled) 3.76 Each 150.00 564.00
Helper to plumber 0.07 Each 170.00 11.90
575.90
b. Add Contractor's Profit & Overhead charges 15% of 575.90 86.39
Total (a+b) 662.29
Rate per metre = 662.29 ÷ 10 = 66.23
say 66.20
3.7.12 Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes
including demolishing of R.C.C. work manually / by mechanical means and stacking of useful
materials near the site and disposal of unserviceable materials within 50 metres lead as per
direction of Engineer-in-Charge
3.7.13 Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various
sizes including demolishing of R.C.C. work manually / by mechanical means and stacking of useful
materials near the site and disposal of unserviceable materials within 50 metres lead as per
direction of Engineer-in-Charge.
173
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.7.14 Dismantling of flushing cistern of all types (C.I. /PVC/Vitrous China) including stacking of
useful materials near the site and disposal of unserviceable materials within 50 metres lead.
3.7.15 Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50
metres
[i] Upto 150 mm diameter
Details of cost for 10 sluice valves (ace.)
100mm
a. Labour charges
Plumber Fitter(S) 0.60 Each 190.00 114.00
Helper to plumber 0.40 Each 170.00 68.00
Man mulia (unskilled) 1.60 Each 150.00 240.00
Removing the R.C.C. cover etc for dismantling sluice valve
LS 133.65
555.65
b. Add Contractor's Profit & Overhead charges 15% of 555.65 83.35
Total (a+b) 639.00
Rate per each = 639.00 ÷ 10 = 63.90
say 63.90
[ ii ] Above 150 mm diameter
3.7.16 Dismantling of spindle fire hydrant including stacking of useful materials within 50 metres
lead.
[ i ] Details of cost for 10 nos
a. Labour charges
Plumber Fitter(S) 1.50 Each 190.00 285.00
Helper to plumber 1.00 Each 170.00 170.00
Man mulia (unskilled) 4.00 Each 150.00 600.00
1055.00
b. Add Contractor's Profit & Overhead charges 15% of 1055.00 158.25
Total (a+b) 1213.25
Rate per each = 1,213.25 ÷ 10 = 121.33
say 121.30
174
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
3.7.17 Disposal of building rubbish / malba / similar unserviceable, dismantled or waste
materials by mechanical means, including loading, transporting, unloading to approved
municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all
leads including all lifts involved.
3.7.18 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated three
times including getting the sample of water from the disinfected main tested in the municipal
laboratory.
175
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iii ] 125 mm diameter C.I. pipe
176
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ vi ] 250 mm diameter C.I. pipe
177
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ix ] 400 mm diameter C.I. pipe
178
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ xii ] 600 mm diameter C.I. pipe
3.7.19 Extra for every operation of disinfecting the C.I. main by flushing with water containing
bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including
getting the samples of water tested in the municipal laboratory
180
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Testing of samples LS 20.14
(a+b) 390.39
c. Add Contractor's Profit & Overhead charges 15% of 390.39 58.56
Total (a+b+c) 448.95
Rate per metre = 448.95 ÷ 100 = 4.49
say 4.50
181
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Testing of samples LS 34.67
(a+b) 711.17
c. Add Contractor's Profit & Overhead charges 15% of 711.17 106.68
Total (a+b+c) 817.85
Rate per metre = 817.85 ÷ 100 = 8.18
say 8.20
3.7.20 Supplying all materials, labour, T&P and cutting asphalt or bituminous road for taking the
sewer line through and making good to the damages including conveyance of all materials to
worksite, payment of royalty, taxes etc all complete as per specification and direction of the
Engineer in charge
Data for 4.88 mtrs.
a. Labour charges
For cutting
Plumber Fitter(S) 0.125 Each 190.00 23.75
Male worker 2 Each 150.00 300.00
For redoing
Male worker 2.50 Each 150.00 375.00
698.75
b. Add Contractor's Profit & Overhead charges 15% of 698.75 104.81
Total (a+b) 803.56
Rate per metre = 803.56 ÷ 4.88 = 164.66
say 164.70
3.7.21 Supplying all materials, labour, T&P and cutting metalled road for taking the sewer line through
and making good to the damages including conveyance of all materials to worksite, payment of
royalty, taxes etc all complete as per specification and direction of the Engineer in charge
182
Section – 4
SEWERAGE
(Sewers and Ancillary Structures)
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
4.1.1 Laying in trenches (to level or slope) and jointing with provision of stiff mixture of cement
mortar in proportion of 1:1 for salt glazed stoneware pipes, Grade-A of the following internal
diameters including testing of pipes and joints complete.
[ ii ] 150mm diameter
Details of cost for 30 metres
a. Materials:
150mm stoneware pipes 60cm long 50 Each 53.00 2650.00
Cement for 50 joints @ 1.94 kg per joint 0.97 Qntl 714.00 692.58
Fine sand (screened and washed) 0.068 Cum 46.00 3.13
Spun Yarn or tarred gasket @ 0.18 per joint x 50 kg
9.00 Kg 50.00 450.00
Coal tar L.S 36.63
b. Labour for jointing and testing
Mason (skilled) 3 Each 190.00 570.00
Male worker (unskilled) 4 Each 150.00 600.00
Bhisti (semiskilled) 1 Each 170.00 170.00
(a+b) 5172.34
c. Add Contractor's Profit & Overhead charges 15% of 5172.34 775.85
Total (a+b+c) 5948.19
Rate per metre = 5,948.19 ÷ 30 = 198.27
say 198.30
183
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for jointing and testing
Mason (skilled) 3.50 Each 190.00 665.00
Male worker (unskilled) 4.50 Each 150.00 675.00
Bhisti (semiskilled) 1.25 Each 170.00 212.50
(a+b) 7683.68
c. Add Contractor's Profit & Overhead charges 15% of 7683.68 1152.55
Total (a+b+c) 8836.23
Rate per metre = 8,836.23 ÷ 30 = 294.54
say 294.50
[ iv ] 250mm diameter
Details of cost for 30 metres
a. Materials:
250mm stoneware pipes 60cm long 50 Each 130.00 6500.00
Cement for 50 joints @ 3.24 kg per joint 1.62 Qntl 714.00 1156.68
Fine sand (screened and washed) 0.113 Cum 46.00 5.20
Spun Yarn or tarred gasket @ 0.30 per joint x 50 kg
15 Kg 50.00 750.00
Coal tar L.S 61.05
b. Labour for jointing and testing
Mason (skilled) 4.50 Each 190.00 855.00
Male worker (unskilled) 5.50 Each 150.00 825.00
Bhisti (semiskilled) 1.50 Each 170.00 255.00
(a+b) 10407.93
c. Add Contractor's Profit & Overhead charges 15% of 10407.93 1561.19
Total (a+b+c) 11969.12
Rate per metre = 11,969.12 ÷ 30 = 398.97
say 399.00
184
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour for jointing and testing
Mason (skilled) 5.50 Each 190.00 1045.00
Male worker (unskilled) 7.00 Each 150.00 1050.00
Bhisti (semiskilled) 1.75 Each 170.00 297.50
(a+b) 18156.06
c. Add Contractor's Profit & Overhead charges 15% of 2392.50 358.88
Total (a+b+c) 18514.94
Rate per metre = 18,514.94 ÷ 30 = 617.16
say 617.20
4.1.2 Providing and laying in trench cement concrete ( 1:4:8 ) with 40mm size hard granite metal in
the following type of bedding for salt-glazed stoneware pipes of the following internal diameter
including curing complete as per specification
[ ii ] 150mm diameter
Details of cost for 10 metres
Cement concrete ( 1:4:8)
10m x 0.48 x 0.165 = 0.792 Cum 2902.69 2298.93
Rate per metre = 2,298.93 ÷ 10 = 229.89
say 229.90
[ iv ] 250mm diameter
Details of cost for 10 metres
Cement concrete ( 1:4:8)
10m x 0.59 x 0.17 = 1.003 Cum 2902.69 2911.40
Rate per metre = 2,911.40 ÷ 10 = 291.14
say 291.10
185
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[B] TYPE- A 2 STANDARD BEDDING
[ ii ] 150mm diameter
Details of cost for 10 metres
Cement concrete ( 1:4:8)
10m x 0.58 x 0.165 = 0.957 Cum 2902.69 2777.87
Rate per metre = 2,777.87 ÷ 10 = 277.79
say 277.80
[ iv ] 250mm diameter
Details of cost for 10 metres
Cement concrete ( 1:4:8)
10m x 0.69 x 0.17 = 1.173 Cum 2902.69 3404.86
Rate per metre = 3,404.86 ÷ 10 = 340.49
say 340.50
4.1.3 Providing and laying in trench cement concrete ( 1:4:8 ) with 40mm size hard granite metal in
the following type of hunching salt-glazed stoneware pipes of the following internal diameters
including concrete for bedding and curing complete as per PH specification and drawing.
[ ii ] 150mm diameter
Details of cost for 10 metres
Here = d = 0.15 m
t = 0.015 m
D = 0.18 m
w = 0.48 m
Φ = 68°
T = 0.15 m
F = 0.083 m
Rectangular portion 10x0.48x0.24= 1.152
Triangular sides 2x10x0.24x0.083/2= 0.199
1.351
Deduct for pipe
Semi-circular base ½x0.026x10=(-) 0.130
Segments 2x0.026x68/360x10=(-) 0.098
Net quantity 1.123 Cum 2902.69 3259.72
Rate per metre = 3,259.72 ÷ 10 = 325.97
say 326.00
[ iv ] 250mm diameter
Details of cost for 10 metres
Here = d = 0.25 m
t = 0.02 m
D = 0.29 m
187
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
w = 0.59 m
Φ = 61°
T = 0.15 m
F = 0.127 m
Rectangular portion 10x0.59x0.295= 1.741
Triangular sides 2x10x0.295x0.127/2= 0.375
2.116
Deduct for pipe
Semi-circular base ½xΠ/4(0.29)²x10=(-)
½x0.066x10=(-) 0.33
Segments 2x0.066x61/360x10=(-) 0.224
Net quantity 1.562 Cum 2902.69 4534.00
Rate per metre = 4,534.00 ÷ 10 = 453.40
say 453.40
188
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ B ] TYPE- B 2 STANDARD BEDDING
[ ii ] 150mm diameter
Details of cost for 10 metres
Here = d = 0.15 m
t = 0.015 m
D = 0.18 m
w = 0.58 m
Φ = 72°
T = 0.15 m
F = 0.086 m
Rectangular portion 10x0.58x0.24= 1.392
Triangular portion 2x10x0.29x0.086/2= 0.249
1.641
Deduct for pipe
Semi-circular base ½xΠ/4(0.18)²x10
½x0.025x10=(-) 0.127
Segments 2x0.025x72/360x10=(-) 0.100
Net quantity 1.414 Cum 2902.69 4104.40
Rate per metre = 4,104.40 ÷ 10 = 410.44
say 410.40
189
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Deduct for pipe
Semi-circular base ½xΠ/4(0.232)²x10
½x0.042x10=(-) 0.211
Segments 2x0.042x68/360x10=(-) 0.159
Net quantity 1.652 Cum 2902.69 4795.24
Rate per metre = 4,795.24 ÷ 10 = 479.52
say 479.50
[ iv ] 250mm diameter
Details of cost for 10 metres
Here = d = 0.25 m
t = 0.02 m
D = 0.29 m
w = 0.69 m
Φ = 65°
T = 0.15 m
F = 0.132 m
Rectangular portion 10x0.69x0.295= 2.036
Triangular sides 2x10x0.345x0.132/2= 0.455
2.491
Deduct for pipe
Semi-circular base ½xΠ/4(0.29)²x10
½x0.066x10=(-) 0.33
Segments 2x0.066x65/360x10=(-) 0.238
Net quantity 1.923 Cum 2902.69 5581.87
Rate per metre = 5,581.87 ÷ 10 = 558.19
say 558.20
190
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Rectangular portion 10x0.81x0.355= 2.876
Triangular portion 2x10x0.405x0.177/2= 0.717
3.593
Deduct for pipe
Semi-circular base ½xΠ/4(0.41)²x10
½x0.132x10=(-) 0.660
Segments 2x0.132x60/360x10=(-) 0.440
Net quantity 2.493 Cum 2902.69 7236.41
Rate per metre = 7,236.41 ÷ 10 = 723.64
say 723.60
4.1.4 Providing and laying in trench cement concrete ( 1:4:8 ) with 40mm size hard granite metal in
the following type of surrounding or encasing salt-glazed stoneware pipes of the following internal
diameter including concrete for bedding and curing complete as per PH specification
[ ii ] 150mm diameter
Details of cost for 10 metres
Here D = 0.18 m
W = 0.48 m
Y = 0.24 m
S = 0.24 m
t = 0.015 m
Rectangular portion 10x0.48x0.24= 1.152
Seme-circular top portion10x½Πx(0.24)²= 0.905
Deduct for pipe 10xΠ/4x(0.18)²=( - ) 0.254
Net quantity 1.803 Cum 2902.69 5233.55
Rate per metre = 5,233.55 ÷ 10 = 523.36
say 523.40
191
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Rectangular portion 10x0.532x0.266= 1.415
Seme-circular top portion
10x½Πx(0.266)²= 1.111
Deduct for pipe 10xΠ/4x(0.232)²=( - ) 0.423
Net quantity 2.103 Cum 2902.69 6104.36
Rate per metre = 6,104.36 ÷ 10 = 610.44
say 610.40
[ iv ] 250mm diameter
Details of cost for 10 metres
Here D = 0.29 m
W = 0.59 m
Y = 0.295 m
S = 0.295 m
t = 0.02 m
Rectangular portion 10x0.59x0.295= 1.741
Seme-circular top portion10x½Πx(0.295)²= 1.367
Deduct for pipe 10xΠ/4x(0.29)²=( - ) 0.661
Net quantity 2.447 Cum 2902.69 7102.88
Rate per metre = 7,102.88 ÷ 10 = 710.29
say 710.30
192
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Rectangular portion 10x0.524x0.162= 0.849
Semi-circular portion 10x½Πx(0.262)²= 1.078
Deduct for pipe 10xΠ/4x(0.124)²=( - ) 0.121
Net quantity 1.806 Cum 2902.69 5242.26
Rate per metre = 5,242.26 ÷ 10 = 524.23
say 524.20
[ ii ] 150mm diameter
Details of cost for 10 metres
Here D = 0.18 m
W = 0.58 m
Y = 0.29 m
S = 0.24 m
t = 0.015 m
Rectangular portion 10x0.58x0.24= 1.392
Semi-circular portion 10x½Πx(0.29)²= 1.321
Deduct for pipe 10xΠ/4x(0.18)²=( - ) 0.254
Net quantity 2.459 Cum 2902.69 7137.71
Rate per metre = 7,137.71 ÷ 10 = 713.77
say 713.80
[ iv ] 250mm diameter
Details of cost for 10 metres
Here D = 0.29 m
W = 0.69 m
Y = 0.345 m
S = 0.295 m
t = 0.02 m
Rectangular portion 10x0.69x0.295= 2.036
Semi-circular portion 10x½Πx(0.345)²= 1.87
Deduct for pipe 10xΠ/4x(0.29)²=( - ) 0.661
Net quantity 3.245 Cum 2902.69 9419.23
Rate per metre = 9,419.23 ÷ 10 = 941.92
say 941.90
193
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Rectangular portion 10x0.75x0.325= 2.438
Semi-circular portion 10x½Πx(0.375)²= 2.209
Deduct for pipe 10xΠ/4x(0.35)²=( - ) 0.962
Net quantity 3.685 Cum 2902.69 10696.41
Rate per metre = 10,696.41 ÷ 10 = 1069.64
say 1069.60
[ vi ] 350mm diameter
Details of cost for 10 metres
Here D = 0.41 m
W = 0.81 m
Y = 0.405 m
S = 0.355 m
t = 0.03 m
Rectangular portion 10x0.81x0.355= 2.876
Semi-circular portion 10x½Πx(0.405)²= 2.576
Deduct for pipe 10xΠ/4x(0.41)²=( - ) 1.32
Net quantity 4.132 Cum 2902.69 11993.92
Rate per metre = 11,993.92 ÷ 10 = 1199.39
say 1199.40
[ iv ] 250mm diameter
Details of cost for 10 metres
Cement concrete (1:4:8)
Quantity of concrete = 0.295 Cum 2902.69 856.29
Rate per metre = 856.29 ÷ 10 = 85.63
say 85.60
[ vi ] 350mm diameter
Details of cost for 10 metres
Cement concrete (1:4:8)
Quantity of concrete = 0.355 Cum 2902.69 1030.45
Rate per metre = 1,030.45 ÷ 10 = 103.05
say 103.10
194
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ B ] For every additional thickness of 50mm or part thereof over standard bedding. (Applicable
for trench depth more than 1.2 metres)
[ i ] 100mm diameter Not applicable
[ iv ] 250mm diameter
Details of cost for 10 metres
Cement concrete (1:4:8)
Quantity of concrete = 0.345 Cum 2902.69 1001.43
Rate per metre = 1,001.43 ÷ 10 = 100.14
say 100.10
[ vi ] 350mm diameter
Details of cost for 10 metres
Cement concrete (1:4:8)
Quantity of concrete = 0.405 Cum 2902.69 1175.59
Rate per metre = 1,175.59 ÷ 10 = 117.56
say 117.60
4.1.6 Extra over item Nos 4.1.1 for every additional depth of 0.30m or part thereof beyond the
initial lift of 1.50 metre for watering and lowering of pipes.
[ ii ] 150mm diameter
Details of cost for 30 metres
Extra for watering and lowering of pipes
Labour charges
a. Male worker (unskilled) 3.00 Each 150.00 450.00
b. Add Contractor's Profit & Overhead charges 15% of 450.00 67.50
517.50
Rate per metre = 517.50 ÷ 30 = 17.25
say 17.30
195
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 250mm diameter
Details of cost for 30 metres
Extra for watering and lowering of pipes
Labour charges
a. Male worker (unskilled) 5.00 Each 150.00 750.00
b. Add Contractor's Profit & Overhead charges 15% of 750.00 112.50
862.50
Rate per metre = 862.50 ÷ 30 = 28.75
say 28.80
[ vi ] 350mm diameter
Details of cost for 30 metres
Extra for watering and lowering of pipes
Labour charges
a. Male worker (unskilled) 6.75 Each 150.00 1012.50
b. Add Contractor's Profit & Overhead charges 15% 1012.50 151.88
1164.38
Rate per metre = 1,164.38 ÷ 30 = 38.81
say 38.80
196
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
4.2 ANCILLARY STRUCTURES (MANHOLES)
4.2.1 Constructing manholes with R.C.C top slab in (1:2:4) mix, foundation concrete (1:4:8), inside
plaster 12mm thick with cement mortar (1:3) finished with neat cement punning, 12mm thick
outside cement plaster (1:3), brick work with K.B bricks having crushing strength not less than
75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5), cement concrete
(1:2:4) finished smooth using 12mm size h.g chips, earthwork in excavation in all kinds of soil and
refilling the cavity around the chamber complete as per specification.
[A] Plain Manholes inside size 900mm x 800mm and 450mm deep - Type A
(i) With Cast Iron Manhole cover and frame ( light duty rectangular type) 450mm x
610mm internal dimension total weight of cover and frame to be not less than 38 kg
(weight of cover 23 kg and weight of frame 15 kg)
Details of cost for one Manhole
a. Earthwork in excavation in all kinds of soil[Excluding CP&OHC)
1.55m x 1.45m x 0.45m= 1.011 100 Cum 6977.25 70.54
b. Cement concrete (1:4:8) using 40mm size hard granite metal on bed[Excluding CP&OHC)
1.55m x 1.45m x 0.20m= 0.450 Cum 2524.08 1135.84
c. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P [Excluding CP&OHC)
4.40m x 0.25m x 0.35m= 0.385 Cum 3032.54 1167.53
d. Cement concrete (1:2:4) using 12mm size h.g chips for benching [Excluding CP&OHC)
2 x 0.90m x 0.80m/2 x (0.30m+0.20m)/2= 0.180
Less pipe=
1 x 0.90m x P/4 x 0.15m x 0.15m = 0.016
0.164 Cum 4047.02 663.71
e. 12mm thick cement plaster (1:3) with neat cement punning to inside face [Excluding CP&OHC]
3.40m x 0.05m = 0.17
2 x 1/2 x 0.80m x 0.10m = 0.08
0.25 Sqm 114.07 28.52
f. 12mm thick cement plaster (1:3) to outside [Excluding CP&OHC)
5.40m x 0.35m = 1.89 Sqm 96.34 182.08
g. R.C.C (1:2:4) using 12mm size h.g chips for slab [Excluding CP&OHC)
1.40m x 1.30m x 0.15m = 0.273
Less cover 0.61m x 0.455m x 0.15 = ( - ) 0.042
0.231 Cum 4047.02 934.86
h. Rigid and smooth centering and shuttering for RCC works including false work and
dismantling them after casting including cost of materials complete.[Excluding
CP&OHC)
Inside area = 0.90m x 0.80m = 0.720
Less cover = 0.61m x 0.455m = (-) 0.278
0.442
Shuttering = 5.40m x 0.15m = 0.810
(0.61m+0.45m)0.15m= 0.159
1.411 1.411 Sqm 258.68 365.00
i. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire[Excluding CP&OHC)
0.23Qtl @1Qtl per cum 0.23 Qntl 5769.58 1327.00
j. Extra labour for making channel
Mason (Special) 0.06 Each 205.00 12.30
Mason (2nd class) 0.06 Each 190.00 11.40
k. Cost of Cast iron Manhole cover with frame 455mm x 610mm (inside)=38kg
1.00 Each 1415.00 1415.00
7313.78
197
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
l. Add Contractor's Profit & Overhead charges 15% of 7313.78 1097.07
8410.85
say 8410.90
(ii) With RCC precast cover (1:2:4) with 12mm size hg chips of cover 810mm x 655mm and 100mm
thick to be provided over a clear opening of 455mm x 610mm in the manhole slab.
Details of cost of one manhole with Cast Iron Manhole cover (excluding cost
of cover)--rate same as in item No.4.2.1 [A] (i) from a to j 5898.78
a. Extra cost of reinforced cement concrete 1:2:4 with 12mm hg chips for slab
0.61m x 0.455m x 0.10m = 0.028 Cum 4047.02 113.32
b. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire
0.81m x 0.655m x 0.10m= 0.053 Qntl 5769.58 305.79
6317.89
c. Add Contractor's Profit & Overhead charges 15% of 6317.89 947.68
7265.57
say 7265.60
(B) Rectangular Manhole inside size 1200mm x 900mm and 900mm deep - Type - B
(i) With Cast Iron Manhole cover and frame (medium duty) 560mm internal diameter total
weight of cover and frame to be not less than 128 kg (weight of cover 64 kg and weight of frame
64 kg)
Details of cost for one Manhole
a. Earthwork in excavation in all kinds of soil
1.85m x 1.55m x 0.90m = 2.581 100Cum 6977.25 180.08
b. Cement concrete (1:4:8) using 40mm size hard granite metal on bed
1.85m x 1.55m x 0.20m = 0.574 Cum 2524.08 1448.82
c. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
2 x 1.70m x 0.25m x 0.80m = 0.680
2 x 0.90m x 0.25m x 0.80m = 0.360
Less pipe = 2 x 0.25m x Π/4 x (0.15)² = 0.009
1.031 Cum 3032.54 3126.55
d. Cement concrete (1:2:4) using 12mm size h.g chips for benching
2 x 1.20m x 0.90m/2 x (0.30m+0.20m)/2= 0.270
Less pipe=
1 x 1.00m x Π/4 x (0.15)² = 0.018
0.252 Cum 4047.02 1019.85
e. 12mm thick cement plaster (1:3) with neat cement punning to inside face
4.20m x 0.50m = 2.10
2 x 1/2 x 0.90m x 0.10m = 0.09
2.19 Sqm 114.07 249.81
f. 12mm thick cement plaster (1:3) to outside
6.20m x 0.80m = 4.96 Sqm 96.34 477.85
g. R.C.C (1:2:4) using 12mm size h.g chips for slab
1.70m x 1.40m x 0.15m = 0.357
Less cover
Π/4 x (0.56)² x 0.15m = 0.037
0.320 Cum 4047.02 1295.05
h. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab
including cutting, bending, binding and tying the grills including cost
of binding wire
0.32Qtl @1Qtl per cum 0.32 Qntl 5769.58 1846.27
198
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
i. Rigid and smooth centering and shuttering for RCC works including false work and
dismantling them after casting including cost of materials complete.
Inside area = 1.20m x 0.90m = 1.08
Less cover = Π/4 x (0.56)² = (-) 0.246
0.834
Shuttering=2(1.70m+1.40m)x0.15m= 0.93
Πx0.56mx0.15m= 0.264
2.028 2.028 Sqm 258.68 524.60
j. Extra labour for making channel
Mason (Special) 0.08 Each 205.00 16.40
Mason (2nd class) 0.08 Each 190.00 15.20
k. Cost of Cast Iron Manhole cover and frame (medium duty)
560mm internal diameter = 128kg 1 Each 4435.00 4435.00
14635.48
l. Add Contractor's Profit & Overhead charges 15% of 14635.48 2195.32
Cost for one Manhole 16830.80
say 16830.80
(ii) With RCC precast cover (1:1½:3) with 12mm size hg chips of cover 760mm diameter and
100mm thick with lifting arrangement to be provided over a clear opening of 560mm diameter in
the manhole slab.
a. Details of cost of one manhole with Cast Iron manhole cover (excluding cost of
cover)--rate as above from a to j 10200.48
b. Extra cost of cement concrete (1:1½:3) with 12mm hg chips for cover slab
Π/4 x (0.76)² x 0.10m = 0.045 Cum 4803.86 216.17
c. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire
0.045 Qntl 5769.58 259.63
10676.28
d. Add Contractor's Profit & Overhead charges 15% of 10676.28 1601.44
12277.72
say 12277.70
4.2.2 Constructing brick masonry arched type Manhole 1400mm x 900mm inside size at bottom
up to crown of the arch and 600mm x 900mm inside size above the crown of the arch with K.B
bricks having crushing strength not less than 75 kg/cm² with dimensional tolerance ± 8 percent in
cement mortar 1:5, arch work with Ist class K.B bricks having crushing strength not less than 75
kg/cm² with dimensional tolerance ± 8 percent in cement mortar 1:3, inside cement plaster 12mm
thick with cement mortar 1:3 with neat cement punning above the benching level, outside cement
plaster 1:3, RCC top slab 1:2:4, foundation concrete (1:4:8) using 40mm size hard granite metal
and making channels in cement concrete (1:2:4) using 12mm size h.g chips, earthwork in
excavation in all kinds of soil and refilling the cavity around the chamber finished smooth including
watering, curing etc all complete as per specification.
(i) With Cast Iron Manhole cover and frame (Medium duty) 560mm internal
diameter total weight of cover and frame to be not less than 128kg (weight of cover
64kg and weight of frame 64 kg)
Details of cost of one Manhole
a. Earthwork in excavation in all kinds of soil within initial lead and lift
2.45m x 1.95m x 1.50m = 7.17 100 Cum 6977.25 499.99
b. Earthwork in excavation in all kinds of soil with first extra lift
2.45m x 1.95m x 1.15m = 5.49 100 Cum 7592.25 417.12
c. Cement concrete (1:4:8) using 40mm size hard granite metal on bed
199
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
2.45m x 1.95m x 0.20m = 0.956 Cum 2524.08 2413.02
d. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
6.10m x 0.37m x 1.20m = 2.708
4.0m x 0.25m x 1.15m = 1.150
3.858
Deduct arch = π/2 x 1.15 x 0.25 x 0.25 = ( - ) 0.113
Deduct pipe portion =
2 x π/4 x 0.15 x 0.15 x 0.375 = ( - ) 0.013
Net quantity 3.732 Cum 3032.54 11317.44
e. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:3)
in arches.
π/2 x 1.15m x 1.05m x 0.25m= 0.474 Cum 3476.45 1647.84
f. Cement concrete (1:2:4) using 12mm size h.g chips for benching
2 x 1.40m x 0.90m/2 x (0.30m+0.20m)/2 = 0.315
Less pipe=
1.40m x π/4 x 0.15² = ( - ) 0.025
0.290 Cum 4047.02 1173.64
g. 12mm thick cement plaster (1:3) with neat cement punning to inside face
4.60m x 0.90m = 4.14
2 x ½ x 0.90 x 0.10 = 0.09
π/2 x 0.90 x 0.80 = 1.131
3.00 x 0.15 = 3.45
8.811 Sqm 114.07 1005.07
h. 12mm thick cement plaster (1:3) to outside
7.60m x 1.20m = 9.12
5.00m x 1.15m = 5.75
π/2 x 1.40 x 0.80 = 1.759
16.629 Sqm 96.34 1602.04
i. R.C.C (1:2:4) using 12mm size h.g chips for slab
1.40m x 1.10m x 0.15m = 0.231
Less cover π/4 x 0.56²m x 0.15m= ( - ) 0.037
0.194 Cum 4047.02 785.12
j. Rigid and smooth centering and shuttering for RCC works including false work and
dismantling them after casting including cost of materials complete.
Inside area = 0.90m x 0.60m = 0.54
5.0m x 0.15m = 0.75
1.29 1.29 Sqm 258.68 333.70
k. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire
0.194Qtl @ 1 Qtl per cum 0.194 Qntl 5769.58 1119.30
l. Extra labour for making channel
Mason (Special) 0.10 Each 205.00 20.50
Mason (2nd class) 0.10 Each 190.00 19.00
m. Cost of Cast iron Manhole cover 560mm internal diameter total weight of cover and
frame to be not less than 128kg
1 Each 4435.00 4435.00
26788.78
n. Add Contractor's Profit & Overhead charges 15% of 26788.78 4018.32
Cost for one Manhole 30807.10
say 30807.10
200
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
(ii) With RCC precast cover (1:1½:3) with 12mm size hg chips, size of cover 760mm diameter and
100mm thick with lifting arrangement to be provided over a clear opening of 560mm diameter in
the manhole slab.
a. Cost of one Manhole with Cast Iron Manhole cover (excluding cost
of cover and frame) - rate same as in item No.4.2.2 (A) (i) from a to l 22353.78
b. Extra cost of reinforced cement concrete (1:1½:3) with 12mm hg chips
Π/4 x (0.76)² x 0.10m = 0.045 Cum 4803.86 216.17
c. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire 18 to 20
gauge.
0.045 Qntl 5769.58 259.63
22829.58
d. Add Contractor's Profit & Overhead charges 15% of 22829.58 3424.44
26254.02
say 26254.00
(i) With Cast Iron Manhole cover and frame (Medium duty) 560mm internal diameter total
weight of cover and frame to be not less than 128 kg (weight of cover 64 kg and weight of frame
64 kg)
Details of cost of one Manhole
a. Earthwork in excavation in all kinds of soil within initial lead and lift
2.70m x 2.20m x 1.50m = 8.910 100Cum 6977.25 621.67
b. Earthwork in excavation in all kinds of soil with first extra lift
2.70m x 2.20m x 1.50m = 8.910 100 Cum 7592.25 676.47
c. Earthwork in excavation in all kinds of soil with second extra lift
2.70m x 2.20m x 0.30m = 1.782 100 Cum 8207.25 146.25
d. Cement concrete (1:4:8) using 40mm size hard granite metal on bed
2.70m x 2.20m x 0.30m = 1.782 Cum 2524.08 4497.91
e. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
6.60m x 0.50m x 1.20m = 3.960
4.50m x 0.375m x 0.50m = 0.844
4.00m x 0.25m x 1.20m = 1.200
6.004
Deduct arch = π/2 x 1.15 x 0.25 x 0.25 = ( - ) 0.113
Deduct pipe portion =
2 x π/4 x 0.15 x 0.15 x 0.50 = ( - ) 0.018
Net quantity 5.873 Cum 3032.54 17810.11
f. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:3)
in arches.
π/2 x 1.15m x 1.175m x 0.25m= 0.531 Cum 3476.45 1845.99
g. Cement concrete (1:2:4) using 12mm size h.g chips for benching
2 x 1.40m x 0.90m/2 x (0.30m+0.20m)/2 = 0.315
Less pipe=
1.40m x π/4 x 0.15²m = ( - ) 0.025
0.290 Cum 4047.02 1173.64
201
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
h. 12mm thick cement plaster (1:3) with neat cement punning to inside face
4.60m x 0.90m = 4.14
2 x ½ x 0.90 x 0.10 = 0.09
π/2 x 0.90 x 0.80 = 1.131
3.00 x 1.70 = 5.100
10.461 Sqm 114.07 1193.29
i. 12mm thick cement plaster (1:3) to outside
8.60m x 1.20m = 10.32
6.00m x 0.50m = 3.00
5.00m x 1.20m = 6.00
π/2 x 1.40 x 0.80 = 1.759
21.079 Sqm 96.34 2030.75
j. R.C.C (1:2:4) using 12mm size h.g chips for slab
1.40m x 1.10m x 0.15m = 0.231
Less cover π/4 x 0.56²m x 0.15m x 0.15 = ( - ) 0.037
0.194 Cum 4047.02 785.12
k. Rigid and smooth centering and shuttering for RCC works including false work and
dismantling them after casting including cost of materials complete.
Inside area = 0.90m x 0.60m = 0.54
5.0m x 0.15m = 0.75
1.29 1.29 Sqm 258.68 333.70
l. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire 18 to 20
gauge.
0.194 Qtl @ 1 Qtl per cum 0.194 Qntl 5769.58 1119.30
m. Extra labour for making channel
Mason (Special) 0.10 Each 205.00 20.50
Mason (2nd class) 0.10 Each 190.00 19.00
n. Cost of Cast Iron Manhole cover and frame (medium duty) 560mm internal diameter
= 128 kg
1 Each 4435.00 4435.00
36708.70
o. Add Contractor's Profit & Overhead charges 15% of 36708.70 5506.31
Cost for one Manhole 42215.01
say 42215.00
(ii) With RCC precast cover (1:1½:3) with 12mm size hg chips of cover 760mm diameter and
100mm thick with lifting arrangement to be provided over a clear opening of 560mm diameter in
the manhole slab.
Details of cost of one manhole
a. Cost of one Manhole with Cast Iron manhole cover (excluding cost of cover and
frame) - rate same as item No.4.2.2 [B] (i) above from a to m 32273.70
b. Extra cost of reinforced cement concrete (1:1½:3) with 12mm hg chips
Π/4 x (0.76)²x 0.10m = 0.045 Cum 4803.86 216.17
c. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire 18 to 20
gauge.
0.045 Qntl 5769.58 259.63
32749.50
d. Add Contractor's Profit & Overhead charges 15% of 32749.50 4912.43
37661.93
say 37661.90
202
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
4.2.3 Extra for every additional depth of 0.10 metre or part thereof of Manhole over item No.
4.2.1 [A] (i), No. 4.2.1 [A] (ii) and No. 4.2.1 [B] (i),(ii),(iii)
[ ii ] Extra for every additional depth of 0.10 metre or part thereof of Manhole over item No.
4.2.1 [B] (i), No. 4.2.1 [B] (ii) and No. 4.2.1 [B] (iii)
From 900mm to 2500mm depth
Details of cost of one additional depth of 0.10m
a. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
5.20m x 0.25m x 0.10m = 0.13 Cum 3032.54 394.23
b. 12mm thick cement plaster (1:3) with neat cement punning to inside face
4.20mx0.10m= 0.42 Sqm 114.07 47.91
c. 12mm thick cement plaster (1:3) to outside
6.20mx0.10m= 0.62 Sqm 96.34 59.73
501.87
d. Add Contractor's Profit & Overhead charges 15% of 501.87 75.28
Extra cost for additional depth of 0.10 metre or part thereof 577.15
say 577.20
[iii] Extra for every additional depth of 0.10m or part thereof of Manhole over item No
4.2.2[A](i), No 4.2.2[A](ii),and No 4.2.2[A](iii)
From 2450mm to 3000mm depth
Details of cost of one additional depth of 0.10m
a. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
4.00m x 0.25m x 0.10m = 0.10 Cum 3032.54 303.25
b. 12mm thick cement plaster (1:3) with neat cement punning to inside face
3.00m x 0.10m = 0.30 Sqm 114.07 34.22
c. 12mm thick cement plaster (1:3) to outside
5.00m x 0.10m = 0.50 Sqm 96.34 48.17
385.64
d. Add Contractor's Profit & Overhead charges 15% of 385.64 57.85
Extra cost for additional depth of 0.10 metre or part thereof 443.49
say 443.50
203
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[iv] Extra for every additional depth of 0.10m or part thereof of Manhole over item No
4.2.2[B](i), No 4.2.2[B](ii) and No 4.2.2[B](iii)
From 3000mm to 4000mm depth
Details of cost of one additional depth of 0.10m
a. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
4.50m x 0.375m x 0.10m = 0.17 Cum 3032.54 512.50
b. 12mm thick cement plaster (1:3) with neat cement punning to inside face
3.00m x 0.10m = 0.30 Sqm 114.07 34.22
c. 12mm thick cement plaster (1:3) to outside
6.00m x 0.10m = 0.60 Sqm 96.34 57.80
604.52
d. Add Contractor's Profit & Overhead charges 15% of 604.52 90.68
Extra cost for additional depth of 0.10 metre or part thereof 695.20
say 695.20
4.2.4 Construction of circular type manhole with top slab made of cement concrete 1:2:4 using 12mm
size hard granite chips foundation concrete (1:4:8) using 40mm size hard granite metal on bed,
walls made of brick masonry using 1st class K.B bricks (25 Cm x 12Cm x 8Cm) having crushing
strength not less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5),
inside plastering 12mm thick (1:3) finished smooth with neat cement punning, outside plaster (1:3)
and making channels with cement concrete (1:2:4) using 12mm size h.g chips complete as per
specification.
[A] 900mm internal diameter x 1110mm depth with sides sloped upto 560mm internal
diameter at top
(i) With Cast Iron Manhole cover and frame (medium duty) 560mm internal diameter
total weight of cover and frame to be not less than 128 kg (weight of cover 64 kg
and weight of frame 64 kg)
Details of cost of one Manhole
a. Earthwork in excavation in all kinds of soil within initial lead and lift[Excluding CP&OHC)
Π/4 x (1.70)² x 1.21 = 2.75 100 Cum 6977.25 191.60
b. Cement concrete (1:4:8) using 40mm size hard granite metal on bed
Π/4 x (1.70)² x 0.20 = 0.454 Cum 2524.08 1145.93
c. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
Π x 1.15 x 0.40 x 0.25 = 0.36
Π x (1.15+0.81)/2 x 0.36 x 0.25 = 0.28
Π x 0.81 x 0.25 x 0.25 = 0.16
0.80 Cum 3032.54 2416.93
d. Cement concrete (1:2:4) using 12mm size h.g chips for benching
For benching
Π/4 x (0.90)²x (0.20+0.30)/2 = 0.159
Less pipe
Π/4 x (0.15)²x 0.90 = (-) 0.016
For fixing cover
Π/4 x (1.06)² x 0.15 = 0.132
Less pipe
Π/4 x (0.56)² x 0.15 = (-) 0.037
0.238 Cum 4047.02 963.19
204
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
e. 12mm thick cement plaster (1:3) with neat cement punning to inside face
Π x 0.90 x 0.10 = 0.283
Π x (0.45+0.28) x √(0.45-0.28)² + (0.36)² = 0.913
Π x 0.56 x 0.25 = 0.440
1.636 Sqm 114.07 186.62
f. 12mm thick cement plaster (1:3) to outside
Π x 1.40 x 0.40 = 1.76
Π x (0.70+0.53) x √(0.70-0.53)²+(0.36)² = 1.54
Π x 1.06 x 0.25 = 0.83
4.13 Sqm 96.34 397.88
g. Extra labour for making channel
Mason (Special) 0.10 Each 205.00 20.50
Mason (2nd class) 0.10 Each 190.00 19.00
h. Cost of Cast iron Manhole cover 560mm internal diameter total weight of cover and
frame (medium duty) to be not less than 128kg
1.00 Each 4435.00 4435.00
9776.65
i. Add Contractor's Profit & Overhead charges 15% of 9776.65 1466.50
Cost for one Manhole 11243.15
say 11243.20
(ii) With RCC precast cover (1:1½:3) with 12mm size hg chips of cover 760mm diameter and
100mm thick with lifting arrangement to be provided over a clear opening of 560mm diameter in
the manhole slab.
Details of cost of one manhole
a. Cost of one manhole with cast iron manhole cover (excluding cost of cover) as in
item No 4.2.4 [A] (i) from a to g 5341.65
b. Extra cost of cement concrete 1:1½:3 with 12mm hg chips
Π/4 x(0.76)²xx0.10=- 0.045 Cum 4803.86 216.17
c. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire 18 to 20
gauge.
0.045 Qntl 5769.58 259.63
5817.45
d. Add Contractor's Profit & Overhead charges 15% of 5817.45 872.62
6690.07
say 6690.10
[B] 1200mm internal diameter x 1670mm depth with sides sloped upto 560mm internal
diameter at top
(i) With Cast Iron Manhole cover and frame (medium duty) 560mm internal diameter total
weight of cover and frame to be not less than 128kg (weight of cover 64 kg and weight of frame
64 kg)
Details of cost of one Manhole
a. Earthwork in excavation in all kinds of soil within initial lead and lift
Π/4 x (2.00)² x 1.50 = 4.71 100Cum 6977.25 328.77
b. Earthwork in excavation in all kinds of soil with first extra lift
Π/4 x (2.00)² x 0.37 = 1.16 100Cum 7592.25 88.22
c. Cement concrete (1:4:8) using 40mm size hard granite metal on bed
Π/4 x (2.00)² x 0.20 = 0.628 Cum 2524.08 1585.12
205
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
d. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
Π x 1.45 x 0.53 x 0.25 = 0.60
Π x (1.45 + 0.81)/2 x 0.79 x 0.25 = 0.70
Π x 0.81 x 0.25 x 0.25 = 0.16
1.46 Cum 3032.54 4439.64
e. Cement concrete (1:2:4) using 12mm size h.g chips for benching
Π/4 x (1.20)² x (0.20+0.30)/2 = 0.283
Less pipe
Π/4 x (0.15)² x 1.20 = (-) 0.021
For fixing cover
Π/4 x (1.06)² x 0.15 = 0.132
Less pipe
Π/4 x (0.56)² x 0.15 = (-) 0.037
0.357 Cum 4047.02 1444.79
f. 12mm thick cement plaster (1:3) with neat cement punning to inside face
Π x 1.20m x 0.23m = 0.87
Π x (0.60+0.28) x √(0.60-0.28)² + (0.792)² =
2.36
Π x 0.56 x 0.25 = 0.44
3.67 Sqm 114.07 418.50
g. 12mm thick cement plaster (1:3) to outside
Π x 1.70 x 0.53 = 2.83
Π x (0.85+0.53) x √(0.85-0.53)² + (0.79)² = 3.70
Π x 1.06 x 0.25 = 0.83
7.36 Sqm 96.34 708.97
h. Extra labour for making channel
Mason (Special) 0.10 Each 205.00 20.50
Mason (2nd class) 0.10 Each 190.00 19.00
i. Cost of Cast Iron Manhole cover and frame (medium duty) 560mm internal dia = 128kg
1 Each 4435.00 4435.00
13488.51
j. Add Contractor's Profit & Overhead charges 15% of 13488.51 2023.28
Cost for one Manhole 15511.79
say 15511.80
(iii) With RCC precast cover (1:1½:3) with 12mm size hg chips of cover 760mm diameter and
100mm thick with lifting arrangement to be provided over a clear opening of 560mm diameter in
the manhole slab.
Details of cost of one Manhole
a. Cost of one Manhole with Cast Iron manhole cover (excluding cost of cover) as in
item No 4.2.4 [B] (i) 9053.51
b. Extra cost of cement concrete 1:1½:3 with 12mm hg chips
Π/4 x (0.76)² x 0.10m = 0.045 Cum 4803.86 216.17
c. M.S reinforcement bars 10mm dia tor steel 10cm c/c bothways in slab including
cutting, bending, binding and tying the grills including cost of binding wire 18 to 20
gauge.
0.045 Qntl 5769.58 259.63
Cost for one Manhole 9529.31
d. Add Contractor's Profit & Overhead charges 15% of 9529.31 1429.40
10958.71
say 10958.70
206
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
4.2.5 Extra for every additional depth of 0.10m or part thereof above 1100mm upto 1650mm
[ i ] depth in circular Manhole 900mm internal diameter as in item No. 4.2.4 [A]
Details of cost of one additional depth of 0.10m
a. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
in F&P
Π x 1.15 x 0.25 x 0.10 = 0.09 Cum 3032.54 272.93
b. 12mm thick cement plaster (1:3) with neat cement punning to inside face
Π x 0.90 x 0.10 = 0.28 Sqm 114.07 32.28
c. 12mm thick cement plaster (1:3) to outside
Π x 1.40 x 0.10 = 0.44 Sqm 96.34 42.39
347.60
d. Add Contractor's Profit & Overhead charges 15% of 347.60 52.14
Extra cost for additional depth of 0.10 metre or part thereof 399.74
say 399.70
[ ii ] Extra for every additional depth of 0.10m or part thereof above 1670mm upto 2300mm
depth in circular Manhole 1200mm internal diameter as in item No. 4.2.4 [ B ]
Details of cost of one additional depth of 0.10m
a. Brickwork with K.B bricks (25 Cm x 12 Cm x 8 Cm) having crushing strength not
less than 75kg/cm² with dimensional tolerance ± 8 percent in cement mortar (1:5)
Π x 1.45 x 0.25 x 0.10 = 0.114 Cum 3032.54 345.71
b. 12mm thick cement plaster (1:3) with neat cement punning to inside face
Π x 1.20 x 0.10 = 0.377 Sqm 114.07 43.00
c. 12mm thick cement plaster (1:3) to outside
Π x 1.70 x 0.10 = 0.534 Sqm 96.34 51.45
Cost of one extra depth of 0.10 mtr 440.16
d. Add Contractor's Profit & Overhead charges 15% of 440.16 66.02
Extra cost for additional depth of 0.10 metre or part thereof 506.18
say 506.20
4.2.6 Making MS step iron in 20mm diameter MS steel bars and fixing into walls of Manhole duly
embedded in cement concrete (1:3:6) complete as per specification.
207
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
4.3 CONCRETE PIPES WITH AND WITHOUT REINFORCEMENT
4.3.1 Laying (to level or slopes) conforming to IS 783-1985 and jointing with cement mortar 1:2 of
concrete pipes Class NP-1, unreinforced non-pressure pipes conforming to IS:458 - 2003 with
socket and spigot ends of the following internal diameter and testing of joints as per specification
complete. (Earthwork in trenches to be measured and paid for separately)
[i] 300mm diameter
[ ii ] 350mm diameter
Details of cost for 10 metres
a. Materials
350mm concrete pipes & socket =10.00m=10pieces
10 Each 258.10 2581.00
Cement for 10 joints=0.0075cum or 0.107Qtl 0.107 Qntl 714.00 76.40
Sand for 10 joints 0.015 Cum 46.00 0.69
b. Labour charges
Mason (2nd class) 3.10 Each 190.00 589.00
Male worker (unskilled) 2.00 Each 150.00 300.00
Bhisti (semiskilled) 0.75 Each 170.00 127.50
(a+b) 3674.59
c. Add Contractor's Profit & Overhead charges 15% of 3674.59 551.19
Total (a+b+c) 4225.78
Rate per metre = 4,225.78 ÷ 10 = 422.58
say 422.60
[ iii ] 400mm diameter
Details of cost for 10 metres
a. Materials
400mm Concrete Pipes & socket =10.00m=10pieces
10 Each 290.80 2908.00
Cement for 10 joints=0.0085cum or 0.122Qtl 0.122 Qntl 714.00 87.11
Sand for 10 joints 0.017 Cum 46.00 0.78
b. Labour charges
Mason (2nd class) 4.00 Each 190.00 760.00
Male worker (unskilled) 2.50 Each 150.00 375.00
Bhisti (semiskilled) 1.00 Each 170.00 170.00
(a+b) 4300.89
c. Add Contractor's Profit & Overhead charges 15% of 4300.89 645.13
Total (a+b+c) 4946.02
Rate per metre = 4,946.02 ÷ 10 = 494.60
say 494.60
208
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 450mm diameter
Details of cost for 10 metres
a. Materials
450mm concrete pipes & socket =10.00m=10pieces
10 Each 338.40 3384.00
Cement for 10 joints=0.012cum or 0.172Qtl 0.172 Qntl 714.00 122.81
Sand for 10 joints 0.024 Cum 46.00 1.10
b. Labour charges
Mason (2nd class) 5.00 Each 190.00 950.00
Male worker (unskilled) 3.00 Each 150.00 450.00
Bhisti (semiskilled) 1.10 Each 170.00 187.00
(a+b) 5094.91
c. Add Contractor's Profit & Overhead charges 15% of 5094.91 764.24
Total (a+b+c) 5859.15
Rate per metre = 5,859.15 ÷ 10 = 585.92
say 585.90
4.3.2 Laying (to level or slopes) conforming to IS 783-1985 and jointing with cement mortar 1:2 of
concrete pipes Class NP-1, unreinforced non-pressure pipes conforming to IS:458 - 2003 with
collars and butt ends prepared for collar joints of the following internal diameter including testing
of joints as per specification.(Earthwork in trenches to be measured and paid for separately)
[ ii ] 350mm diameter
Details of cost for 10 metres
a. Materials
350mm Class-NP-1 pipes =1.00m x 10nos 10 Each 258.10 2581.00
350mm dia collar = 10nos 10 Each 99.00 990.00
Cement for 10 joints=0.017cum or 0.243Qtl 0.243 Qtl 714.00 173.50
Sand for 10 joints 0.034 Cum 46.00 1.56
b. Labour charges
Mason (2nd class) 3.10 Each 190.00 589.00
Male worker (unskilled) 2.00 Each 150.00 300.00
Bhisti (semiskilled) 0.75 Each 170.00 127.50
(a+b) 4762.56
c. Add Contractor's Profit & Overhead charges 15% of 4762.56 714.38
Total (a+b+c) 5476.94
Rate per metre = 5,476.94 ÷ 10 = 547.69
say 547.70
209
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iv ] 450mm diameter
Details of cost for 10 metres
a. Materials
450mm Class-NP-2 pipes =1.00mx10nos 10 Each 338.40 3384.00
450mm dia collar = 10nos 10 Each 139.00 1390.00
Cement for 10 joints=0.047cum or 0.47Qtl 0.47 Qtl 714.00 335.58
Sand for 10 joints 0.0665 Cum 46.00 3.06
b. Labour charges
Mason (2nd class) 5.00 Each 190.00 950.00
Male worker (unskilled) 3.00 Each 150.00 450.00
Bhisti (semiskilled) 1.10 Each 170.00 187.00
(a+b) 6699.64
c. Add Contractor's Profit & Overhead charges 15% of 6699.64 1004.95
Total (a+b+c) 7704.59
Rate per metre = 7,704.59 ÷ 10 = 770.46
say 770.50
4.3.3 Laying (to level or slopes) conforming to IS 783-1959 and jointing with cement mortar 1:2 of
concrete pipes Class NP-2, reinforced light duty non-pressure pipes conforming to IS:458 -
2003 with collars and butt ends prepared for collar joints of the following internal diameter as per
specification complete.(Earthwork in trenches to be measured and paid for separately)
210
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ii ] 350mm diameter
Details of cost for 10 metres
a. Materials
350mm Class-NP-2 pipes =1.00mx10nos 10 Each 360.00 3600.00
Cement for 5 joints=0.0085cum or 0.122Qtl 0.122 Qtl 714.00 87.11
Sand for 5 joints 0.017 Cum 46.00 0.78
b. Labour charges
Mason (2nd class) 1.30 Each 190.00 247.00
Male worker (unskilled) 1.30 Each 150.00 195.00
Bhisti (semiskilled) 0.20 Each 170.00 34.00
(a+b) 4163.89
c. Add Contractor's Profit & Overhead charges 15% of 4163.89 624.58
Total (a+b+c) 4788.47
Rate per metre = 4,788.47 ÷ 10 = 478.85
say 478.90
[ iv ] 450mm diameter
Details of cost for 10 metres
a. Materials
450mm Class-NP-2 pipes =1.00mx10nos 10 Each 555.00 5550.00
Cement for 4 joints=0.0133cum or 0.19Qtl 0.19 Qtl 714.00 135.66
Sand for 4 joints 0.0266 Cum 46.00 1.22
b. Labour charges
Mason (2nd class) 1.50 Each 190.00 285.00
Male worker (unskilled) 1.50 Each 150.00 225.00
Bhisti (semiskilled) 0.33 Each 170.00 56.10
(a+b) 6252.98
c. Add Contractor's Profit & Overhead charges 15% of 6252.98 937.95
Total (a+b+c) 7190.93
Rate per metre = 7,190.93 ÷ 10 = 719.09
say 719.10
211
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Mason (2nd class) 1.62 Each 190.00 307.80
Male worker (unskilled) 1.62 Each 150.00 243.00
Bhisti (semiskilled) 0.33 Each 170.00 56.10
(a+b) 7037.47
c. Add Contractor's Profit & Overhead charges 15% of 7037.47 1055.62
Total (a+b+c) 8093.09
Rate per metre = 8,093.09 ÷ 10 = 809.31
say 809.30
[ vi ] 600mm diameter
Details of cost for 10 metres
a. Materials
600mm Class-NP-2 pipes =1.00mx10nos 10 Each 878.00 8780.00
Cement for 4 joints=0.0172cum or 0.246Qtl 0.246 Qtl 714.00 175.64
Sand for 4 joints 0.0344 Cum 46.00 1.58
b. Labour charges
Mason (2nd class) 1.84 Each 190.00 349.60
Male worker (unskilled) 1.84 Each 150.00 276.00
Bhisti (semiskilled) 0.33 Each 170.00 56.10
(a+b) 9638.92
c. Add Contractor's Profit & Overhead charges 15% of 9638.92 1445.84
Total (a+b+c) 11084.76
Rate per metre = 11,084.76 ÷ 10 = 1108.48
say 1108.50
212
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ ix ] 900mm diameter
Details of cost for 10 metres
a. Materials
900mm Class-NP-2 pipes =1.00mx10nos 10 Each 1771.00 17710.00
Cement for 4 joints=0.0253cum or 0.362Qtl 0.362 Qtl 714.00 258.47
Sand for 4 joints 0.0506 Cum 46.00 2.33
b. Labour charges
Mason (2nd class) 2.50 Each 190.00 475.00
Male worker (unskilled) 3.00 Each 150.00 450.00
Bhisti (semiskilled) 0.50 Each 170.00 85.00
(a+b) 18980.80
c. Add Contractor's Profit & Overhead charges 15% of 18980.80 2847.12
Total (a+b+c) 21827.92
Rate per metre = 21,827.92 ÷ 10 = 2182.79
say 2182.80
[ xi ] 1100mm diameter
Details of cost for 10 metres
a. Materials
1100mm Class-NP-2 pipes =1.00mx10nos 10 Each 2458.00 24580.00
Cement for 4 joints=0.0308cum or 0.44Qtl 0.440 Qtl 714.00 314.16
Sand for 4 joints 0.0616 Cum 46.00 2.83
b. Labour charges
Mason (2nd class) 2.94 Each 190.00 558.60
Male worker (unskilled) 6.30 Each 150.00 945.00
Bhisti (semiskilled) 0.60 Each 170.00 102.00
(a+b) 26502.59
c. Add Contractor's Profit & Overhead charges 15% of 26502.59 3975.39
Total (a+b+c) 30477.98
Rate per metre = 30,477.98 ÷ 10 = 3047.80
say 3047.80
213
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
b. Labour charges
Mason (2nd class) 3.18 Each 190.00 604.20
Male worker (unskilled) 8.67 Each 150.00 1300.50
Bhisti (semiskilled) 0.67 Each 170.00 113.90
(a+b) 30653.69
c. Add Contractor's Profit & Overhead charges 15% of 30653.69 4598.05
Total (a+b+c) 35251.74
Rate per metre = 35,251.74 ÷ 10 = 3525.17
say 3525.20
4.3.4 Laying (to level or slopes) and jointing with rubber rings pre-cast reinforced socket and
spigot concrete pipes Class NP-2 conforming to IS:458 - 2003 suitable for rubber ring roll on
joint of the following internal diameter as per specification complete.(Earthwork in trenches to be
measured and paid for separately)
[ ii ] 150mm diameter
Details of cost for 10 joints =10x1.93=19.3 mtrs
a. Materials
150mm Concrete S/S Pipes Class NP-2 19.30 mtr 305.70 5900.01
labour for laying (same as C.I pipe)
wt. of 10 pcs of pipe= 19.3x37.8238=729.99 kg =7.30 qntl
7.30 qntl 50.72 370.26
Jointing with rubber ring
150 mm dia rubber ring for 10 joints 10.000 each 40.00 400.00
b. Labour charges
Plumber Fitter(S) = 4/3 1.33 Each 190 253.33
Helper to plumber or fitter=2/3 0.67 Each 170 113.33
Male worker=29/12 2.42 Each 150 362.50
(a+b) 7399.43
c. Add Contractor's Profit & Overhead charges 15% of 7399.43 1109.91
Total (a+b+c) 8509.34
Rate per metre = 8,509.34 ÷ 19.3 = 440.90
say 440.90
214
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ iii ] 200mm diameter
Details of cost for 10 joints =10x1.93=19.3 mtrs
a. Materials
200mm Concrete S/S Pipes Class NP-2 19.30 mtr 365.28 7049.90
labour for laying (same as C.I pipe)
wt. of 10 pcs of pipe= 19.30 x 48.92=944.156 kg =9.4416 qntl
9.4416 qntl 50.72 478.88
Jointing with rubber ring
200 mm dia rubber ring for 10 joints 10 each 45.00 450.00
b. Labour charges
Plumber Fitter(S) 1.33 Each 190 253.33
Helper to plumber or fitter 1.00 Each 170 170.00
Male worker 3.00 Each 150 450.00
(a+b) 8852.11
c. Add Contractor's Profit & Overhead charges 15% of 8852.11 1327.82
Total (a+b+c) 10179.93
Rate per metre = 10,179.93 ÷ 19.30 = 527.46
say 527.50
[ iv ] 250mm diameter
Details of cost for 10 joints =10x2.43=24.30 mtrs
a. Materials
250mm Concrete S/S Pipes Class NP-2 24.30 mtr 401.23 9749.89
Labour for laying (same as C.I pipe)
Wt. of 10 pcs of pipe= 24.30 x 58.43=1419.849 kg =14.1985 qntl
14.1985 qntl 50.72 720.15
Jointing with rubber ring
250 mm dia rubber ring for 10 joints 10 each 50.00 500.00
b. Labour charges
Plumber Fitter(S)=4/3 1.33 Each 190 253.33
Helper to plumber or fitter=1 1.00 Each 170 170.00
Male worker=3 3.00 Each 150 450.00
(a+b) 11843.37
c. Add Contractor's Profit & Overhead charges 15% of 11843.37 1776.51
Total (a+b+c) 13619.88
Rate per metre = 13,619.88 ÷ 24.3 = 560.49
say 560.50
4.3.5 Laying (to level or slopes) and jointing with rubber rings pre-cast reinforced socket and
spigot concrete pipes Class NP-3 conforming to IS:458 - 2003 suitable for rubber ring roll on
joint of the following internal diameter as per specification complete. (Earthwork in trenches to be
measured and paid for separately)
215
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% of 19983.31 2997.50
Total (a+b+c) 22980.81
Rate per metre = 22,980.81 ÷ 24.1 = 953.56
say 953.60
[ ii ] 350mm diameter
Details of cost for 10 joints =10x2.38=23.80 mtrs
a. Materials
350mm Concrete S/S Pipes Class NP-3 23.80 mtr 1260.50 29999.90
Labour for laying (same as C.I pipe)
Wt. of 10 pcs of pipe= 23.80 x 666.55/2.38=23.80x280.063kg =66.655 qntl
66.66 qntl 50.72 3380.74
Jointing with rubber ring
350 mm dia rubber ring for 10 joints 10 each 105.00 1050.00
b. Labour charges
Plumber Fitter(S)=3/2 1.50 Each 190 285.00
Helper to plumber or fitter=2 2.00 Each 170 340.00
Male worker=9/2 4.50 Each 150 675.00
(a+b) 35730.64
c. Add Contractor's Profit & Overhead charges 15% of 35730.64 5359.60
Total (a+b+c) 41090.24
Rate per metre = 41,090.24 ÷ 23.80 = 1726.48
say 1726.50
[ iv ] 450mm diameter
Details of cost for 10 joints =10x2.38=23.80 mtrs
a. Materials
450mm Concrete S/S Pipes Class NP-3 23.80 mtr 1552.52 36949.98
Labour for laying (same as C.I pipe)
Wt. of 10 pcs of pipe= 23.80 x 818.96/2.38=23.80x344.1008kg =8189.599 kg
81.896 qntl 50.72 4153.77
Jointing with rubber ring
450 mm dia rubber ring for 10 joints 10 each 170.00 1700.00
b. Labour charges
Plumber Fitter(S)=2 2.00 Each 190 380.00
Helper to plumber or fitter=2 2.00 Each 170 340.00
Male worker=5 5.00 Each 150 750.00
(a+b) 44273.75
216
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% of 44273.75 6641.06
Total (a+b+c) 50914.81
Rate per metre = 50,914.81 ÷ 23.80 = 2139.28
say 2139.30
[ vi ] 600mm diameter
Details of cost for 10 joints =10x2.35=23.50 mtrs
a. Materials
600mm Concrete S/S Pipes Class NP-3 23.50 mtr 2278.72 53549.92
Labour for laying (same as C.I pipe)
Wt. of 10 pcs of pipe= 23.50 x1217.55/2.35=23.50x518.1064kg =12175.50 kg
121.755 qntl 50.72 6175.41
Jointing with rubber ring
600 mm dia rubber ring for 10 joints 10 each 240.00 2400.00
b. Labour charges
Plumber Fitter(S)=8/3 2.67 Each 190 506.67
Helper to plumber or fitter=8/3 2.67 Each 170 453.33
Male worker=23/3 7.67 Each 150 1150.00
(a+b) 64235.33
c. Add Contractor's Profit & Overhead charges 15% of 64235.33 9635.30
Total (a+b+c) 73870.63
Rate per metre = 73,870.63 ÷ 23.50 = 3143.43
say 3143.40
217
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
c. Add Contractor's Profit & Overhead charges 15% of 82167.80 12325.17
Total (a+b+c) 94492.97
Rate per metre = 94,492.97 ÷ 23.50 = 4020.98
say 4021.00
[ ix ] 900mm diameter
Details of cost for 10 joints =10x2.35=23.50 mtrs
a. Materials
900mm Concrete S/S Pipes Class NP-3 23.50 mtr 4127.66 97000.01
Labour for laying (same as C.I pipe)
Wt. of 10 pcs of pipe= 23.50 x2096.34/2.35=892.0596kgx23.50 =20963.400 kg
209.63 qntl 50.72 10632.64
Jointing with rubber ring
900 mm dia rubber ring for 10 joints 10 each 480.00 4800.00
b. Labour charges
Plumber Fitter(S) 5.13 Each 190 973.75
Helper to plumber or fitter 5.13 Each 170 871.25
Male worker=19 7/8 19.88 Each 150 2981.25
(a+b) 117258.90
c. Add Contractor's Profit & Overhead charges 15% of 117258.90 17588.84
Total (a+b+c) 134847.74
Rate per metre = 134,847.74 ÷ 23.50 = 5738.20
say 5738.20
218
Section – 5
5.1.1 Labour for drilling a perfectly vertical bore hole of specified dia for a specified depth below ground
level through consolidated and unconsolidated rock with down the hole hammer drilling rigs or
combination drilling rigs (1200 cfm/ 300 psi) as required to suit the site condition as per the
direction of Engineer-in-charge including use of own rigs with its accessories, tools and plant and
consumables etc for lowering of 200 mm dia PVC/GI pipes for housing fitted with socket and with
or without well screen as per the necessity for soft, medium, hard and boulder formation (GI/PVC
casing pipes if required to prevent collapse of over burden is to be provided by the contractor
including lowering and withdrawing after completion of the tube well).
= 68,88,000.00
219
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
(i) Ownership Cost = Depriciation per hour + Interest Charge per hour
= 718.75/hr
(b) Interest Charge per hour = (Avg. Capital investment/ Scheduled
Working Hour) x Rate of Interest
= (68,88,000/2000) x 14/100
= 482.16
Ownership Cost = (a) + (b)
718.75 + 482.16
1200.91 /hr
(ii) Operational Cost
Repair Cost per hour = Capital Cost/ Life of Equipment x 100/100
= (12000000/16,000) x 100/100
= 750.00 /hr
(iii) Operation & Maintenance Cost
(a) Driller 1 Each 205.00 205.00
(b) Helper 1 Each 170.00 170.00
375.00
For 1 hour = 375.00 ÷ 8 46.88
(iv) Supervision Charges (15% of use rate)
15% of use rate = (Ownership cost + Repair cost-Rate Interest Charges ) x 15%
=( 1200.91 + 750.00 - 482.16 ) x 15%
= 1468.75 x 15%
= 220.31
(v) Surcharge = 10% of Repair Cost
= 750.00 x 10%
= 75.00
Total Hire Charges/ hr. = Ownership Cost + Operational Cost + Operation &
Maintenance Cost + Supervision Charges + Surcharge
1200.91 + 750.00 + 46.88
+ 220.31 + 75.00 = 2293.10
Hire Charges for approxmate 16 hours required for sinking of a tube well
Hire Charges 16 hrs = 2293.10 x 16 = 36689.60
(A+B+C+D) 80366.85
220
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.1.2 Lowering the following size G.I/ PVC pipes with or without slotted pipes as per the necessity
from ground level and fitted and fixed up in perfectly vertical position, including cutting and
threading pipe and slotted pipe and supplying and fixing all jointing materials, tools and plant etc.
complete and keeping the top of the casing pipe threaded including plugging tube wells to prevent
entry of foreign materials from above.
5.1.3 Cleaning and developing the tube well using their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per the direction of Engineer-in-Charge.
5.1.4 Supplying all materials, labour, tools and plant and withdrawing casing pipes from the
unsuccessful bore and depositing in the departmental store in good condition.
221
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ B ] Fuel & Lubricants for developing
HSD requirement for 2 hour for both compressor and power pack
30 Litre 55.00 1650.00
Add 5% for lubricant 82.50
[ C ] Hire Charges of the DTH / Combination Rig
Hire Charges for 1 hour use of compressor & power pack to withdraw
casing pipe detailed calculated in item No.1 (c) 2293.10
4818.10
[ D ] Add Contractor's Profit & Overhead charges 15% of 4818.10 722.72
Total (A+B+C+D) 5540.82
Rate per metre = 5,540.82 ÷ 30 = 184.69
or say 185.00
222
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.2 Sinking of 125mm x 100mm size Tube well through D.T.H or Combination drilling rigs
in hard rock areas with CI/PVC casing pipes
5.2.1 Labour for drilling a perfectly vertical bore hole of specified dia for a specified depth below
ground level through consolidated and unconsolidated rock with down the hole hammer drilling rigs
or combination drilling rigs (650 cfm/ 200 psi) as required to suit the site condition as per the
direction of Engineer-in-charge including use of own rigs with its accessories, tools and plant and
consumables etc for lowering of 125 mm dia PVC/GI pipes for housing fitted with socket and with
or without well screen as per the necessity for soft, medium, hard and boulder formation (GI/PVC
casing pipes if required to prevent collapse of over burden is to be provided by the contractor
including lowering and withdrawing after completion of the tube well).
= 5166000.00
(i) Ownership Cost = Depriciation per hour + Interest Charge per hour
5.2.2 Lowering the following size G.I/ PVC pipes with or without slotted pipes as per the necessity
from ground level and fitted and fixed up in perfectly vertical position, including cutting and
threading pipe and slotted pipe and supplying and fixing all jointing materials, tools and plant etc.
complete and keeping the top of the casing pipe threaded including plugging tube wells to prevent
entry of foreign materials from above.
224
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ B ] Fuel & Lubricants for 0 to 30 Mtrs. of lowering
HSD requirement for 1 hour of lowering for both compressor and power pack
HSD requirement for 2 hour for both compressor and power pack
30 Litre 55.00 1650.00
Add 5% for lubricant 82.50
1866.88
Add Contractor's Profit & Overhead charges 15% of 1866.88 280.03
2146.91
Rate per metre = 2,146.91 ÷ 30 = 71.56
say 71.60
5.2.3 Cleaning and developing the tube well using their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per the direction of Engineer-in-Charge.
5.2.4 Supplying all materials, labour, tools and plant and withdrawing casing pipes from the
unsuccessful bore and depositing in the departmental store in good condition.
225
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.3 Sinking of 125mm x 100mm size Tube well through calix rigs in hard granite including
boulder formation areas with PVC/GI casing pipes
5.3.1 Labour for drilling of a perfectly vertical bore hole of specified diameter for a specified depth below
ground level through hard and boulder formation by means of Calix rigs as required to suit the site
condition as per the direction of the Engineer in charge including deployment of rigs with its
accessories, tools and plant and consumables etc for a finished bore suitable for lowering of 125
mm x 100 mm nominal dia GI or PVC casing pipes fitted with socket and with or without well
screen as per the necessary for soft and hard formations drilled by combination drilling method.
[ A ] Labour for drilling of 125 mm dia bore 00 mtrs. to 30 Mtrs. and 100 mm dia bore
beyond 30 Mtrs. upto 60 Mtrs.
Labour charges
Approx. 8 days required with 8 hours of drilling daily for drilling upto 60 Mtrs. depth
a. Rig driller 8 x 1 = 8 Each 205.00 1640.00
b. Asst driller 8 x 1 = 8 Each 190.00 1520.00
c. Khallasi/ Mate 8 x 6 = 48 Each 170.00 8160.00
[ B ] Fuel & Lubricants for developing
HSD requirement for 8 days x 8 hours = 64 hours of drilling by Calix Rig
2 ltr.s per Hours 128 Litre 55.00 7040.00
Add 5% for lubricant 352.00
[ C ] Hire Charges of the Calix Rig
C = Cost of the Equipments
N = No. of Blocks
(2000 Hours in One Block)
L = Life of the Equipment
(Considering 10 Yrs. Life Span)
Daily working Hours= 8 Hours
Schedule Working days in Year = 200 Days)
= 10 x 200 x 8 = 16000 Hours
N = 16000 ÷ 2000 = 8
C = 350000..00
= 2,00,900.00
(i) Ownership Cost
226
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
(b) Interest Charge per hour = (Avg. Capital investment/ Scheduled
Working Hour) x Rate of Interest
= (2,00,900/2000) x 14/100
= 14.06
Ownership Cost = (a) + (b)
20.96 + 14.06
35.02 /hr
(ii) Operational Cost
(a) Repair Cost per hour = Capital Cost/ Life of Equipment x 100/100
= (3,50,000/16,000) x 100/100
= 21.90 /hr
(iii) Operation & Maintenance Cost
(a) Driller 1 Each 205.00 205.00
(b) Helper 1 Each 170.00 170.00
375.00
For 1 hours = 375.00 ÷ 8 46.88
(iv) Supervision Charges 15% of use rate
Use rate = Ownership cost + Repair cost-Rate Interest Charges
= 35.02 + 21.90 - 14.06
= 42.86 x 15%
= 6.43
(v) Surcharge = 10% of Repair Cost
= 21.90 x 10%
= 2.19
Total Hire Charges/ hr. = Ownership Cost + Operational Cost + Operation &
5.3.2 Labour for lowering the following sizes of G.I or P.V.C pipes with or without strainers as per
the necessity and fitted and fixed up in perfectly vertical position including cutting and threading
the pipes as may be necessary and supplying all jointing materials, extra sockets (GI or PVC heavy
quality) tools and plant etc complete and keeping the top of casing pipe threaded including
plugging tube wells to prevent entry of foreign materials from above.
227
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ B ] Fuel & Lubricants for 0 to 30 Mtrs. of Lowering
HSD requirement for 5 hours @ 2 ltr.s per hour
10 Litre 55.00 550.00
Add 5% for lubricant 27.50
1992.50
[ C ] Add Contractor's Profit & Overhead charges 15% of 1992.50 298.88
2291.38
Rate per metre = 2,291.38 ÷ 30 = 76.38
say 76.40
5.3.3 Cleaning and developing the tube well with their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per direction of the Engineer in charge
5.3.4 Supplying all materials, labour, tools and plant and providing sanitary sealing by cement
concrete grouting of annular space around GI/PVC/MS housing pipe upto 5 mtrs below ground
level (as per drawing) to plug the bore hole including cost of cement etc. all complete as per
direction of Engineer in charge. Minimum one metre of casing pipe to be inserted in the bore into
the rock at the bottom to ensure sanitary sealing
228
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.3.5 Supplying all materials, labour, tools and plant and withdrawing casing pipe from the
unsuccessful bore and depositing in the departmental store in good condition.
229
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.4 Sinking of 125mm x 100mm size Tube well through calix rigs in hard granite including
boulder formation areas with PVC/GI casing pipes (In hilly areas)
5.4.1 Labour for drilling of a perfectly vertical bore hole of specified diameter for a specified depth
below ground level through hard and boulder formation by means of Calix rigs as required to suit
the site condition as per the direction of the Engineer in charge including deployment of rigs with
its accessories, tools and plant and consumables etc for a finished bore suitable for lowering of 125
mm x 100 mm nominal dia GI or PVC casing pipes fitted with socket and with or without well
screen as per the necessary for soft and hard formations drilled by combination drilling method.
[A] Labour for drilling of 125 mm dia bore 00 mtrs. to 30 Mtrs. and 100 mm dia bore
beyond 30 Mtrs. upto 60 Mtrs.
Labour charges
Approx. 20 days required with 8 hours of drilling daily for drilling upto 60 Mtrs. depth
a. Rig driller (20 x 1)= 20 Each 205.00 4100.00
b. Asst driller (20 x 1)= 20 Each 190.00 3800.00
c. Khallasi/ Mate (20 x 6)= 120 Each 170.00 20400.00
[B] Fuel & Lubricants for 0 to 60 Mtrs. of drilling
HSD requirement for 20 days x 8 hours = 160 hours of drilling by Calix Rig
@ 2 ltr.s per hour 320 Litre 55.00 17600.00
Add 5% for lubricant 880.00
[C] Hire Charges of the Calix Rig
C = Cost of the Equipments
N = No. of Blocks
(2000 Hours in One Block)
L = Life of the Equipment
(Considering 10 Yrs. Life Span)
Daily working Hours= 8 Hours
Schedule Working days in Year = 200 Days)
= 10 x 200 x 8 = 16000 Hours
N = 16000 ÷ 2000 = 8
C = 350000..00
Average Capital Investment =
= 2,00,900.00
(i) Ownership Cost
230
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
(ii) Operational Cost
(a) Repair Cost per hour = Capital Cost/ Life of Equipment x 100/100
= (3,50,000/16,000) x 100/100
= 21.90 /hr
(iii) Operation & Maintenance Cost
(a) Driller 1 Each 205.00 205.00
(b) Helper 1 Each 170.00 170.00
375.00
For 1 hour = 375.00 ÷ 8 46.88
(iv) Supervision Charges 15% of use rate
15% of Use rate = (Ownership cost + Repair cost-Rate Interest Charges)x15%
=( 35.02 + 21.90 - 14.06 )x15%
= 42.86 x 15%
= 6.43
(v) Surcharge = 10% of Repair Cost
= 21.90 x 10%
= 2.19
Total Hire Charges/ hr. = Ownership Cost + Operational Cost + Operation &
5.4.2 Lowering the following size G.I/ PVC pipes with or without strainers as per the necessity,
fitted and fixed up in perfectly vertical position, including cutting and threading pipes as may be
necessary and suplying and fixing all jointing materials extra sockets (GI or PVC heavy quality),
tools and plant etc. complete and keeping the top of the casing pipe threaded including plugging
tube wells to prevent entry of foreign materials from above.
231
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.4.3 Cleaning and developing the tube well using their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per the direction of Engineer-in-Charge.
5.4.4 Supplying all materials, labour, tools and plant and providing sanitary sealing by cement
concrete grouting of annular space around GI/PVC/MS housing pipe upto 5 mtrs below ground
level (as per drawing) to plug the bore hole including cost of cement etc. all complete as per
direction of Engineer in charge. Minimum one metre of casing pipe to be inserted in the bore into
the rock at the bottom to ensure sanitary sealing
5.5 Sinking of 125/100 mm x 50 mm size tube well through Hand Boring (Water Jet)
Method with Sanitary/ Saline Sealing (in all kinds of soil)
5.5.1 Supplying all materials, labour, tools and plant and setting up boring equipments including
erection of suitable staging for installation of the required size of tubewell, dismantling and
removing the same after completion of the work, includifng transportation of the boring
equipments, cleaning and levelling the site, excavation of mud pit, channels etc. levelling of site all
complete as per direction of Engineer-in-charge.
5.5.2 Supplying all labour, tools and plants and transporting boring pipes, top casing, grouting
pipes, PVC pipes and fittings, PVC well screens, cement bentonite and gravels etc to work sites
including loading and unloading etc. complete as per the direction of the Engineer-in-charge
233
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.5.3 Supplying all labour, tools and plants and drilling pilot bore not less than 102 mm dia without
casing pipes in all kinds of soils for the following depths excluding supply of necessary cutting
equipments, extra sockets (whenever required) etc and withdrawing the boring pipes, washing and
keeping the bore clear for logging if required all complete as per the direction of Engineer-in-
charge
5.5.4 Supplying all required labour for logging the bore through departmental logging team (till
logging team arrives at the site, the contractor is to keep the bore intact by circulating mud
through the mud circulating system) and when the logging team arrives at the site, the contractor
will withdraw the boring pipe with cutter etc. and keep the bore suitable for loggifng and supply
required labour to carry out the logging operation.
5.5.5 Supplying all labour, tools land plant and reaming the pilot bore to the following sizes and
depths without casing pipes including withdrawing the boring pipes, washing the bore by means of
pipe cylinder etc. all complete as per direction of Engineer-in-Charge.
234
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ C ] Reaming from 200 mm to 250 mm dia, 0 mtr to 360 mtr
Labour charges
a. Boring Mistry 0.17 Each 190.00 32.30
b. Boring Helper 0.35 Each 170.00 59.50
91.80
c. Add Contractor's Profit & Overhead charges 15% of 91.80 13.77
105.57
say 105.60
5.5.6 Supplying all labour, tools and plant and jointing materials and lowering the 300mm dia top casing
pipes into the positioin and removing the same after use all complete as per direction of Engineer-
in-Charge.
Labour charges
a. Boring Mistry 0.75 Each 190.00 142.50
b. Boring Helper 3.00 Each 170.00 510.00
652.50
c. Add Contractor's Profit & Overhead charges 15% of 652.50 97.88
750.38
say 750.40
5.5.7 Supplying all labour, tools and plant and jointing materials and lowering the pvc casing pipes,
fittings and well screens in position, including fitting and fixing of centraliser, cutter plug and
washing the bore etc complete as per the direction of the Engineer in charge
5.5.8 Supplying all labour, tools and plant and grouting with cement bentonite slurry for saline sealing
in the bore around the 50mm dia pvc Casing pipe etc all complete as per the direction of the
Engineer-in-Charge excluding the cost of Cement.
Labour charges
a. Boring Mistry 3.50 Each 190.00 665.00
b. Boring Helper 9.00 Each 170.00 1530.00
2195.00
c. Add Contractor's Profit & Overhead charges 15% of 2195.00 329.25
2524.25
say 2524.30
235
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.5.9 Supplying all labour, tools and plant and packing the bore with washed gravel (size P-6)
around the pipes in good quality excluding cost of gravel etc all complete as per the direction of
the Engineer-in-charge
Labour charges
a. Boring Mistry 1 Each 190.00 190.00
b. Boring Helper 3 Each 170.00 510.00
700.00
c. Add Contractor's Profit & Overhead charges 15% of 700.00 105.00
805.00
say 805.00
5.5.10 Supplying all labour, tools and plant and grouting with cement slurry for sanitary sealing in the
bore around the upper most 3 metres of 125/100 mm dia PVC casing pipe properly as per the
direction of the Engineer-in-Charge. (Excluding the cost of cement)
Labour charges
a. Boring Mistry 1 Each 190.00 190.00
b. Boring Helper 2 Each 170.00 340.00
530.00
c. Add Contractor's Profit & Overhead charges 15% of 530.00 79.50
609.50
say 609.50
5.5.11 Supplying all labour, tools and plant and materials for cleaning and developing the tubewell
with compressor continuously washed till clean and adequate discharge is obtained from the tube
well including supply and use of necessary equipments and labour complete in all respect as per
the direction of the Engineer-in-Charge.
5.5.12 Supplying all labour T&P for fitting and fixing of IM-II/IM-III hand pumps with 32/65 mm dia
G.I pipe 24mtr and C.I cylinders and 12 mm B.S connecting rod including lowering with fitting of
extra socket etc.as per the direction of the Engineer-in-charge
Labour charges
a. Boring Mistry 0.75 Each 190.00 142.50
b. Boring Helper 2.80 Each 170.00 476.00
618.50
c. Add Contractor's Profit & Overhead charges 15% of 618.50 92.78
711.28
say 711.30
236
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.6 Sinking of 200 mm dia (8") Gravel Packed Production Well including saline sealing
where necessary through Rotary Drilling Rig 300 Mtrs with PVC/ GI Casing Pipes
5.6.1 Labour for drilling a perfectly vertical bore hole of specified dia for a specified depth below
ground level in alluvial soil strata by Mud Rotary Rig drilling as required to suit the site condition as
per the direction of Engineer-in-Charge including use of own rigs with its accessories, tools and
plant and consumables etc for lowering of finished bore suitable for lowering of 200 mm dia
GI/PVC pipes for housing, fitted with socket and with or without well screen as per the necessity
for the soft, medium, hard and boulder formation (GI/PVC casing pipes if required by the
contractor to prevent collapse of over burden portion) including lower and withdrawing of casing
pipe after drilling 200 mm to 450 mm dia in over burden portion.
= 5166000.00
(i) Ownership Cost
[ A ] Labour charges
Considering 6 days require with 8 hours per day for drilling of 101 to 200 m of one Production Well
a. Rig driller 6 x 1 = 6 Each 205.00 1230.00
b. Asst driller 6 x 1 = 6 Each 190.00 1140.00
c. Khallasi/ Mate 6 x 9 = 54 54 Each 170.00 9180.00
[ B ] Fuel & Lubricants for 101 to 200 Mtrs. of drilling
HSD requirement for 48 hours @ 12 Ltrs/hour of drilling for both compressor and power pack
576 Ltrs 55.00 31680.00
Add 5% for lubricant 1584.00
[ C ] Hire Charges of the Mud Rotary Rig
Hire Charges for approxmate 48 hours required for sinking of a production well -
as per item No. 1 ( C )
Hire Charges 48 Hrs 1731.54 83113.92
[ D ] Cost of Bentonite 15 bags @ 25kg / Bag 3.75 Qntl 269.00 1008.75
128936.67
Add Contractor's Profit & Overhead charges 15% of 128936.67 19340.50
148277.17
Rate per metre = 148,277.17 ÷ 100 = 1482.77
say 1482.80
238
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
( III ) 200 Mtrs to 300 Mtrs. and above
[ A ] Labour charges
Considering 7 days require with 8 hours per day for drilling of 201 to 300 mtr & above of one
Production Well
a. Rig driller 6 x 1 = 6 Each 205.00 1230.00
b. Asst driller 6 x 1 = 6 Each 190.00 1140.00
c. Khallasi/ Mate 6 x 9 = 54 54 Each 170.00 9180.00
[ B ] Fuel & Lubricants for 201 to 300 Mtrs. & above of drilling
HSD requirement for 56 hours @ 12 Ltrs/hour of drilling for both compressor and power pack
672 Ltrs 55.00 36960.00
Add 5% for lubricant 1848.00
[ C ] Hire Charges of the Mud Rotary Rig
Hire Charges for approxmate 56 hours required for sinking of a production well -
as per itemNo.1(C)
Hire Charges 56 Hrs 1731.54 96966.24
[ D ] Cost of Bentonite 17.5 bags @ 25kg / Bag 4.38 Qntl 269.00 1176.88
148501.12
Add Contractor's Profit & Overhead charges 15% of 148501.12 22275.17
170776.29
Rate per metre = 170,776.29 ÷ 100 = 1707.76
say 1707.80
5.6.2 Supply of all labour & T&P for lowering the following size G.I./PVC pipes with or without
slotted pipes as per the necessity from ground level and fitted and fixed up in perfectly vertical
position, including cutting and threading pipe and slotted pipe and fixing all jointing materials etc.
complete and keeping the top of the casing pipe threaded including plugging tube wells to prevent
entry of foreign materials from above excluding cost of fittings & jointing materials.
5.6.3 Cleaning and developing the production well using their own compressor continuously
worked till clear and adequate discharge is obtained from the tube well including supply and use of
all necessary equipment and labour as per the direction of Engineer-in-Charge.
239
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
Considering 8 hour. required for development of production well
a. Rig driller = 1 x 1 = 1 1 Each 205.00 205.00
b. Asst driller = 1 x 1 = 1 1 Each 190.00 190.00
c. Khallasi/ Mate = 1 x 4 = 4 4 Each 170.00 680.00
(B) Fuel & Lubricants for developing
HSD requirement for 8 hour for both compressor and power pack
80 Litre 55.00 4400.00
Add 5% for lubricant 220.00
[C] Hire Charges for approxmate 8 hours required for developing of productionwell
Hire Charges 8 Hrs 1731.54 13852.32
19547.32
Add Contractor's Profit & Overhead charges 15% of 19547.32 2932.10
22479.42
say 22479.40
5.6.4 Supplying all labour, tools and plant and grouting with cement bentonite slurry for saline sealing
in the bore around the 200mm dia P.V.C. Casing pipe etc all complete as per the direction of the
Engineer-in-Charge. (Excluding the cost of Cement.)
5.6.5 Supplying all labour,T&P and materials for packing the bore with washed gravel (size P-6)
around the pipes in good quality excluding cost of gravel etc complete as per the direction of the
Engineer-in-Charge.
5.6.6 Supplying all materials labour and T&P and grouting with cement slurry for sanitary sealing
around the GI/PVC casing pipe up to 3 mtrs. Below ground level including cost of cement all
complete as per the direction of Engineer-in-Charge
N.B::- Each bag cement (50 kg) added with 24 ltr of water and 1 to 2 kg bentonite
powder will form 40ltrs of slurry (0.021 cum)
240
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.6.7 Supplying all materials, labour, tools and plant and withdrawing casing pipe from the
unsuccessful bore and depositing in the departmental store in good condition.
241
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.7 CONSTRUCTION OF 150MM DIA GRAVEL PACKED PRODUCTION
WELL THROUGH HAND BORING (WATER JET) METHOD WITH
SANITARY/SALINE SEALING
5.7.1 Supplying all materials, labour, tools and plant and setting up boring equipments including
erection of suitable staging for installation of the required size of tubewell, dismantling and
removing the same after completion of the work, includifng transportation of the boring
equipments, cleaning and levelling the site, excavation of mud pit, channels etc. levelling of site all
complete as per direction of Engineer-in-charge.
Labour charges
a. Boring mistry 4 Each 190.00 760.00
b. Boring helper 23 Each 170.00 3910.00
c. Cost of bullah, bamboo and kata rasi etc LS 800.00
5470.00
d. Add Contractor's Profit & Overhead charges 15% of 5470.00 820.50
6290.50
Rate per setting or say 6291.00
5.7.2 Supplying all labour, tools and plants and transporting boring pipes, top casing, grouting
pipes, PVC pipes and fittings, PVC well screens, cement bentonite and gravels etc to work sites
including loading and unloading etc. complete as per the direction of the Engineer-in-charge
5.7.3 Supplying all labour, tools and plants and drilling pilot bore not less than 102 mm dia without
casing pipes in all kinds of soils for the following depths excluding supply of necessary cutting
equipments, extra sockets (whenever required) etc and withdrawing the boring pipes, washing and
keeping the bore clear for logging if required all complete as per the direction of Engineer-in-
charge
5.7.5 Supplying all labour, tools land plant and reaming the pilot bore to the following sizes and
depths without casing pipes including withdrawing the boring pipes, washing the bore by means of
pipe cylinder etc all complete as per direction of Engineer-in-Charge.
5.7.6 Supplying all labour, tools and plant and jointing materials and lowering the 300mm dia top casing
pipes into the positioin and removing the same after use all complete as per direction of Engineer-
in-Charge.
Labour charges
a. Boring Mistry 0.75 Each 190.00 142.50
b. Boring Helper 3.00 Each 170.00 510.00
652.50
c. Add Contractor's Profit & Overhead charges 15% of 652.50 97.88
750.38
say 750.40
5.7.7 Supplying all labour, tools and plant and jointing materials and lowering the pvc casing pipes,
fittings and well screens in position including fitting and fixing of centraliser, cutter plug and
washing the bore etc complete as per the direction of the Engineer in charge
243
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.7.8 Supplying all labour, tools and plant and grouting with cement bentonite slurry for saline sealing
in the bore around the 150mm dia pvc Casing pipe etc all complete as per the direction of the
Engineer-in-Charge excluding the cost of Cement.
Labour charges
a. Boring Mistry 3.50 Each 190.00 665.00
b. Boring Helper 9.00 Each 170.00 1530.00
2195.00
c. Add Contractor's Profit & Overhead charges 15% of 2195.00 329.25
2524.25
say 2524.30
5.7.9 Supplying all labour, tools and plant and packing the bore with washed gravel (size P-6)
around the pipes in good quality excluding cost of gravel etc all complete as per the direction of
the Engineer-in-charge
Labour charges
a. Boring Mistry 1 Each 190.00 190.00
b. Boring Helper 3 Each 170.00 510.00
700.00
c. Add Contractor's Profit & Overhead charges 15% of 700.00 105.00
805.00
say 805.00
5.7.10 Supplying all labour, tools and plant and grouting with cement slurry for sanitary sealing in the
bore around the upper most 3 metres of 150 mm dia PVC casing pipe properly as per the direction
of the Engineer-in-Charge. (Excluding the cost of cement)
Labour charges
a. Boring Mistry 1 Each 190.00 190.00
b. Boring Helper 2 Each 170.00 340.00
530.00
c. Add Contractor's Profit & Overhead charges 15% of 530.00 79.50
609.50
say 609.50
5.7.11 Supplying all labour, tools and plant and materials for cleaning and developing the tubewell
with compressor continuously washed till clean and adequate discharge is obtained from the tube
well including supply and use of necessary equipments and labour complete in all respect as per
the direction of the Engineer-in-Charge.
244
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.8 Sinking of 150x125 mm dia Production Well through D.T.H or
Combination drilling rig in hard rock areas with PVC/GI casing pipe
5.8.1 Labour for drilling a perfectly vertical bore hole of specified dia for a specifieddepth below
ground level through consolidated and unconsolidated rock with down the hole hammer drilling rigs
or combination drilling rigs (650 cfm/200 psi) as required to suit the site condition as per the
direction of Engineer-in-Charge including use of own rigs with its accessories, tools and plant and
consumables etc for lowering of 150 mm dia PVC/GI pipes for housing fitted with socket and with
or without well screen as per the necessity for soft, medium, hard and houlder formation(GI/PVC
casing pipes if required to prevent collapse of over burden is to be provided by the contractor
including lowering and withdrawing after completion of the tube well). Withdrawing after
completion of the tube well
A] Labour for drilling 150mm dia bore
0mtr to 30mtr
Considering four hours required for drilling of 150mm dia from 0mtr to 30mtr
a) Rig Driller 0.30 Each 205.00 61.50
b) Asst. Driller 0.30 Each 190.00 57.00
c) Khallasi/Mate 2.00 Each 170.00 340.00
458.50
B] Labour for drilling of 125mm dia Bore (30m.to 150m)
a) Rig Driller 0.75 Each 205.00 153.75
b) Asst. Driller 0.75 Each 190.00 142.50
c) Khallasi/Mate 4.50 Each 170.00 765.00
1061.25
C] Fuel & lubricants for 0 to 150mtr of drilling
HSD requirement for 9 hours of drilling for both compressor and power pack
720 Ltr 55.00 39600.00
Add 5% for lubricant 1980.00
41580.00
D] Hire charges of the DTH combination rig
as per 200mm dia/150mm dia production well 36689.60
79789.35
Add Contractor's Profit & Overhead charges 15% of 79789.35 11968.40
91757.75
Rate per metre = 91,757.75 ÷ 150 = 611.72
say 611.70
5.8.2 Lowering the following size G.I/ PVC pipes with or without slotted pipes as per the necessity
from ground level and fitted and fixed up in perfectly vertical position, including cutting and
threading pipe and slotted pipe and supplying and fixing all jointing materials, tools and plant etc.
complete and keeping the top of the casing pipe threaded including plugging tube wells to prevent
entry of foreign materials from above.
245
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
[ B ] Fuel & Lubricants for 0 to 45 Mtrs. and above of Lowering
HSD requirement for 1 hour of lowering for both compressor and power pack
60 Litre 55.00 3300.00
Add 5% for lubricant 165.00
3606.50
[ C ] Add Contractor's Profit & Overhead charges 15% of 3606.50 540.98
4147.48
Rate per metre = 4,147.48 ÷ 45 = 92.17
say 92.20
5.8.3 Cleaning and developing the tube well using their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per the direction of Engineer-in-Charge.
5.8.4 Supplying all materials, labour, tools and plant and withdrawing casing pipes from the
unsuccessful bore and depositing in the departmental store in good condition.
246
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.9 Sinking of 125mm/100mm size tube well through D.T.H or
Combination drilling rigs in boulder formation areas with M.S casing
pipes.
5.9.1 Supplying all labour and drilling perfectly vertical bore holes in boulder formation areas with
down the hole hammer drilling rigs or combination drilling rigs to suit the site condition with
deployment of rig, necessary accessories and consumables for a specified depth below ground level
including supply of necessary cashing shoe, odex tools and plants, jointing materials, extra sockets
where required withdrawing of pipes, lowering the M.S. (ERW) pipes and fitting and fixing in
perfectly vertical position including cutting and welding for jointing the pipes for simultaneous
casing lowering in over burden boulder formation till encounter of hard rock and to drill 125mm
DTH upto the desired depth as may be necessary, clearing the site and washing bore etc., all
complete providing sanitary sealing upto 5 metres depth below ground level as per the direction of
Engineer-in-charge
= 68,88,000.00
247
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
(i) Ownership Cost
248
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.9.2 Labour for drilling a perfectly vertical bore hole of 100mm dia for a specified depth below
boulder zone through consolidated and unconsolidated rock with down the hole hammer drilling
rigs or combination drilling rigs as required to suit the site condition as per the direction of
Engineer-in-charge including use of own rigs with its accessories, tools and plant and consumables
etc.
5.9.3 Cleaning and developing the tube well using their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per the direction of Engineer-in-Charge
5.9.4 Supplying all materials, labour, tools and plant and withdrawing casing pipe from the
unsuccessful bore and depositing in the departmental store in good condition
249
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.10 Sinking of 200mm/150mm size tube well through D.T.H or
Combination drilling rigs in boulder formation areas with M.S casing
pipes.
5.10.1 Supplying all labour and drilling perfectly vertical bore holes in boulder formation areas with
down the hole hammer drilling rigs or combination drilling rigs to suit the site condition with
deployment of rig, necessary accessories and consumables for a specified depth below ground level
including supply of necessary cashing shoe, odex tools and plants, jointing materials, extra sockets
where required withdrawing of pipes, lowering the M.S. (ERW) pipes and fitting and fixing in
perfectly vertical position including cutting and welding for jointing the pipes for simultaneous
casing lowering in over burden boulder formation till encounter of hard rock and to drill 200mm
DTH upto the desired depth as may be necessary, clearing the site and washing bore etc., all
complete providing sanitary sealing upto 5 metres depth below ground level as per the direction of
Engineer-in-charge
1,50,00,000
= 8
0.514 𝑋 8 + 0.48
= 8,610,000.00
250
8
0.514 𝑋 8 + 0.48
251
Sl No Description Quantity Unit Rate (Rs) Amount (Rs)
1 2 3 4 5 6
5.10.2 Labour for drilling a perfectly vertical bore hole of 100mm dia for a specified depth below
boulder zone through consolidated and unconsolidated rock with down the hole hammer drilling
rigs or combination drilling rigs as required to suit the site condition as per the direction of
Engineer-in-charge including use of own rigs with its accessories, tools and plant and consumables
etc.
5.10.3 Cleaning and developing the tube well using their own compressor continuously worked till
clear and adequate discharge is obtained from the tube well including supply and use of all
necessary equipment and labour as per the direction of Engineer-in-Charge
5.10.4 Supplying all materials, labour, tools and plant and withdrawing casing pipe from the
unsuccessful bore and depositing in the departmental store in good condition
252
ANNEXURES
Annexure-1
Table - 1.1
Class-LA
Dia in
Sl No. Weight in Rate per
mm Amount
Quintal Mtr
1 80 0.161 664.49 773.60
2 100 0.205 832.15 968.90
3 125 0.268 1057.91 1232.20
4 150 0.333 1283.13 1495.00
5 200 0.486 1869.15 2177.90
6 250 0.656 2520.20 2936.50
7 300 0.847 3255.26 3793.00
8 350 1.066 4096.37 4773.00
9 400 1.295 4979.79 5802.30
10 450 1.563 6009.36 7001.90
11 500 1.833 7049.45 8213.80
12 600 2.443 9392.26 10943.60
13 700 3.150 12113.28 14114.00
14 750 3.533 13584.11 15827.80
15 800 3.954 15202.01 17712.90
16 900 4.817 18521.87 21581.10
17 1000 5.790 22261.97 25939.00
Table - 1.2
Class-A
Dia in
Sl No. Weight in Rate per
mm Amount
Quintal Mtr
1 80 0.175 721.70 840.20
2 100 0.224 909.63 1059.10
3 125 0.290 1145.78 1334.60
4 150 0.363 1397.32 1628.10
5 200 0.527 2025.42 2360.00
6 250 0.713 2740.28 3192.90
7 300 0.921 3539.69 4124.40
8 350 1.153 4432.46 5164.60
9 400 1.413 5433.20 6330.60
10 450 1.713 6586.75 7674.70
11 500 1.989 7648.01 8911.20
12 600 2.658 10220.42 11908.50
13 700 3.434 13204.26 15385.20
14 750 3.850 14803.84 17249.00
15 800 4.295 16514.93 19242.70
16 900 5.240 20148.60 23476.50
17 1000 6.306 24247.53 28252.50
Table - 1.3
Class-B
Dia in
Sl No. Weight in Rate per
mm Amount
Quintal Mtr
1 80 0.189 780.05 908.10
2 100 0.240 974.61 1134.80
3 125 0.311 1228.75 1431.20
4 150 0.391 1505.11 1753.70
5 200 0.566 2175.31 2534.60
6 250 0.768 2951.66 3439.20
7 300 0.995 3824.09 4455.70
8 350 1.249 4801.51 5594.60
9 400 1.522 5852.32 6818.90
10 450 1.844 7090.46 8261.60
11 500 2.148 8259.39 9623.60
12 600 2.874 11050.97 12876.30
13 700 3.702 14234.76 16585.90
14 750 4.167 16022.75 18669.20
15 800 4.634 17818.44 20761.50
16 900 5.664 21778.95 25376.20
17 1000 6.801 26150.89 30470.20
For deriving cost of all types of CI pipes, specials the following rates have been considered.
1 80mm dia = Rs.41,272.44/MT
2 100mm dia = Rs.40,608.68/MT
3 125mm dia = Rs.39,509.70/MT
4 150mm dia = Rs.38,493.78/MT
5 200mm dia = Rs.38,433.10/MT
6 250mm dia = Rs.38,433.10/MT
7 300mm dia = Rs.38,433.10/MT
8 350mm dia = Rs.38,442.84/MT
9 400mm dia = Rs.38,451.53/MT
2
Annexure-2
Table - 2.1
Class-A
Sl No. Dia in mm Weight in Rate per Amount
Quintal Mtr
1 80 0.203 837.83 975.30
2 100 0.255 1035.52 1205.70
3 125 0.330 1303.82 1518.60
4 150 0.414 1593.64 1856.80
5 200 0.595 2286.77 2664.50
6 250 0.797 3063.12 3569.10
7 300 1.026 3943.24 4594.60
8 350 1.262 4851.49 5652.80
9 400 1.560 5998.44 6989.20
10 450 1.886 7251.96 8449.80
11 500 2.191 8424.73 9816.20
12 600 2.938 11297.06 13163.00
Table - 2.2
Class-B
Sl No. Dia in mm Weight in Rate per Amount
Quintal Mtr
1 80 0.216 891.48 1037.80
2 100 0.270 1096.43 1276.60
3 125 0.353 1394.69 1624.50
4 150 0.441 1697.58 1977.90
5 200 0.635 2440.50 2843.60
6 250 0.853 3278.34 3819.80
7 300 1.100 4227.64 4925.90
8 350 1.357 5216.69 6078.30
9 400 1.668 6413.72 7473.10
10 450 1.994 7667.24 8933.60
11 500 2.353 9047.65 10542.00
12 600 3.153 12123.77 14126.20
3
Annexure-3
Table - 3.1
Class-A
Dia in
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.175 721.70 840.20
2 100 0.224 909.63 1059.10
3 125 0.290 1145.78 1334.60
4 150 0.363 1397.32 1628.10
5 200 0.527 2025.42 2360.00
6 250 0.713 2740.28 3192.90
7 300 0.921 3539.69 4124.40
8 350 1.153 4432.46 5164.60
9 400 1.413 5433.20 6330.60
10 450 1.713 6586.75 7674.70
11 500 1.989 7648.01 8911.20
12 600 2.658 10220.42 11908.50
13 700 3.434 13204.26 15385.20
14 750 3.850 14803.84 17249.00
15 800 4.295 16514.93 19242.70
16 900 5.240 20148.60 23476.50
17 1000 6.306 24247.53 28252.50
Table - 3.2
Class-B
Dia in
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.189 780.05 908.10
2 100 0.240 974.61 1134.80
3 125 0.311 1228.75 1431.20
4 150 0.391 1505.11 1753.70
5 200 0.566 2175.31 2534.60
6 250 0.768 2951.66 3439.20
7 300 0.995 3824.09 4455.70
8 350 1.249 4801.51 5594.60
9 400 1.522 5852.32 6818.90
10 450 1.844 7090.46 8261.60
11 500 2.148 8259.39 9623.60
12 600 2.874 11050.97 12876.30
13 700 3.702 14234.76 16585.90
14 750 4.167 16022.75 18669.20
15 800 4.634 17818.44 20761.50
16 900 5.664 21778.95 25376.20
17 1000 6.801 26150.89 30470.20
4
Annexure-4
Table - 4.1
Dia in Class-A
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.197 813.07 946.50
2 100 0.247 1003.03 1167.90
3 125 0.317 1252.46 1458.80
4 150 0.399 1535.90 1789.60
5 200 0.574 2206.06 2570.40
6 250 0.770 2959.35 3448.20
7 300 0.988 3797.19 4424.40
8 350 1.240 4766.91 5554.30
9 400 1.521 5848.48 6814.50
10 450 1.825 7017.40 8176.50
11 500 2.131 8194.02 9547.40
12 600 2.854 10974.07 12786.60
13 700 3.715 14284.74 16644.10
14 750 4.187 16099.66 18758.80
15 800 4.699 18068.37 21052.70
16 900 5.689 21875.08 25488.20
17 1000 6.900 26531.56 30913.80
Table - 4.2
Class-B
Dia in
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.210 866.72 1009.00
2 100 0.262 1063.95 1238.80
3 125 0.340 1343.33 1564.70
4 150 0.426 1639.84 1910.70
5 200 0.614 2359.79 2749.60
6 250 0.826 3174.57 3698.90
7 300 1.062 4081.60 4755.80
8 350 1.335 5132.12 5979.80
9 400 1.629 6263.75 7298.30
10 450 1.955 7517.27 8758.90
11 500 2.288 8797.71 10250.80
12 600 3.069 11800.77 13749.90
13 700 3.981 15307.55 17835.90
14 750 4.504 17318.57 20179.10
15 800 5.039 19375.73 22576.00
16 900 6.112 23501.58 27383.30
17 1000 7.392 28423.37 33118.00
5
Annexure-5
Table - 5.1
Dia in Class-B
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.225 928.63 1081.00
2 100 0.285 1157.35 1347.60
3 125 0.370 1461.86 1702.70
4 150 0.465 1789.96 2085.60
5 200 0.669 2571.17 2995.90
6 250 0.905 3478.20 4052.70
7 300 1.169 4492.83 5234.90
8 350 1.473 5662.63 6597.90
9 400 1.796 6905.89 8046.50
10 450 2.163 8317.07 9690.80
11 500 2.526 9712.86 11317.10
12 600 3.385 13015.84 15165.70
13 700 4.379 16837.92 19619.00
14 750 4.945 19014.28 22154.90
6
Annexure-6
Table - 6.1
Dia in LP
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.120 495.27 576.60
2 100 0.142 576.64 671.40
3 125 0.189 746.73 869.80
4 150 0.232 893.06 1040.60
5 200 0.369 1418.18 1652.40
6 250 0.484 1860.16 2167.40
7 300 0.623 2394.38 2789.90
8 350 0.825 3171.53 3695.40
9 400 1.003 3856.69 4493.70
10 450 1.210 4652.64 5421.10
11 500 1.503 5779.26 6733.80
12 600 2.003 7701.84 8973.90
7
Annexure-7
Table - 7.1
Class-K-9
Sl No. Dia in mm Weight in Rate per Amount
Quintal Mtr
1 80 0.130 638.50 741.90
2 100 0.163 800.60 930.20
3 125 0.205 996.30 1157.70
4 150 0.248 1178.07 1369.20
5 200 0.333 1618.35 1880.50
6 250 0.438 2171.81 2523.10
7 300 0.555 2753.80 3199.20
8 350 0.693 3360.81 3905.40
9 400 0.828 4035.79 4689.50
10 450 0.988 4794.03 5570.80
11 500 1.150 5600.78 6508.00
12 600 1.520 7395.22 8593.20
13 700 1.938 9443.30 10972.80
14 750 2.175 10600.56 12317.50
15 800 2.408 11719.62 13618.00
16 900 2.928 14265.68 16576.30
17 1000 3.498 17049.71 19811.20
Table - 7.2
Class-K-7
Sl No. Dia in mm Weight in Rate per Amount
Quintal Mtr
1 80 0.121 546.53 635.60
2 100 0.154 695.58 808.90
3 125 0.185 830.87 966.30
4 150 0.228 1023.99 1190.90
5 200 0.301 1343.52 1562.60
6 250 0.393 1771.95 2060.70
7 300 0.484 2243.22 2607.90
8 350 0.660 2740.41 3190.00
9 400 0.783 3294.12 3833.90
10 450 0.914 3873.64 4508.00
11 500 1.066 4571.33 5319.20
12 600 1.386 6042.67 7029.90
13 700 1.889 8192.40 9531.40
14 750 2.135 9426.51 10965.00
15 800 2.395 10757.71 12511.10
16 900 2.827 13104.78 15235.40
17 1000 3.482 15670.81 18224.50
8
Annexure-8
Table - 8.1
Class-K-9 Flanged
Dia in Weight in Rate per Amount
Sl No.
mm Quintal Mtr
Table - 8.2
Class-K-7 Flanged
Dia in
Sl No. Weight in Rate per Amount
mm
Quintal Mtr
1 80 0.130 587.18 682.80
2 100 0.161 727.20 845.70
3 125 0.190 853.33 992.40
4 150 0.230 1032.97 1201.30
5 200 0.308 1374.76 1598.90
6 250 0.405 1826.06 2123.60
7 300 0.499 2312.74 2688.80
8 350 0.667 2769.47 3223.80
9 400 0.795 3344.60 3892.70
10 450 0.916 3882.12 4517.90
11 500 1.066 4571.33 5319.20
12 600 1.396 6086.27 7080.60
13 700 1.891 8201.07 9541.50
14 750 2.150 9492.74 11042.10
15 800 2.417 10856.53 12626.00
16 900 2.819 13067.70 15192.30
17 1000 3.484 15679.81 18235.00
9
Annexure-9
Table - 9.1
90° bend
Dia in
Sl No. Weight in Rate per Amount
mm
Quintal Each
1 80 0.180 742.90 872.60
2 100 0.240 974.61 1145.20
3 125 0.330 1303.82 1532.90
4 150 0.430 1655.23 1947.20
5 200 0.670 2575.02 3029.40
6 250 0.980 3766.44 4431.00
7 300 1.350 5188.47 6104.00
8 350 1.810 6958.15 8185.90
9 400 2.340 8997.66 10585.20
10 450 2.900 11150.94 13118.40
11 500 3.700 14227.07 16737.20
12 600 5.460 20994.54 24698.70
13 700 7.700 29607.68 34831.50
14 750 8.990 34567.93 40666.90
15 800 10.470 40258.75 47361.80
16 900 13.890 53409.18 62832.50
17 1000 17.800 68443.72 80519.60
Table - 9.2
45° bend
Dia in Weight in Rate per Amount
Sl No.
mm Quintal Each
10
Table - 9.3
o
22.50 bend
Dia in
Sl No. Weight in Rate per
mm Amount
Quintal Each
1 80 0.160 660.36 775.70
2 100 0.210 852.78 1002.00
3 125 0.270 1066.76 1254.20
4 150 0.350 1347.28 1584.90
5 200 0.530 2036.95 2396.40
6 250 0.750 2882.48 3391.10
7 300 1.000 3843.31 4521.50
8 350 1.300 4997.57 5879.30
9 400 1.640 6306.05 7418.70
10 450 1.970 7574.95 8911.40
11 500 2.460 9459.08 11128.00
12 600 3.510 13496.49 15877.70
13 700 4.780 18379.83 21622.70
14 750 5.510 21186.79 24924.90
15 800 6.320 24301.37 28589.00
16 900 8.130 31261.09 36776.70
17 1000 10.240 39374.37 46321.40
Table - 9.4
11.25° bend
Dia in
Sl No. Weight in Rate per
mm Amount
Quintal Each
1 80 0.150 619.09 727.20
2 100 0.190 771.56 906.60
3 125 0.250 987.74 1161.30
4 150 0.320 1231.80 1449.10
5 200 0.480 1844.79 2170.30
6 250 0.670 2575.02 3029.40
7 300 0.890 3420.55 4024.10
8 350 1.150 4420.93 5201.00
9 400 1.140 4383.47 5156.90
10 450 1.720 6613.66 7780.50
11 500 2.150 8267.08 9725.70
12 600 3.020 11612.36 13661.20
13 700 4.080 15688.22 18456.20
14 750 4.690 18033.77 21215.60
15 800 5.340 20533.12 24155.90
16 900 6.820 26223.94 30850.80
17 1000 8.520 32760.70 38540.90
11
Annexure-10
Table - 10.1
Size in Weight in Rate per Amount
Sl No.
mm Quintal Each
1 80x80 0.230 949.27 1115.00
2 100x80 0.280 1137.04 1336.10
3 100x100 0.300 1218.26 1431.50
4 125x80 0.360 1422.35 1672.30
5 125x100 0.380 1501.37 1765.20
6 125x125 0.410 1619.90 1904.60
7 150x80 0.450 1732.22 2037.80
8 150x100 0.470 1809.21 2128.40
9 150x125 0.500 1924.69 2264.20
10 150x150 0.530 2040.17 2400.10
11 200x80 0.670 2575.02 3029.40
12 200x100 0.690 2651.88 3119.80
13 200x125 0.710 2728.75 3210.20
14 200x150 0.740 2844.05 3345.90
15 200x200 0.810 3113.08 3662.40
16 250x80 0.940 3612.71 4250.20
17 250x100 0.960 3689.58 4340.60
18 250x125 0.990 3804.88 4476.20
19 250x150 1.020 3920.18 4611.90
20 250x200 1.080 4150.77 4883.20
21 250x250 1.160 4458.24 5244.90
22 300x80 1.280 4919.44 5787.50
23 300x100 1.290 4957.87 5832.70
24 300x125 1.320 5073.17 5968.30
25 300x150 1.340 5150.04 6058.80
26 300x200 1.420 5457.50 6420.50
27 300x250 1.500 5764.97 6782.20
28 300x300 1.590 6110.86 7189.10
29 350x200 1.820 6996.60 8231.10
30 350x250 1.900 7304.14 8592.90
31 350x300 1.990 7650.13 8999.90
32 350x350 2.090 8034.55 9452.20
33 400x200 2.290 8805.40 10359.00
34 400x250 2.370 9113.01 10720.90
35 400x300 2.460 9459.08 11128.00
36 400x350 2.560 9843.59 11580.30
37 400x400 2.860 10997.14 12937.40
38 450x250 2.950 11343.20 13344.50
39 450x300 3.040 11689.27 13751.70
40 450x350 3.140 12073.78 14204.00
41 450x400 3.240 12458.30 14656.40
42 450x450 3.370 12958.17 15244.50
43 500x250 3.560 13688.74 16103.90
44 500x300 3.650 14034.81 16511.00
45 500x350 3.750 14419.32 16963.40
46 500x400 3.860 14842.29 17461.00
47 500x450 3.980 15303.71 18003.80
48 500x500 4.130 15880.48 18682.40
49 600x300 5.210 20033.25 23567.80
50 600x350 5.310 20417.76 24020.20
51 600x400 5.430 20879.18 24563.00
52 600x450 5.560 21379.05 25151.10
53 600x500 5.690 21878.92 25739.10
54 600x600 6.020 23147.82 27231.90
12
Size in Weight in Rate per Amount
Sl No.
mm Quintal Each
55 700x350 7.290 28031.17 32976.90
56 700x400 7.420 28531.04 33564.90
57 700x450 7.560 29069.36 34198.20
58 700x500 7.690 29569.23 34786.30
59 700x600 7.950 30568.97 35962.40
60 700x700 8.320 31991.67 37636.10
61 750x400 8.550 32876.06 38676.60
62 750x450 8.690 33414.38 39309.90
63 750x500 8.840 33991.15 39988.40
64 750x600 9.110 35029.34 41209.80
65 750x700 9.420 36221.34 42612.10
66 750x750 9.650 37105.73 43652.50
67 800x400 9.820 37759.40 44421.50
68 800x450 9.960 38297.72 45054.80
69 800x500 10.100 38836.05 45688.10
70 800x600 10.400 39989.59 47045.20
71 800x700 10.720 41220.04 48492.70
72 800x750 10.890 41873.72 49261.70
73 800x800 11.140 42835.00 50392.60
74 900x450 12.880 49525.57 58263.60
75 900x500 13.020 50063.89 58896.90
76 900x600 13.370 51409.70 60480.20
77 900x700 13.710 52717.05 62018.20
78 900x750 13.880 53370.72 62787.20
79 900x800 14.050 54024.40 63556.20
80 900x900 14.530 55870.07 65727.50
81 1000x500 16.480 63368.12 74548.50
82 1000x600 16.810 64637.02 76041.30
83 1000x700 17.230 66251.99 77941.20
84 1000x750 17.410 66944.11 78755.40
85 1000x800 17.590 67636.24 79569.70
86 1000x900 17.970 69097.40 81288.60
87 1000x1000 18.520 71212.23 83776.60
13
Annexure-11
Table - 11.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80 0.03 123.82 145.40
2 100 0.04 162.43 190.90
3 125 0.06 237.06 278.70
4 150 0.09 346.44 407.60
5 200 0.14 538.06 633.00
6 250 0.22 845.53 994.70
7 300 0.30 1152.99 1356.40
8 350 0.41 1576.16 1854.30
9 400 0.54 2076.38 2442.70
10 450 0.69 2653.16 3121.30
11 500 0.86 3306.83 3890.30
12 600 1.27 4883.34 5744.90
13 700 1.80 6921.28 8142.40
14 750 2.11 8113.27 9544.70
15 800 2.46 9459.08 11128.00
16 900 3.21 12342.94 14520.70
17 1000 4.11 15803.58 18591.90
14
Annexure-12
Table - 12.1
90° bend
Dia in
Sl No. Weight in Rate per
mm Amount
Quintal Each
1 80 0.130 536.54 630.20
2 100 0.170 690.35 811.20
3 125 0.230 908.72 1068.40
4 150 0.310 1193.31 1403.80
5 200 0.490 1883.22 2215.50
6 250 0.720 2767.18 3255.40
7 300 1.000 3843.31 4521.50
8 350 1.370 5266.67 6195.90
9 400 1.810 6959.73 8187.70
10 450 2.260 8690.05 10223.30
11 500 2.900 11150.94 13118.40
12 600 4.420 16995.58 19994.20
13 700 6.390 24570.53 28905.60
14 750 7.550 29030.91 34153.00
15 800 8.900 34221.86 40259.80
16 900 11.790 45334.35 53332.90
17 1000 15.440 59369.16 69844.00
Table - 12.2
Sl No. Dia in 45° bend
mm Weight in Rate per Amount
1 80 0.140 577.81 664.50
2 100 0.180 730.96 840.60
3 125 0.250 987.74 1135.90
4 150 0.340 1308.79 1505.10
5 200 0.540 2075.39 2386.70
6 250 0.800 3074.65 3535.80
7 300 1.120 4304.51 4950.20
8 350 1.150 4420.93 5084.10
9 400 1.490 5729.28 6588.70
10 450 1.850 7113.53 8180.60
11 500 2.310 8882.30 10214.60
12 600 3.420 13150.42 15123.00
13 700 4.850 18648.99 21446.30
14 750 5.720 21994.28 25293.40
15 800 6.670 25647.17 29494.20
16 900 8.680 33375.93 38382.30
17 1000 11.250 43257.97 49746.70
15
Annexure-13
Table - 13.1
Sl No. Dia in Weight in Rate per Amount
1 80 0.210 866.72 1018.10
2 100 0.260 1055.83 1240.60
3 125 0.360 1422.35 1672.30
4 150 0.470 1809.21 2128.40
5 200 0.740 2844.05 3345.90
6 250 1.110 4266.07 5018.80
7 300 1.560 5995.56 7053.50
8 350 2.140 8226.77 9678.30
9 400 2.810 10804.88 12711.20
10 450 3.500 13458.04 15832.50
11 500 4.460 17149.38 20175.10
12 600 6.770 26031.69 30624.60
16
Annexure-14
Table - 14.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80x80 0.210 866.72 1018.10
2 100x80 0.250 1015.22 1192.90
3 100x100 0.260 1055.83 1240.60
4 125x80 0.320 1264.31 1486.50
5 125x100 0.340 1343.33 1579.40
6 125x125 0.360 1422.35 1672.30
7 150x80 0.410 1578.24 1856.70
8 150x100 0.420 1616.74 1901.90
9 150x125 0.450 1732.22 2037.80
10 150x150 0.470 1809.21 2128.40
11 200x80 0.620 2382.85 2803.30
12 200x100 0.630 2421.29 2848.50
13 200x125 0.660 2536.58 2984.20
14 200x150 0.680 2613.45 3074.60
15 200x200 0.740 2844.05 3345.90
16 250x80 0.890 3420.55 4024.10
17 250x100 0.900 3458.98 4069.30
18 250x125 0.930 3574.28 4205.00
19 250x150 0.960 3689.58 4340.60
20 250x200 1.020 3920.18 4611.90
21 250x250 1.090 4189.21 4928.40
22 300x80 1.220 4688.84 5516.20
23 300x100 1.240 4765.70 5606.60
24 300x125 1.260 4842.57 5697.00
25 300x150 1.290 4957.87 5832.70
26 300x200 1.360 5226.90 6149.20
27 300x250 1.430 5495.93 6465.70
28 300x300 1.510 5803.40 6827.40
29 350x200 1.690 6496.84 7643.20
30 350x250 1.730 6650.61 7648.20
31 350x300 1.880 7227.25 8311.30
32 350x350 1.950 7496.35 8620.80
33 400x200 2.110 8113.27 9330.30
34 400x250 2.150 8267.08 9507.10
35 400x300 2.320 8920.75 10258.90
36 400x350 2.390 9189.92 10568.40
37 400x400 2.460 9459.08 10877.90
38 450x250 2.600 9997.40 11497.00
39 450x300 2.770 10651.07 12248.70
40 450x350 2.840 10920.23 12558.30
41 450x400 2.900 11150.94 12823.60
42 450x450 2.960 11381.65 13088.90
43 500x250 3.150 12112.23 13929.10
44 500x300 3.340 12842.81 14769.20
45 500x350 3.420 13150.42 15123.00
46 500x400 3.490 13419.58 15432.50
47 500x450 3.560 13688.74 15742.10
48 500x500 3.630 13957.91 16051.60
49 600x300 4.660 17918.41 20606.20
50 600x350 4.750 18264.48 21004.20
51 600x400 4.850 18648.99 21446.30
52 600x450 4.920 18918.15 21755.90
53 600x500 4.990 19187.31 22065.40
54 600x600 5.160 19840.99 22817.10
55 700x350 6.420 24685.88 28388.80
56 700x400 6.510 25031.95 28786.70
17
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
57 700x450 6.600 25378.01 29184.70
58 700x500 6.690 25724.07 29582.70
59 700x600 6.860 26377.75 30334.40
60 700x700 7.070 27185.23 31263.00
61 750x400 7.460 28684.84 32987.60
62 750x450 7.540 28992.45 33341.30
63 750x500 7.660 29453.87 33872.00
64 750x600 7.790 29953.74 34446.80
65 750x700 7.920 30453.61 35021.70
66 750x750 8.050 30953.48 35596.50
67 800x400 8.580 32991.41 37940.10
68 800x450 8.670 33337.48 38338.10
69 800x500 8.770 33721.99 38780.30
70 800x600 8.970 34491.02 39664.70
71 800x700 9.160 35221.60 40504.80
72 800x750 9.280 35683.02 41035.50
73 800x800 9.410 36182.89 41610.30
74 900x450 10.410 40028.04 46032.20
75 900x500 11.060 42527.39 48906.50
76 900x600 11.280 43373.33 49879.30
77 900x700 11.490 44180.81 50807.90
78 900x750 11.610 44642.23 51338.60
79 900x800 11.730 45103.64 51869.20
80 900x900 11.900 45757.32 52620.90
81 1000x500 13.960 53678.34 61730.10
82 1000x600 14.180 54524.27 62702.90
83 1000x700 14.460 55600.91 63941.00
84 1000x750 14.570 56023.88 64427.50
85 1000x800 14.680 56446.85 64913.90
86 1000x900 14.840 57062.07 65621.40
87 1000x1000 15.130 58177.16 66903.70
18
Annexure-15
Table - 15.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80 0.300 1238.17 1454.40
2 100 0.390 1583.74 1860.90
3 125 0.520 2054.50 2415.50
4 150 0.670 2579.08 3034.00
5 200 1.020 3920.18 4611.90
6 250 1.450 5572.80 6556.10
7 300 1.970 7571.32 8907.30
19
Annexure-16
Table - 16.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80 0.140 577.81 678.70
2 100 0.170 690.35 811.20
3 125 0.220 869.21 1022.00
4 150 0.280 1077.83 1268.00
5 200 0.400 1537.32 1808.60
6 250 0.550 2113.82 2486.80
7 300 0.710 2728.75 3210.20
8 350 0.900 3459.86 4070.30
9 400 1.100 4229.67 4975.90
10 450 1.330 5114.05 6016.40
11 500 1.590 6113.79 7192.50
12 600 2.160 8305.53 9770.90
13 700 2.830 10881.78 12801.70
14 750 3.200 12304.49 14475.40
15 800 3.600 13842.55 16284.90
16 900 4.480 17226.29 20265.60
17 1000 5.470 21032.99 24744.00
20
Annexure-17
Table - 17.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80 0.070 288.91 339.40
2 100 0.090 365.48 429.50
3 125 0.120 474.12 557.40
4 150 0.150 577.41 679.30
5 200 0.240 922.39 1085.10
6 250 0.340 1306.73 1537.30
7 300 0.460 1767.92 2079.90
8 350 0.610 2345.01 2758.80
9 400 0.770 2960.77 3483.20
10 450 0.970 3729.80 4387.90
11 500 1.180 4537.28 5337.80
12 600 1.710 6575.21 7735.30
13 700 2.350 9036.11 10630.40
14 750 2.720 10458.82 12304.10
15 800 3.140 12073.78 14204.00
16 900 4.050 15572.87 18320.50
17 1000 5.140 19764.09 23251.20
21
Annexure-18
Table - 18.1
Sl No. Dia in Weight in Rate per Amount
mm Quintal Each
1 80 0.130 536.54 630.20
2 100 0.160 649.74 763.50
3 125 0.200 790.19 929.00
4 150 0.260 1000.84 1177.40
5 200 0.370 1422.02 1672.90
6 250 0.620 2382.85 2803.30
7 300 0.790 3036.21 3571.90
8 350 1.000 3844.28 4522.60
9 400 1.230 4729.54 5564.00
10 450 1.420 5460.12 6423.50
11 500 1.730 6652.11 7825.80
12 600 2.340 8997.66 10585.20
13 700 3.060 11766.17 13842.10
14 750 3.470 13342.68 15696.80
15 800 3.910 15034.55 17687.20
16 900 4.760 18302.93 21532.20
17 1000 5.800 22301.89 26236.70
22
Annexure-19
Table - 19.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80 0.120 495.27 581.80
2 100 0.140 568.52 668.00
3 125 0.190 750.68 882.60
4 150 0.230 885.36 1041.50
5 200 0.390 1498.89 1763.40
5 250 0.530 2036.95 2396.40
5 300 0.680 2613.45 3074.60
5 350 0.850 3267.64 3844.20
5 400 1.040 3998.96 4704.50
5 450 1.230 4729.54 5564.00
5 500 1.460 5613.92 6604.40
5 600 2.270 8728.50 10268.50
5 700 2.950 11343.20 13344.50
5 750 3.340 12842.81 15108.70
5 800 3.750 14419.32 16963.40
5 900 4.550 17495.45 20582.30
5 1000 5.520 21225.24 24970.10
23
Annexure-20
Table - 20.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80 0.270 1114.36 1309.00
2 100 0.340 1380.70 1622.40
3 125 0.460 1817.45 2136.80
4 150 0.600 2309.63 2717.10
5 200 0.930 3574.28 4205.00
5 250 1.350 5188.47 6104.00
5 300 1.860 7148.56 8409.90
24
Annexure-21
Table - 21.1
Dia in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 100x80 0.120 495.27 581.80
2 125x80 0.200 790.19 929.00
3 125x100 0.220 869.21 1022.00
4 150x80 0.230 885.36 1041.50
5 150x100 0.250 962.34 1132.10
6 150x125 0.270 1039.33 1222.70
7 200x100 0.310 1191.43 1401.70
8 200x125 0.340 1306.73 1537.30
9 200x150 0.370 1422.02 1672.90
10 250x125 0.410 1575.76 1853.80
11 250x150 0.440 1691.06 1989.40
12 250x200 0.550 2113.82 2486.80
13 300x150 0.510 1960.09 2305.90
14 300x200 0.580 2229.12 2622.40
15 300x250 0.650 2498.15 2938.90
16 350x200 0.870 3344.53 3934.60
17 350x250 0.960 3690.51 4341.70
18 350x300 1.060 4074.94 4793.90
19 400x250 1.090 4191.22 4930.70
20 400x300 1.200 4614.18 5428.30
21 400x350 1.320 5075.60 5971.10
22 450x300 1.300 4998.70 5748.50
23 450x350 1.450 5575.47 6411.80
24 450x400 1.580 6075.34 6986.60
25 500x350 1.600 6152.24 7075.10
26 500x400 1.740 6690.57 7694.20
27 500x450 1.860 7151.98 8224.80
28 600x400 2.100 8074.82 9286.00
29 600x450 2.220 8536.24 9816.70
30 600x500 2.390 9189.92 10568.40
31 700x500 2.810 10804.88 12425.60
32 700x600 3.170 12189.14 14017.50
33 750x600 3.380 12996.62 14946.10
34 750x700 3.800 14611.58 16803.30
35 800x600 3.680 14150.16 16272.70
36 800x700 4.100 15765.13 18129.90
37 800x750 4.280 16457.25 18925.80
38 900x700 4.580 17610.80 20252.40
39 900x750 4.780 18379.83 21136.80
40 900x800 5.080 19533.38 22463.40
41 1000x800 5.700 21917.37 25205.00
25
Annexure-22
Table - 22.1
Dia in Weight in Rate per Amount
Sl No.
mm Quintal Each
1 80x80 0.220 907.99 1066.60
2 100x80 0.280 1137.04 1336.10
3 125x80 0.360 1422.35 1672.30
4 150x80 0.450 1732.22 2037.80
5 200x80 0.670 2575.02 3029.40
6 250x80 0.940 3612.71 4250.20
7 300x80 1.280 4919.44 5787.50
8 300x100 1.290 4957.87 5832.70
26
Annexure-23
Table - 23.1
Size in Weight in Rate per
Sl No. Amount
mm Quintal Each
1 80x125 0.070 288.91 339.40
2 100x150 0.090 365.48 429.50
3 125x175 0.120 474.12 557.40
4 150x200 0.150 577.41 679.30
5 200x285 0.230 883.96 1039.90
6 250x350 0.310 1191.43 1401.70
7 300x450 0.450 1729.49 2034.70
8 350x525 0.580 2229.68 2623.10
9 400x600 0.800 3076.12 3618.90
10 450x650 0.930 3575.99 4206.90
11 500x750 1.200 4614.18 5428.30
12 600x900 2.010 7728.76 9092.40
13 700x1050 3.040 11689.27 13751.70
14 800x1200 4.350 16726.42 19677.60
15 900x1350 5.750 22109.63 26010.60
16 1000x1500 7.920 30453.61 35826.70
27