Project Execution Plan
Project Execution Plan
Mardakan Villas
Nasimi Musayev
11-27-2024
PROJECT EXECUTION PLAN
1. Project Overview
The project involves constructing 45 villas across four different sites, with
key activities such as groundwork, insulation, foundations, columns, concrete
crossbars, monolithic concrete, drainage, fencing, and swimming pool
construction. The villas will be distributed as follows:
Activities:
o Mobilization of equipment, materials, and labor to all
sites
o Site survey, staking out, and marking of villa locations
o Setting up temporary facilities (offices, storage, safety
barriers)
o Installation of access roads and utilities
o Fencing of the site for safety and security
Activities:
o Excavation of the site for foundations and utilities
1
PROJECT EXECUTION PLAN
o Site grading, leveling, and compaction
o Trenching for utilities, drainage, and sewerage lines
o Ground preparation for foundation work
o Installation of temporary drainage systems to manage
stormwater runoff if necessary
Activities:
o Setting out foundation trenches and formwork based on
architectural and engineering designs
o Installation of reinforcement bars (rebar) in trenches
and foundation slabs
o Pouring of concrete for foundation slabs, footing, and
walls for all villas
o Curing of foundation concrete for strength development
o Inspections and quality checks on foundation work
Activities:
o Installation of thermal insulation for walls and floors
o Waterproofing the foundations and external walls with
appropriate membranes and coatings
o Insulation in critical areas such as garages, basements,
and swimming pools to ensure energy efficiency
o Inspection and quality checks for insulation materials
Activities:
o Erection of formwork for the concrete frames
o Placement of steel reinforcement (rebar) within the
formwork for concrete frames
o Pouring of high-strength concrete into the formwork for
the frames (entire frame structure)
o Concrete curing for the required period to achieve
desired strength
o Inspection of the structural frame to ensure stability
and safety
Activities:
2
PROJECT EXECUTION PLAN
o Installation of stormwater drains, sewerage lines, and
water supply pipes
o Testing of installed drainage and utilities to ensure
functionality
o Final inspection and approval of drainage systems
Activities:
o Excavation for swimming pool foundations and digging
pool basins
o Construction of pool walls and base slab (concrete
work)
Activities:
o Erection of concrete columns and beam structure on
top of the concrete frames
o Pouring of concrete for additional support beams and
roof slab (if applicable)
Activities:
o Final quality inspection and punch list completion
o Finalization of all documentation (as-built drawings,
warranties)
o Handover of completed villas to the client
o Issuance of completion certificates
3. Resource Allocation
Labor:
o Site engineers, architects, construction workers
o Project managers and supervisors
o Safety officers and quality control inspectors
Materials:
o Concrete and cement for foundation, concrete frames,
and pool structures
o Steel reinforcement bars for foundations, columns, and
frames
o Insulation materials (foam, membranes, spray foams)
3
PROJECT EXECUTION PLAN
o Fencing materials (blocks, concrete)
Safety Measures:
o Provision of personal protective equipment (PPE) to all
site workers
o Safety orientation for workers at the start of the project
o Regular safety audits and inspections by safety officers
o Adherence to local safety regulations and guidelines
Environmental Considerations:
o Waste management strategies for recycling and
disposal
o Minimizing environmental impact through dust
suppression and noise control
o Proper management of site runoff and stormwater
o Use of environmentally friendly materials where
possible
o Erosion control during excavation works
Risk Identification:
o Delays in concrete supply or curing time
o Adverse weather (rain or extreme heat) affecting work
schedules
o Unforeseen site conditions (e.g., poor soil quality)
o Safety incidents or accidents on-site
o Supply chain disruptions for materials or equipment
Contingency Measures:
o Stockpiling essential materials to avoid supply delays
o Adapting construction schedules for weather-related
delays
o Conducting soil tests before excavation to anticipate
issues
o Regular safety training and emergency preparedness
plans for the workforce
o Having backup suppliers for key materials
4
PROJECT EXECUTION PLAN
A detailed project budget will be prepared, which will include estimated costs
for labor, materials, equipment, and overhead. Contingency funds will be
allocated for unforeseen challenges, and regular cost tracking will ensure the
project stays within budget.