Vegetation Management
Vegetation Management
Best practice vegetation management involves giving appropriate consideration to the following
issues. Not all the issues will be relevant on every site.
Land clearing
Vegetation clearing must to be conducted in a manner that minimises damage to any retained
vegetation including protected trees, buffer zones and native vegetation corridors. Best practice
site management includes appropriate consideration of the following points.
• Ensure all local and State Government approvals are obtained before any disturbance
occurs to vegetation, and then disturb only the minimum necessary.
• Clearly identify any vegetation protected by legislation or Planning Schemes.
• Land clearing should not occur unless preceded by the installation of all necessary drainage
and sediment control measures. The exception being any land clearing necessary to allow
installation of these control measures.
• Land clearing should be staged to minimise the extent and duration of soil exposure.
Sequential clearing provides many advantages for erosion and sediment control, and can
also improve the natural relocation of local wildlife. It should be noted that partially hollow
trees (dead or living) often need to be saved for the habitat value these trees provide to
local wildlife (Photo 3).
Photo 3 – Tree hollows can provide Photo 4 – Land clearing without root
essential habitat grubbing
• If vegetation clearing must be carried out well in advance of earthworks, then this clearing
should be limited to the removal of woody vegetation only (Photo 4). Wherever reasonable
and practicable, the grubbing and the removal of any ground cover (mulch or vegetation)
should not occur until immediately prior to earthworks occurring within that stage of works.
− The exception to this rule being when construction works are carried out during an
extended dry period when erosive rainfall and/or winds are unlikely to occur. In any
case, the intent should be to minimise the duration that soils are exposed to the erosive
effects of wind, rain or flowing water, without causing an unnecessary financial burden
to the project.
• Land clearing should not extend beyond that necessary to provide up to eight (8) weeks of
site activity during those months when the expected rainfall erosivity is less than 100, six (6)
if between 100 and 285, four (4) weeks if between 285 and 1500, and two (2) weeks if
greater than 1500.
− Alternatively, land clearing should not extend beyond that necessary to provide up to
eight (8) weeks of site activity during those months when the actual or average rainfall is
less than 45mm, six (6) if between 45 and 100mm, four (4) weeks if between 100 and
225mm, and two (2) weeks if greater than 225mm.
• Wherever reasonable and practicable, land clearing should be limited to 5m from the edge
of proposed constructed works, 2m of essential construction traffic routes, and a total of
10m width for construction access. Protected vegetation must remain protected irrespective
of the above recommendations.
• Disturbance to natural watercourses (including bed and banks) and their associated riparian
zones must be limited to the minimum necessary to complete the approved works.
• Land clearing should ideally occur while the soil has a light moisture condition. If the soil is
too dry, heavy machinery can pulverise the soil, if too wet and it may lead to clodding or
hardsetting, particularly if the soil has a high silt or clay content.
• Wherever reasonable and practicable, cleared vegetation should be mulched (e.g. via tub
grinding) for use on the site as an erosion control aid and to satisfy landscaping
requirements. Mulch produced by tub grinding is generally more hydraulically stable than
mulch produced chipping, thus allowing its use in the formation of mulch berms (Photo 5).
• The practice of selling/disposing of potential mulch early in the construction program, only to
import mulch at a later date, must be avoided unless justified by sound landscaping
practice.
• Avoid trunk damage—it can result in long-term vegetation problems (Photo 6).
Photo 5 – Mulch berm produced by tub- Photo 6 – Undesirable tree trunk damage
grinding cleared vegetation
Photo 7 – Stair stepping steep batters Photo 8 – Scarifying the soil surface
Best practice vegetation management requires giving appropriate consideration to the following:
• Ensure site revegetation is carried out by qualified contractors.
• Seek expert advice on the most appropriate means of protecting retained vegetation.
• Preparation of a Vegetation Management Plan (VMP) prior to commencement of works.
Such a plan should clarify how all retained vegetation will be protected during the
construction phase, including the identification of required Tree Protection Zones.
• Establish and maintain Tree Protection Zones around retained vegetation. Such zones are
usually measured as a minimum of 10 times the trunk diameter of the tree measured at an
elevation of 1m from the ground, or the width of the tree canopy at its widest point,
whichever is the greater.
• Ensure that there is no encroachment of construction/building works within identified Tree
Protection Zones unless via trenchless digging or directional boring for the installation of
services. No root in excess of 25mm diameter should be disturbed within protected zones.
• Minimise changes in ground elevation adjacent to retained vegetation (Photos 9 & 10). If
land reshaping must occur adjacent to retained vegetation, then it must be performed in a
manner that will not cut these plants off from essential soil moisture.
Photo 9 – Recent earthworks have left this Photo 10 – Road works have left these
protected tree elevated well above the native trees partially buried
surrounding ground level