SR406
SR406
and Outfalls:
Recommendations on Design
M Escarameia
R W P May
Report SR 406
March 1995
!!!l HR Wallingford
Registered Office: HR Wnllingford Ltd. Howbery Park, Wallingford, Oxfordshire, OX10 8BA, UK
Telephone: 0491 835381 International + 44 491 835381 Telex: 848552 HRSWAL G.
Facsinlile: 0491 832233 International + 44 491 832233 Registered in England No. 2562099
HR Wallingford Ltd. is a wholly owned subsidiary of HR Wallingford Group Limited.
Contract
This report describes work funded by the Department of Transport (DOT)
under Research Contract DPU 8/9/03 for which the nominated officers were
Mr S V Santhalingam for DOT and Dr W R White for HR Wallingford. The
work was carried out in association with the Transport Research Laboratory
(TRL) who provided specialist input on construction, on safety aspects and on
the review of existing surface water channels. The HR job number was RTS
0263. The report is published on behalf of the Department of Transport, but
any opinions expressed in this report are not necessarily those of the funding
department. The work was carried out by MS M Escarameia and Mr R W P
May who also managed the project, with contributions from Dr B J Chaddock
and Mr B Robinson from T R L.
Approved by ..........................
Date 15 MYS
.................................
R W P May
M Escarameia
Report SR 406
March 1995
To achieve the first of these objectives two questionnaires were produced and
several site visits were carried out. The first, and more general, questionnaire
was circulated to regional operating units of DOT in England and to
corresponding organisations in DOE Northern Ireland, and the Scottish and
Welsh Offices. A very positive response was obtained from these
organisations: general information was collated from 39 schemes that had
already been built or were at various stages between design and construction.
The information gathered concerned the geometric characteristics of the
surface water channels, the type and gradient of the road, and the type and
size of the outfalls. A second, more detailed, questionnaire was prepared and
used as a check list during site meetings to obtain qualitative information about
the experience of road engineers in designing, constructing and maintaining
surface water channels.
a design depth of 0.150m, base width of 0.300m and cross-falls of 1:4.5. This
trapezoidal channel provides an increase in capacity of 45% in relation to a
triangular channel of the same depth and cross-falls of 1:5. Two types of
outlet were studied, according to their position along the channel: intermediate
outlets, which are located at points part-way along a length of channel, and
terminal outlets located at low points. Both in-line and off-line outlet designs
were tested for each of the two types of channel. Tests were also carried out
to determine the hydraulic performance of a type of outlet which is suitable for
very high velocity flows such as those occurring in steep roads. This design
consists of a side transition which gently directs the water away from the
carriageway onto the verge side and then over a side weir into a lower
collecting chamber. The test results, as well as the information obtained from
the questionnaires and the site visits, were used to produce design
recommendations in a draft Advice Note on Outfall Design. The Advice Note
is presented in Appendix Ill of this report.
The main conclusions drawn from the study and recommendations for further
work are presented in the last part of the report. These refer to the design,
construction and use of surface water channels and to further work that is
required for revision of the existing Advice Note HA 37/88.
List of Symbols
Title page
Contract
Summary
List of Symbols
Contents
B.l INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
B.2 GENERAL QUESTIONNAIRE . . . . . . . . . . . . . . . . . . . . . . . . 5
B.2.1 Overall description of the schemes
(Questions A and D of the questionnaire) . . . . . . . . . . 5
B.2.2 Description of the channels
(Question E of the questionnaire) . . . . . . . . . . . . . . . . 6
8.2.3 Description of channel outfalls
(Question F of the questionnaire . . . . . . . . . . . . . . . . . 7
8.3 SITE VISITS TO SELECTED SCHEMES . . . . . . . . . . . . . . . . 7
8.3.1 Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
B.3.2 Data from visits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
8.4 MEETINGS AND SECOND-STAGE QUESTIONNAIRE . . . . . . . . 10
8.4.1 General considerations . . . . . . . . . . . . . . . . . . . . . . . 10
8.4.2 Hydraulic design of channels . . . . . . . . . . . . . . . . . . . 11
8.4.3 Pavement drainage . . . . . . . . . . . . . . . . . . . . . . . . . . 12
8.4.4 Hydraulic design of outfalls . . . . . . . . . . . . . . . . . . . . 12
B.4.5 Constructional aspects . . . . . . . . . . . . . . . . . . . . . . . . 12
8.4.6 Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
8.4.7 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
8.5 DISCUSSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
B.6 CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
C.l INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
C.2 FIELDTESTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
C.2.1 Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
C.2.2 Description of the sites . . . . . . . . . . . . . . . . . . . . . . . 22
C.2.2.1 A20 Folkestone to Dover (Contract 1) .... 23
C.2.2.2 A487 Port Dinorwic Bypass . . . . . . . . . . . . . . 23
C.2.3 Measurements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
C.2.3.1 Equipment and test procedure . . . . . . . . . . . . 24
C.2.3.2 Tests at A20 Folkestone to Dover (Contract 1) 24
Contents continued
ACKNOWLEDGEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
Tables
Table 1 Summary of results of questionnaire
Overall description of scheme
Table 2 Summary of results of questionnaire
Surface water channels in verge
Table 3 Summary of results of questionnaire
Surface water channels in central reserve
Table 4 Summary of results of questionnaire
Description of channel outfalls
Table 5 Schemes visited
Table 6 List of meetings with resident engineers of schemes visited
Table 7 Results of field tests at A20 Folkestone to Dover (Contract 1)
Table 8 Results of field tests at A487 Port Dinorwic Bypass
Contents continued
Figures
Figure 1 Results of general questionnaire
a) Maximum longitudinal gradient of road
b) Channel depth
Figure 2 Results of general questionnaire
Minimum and maximum distances between outlets
Figure 3 Results of general questionnaire
Where outlets discharge into
Figure 4 General layout of test rig
Figure 5 Bar patterns used in laboratory tests
Figure 6 Triangular channel - In-line outlet
Figure 7 Triangular channel - Section A-A of in-line outlet
Figure 8 Triangular channel - Off-line outlet
Figure 9 Triangular channel - Section A-A of off-line outlet
Figure 10 Trapezoidal channel 1:4.5 - In-line outlet
Figure 11 Trapezoidal channel 1:4.5 - Section A-A of in-line outlet
Figure 12 Trapezoidal channel 1:4.5 - Off-line outlet
Figure 13 Trapezoidal channel 1:4.5 - Section A-A of off-line outlet
Figure 14 Weir outlet
Figure 15 Design curves. Triangular channel - In-line outlet
Channel-full
Figure 16 Design curves. Triangular channel - In-line outlet
Surcharged channel
Contents continued
Plates
Plate 1 Example of asymmetrical triangular channel
Plate 2 Example of symmetrical triangular channel
Plate 3 A20 Folkestone to Dover (Contract 1). Central reserve
outlets
Plate 4 A20 Folkestone to Dover (Contract 1). Test of central
reserve outlets
Plate 5 A20 Folkestone to Dover (Contract 1). Test of verge outlet
Plate 6 A487 Port Dinorwic Bypass. Terminal outlet
Plate 7 A487 Port Dinorwic Bypass. Test of terminal outlet
Plate 8 A487 Port Dinorwic Bypass. Test of intermediate outlet
(slope 1: l 6.5)
Plate 9 A487 Port Dinorwic Bypass. Test of intermediate outlet
(slope 1:204)
Plate 10 General view of flume with in-line outlet in triangular channel
(2 pairs of gratings)
Plate 11 Triangular channel
In-line outlet, 2 pairs of gratings
Channel-full, slope 1.60
Plate 12 General view of flume with off-line in triangular channel
(3 gratings)
Plate 13 Triangular channel
Off-line outlet, 3 gratings
Surcharged slope 1:l 00
Plate 14 Triangular channel
Off -line outlet
Ramps between gratings
Plate 15 Triangular channel
Ramps between gratings
Channel-full, slope 1.60
Plate 16 Trapezoidal channel
In-line outlet, 3 gratings
Plate 17 Trapezoidal channel
In-line outlet, 3 gratings
Channel-full, slope 1:400
Plate 18 Trapezoidal channel
Off-line outlet, 3 gratings
Contents continued
Plate 19 Trapezoidal channel
Off-line outlet, 3 gratings
Channel-f ull, slope 1:400
Plate 20 Weir outlet with grating
Slope 1.40
Appendices
Appendix I General questionnaire
Appendix II Detailed questionnaire
Appendix Ill Advice Note on Design of outfalls for surface water
channels
PARTA SCOPE OF STUDY
This final report of the project is divided into four main parts. Part A comprises
this general introduction and details of the technical specification for the work.
Part B describes the results of two surveys and several site visits that were
carried out to collect data and experience on existing schemes with surface
water channels. Part C describes the experimental work on outfall designs that
was carried out in the laboratory at HR Wallingford and in the field on two road
schemes. The text also explains how the data were analysed and used to
produce the design recommendations contained in the draft Advice Note, a
copy of which is included as Appendix Ill. Part D draws together the main
results from Parts B and C and identifies what changes are necessary or
desirable in other design documents relating to the use of surface water
drainage channels.
review the current situation and research needs concerning the use of
surface water channels.
prepare recommendations on outlet design together with general
recommendations on the use of surface water channels.
The items of work and the methods needed to achieve these objectives can
be summarised as follows:
B.l INTRODUCTION
It was explained in Section A.2 that one of the objectives of the project was to
collate information and experience on the use of surface water channels in
existing road schemes. The information was needed in order to identify
possible improvements in design and construction and to produce guidance on
the applicability of channels to different types of drainage problem. Data about
the various designs of outfall already in use were also needed when planning
the laboratory and field tests.
The collection of the information about existing schemes therefore formed the
first stage of the project and was carried out by means of two questionnaires
and several site visits. Details held centrally by DOT on a number of projects
with surface water channels were also made available.
The purpose of the first questionnaire was to obtain basic quantitative data
about factors such as the size and shape of the channels, the slopes of the
roads and the typical distances between outlets. Based on advice from the
Highways Engineering Division of DOT, it was decided to circulate the
questionnaire to the nine regional Operating Units in England and to the
corresponding organizations in DOE for Northern Ireland, the Scottish Office
and the Welsh Office. Each Operating Unit was requested to provide separate
details for each of the schemes in its area with surface water channels that
had either been built or were at any stage between design and construction.
The Operating Units in turn passed the questionnaires to relevant
organisations such as County Council highway departments and Consulting
Engineers who held the required information for particular schemes. The main
batch of questionnaires was sent out in December 1992 after approval by DOT
and replies were received up until about July 1993. The questionnaire is
described in Section 8.2 where the results are also discussed.
From the total number of schemes with channels, approximately half (23
schemes) had been completed at the time the questionnaires were answered
(between December 1992 and July 1993); amongst the other 16 schemes, 10
were being constructed. The great majority of surface water channels has
been built in rural roads (as opposed to urban): 20 of the schemes are dual
carriageways, 10 are single carriageways, 5 are motorways, and two schemes
correspond to a slip road and an urban road, respectively.
In all but 4 schemes the type of road pavement is flexible, the exceptions
being composite pavements. No information was obtained regarding rigid
pavements associated with surface water channels. In total, the length of the
schemes where channels have been incorporated adds to about 250km,
although not all this length corresponds to the actual length of the channels.
For instance, in dual carriageways the channel length can be twice the length
of the road if channels are used continuously. A precise value for the channel
length can not be directly obtained from the responses to the questionnaire,
but the total length of the schemes gives some indication of the present usage
of this type of surface road drainage in the UK. As can be seen in the Tables,
surface water channels appear to be more widely used in the East and South
East regions of England and in Wales: 10 schemes were identified in the
Eastern CPD, 8 in the South East CPD and 6 in Wales. The fact that the first
two schemes to be built in the UK were the A21 Pembury Bypass and the A1 1
Thetford Bypass in the South East and East Anglia, respectively, may possibly
account for the more rapid spread of surface water channels in these two
regions.
The replies from the questionnaires show that surface water channels have
been used in schemes varying from generally flat to generally steep
longitudinal gradients. The maximum gradients reported varied between 1: l 2
and 1:250, whereas the minimum gradients varied from 1:l00 to virtually flat.
Figure l a ) is a chart showing the maximum longitudinal gradients in the road
schemes. It can be seen that the majority of schemes have maximum
gradients of the order of 3-4%
Regarding the type of sub-surface drainage, it was found that the most
common systems were either fin drains or narrow filter drains, each type
accounting for approximately 40% of the schemes. A combination of these two
types was used in 5 of the schemes and two schemes incorporated narrow
filter drains and also French drains. One scheme reported no sub-surface
drainage due to the free draining nature of the subgrade (gravel).
Apart from two exceptions, all the channels described had a triangular cross-
section which was either asymmetrical (mainly used in channels in the verge
of the carriageway) or symmetrical (mainly used in channels in the central
reserve). The range of side-slopes adopted for these triangular channels was
quite wide: in the verge it varied from slopes as steep as 1: l (verge side) and
1:2.3 (carriageway side) to a symmetrical channel with slopes of 1:5. In the
central reserve the steepest channel recorded had cross-falls of 1:land 1:2.3,
and the flattest was symmetrical with cross-falls of 1:20. However, most of the
channels in the central reserve were designed to be symmetrical and to have
slopes not steeper than 1:4. A trapezoidal channel with side-slopes of 1: l was
also reported, as well as a dished channel but no detailed information was
given on the dimensions of this latter channel. It should be noted that the
design of some of these schemes started before the publication in 1991 of the
Amendment No.1 to the Advice Note HA 37/88 which recommended the use
of symmetrical channels with cross-falls of 1:5 both in the verge and in the
central reserve.
The replies to the questionnaire showed that in approximately two thirds of the
schemes the outlets were set in the channel invert and in one third these were
set back in the verge of the carriageway. One scheme reported both types of
positioning.
Figure 2 shows two bar charts with the minimum and maximum distances
between outlets that were adopted in the schemes. The outlets were spaced
as far apart as 1100m in one scheme, but the minimum distances reported
were as short as only 5m, presumably in sag points and at crests. The
maximum distances between outlets varied from 30 to 11OOm, whereas the
minimum distance varied between 5 and 364m. The chart for maximum
distances shows that in almost 30% of the schemes the outlets were spaced
more than 500m apart; however, in half the schemes this distance was less
than 150m.
A variety of systems has been used to convey the water from the outlets in the
schemes reported, but the majority of the schemes relied on carrier drains or
a combination of these with other systems, as shown in Figure 3. Toe ditches,
watercourses and soakaways have been used in conjunction with carrier
drains in about 20% of the schemes. Soakaways as the sole means of
discharging the flow were adopted in two schemes, and the exclusive use of
toe ditches was adopted in only one scheme.
6.3.1 Considerations
Visits were made during the project to thirteen different road schemes with
surface water channels. The schemes are listed in Table 5 and were selected
on the basis of the information from the first-stage questionnaire so as to cover
a representative range of channel and outlet types. Ten of the schemes were
already open to traffic and three were under construction. Eight of the
schemes that were open were visited without requiring the involvement of local
highways staff. The five other schemes were visited in the company of site
staff either as part of the meetings carried out for the second-stage
questionnaire (see Section B.4) or during the field tests on outlet performance
(see Section C.2). The principal objectives of the visits were to: assess the
design and construction aspects of the surface water channels; identify any
problems with the durability or maintenance of channels already in use; and
identify and record the main types of outlet design already in use.
The transition from the channel to the outlet was in a few cases quite abrupt.
In one particular scheme (Reference D in Table 5) the outlet, which consisted
of a single grating set back in the verge, was positioned without any sort of
transition to assist turning of the flow from the channel. This solution is likely
to be inefficient at collecting flow from the channel and preventing it bypassing
the outlet. However, in most schemes, transitions have been built to direct the
flow more smoothly from the channel towards the gratings. Transitions with
slopes from 1:lto 1:3 in plan were recorded during the visits and some of the
designs had curved walls. From the hydraulic viewpoint, some of these slopes
may still be too sharp to give a satisfactory performance.
In some outfalls the gratings were set at a level lower than that of the channel
invert (depressed gratings) in order to increase the head over the grating;
some outfalls included more than one grating and the longitudinal spacing
between them was found to vary from about 1m to 2.5m. The variety of
geometries observed highlighted the need for guidelines on an efficient design
for outfalls.
Although the discussions revolved around the four specific schemes, general
comments based on the experience of using this type of road drainage were
also recorded. This applied particularly to the meetings with the two channel
contractors (SIAC and Extrudaketb). During the first of these meetings it
became evident that the list of schemes obtained through the first-stage
questionnaire was incomplete. Since most channels have been slipformed it
was thought useful to ask slipforming companies for lists of the schemes that
they had built. The umbrella organisation BRITPAVE was contacted for this
purpose and provided the names of a number of other channel contractors.
These were in turn contacted and led to 49 more schemes being added to the
ones identified from the first-stage questionnaire.
Some outfalls have been designed with the grating(s) set back in the verge
andfor with a depressed sole to increase the head over the grating (eg
Schemes E and G in Table 5). In some cases two or three gratings were
installed so that, if blockage of one grating were to happen, there would still
be sufficient capacity available to drain the flow. Some bypass flow (25%) has
been allowed in the design of the outfalls of Schemes E and G.
The amount of concrete used to form the channels can be quite considerable
since the channels are generally founded on the road sub-base. The overall
depth of the channels could be reduced if structural tests showed that their
strength would still be satisfactory. A concrete thickness below the invert of
approximately lOOmm has been suggested as suitable from the channel
contractors viewpoint. Assuming a 150mm depth channel profile it would
result in an overall concrete depth of about 250mm. At present it is common
to find overall depths (measured from the carriageway edge) of the order of
450mm. However, channel construction represents only part of the total
construction costs. If thinner channels are laid on a bound pavement material,
little economy would be achieved. Construction on a locally thicker layer of
unbound sub-base would result in savings in material costs but would
complicate pavement construction.
Shape
From the constructional viewpoint the shape of the channels does not appear
to be a critical factor. Very wide channels (2m or more) can be built with no
special difficulties by the major slipforming contractors. Flatter cross-falls (as
opposed to 1:l cross-falls), rounded edges and sloping outer sides (which are
now recommended by DOT) are generally preferred.
It was noted during the site visits that in some channels the sides are locally
convex in cross-section and so do not have the required triangular shape.
This probably results from differential slump of the concrete. The bowing out
of the sides will tend to reduce the capacity of the channel.
Constructional tolerances
Matching the tolerances on level for the carriageway edge of the channels and
for the bituminous wearing course appears to have been difficult in many
schemes. The slipform contractors normally aim to construct the channel so
that the top edge on the carriageway side is 5mm below the level specified for
the finished road surface. Allowing for a working tolerance of +5mm (which
experienced contractors consider to be reasonable) should result in a final
concrete level of 0 to -10mm relative to the specified level; this variation is
equal to the HCD limit on the allowable size of step at the edge of the channel.
However, this does not take account of the permitted tolerance on the level of
the bituminous wearing course which is 0 to +6mm relative to the specified
level. In combination, the separate application of the two sets of tolerances
could result in a maximum downward step of 16mm from the pavement to the
adjacent edge of the surface water channel, which is beyond the permitted
limit of 10mm. From their viewpoint, the slipform contractors feel that they are
sometimes unfairly penalised for errors in level that were not of their own
making. The level pins used to set out a surface water channel have often
been lost or replaced by the time the pavement is laid so it can then be difficult
to prove whether or not the channel was constructed to specification.
Remedial work can be carried out to bring the step between the channel and
the road surface within specification. Solutions include: planing of the
bituminous material forming the hardstrip, grinding the concrete in the channels
and introduction of epoxy-concrete patches to bring the channel to a higher
level locally. This latter approach was used in parts of Scheme B (see Table
5) but does not seem satisfactory because the joints between the epoxy patch
and the underlying concrete remain weak points which could cause premature
deterioration of the channels. A better solution, which has been adopted in
some other cases, is to remove sections of the channel and construct them
again to the right level. Grinding of the channels is also not considered
advisable over longer stretches as it exposes the aggregates, increases the
roughness of the channel and may lead to frost damage.
Tolerances should not only apply to the edge of the channel but also to the
overall shape of the channel. It is possible for the concrete in the channel to
show different slump levels depending on whether the concrete is on the edge,
or say, the invert of the channel. Since the capacity of the channel is a
function of its depth, it would be advisable to check that the invert level is
correctly set.
Overlays
It is often necessary to rehabilitate flexible roads as they wear and their
surfaces deform, crack and loose their texture. This can be readily performed
with roads with surface water channels by planing off the old pavement surface
and replacing it by a new pavement surface whilst at the same time
maintaining the surface level of the pavement and limiting the step between
the pavement and the edge of the channel to the specified limit of 1Omm.
Flexible pavements, however, often require strengthening during their life either
due to wear or to increase in the amount of traffic that can be carried in their
design life. This can involve pavement overlays with thicknesses between
40mm and 300mm. The surface water channels would also require to be built
up to this thickness to avoid a large drop into the channel. Overlay techniques
should be developed prior to the need to provide structural overlays to roads
that have been built with surface water channels.
Concrete mix
The workability of the concrete used in surface water channels is a major
constructional factor. From experience the slipforming contractors have come
up with their own specifications for the concrete which maintain workabilrty with
a lower than normal slump while producing the cube-strengths required by the
HCD. It appears that concrete grade C35 with a 6% air content has been
generally adopted by the contractors with success. Some Resident Engineers
have argued that certain mixes did not conform to the DOT requirements, but
this problem has since been resolved by changes adopted in the August 1993
amendment to the HCD and Specification for Highway Works (SHW); this
question is discussed again i~Section B.5.
The contractors consider they need to be able to add some water on site to
improve workability when the concrete mixture is too dry, and some Resident
Engineers permit this to be done. The contractors argue that if the amount of
water added were sufficient to reduce the concrete strength below
specification, the mix would be too wet to be used successfully for slipforming.
The counter argument is that the unquantified addition of water can lead to
inconsistent batches of concrete and an increased risk of sub-standard
sections of channel. There is some confusion over whether there is an
applicable DOT specification for the workability of the concrete. Clause 1005
of the Specification for Highway Works (1991) states that the optimum
workability required "shall be determined by the Contractor and approved by
the Engineer". The slipform contractors consider that slumps in the range
15mm to 35m are generally satisfactory.
The current sampling of the concrete ever 30 linear metres (which is suitable
for pavements) may be excessive for surface water channels. The criterion
should preferably take account of volume of concrete laid as well as the
length. The distance between samples should be chosen so that
unsatisfactory sections of channel are identified and satisfactory concrete is
not removed unnecessarily.
Joints
There appears to be some confusion regarding the depth at which the joints
should be formed. The recommended depth is 25mm below invert level but
it is not clear whether, on the sides of the channel, the joint should be cut
25mm below the surface or to a horizontal level corresponding to 25mm below
the invert. Clarification on this point by the DOT seems necessary.
Ib) Outfalls
The outfalls are normally moulded by hand. In some schemes, it appears that
the slipforming machine was stopped just before the outlet position, moved
forward a few metres and started again on the other side, the outlet was later
formed in situ in the gap left between the two sections of channel. This
method has the disadvantage that the machine tends to settle slightly when it
is stopped so that the channel has a low point either side of the outlet. An
alternative method (used, for example, in Scheme L in Table 5) is not to
interrupt the slip-forming process but remove whole sections of channel at the
outlet positions while the concrete is still green. This produces a better
longitudinal profile but can waste a significant quantity of concrete when outlets
are closely spaced. From the slipforming point of view it is better to design the
outfall so that the gratings are positioned with their carriageway edges on the
invert of the channel or set back into the verge. With this layout the channel
can be slipformed continuously and only the verge side of the channel needs
to be cut out to build the outfall.
B.4.7 Safety
Safety questions were raised during the meetings but no incident was reported
where a surface water channel had been considered to have caused an
accident or made one worse. Signs of an accident were observed at one site
(Reference J in Table 5). Although the vehicle had crossed the central reserve
channel at an angle of about 45", the adjacent safety barrier appeared to have
successfully absorbed the energy of the vehicle by means of plastic
deformation. The presence of the channel did not therefore appear to have
altered the level or pitch angle of the vehicle beyond the limits within which the
safety barrier was able to perform as intended.
B.5 DISCUSSION
The purpose of this Section is to discuss the implications of some of the
information obtained from the second-stage questionnaire (see Section B.4)
and to include additional comments on the use of surface water channels
based on the experience of the HFUTRL project team
Some developments are also possible in the geometry of the existing type of
surface water channel. The limitations on maximum depth and cross-fall do
not prevent the use of trapezoidal cross-sections, and these will usually give
a higher flow capacity than equivalent triangular profiles. Sediment may
deposit on the flat invert of a trapezoidal channel but such deposition is also
observed to occur in triangular channels when flow velocities are low. The
width of deposition in a trapezoidal channel may be reduced if the invert is not
truly horizontal but given a small transverse cross-fall (eg 1/40 as in
conventional kerb-and-gully designs).
A linked problem concerns the time taken for rain falling on a carriageway to
reach the adjacent surface water channel. This time is typically 1-2 minutes
and is not taken into account by the design procedure in HA 37/88. It was
originally expected that design storm durations would be much longer than two
minutes so that any errors would be negligible. However, the time of entry to
the channel will need to be included if the method in HA 37/88 is revised to
allow durations of less than 8 minutes.
(d) Maintenance
Surface water channels need regular cleaning because sediment and debris
washed from fairly large areas of road tend to become concentrated at low
points and outlets. Little cleaning appeared to have been carried out on some
schemes that were visited. Blocked gratings can cause more serious
problems in surface channels than in kerb-and-gullysystems where the outlets
are more closely spaced and flows are smaller.
It is not known whether surface water channels in the central reserve are
proving difficult to clean. Use of cleaning vehicles in the fast-lane of a dual
carriageway would seem to present safety problems, but the site inspections
did not suggest that the level of maintenance was any worse than for channels
in the verge. The adoption of symmetrical 1:5 triangular channels in most of
the new schemes suggest that the development of a lorry-mounted cleaning
system using appropriately shaped brushes would be justified.
B.6 CONCLUSIONS
(1) The general questionnaire had a very positive response which led to the
identification of 39 schemes where surface water channels have been (or
are going to be) used as the major surface drainage system. The
regions which appear to have a higher density of this type of road
drainage are the East and South East of England, and Wales.
Approximately 50% of the schemes had not been completed at the time
of the survey (between December 1992 and July 1993), which appears
to indicate a rapid adoption of surface water channels in recent years.
(8) It is recommended that rodding eyes are installed for inspection and
cleaning of fin drains. Sub-surface drainage should be kept separate
from the surface water drainage in order to retain one of the advantages
of surface water channels.
(10) Suitable techniques for adding overlays to roads with surface water
channels need to be developed at this stage in time before structural
overlays are required in the existing schemes.
(12) The depth at which joints are formed in surface water channels needs
clarification. The present DOT recommendation is not clear about
whether the recommended depth of 25mm corresponds to a horizontal
level below the invert or below the surface.
.papuaururoaa~
Aliua.t~nase 'ururog Aluo 40 peaisu! ap!s peoA aql spJeMoi Alleluozuoq
ururogl inoqe 01 papuawa slauueqa JaleM aaeyns aqi Japun sal!waloa6
aqi pa~o.tdur!aq p(noM a6eu!e~paz~eyns-qnsaqijo uo!iz~ruisuoz~ a q l (€1)
PARTC EXPERIMENTALSTUDYOFOUTFALLS
C.l INTRODUCTION
A detailed experimental study was necessary to complement the information
gathered from the questionnaires and enable the development of suitable
methods for the design of channel outfalls. This involved both field
measurements and laboratory tests, but the methods for the hydraulic design
of outfalls were mainly developed from the laboratory tests because these
allowed a more systematic way of varying the geometric features of the outfalls
and the flow conditions.
In this study the outfall is defined as the drainage system that collects and
removes water from the surface water channels and conveys it to a
downstream point of discharge. The outfall is formed by the outlet (which
collects the flow and removes it from the surface) and the outfall structures
(which consist of the chamber below the outlet and of the arrangements for
conveying the water to a collector pipe, a soakaway or a watercourse).
C.2.1 Objectives
The purpose of the field tests was to measure the performance of existing
outlets in two selected road schemes. The performance of an outlet can be
assessed both qualitatively (by visual observation) and quantitatively (by
measurements of the approach flow and the bypass flow).
Features of surface water channels such as shape and surface texture, as well
as contraction and expansion joints, affect the total roughness of the channels
and the velocities approaching the outlet. Measurements allow an estimate of
the Manning's roughness value for the channel "as built". Visual observation
of the flow patterns at the gratings of the outlets can help identify causes of
possibly inadequate capacity of an outfall. Improvements in the performance
can then be obtained by changes to the outfall layout.
1 The road scheme should be completed or nearly completed but not yet
open to traffic to avoid traffic disruption caused by the need to cone off
part of the road;
3 The channels in the two road schemes should preferably have different
geometries (ie. different surface width and side-slopes); the outfalls
should have different layouts and different positions in relation to the
channel invert (ie. in-line and off-line outlets).
The two sites chosen for the tests were selected from the road schemes
visited earlier in this study. They were the A20 Folkestone to Dover - Contract
1, in Kent, and the A487 Port Dinorwic Bypass, in Gwynedd, Wales. The tests
in the first scheme were carried out on 26 and 27 October 1993, and in the
second scheme on 29 and 30 November 1993. Both schemes were due to
open soon after the field tests were carried out.
The outlets are formed by a triple grating set on the invert of the channel.
These gratings, Brickhouse Dudley, Triple Waterway 450mm x1350mm, were
set horizontally on the channel invert. A smooth transition was formed between
the channel invert and the outlets. The same geometry was used for the
terminal and intermediate outlets.
In most of the scheme the channel outlets are set in relatively mild longitudinal
slopes which vary between 1:2000 and 1:400. It was initially thought that the
water necessary for the tests might be obtained from a nearby watercourse.
However, there were no streams in the vicinity of the scheme from where
water could be easily pumped to supply the flow for the tests. For this reason
it was necessary to use a road tanker which had to return to a depot in
Folkestone to refill before each test.
The outlets are formed by double triangular gratings, Glynwed Niagara 200
type, 650mmx650mm in size. In the terminal outlets two gratings are used with
a horizontal distance of 1570mm between them. The terminal outlets end with
a kerb at right angles to the carriageway. Intermediate outlets consist of a
single grating. In both types of outlets the gratings are set back into the verge
with the side of the grating closest to the carriageway coinciding with the
channel invert.
This scheme includes some very steep longitudinal slopes of the order of
1:16.7 (or 6%) in places, which is the normal maximum value permitted for
high-speed roads. It was found most convenient to use a tractor-drawntanker
for the tests and to re-fill it from a nearby watercourse.
C.2.3 Measurements
C.2.3.1 Equipment and test procedure
The equipment used in the tests consisted of three point gauges to measure
the water level, and current meters to measure the flow velocity in the channel
and in the vicinity of the outlets. Two types of current meter were used: two
miniature current meters which can measure flow velocities up to l d s , and
two miniature impeller meters (Valeport BFM004) designed to measure flow
velocities up to 2 d s . The two types of current meter were connected to
counter units which gave readings of the rate of rotation of the propellers.
These readings were later converted into values of flow velocity by using the
calibration curves of the instruments.
The procedure adopted in the field tests was first to identify suitable outlets to
test. As mentioned before, it was considered important to cover a wide range
of channel and outlet geometries, slopes and flow conditions. Once the
outlets were selected, a careful survey was carried out of the channel
upstream and downstream of the outlets. The survey of the invert level
extended from about 30m upstream of the outlets to 4m downstream of
intermediate outlets. In terminal outlets the survey was carried out to the
downstream end of the outlet. The longitudinal slope of the channel was
thereby determined. Detailed surveys were carried out at particular sections
where the measurements were to be taken with the point gauges and the
current meters. This was used to determine the channel cross-section as
built, in particular the side-slopes and depth of the channels. The location of
these sections relative to the outlets varied from test to test and will be
described later.
One tanker load was required to carry out each test. After some trial runs the
tankers proved to be adequate in supplying water to the channels. However,
the tankers could not supply enough water to fill the channels in the steeper
slopes of the Port Dinorwic scheme.
The water was introduced into the channel about 40m upstream of the outfalls
by means of flexible hoses. The hose used at Folkestonewas nominally 75mm
in diameter, whereas two different sizes of hose, of 25 and 100mm nominal
diameter, were used at Port Dinorwic. In this scheme it was possible to vary
the flow rate by either pumping the water or allowing it to flow by gravity.
Readings of water levels and flow velocities in the channel were taken when
the levels were considered stable after the initial surge caused by the
introduction of the water by the tanker hose. The tests in the two sites were
carried out with various water depths in the channels ranging from almost
channel-full to about one third full.
No bypass flow of any significance was recorded during the tests, ie all the
flow was collected by the gratings. In most tests the water was all intercepted
by the first and second sections of the triple grating; only in one test of the
outfall in the verge was the flow also collected by the last section of the triple
grating.
Flow bypassing the gratings occurred only during two tests of the intermediate
outfall set in the steeper slope of 6%. In all the other tests the outfalls had
enough capacity to collect the flow introduced into the channel.
In sections where the water depth was sufficiently high to allow several
readings of the flow velocity, the mid-section method was applied to calculate
the flow discharge. In this method the channel cross-section is subdivided into
several vertical sections; the mean velocity and depth at a subdivision point
are multiplied by the section width measured between the mid points of
neighbouring sections. In tests where only a single value of velocity was
possible to record, this was done at the centreline of the channel, at about
mid-depth. A correction was necessary in these cases in order to obtain a
value representativeof the mean flow velocity of the whole cross-section. From
published data on velocity patterns in triangular channels, it was found that the
measured values should be multiplied by a factor approximately equal to 0.8.
This was carried out before proceeding with the analysis of the field data.
During the tests some difficulties were encountered in measuring the flow
velocity with the Valeport impeller meters. These were therefore replaced by
the miniature current meters in tests where the flow velocity did not
significantly exceed the range of the current meters (Imls). In tests with
higher flow velocities, which occurred mainly in the steeper channels of the
A487 Port Dinorwic Bypass, the flow discharge had to be estimated by an
alternative means. The procedure adopted was to calculate the Manning's
roughness value corresponding to the tests where a high number of velocity
readings was available, ie the tests carried out on the milder slope. The
Manning's roughness value, n, can be obtained as follows:
The average value obtained, n=0.009, was then used to estimate the velocity
and flow discharge in the steeper channels.
The results of the tests are shown in Tables 7, 8 and 9. In the tables, h is the
water depth and V is the mean flow velocity at the measuring sections which
were a few metres upstream of the outlets; Q is the flow rate in the channel
approaching the outlet, and hp is the water depth of the flow Qp that bypasses
the outlet. In Table 9, q represents the efficiency of the outlet which was
calculated as the ratio (Q-Qp)/Q.
As mentioned before, the values of Q were determined with the flow area
based on the side-slopes obtained in the survey of the channels' cross-
sections. The values of velocity between brackets in Table 8 were obtained by
dividing the estimated flows by the measured flow area.
Further analysis was carried out on the results of the field tests following the
laboratory tests and the preparation of the Advice Note on Outfalls (see
Section C.4.6).
C.2.5 Conclusions
The following conclusions can be drawn from the field tests:
1. Roughness values were determined for the surface water channels in the
two sites selected for field tests. The tests carried out in the first site, the
A20 Folkestone to Dover (Contract 1) showed values of Manning's n of
0.007 to 0.008 whereas the second site, the A487 Port Dinorwic Bypass,
indicated values of n of about 0.009.
Although the tests were not carried out at the full channel capacity, they
showed that the outlets used in the milder slopes are adequate for
channel-full conditions on these slopes. In the A487 Port Dinorwic
Bypass, excessive bypass flow was registered in an intermediate outlet
set on a slope of 6%. With channel-full conditions it is likely also that the
terminal outfalls would not be able to cope with the very high velocities
generated by slopes of this order of magnitude. An increase in the length
of the outlet, and possibly the introduction of additional gratings, would
be required for an adequate design.
C.3.1 lr~troduction
The purpose of the laboratory tests was to develop suitable designs of outlet
for surface water channels and to obtain in a systematic way quantitative
information on their hydraulic performance for use in a new Advice Note. As
explained in Section A.2, the Contract allowed for testing two different channel
geometries and three outfall designs for each of the channel geometries.
The laboratory testing of the outlets was carried out following the survey of
existing channels and the field tests described in Part B and Section C.2.
These earlier stages of the study helped identify the sizes and slopes of
channel that are representative of existing schemes and also highlighted the
need to develop more efficient designs of outlet. When selecting the channel
shapes to be tested, account was also taken of conclusions arising from a
concurrent study of safety aspects that was being carried out by Mr B
Robinson at the Transport Research Laboratory (TRL). Following discussions
with DOT and TRL, it was decided to test outfalls in symmetrical triangular
channels with cross-falls of 1:5 and in a higher capacity channel of trapezoidal
cross-section, with a design depth of 0.150m and cross-falls of 1:4.5. The first
channel shape correspondsto the standard profile recommended in the current
Highway Construction Details and HA 39189. The second shape is being
considered by DOT as a means of providing higher flow capacity for wider or
flat roads while not exceeding existing limitations on depth and cross-fall. The
capacity of this trapezoidal channel is 45% higher than that of a 0.150m deep
trangular channel with cross-falls of 1:5. The sole width of the trapezoidal
channel was chosen so that the cross-falls would not exceed 1:4 at the outlet
if gratings of 450mm X 450mm were to be installed on the sole of the channel.
This meant that the sole width would be equal to 0.300m and therefore the
design surface width would correspond to 1.65m. As will be explained later,
DOT is also considering an atternative trapezoidal shape having the same
values of depth and sole width but with cross-falls of 1:5 and a design surface
width of 1.8m. Only the first trapezoidal shape (1:4.5 cross-falls and 1.65m
surface width) was studied experimentally, but the results were used to make
approximate estimates of outlet performance for the alternative trapezoidal
shape.
Two types of outlet were studied, defined according to their position along the
channel as 'intermediate' and 'terminal' outlets. Intermediate outlets are
located at points part-way along a length of channel where the flow rate of
water from the road reaches the canying capacity of the channel. Terminal
outlets are located at low points along a length of channel and need to be able
to collect practically all the flow carried by the channel.
The design of outlets for surface water channels must be based on the flow
conditions at the approach to the outlet, namely the velocity, depth and
direction of the flow, since these are the fundamental independent factors that
determine the performance of an outlet. It is therefore important to reproduce
correctly in the laboratory test rig the flow depth and velocity approaching the
outlet but it is not necessary to reproduce a particular roughness for the
channel, defined usually by the Manning's roughness value, n.
The channels tested were built in a 12.5m long section which started 7.125m
downstream from the upstream end of the flume. For the testing of both types
of channel it was decided to adopt a length of at least 6m of uniform channel
upstream of the test section to produce uniform flow conditions approaching
the outlets.
A tank was built at the end of the channel to collect and allow measurement
of the flow that bypassed the gratings. This tank measured 1.5m X 1.9m and
discharged into the tank downstream of the flume by means of a 200mm
diameter pipe. The outlet from the tank was protected by an anti-vortex device
which is formed by a horizontal plate fixed 0.1 0m above the orifice. The
measurement of the bypass flow could be carried out in two different ways
depending on the amount of flow. For very low flows (flows smaller than 3.0
Vs ) it was found to be more accurate to use the tank as a volumetric device
and to measure the depth of water accumulated during a given period of time.
To achieve this the flow was retained in the tank by closing a valve at the
downstream end of the discharging pipe (see Figure 4). The time was
recorded with a stop-watch and the depth of water was measured with the aid
of a ruler stick fixed to one wall of the tank. The flow rate was calculated by
dividing the volume of water by the time. For higher flows, direct values of
flow rate were obtained by means of a 200mm diameter electromagnetic flow
meter installed in the pipework.
Water levels in the channel were measured using electronic point gauges
mounted on horizontal bars set transversely to the channel. The location of
the measuring sections varied with the type of outlet studied, but generally
values of the water depth were recorded in the channel at a distance
upstream of the outlets between 0.5 and Im, and also at points between
gratings and downstream of the outlets to measure the depth of the bypass
flow. The distance upstream of the outlets was chosen so that the water levels
were representative of the flow conditions in the channel undisturbed by the
drawdown at the gratings.
Rather than testing real gratings, it was decided to use representative wooden
models to avoid linking the results to any particular commercial patterns (see
Figure 5). The gratings were designed so that the waterway areas
corresponded to the minimum values recommended in BS 497: Partl: 1976.
They were made to have a waterway area of 0.44~*,where G is the width of
the gratings. Gratings with larger waterway areas than required by BS 497 or
with relatively thinner bars should therefore provide some margin of safety
compared with the present experimental results. The depth of the bars in the
model gratings needed to be kept as small as possible because the walls of
the flume strictly limited the total depth of the collecting chamber beneath the
gratings. The model bars were therefore made 25mm deep which was judged
sufficient to reproduce any 'choking' effect caused by water hitting the sides
of the bars and flowing out again.
The slope of the flume was adjusted at the beginning of a test and the flow
rate was set so that channel-full or surcharged conditions were achieved in the
channel. These were reached when the water depth measured with the point
gauges corresponded to the design water depth in the channel (channel-full)
and to flooding of 1m of hard-strip (surcharged). In the testing of terminal
outlets a ramp with a slope of 1:4 in the direction of the flow was positioned
downstream of the outlet to simulate the end of the channel.
As with the other measurements, the measurement of the bypass flow was
carried out once the flow conditions had become stable, using either the
volumetric tank or the flowmeter, depending on the amount of flow.
The triangular channel was reproduced in the flume in two different parts: the
upstream reach was built in wood and the 6.5m long outfall section was made
of wood for the in-line outlet and moulded in smooth concrete over a wooden
base for the off-line outlet. In the test rig the width of the flume was made up
of a small section of verge, the surface water channel (with the verge side at
a higher level than the road side to allow surcharging of the carriageway), and
a width representing the hard-strip (or hard-shoulder). This latter width was
built to a slope of 1:40. Plate 10 shows a general view of the flume with the
in-line outlet formed by two pairs of gratings.
For the testing of both types of channel it was decided to adopt a length of at
least 6m of uniform channel upstream of the test section to ensure uniform
flow conditions before the approach to the outlets.
As can be seen in Figure 6, the distance between the two pairs of gratings
was chosen to be equal to 0.750m to allow space for debris to deposit in the
channel rather than on the gratings. The same reasoning was followed in
choosing the location of the terminal ramp in the tests of the terminal outlet.
These were carried out at first with the ramp 0.250m downstream of the
gratings but it was observed that a longer distance was beneficial in reducing
blockage of the gratings by debris.
The size of the gratings adopted in the tests was chosen to maximise flow
collection in the channel tested and to conform with commercially available
sizes. Gratings of size 450mm X 450mm were adopted with a waterway area
which corresponded to the minimum area recommended in BS
497:Partl:1976.Tests were carried out with two different bar patterns: a
diagonal pattern and a straight pattern (see Figure 5). The gratings with
straight pattern could be positioned in the channel either transversely or
longitudinally to the flow direction.
The results of the tests of the intermediate outlet are summarised in Table 10,
and those of the terminal outlet are presented in Table 11, where Q is the flow
rate, Qp is the flow that bypassed the outlet and h is the upstream water depth
in the channel. The effect of the bar pattern was also investigated by carrying
out tests with similar flow conditions but with gratings having bars set
diagonally, transversely or longitudinally relative to the direction of flow. The
results of these tests are shown in Table 12 where the data for tests with the
gratings completely removed are also given for comparison purposes.
The results of the tests of the intermediate outlet are summarised in Table 13
for channel-full and surcharged conditions. Plate 13 shows a test carried out
with surcharged conditions at a slope of 1:100.
Additional tests were carried out to try to improve the efficiency of the outlet.
The previous tests had highlighted the fact that in high velocity conditions the
water tended to hit the bars of the gratings nearly horizontally, which reduced
the efficiency. It was therefore decided to try methods of deflecting the flow
vertically so that it entered the gratings at a more downward angle. After some
attempts, an increase in performance was observed with the introduction of
small ramps between the gratings (see Plate 14). The results of the tests
carried out with these ramps are presented in Table 14. Plate 15 illustrates
one of these tests with channel-full conditions, at a longitudinal slope of 1:60.
velocity 1.36°.5 = 1. l 66
The large scale of the model means that any scaling errors associated with the
turbulence and the local channel roughness are likely to be small and much
less than in most studies carried out with Froudian models.
The test results (in model values) corresponding to the intermediate outlet are
shown in Table 15 whereas those corresponding to the terminal outlet are
shown in Table 16. Plate 17 illustrates a test with channel-full conditions at a
longitudinal slope of 1:400.
The test results (in model values) corresponding to the intermediate outlet are
presented in Table 17 whereas those corresponding to the terminal outlet are
presented in Table 18. Plate 19 illustrates a test with channel-full conditions
at a longitudinal slope of 1:400.
The options available for this type of outlet are very limited by safety
considerations which do not allow any deepening of the channel below 150mm
or side-slopes locally steeper than 1:4. A weir outlet was first buitt in the flume
with a layout similar to that shown in Figure 14 but with a straight transition on
the carriageway side. This geometry was later changed in order to produce a
more gradual turning of the flow towards the weir. In the proposed geometry,
the side transition is initially curved in plan and a safety fence will normally be
necessary along the side weir to prevent the possibility of vehicle wheels
dropping into the lower side channel. Although the weir outlet was tested only
with the trapezoidal channel shape, it is also applicable with modifications to
triangular channels.
When a high-velocity flow is turned laterally, the water level on the outside of
the bend can increase significantly. Thus, with the weir outlet design, it is very
difficult to prevent water spilling out on to the hardstrip if the channel is flowing
full at the entrance to the transition section. It is therefore necessary to lower
the water level entering the transition so that some freeboard is available when
the flow is turned towards the side weir; the smaller the amount of freeboard,
the more gradual and longer the transition needs to be to prevent water
flowing back on to the road.
Tests were initially carried out with a 610mm X 610mm grating (prototype size)
installed on the invert at the upstream end of the outlet (see Plate 20). At
lower channel slopes and flow velocities, the grating removed enough water
to create the necessary freeboard in the transition section. However, the
grating became progressively less effective at higher velocities so that very
long lengths of transition and side weir would have been needed to prevent
overtopping. Results from these tests, which were carried out with channel-full
conditions upstream of the grating, are given in model terms in Table 19. The
table contains measured values of water depth in the channel as well as the
water depths at the downstream end of the grating, y,, and the water depths
yb, which will be explained later.
The use of a gully grating in combination with the weir outlet does not provide
a complete solution for all cases and the extra complication and cost may not
be justified. It was therefore decided that a more practical alternative would
be to limit the design flow depth in the surface water channel to less than the
channel depth upstream of the weir outlet; this would therefore provide the
freeboard needed in the transition section of the weir outlet. If a triangular
surface water channel is relatively small, it would be possible to locally
increase its size just upstream of the weir outlet so that it is flowing part-full
under design conditions. This option is not possible in the case of the
trapezoidal channel or large triangular channels because the depth cannot be
increased beyond the allowable limit of 150mm. In these cases, it will be
necessary to determine the spacing between the outlets so that the channel
flows only part-full under design conditions. Although this means that the
channel has effectively to be over-sized, it will normally only be necessary at
a few locations where steep longitudinal gradients occur. Although the
channel cannot be used to its full capacity, long spacings will still be possible
because the steep gradients will still produce high flow rates under part-full
conditions.
Tests with the weir outlet shown in Figure 14 were therefore carried out with
the trapezoidal channel upstream flowing 83% full and 68% full. In the test rig
the angle 0 was equal to 22O, the total length of the weir,,,,,l was 4.5m and
the lengths L, and L, were 1.3m and 3.2m, respectively. The results of the
tests (in model terms) are given in Table 19.
Different approaches were adopted in the analysis of the grated outlets in the
triangular channel and in the trapezoidal channel, and in the analysis of the
weir outlet. As mentioned before, the study of outfalls in triangular channels
was carried out in the laboratory using a particular size of channel. If the
results are analysed in non-dimensional form, the triangular shape allows
correct transposition of results between channels of different dimensions: for
channels with the same cross-falls there is direct proportionality of the water
depths and hydraulic radii in different sizes of channels. The study of the
trapezoidal channel was carried out as a Froudian model at a scale of 1: l .36
(see Section C.3.5.1). Due to the limited number of test results with the weir
outlet and the need to extrapolate results to very steep slopes, a theoretical
approach was adopted for the analysis. This was based on the oblique wave
theory as described later in Section C.4.4.
For the analysis of the test data it was necessary to assess the performance
of the outlets under various flow conditions. For this purpose, the efficiency of
an outlet was defined as the ratio of the flow intercepted by the outlet, Qi, to
the total flow approachirlg it:
where subscripts o and S refer to channel-full and surcharged conditions.
Based on previous studies of road drainage, it was decided to adopt a
minimum efficiency of 80% for intermediateoutlets operating under channel-full
conditions. When an outlet does not achieve this minimum a different geometry
is assumed to be required for the outlet. For terminal outlets a minimum
efficiency of 97.5% was adopted: terminal outlets need to be designed for
efficiencies close to 100% because any substantial bypass may cause flooding
of the verges or the carriageway. It should also be added that terminal outlets
have generally higher efficienciesthan intermediate outlets due to the ponding
effect caused by the terminal ramp.
As mentioned before (see Section C.3.4.1), the present study also assessed
the effect of bar patterns of gratings different from diagonal. In cases where
surface water channels are buitt behind safety fences it is possible to adopt
gratings with a longitudinal bar pattern. The tests showed that these have a
higher efficiency when compared with gratings of the same overall size and
waterway area but diagonal bars. From tests carried out with similar flow
conditions it was possible to establish the following approximate relationship
between the efficiency of equivalent gratings with diagonal and longitudinal
bars:
It was also observed in the tests that the efficiencies of gratings with bars
transverse to the flow were significantly smaller than those with diagonal bars.
This is more noticeable in higher velocity flows where the water tends to hit the
bars of the grating; the bigger the horizontal angle between the bars and the
direction of the flow, the more the water will jet over the grating (compare, for
the same total flow, the values of the bypass flow Clp for diagonal and
transverse bars in Table 12).
where Q is the approach flow to the outfall, B is the water surface width just
upstream of the outfall, A is the corresponding flow area and g is the
acceleration due to gravity.
For triangular channels with side-slopes of 1:5 and channel-full conditions the
Froude number is given by:
where Q, is the approach flow (in m3/s) and B, is the surface width of flow (in
m) for channel-full conditions. The numerical constant was determined so that
F, is equal to 1 when the flow in the channel is at critical depth for channel-full
situations.
The flow conditions occurring under surcharged conditions are more complex
because the velocity of the water in the main channel is considerably greater
than in the shallow flow along the hard strip or hard shoulder. Since the
allowable depth of surcharging in surface water channels is fixed at 25mm
above the normal design depth, the resulting increase in flow capacity is
relatively larger in small channels than in large ones. To assist users of the
Advice Note, a design chart was produced showing the relationship between
the surcharged capacity, Q, and the design capacity, Q, for different sizes
of channel (as defined by the design flow width B,). The curve, which is
shown in Appendix Ill (Figure 3 of the Advice Note) was obtained from the
equations for surcharged channels given in Section 15 of HA 37/88; the values
assumed were y3 - y, = 25mm, y3 - y2 = 20mm, n = 0.013 for the channel and
n = 0.017 for the hard strip. The values of QJQ, obtained from the tests with
the laboratory channel (B, = 1.00m) were found to be in reasonable
agreement with the corresponding value given by Figure 3 of Appendix Ill.
As explained above, the test data can be applied to other sizes of triangular
channel if the results are expressed in terms of interception efficiency, v,
versus a non-dimensional Froude number. Geometric similarity between
different sizes of channel is not exactly achieved under surcharged conditions
because the depth of surcharging is fixed at 25mm. However, the differences
are relatively small and the laboratory results will err on the safe side for
channels larger than the one tested (B, = 1.00m). Since the flow on the hard
strip has very little influence on the performance of an outlet, it is appropriate
to define the Froude number in terms of the surcharged width, B,, in the main
channel (see Figure 1 of Advice IVote in Appendix Ill). The definition adopted
was therefore:
In a few cases the test results were extrapolated to cover conditions not
reproduced in the laboratory tests. Two different situations were considered:
extrapolation to a larger or smaller number of gratings; and extrapolation to
flow conditions which could not be achieved in the test rig (eg flows at slopes
steeper than 1:40). The first type of extrapolation was carried out for the in-line
outlet with three pairs of gratings and for one and two gratings in the
surcharged off-line outlet, as can be seen in Figures 15, 16 and 18 (dashed
lines). A conservative approach was adopted when extrapolating results from
the tests so that the recommended curves would lead to safe designs. It was
assumed that, for the same flow conditions, the individual efficiency of any
additional gratings that were not tested would be the same as that of gratings
further upstream. This is a conservative approach because the efficiency tends
to increase as more of the flow is intercepted by gratings positioned upstream.
The shapes of the curves for which considerable amounts of data existed were
also taken into account in the extrapolations. The second type of extrapolation
was carried out in order to extend the range of the design curves to steeper
slopes. The intercepted flow corresponding to the most severe conditions
tested was assumed to remain constant for steeper slopes; the efficiencies
were calculated by dividing the intercepted flow by the total flow calculated
using Manning's equation with a mean roughness coefficient of 0.013.
The gratings recommended in the Advice Note for the in-line outlet are
specified to have sizes within certain limits (see Appendix Ill). The limits are
given in terms of the channel design depth so that they are applicable to
channels of various dimensions. The lower limit was directly obtained from the
tests and corresponds to the minimum width of grating that can achieve the
necessary performance; the upper limit correspondsto the maximumwidth that
can physically be installed in the channel. For the off-line outlet only the lower
limit is applicable.
The experimental points are plotted in these figures; in the case of the off-line
outlet, data points corresponding to one single grating can be seen plotted in
Figures 21 and 22. However, it was decided not to present a design curve in
the Advice Note for an outlet with one grating only because of the risk of
blockage in such a high capacity channel. Extrapolations from the test data
were carried out using the same procedures as those described in Section
C.4.2 for triangular channels.
After the tests were completed, DOT requested that the Advice Note should
also include curves for the design of trapezoidal channels with the same base
width of 0.3m but side-slopes of 1:5 (see Appendix Ill). The curves obtained
for the efficiency of outlets in the 1:4.5 channel were therefore revised in order
to produce conservative recommendations for the 1 :5 trapezoidal channel.
The concept of channel conveyance was used to estimate the relative
difference in flow capacity between the 1:4.5 and 1:5 trapezoidal channels for
equal values of longitudinal slope and roughness. The ratio of the
conveyances of the two channels was calculated assuming the Manning
resistance equation and is given by:
where A4.5and A5 are the cross-sectional areas of the channels and R4.5and
R5 are the two hydraulic radii. It was assumed that the flow rate collected by
an outlet in the 1 :5 channel would be equal to that measured under the same
conditions of slope and roughness in the 1:4.5 channel. This means that the
efficiency of the outlet in the 1 :S channel is assumed to be about 6% smaller
than in the tested channel because of the higher corresponding flow rate in the
1 : s channel. The design curves are therefore likely to produce slightly
conservative designs.
The equations that describe the formation of oblique waves caused by such
disturbances are:
and
where Fa and ya are, respectively, the Froude number of the flow and the
water depth upstream of the disturbance, and yb is the depth of water
downstream of the wave; the angle P is the angle of the oblique wave in
relation to the direction of the flow and 0 is the angle of deflection of the wall
of the channel (see Figure 23).
The applicability of the oblique wave theory was investigated by comparing its
predictions with the results of the tests carried out on the weir outlet (see
Table 19). Some of the tests were made WI+ the upstream trapezoidal
channel flowing full but with a gully grating installed (see Plate 20) which had
the effect of removing some of the water a ~ ~ lowering
d the flow depth
approaching the transition on the carriageway sidt of the channel. Other tests
were made without the grating in operation but with the upstream channel
flowing either 83% or 68% full. In the tests the discharge and the slope of the
channel were varied, and measurements were made of the water depth
upstream of the transition and of the corresponding maximum downstream
depth produced by the oblique wave. For a particular upstream condition, the
limiting flow capacity of the outlet was obtained when the downstream water
level just reached the top of the channel. The efficiency of the outlet in this
limiting state was 100%; any increase in discharge would have caused some
water to spill out onto the carriageway and bypass the outlet.
Calculations were first made using the measured values of water depth ya and
yb just upstream and downstream of the oblique wave (see Table 19). On this
basis, the predicted values of wall angle, 0, given by Equations (9) and (10)
varied from 14.0" to 26.5", with an average value for seven tests of 20.0".
These results compared satisfactorily with the actual weir angle of 0 = 22"
used in the model, and suggested that the oblique wave theory was a
reasonable basis for design. However, study of the data in Table 19 showed
that the relationship between the upstream water depth, h, in the channel and
the local depth, y, at the start of the transition was complex and difficult to
predict. It was therefore decided to re-analyse the data for the channel flowing
83% and 68% full using the measured values of h in place of ya in Equations
(9) and (10), since the upstream depth, h, is the parameter that is specified in
the design situation. The predicted values of 0 given by the equations varied
from 9" - 11" for the channel flowing 68% full to 5" for the channel 83% full.
As explained, the differences relative to the actual weir angle of 0 = 22" were
due to the local reduction in water depth that occurs as the flow approaches
the side transition. Also, in some cases, the oblique wave formed on the
curved portion of the transition where the effective value of 0 was less than
along the straight portion.
Based on these results, it was decided to use the oblique wave theory to
produce general design curves for the Advice Note relating the wall angle, 0,
and the total weir length, ,L, to the upstream flow conditions in the channel.
The required values of 0 were assumed to be greater than the predicted
values, Op, given by Equations (9) and (10) according to the ratio: tan 0 =
2 tan O,,; this assumption is on the safe side compared with all the test data.
After considering alternative options, it was decided to base the curves on a
specified proportional flow depth of 67% in the channel upstream of the outlet.
This gave a reasonable balance between the required length of the outlet
structure and the loss of potential flow capacity in the channel due to the need
to design for part-full conditions. Although the full capacity cannot be utilised,
high flow rates can still be achieved because of the steep channel gradients
that apply when weir outlets are necessary.
In the case of trapezoidal channels, the design curves are based on the flow
rate approaching the outlet (see Figures 29 and 31 of Advice Note in Appendix
Ill). Although tests were not carried out with triangular channels, the oblique
wave theory is still applicable because the angle of the side transitions is the
principal factor determining the limiting capacity of the outlet. The design
curves (see Figure 27 of Advice Note in Appendix Ill) are defined in terms of
the upstream Froude number, F, corresponding to the proportionalflow depth
of 67%; this enables the curves to be applied to different sizes of triangular
channel.
The total length, ,L, of the weir (see Figure 14) is made up of two
components. L, corresponds to the upstream section of the outlet which has
a straight side wall. Based on the laboratory tests, L, is related to the overall
width of the upstream channel by:
where K is a constant which is equal to 1.0 for the trapezoidal channel tested
and is equal to 1.2 for triangular channels. Since the tests of the weir outlet
were only carried out with a trapezoidal channel, it was decided to adopt a
higher value of K for triangular channels. This higher value was chosen in
order to give the required initial distance for the flow to expand. The second
component, L, depends on the angle, 0, of the side transition and is given by:
L, = B1
-
tan 0
Standard circular gully pots can be used for outlets that consist of a single
grating or of two gratings installed in the in-line arrangement shown in Figure
A.2 of the Advice Note (see Appendix Ill). For larger outlets, it may be more
convenient to construct a single brick or concrete chamber beneath the
gratings. In this case, the invert level of the outgoing pipe from the chamber
should be above the floor so as to enable sediment to deposit and not be
discharged into the downstream pipe system or watercourse. As a rough
guide, the depth allowed for storage of sediment should not be less than that
provided by standard circular gully pots. The high flow rates that will occur
through outlets from surface water channels may cause the sediment-collecting
efficiency of the chambers to be less than is achieved with gully pots in normal
kerb-and-gully situations. Standard circular gully pots also have a limited flow
capacity and designs with an outlet pipe of 150mm diameter may not be able
to pass more than about 2511s without the water level reaching close to the
underside of the gratings.
The outlets tested in the central reserve of the A20 Folkestone to Dover
(Contract 1) were terminal outlets formed by triple gratings, measuring 450mm
X 1350mm overall, set flat on the line of the channel invert. This particular
layout does not fall into any of the types of outfall recommended in the Advice
Note, but it was nevertheless decided to check its design against the
recommendations for terminal in-line and off-line outlets. The values of the
Froude number were calculated for the three tests and are presented in Table
20. It can be seen in Table 1 of Appendix Ill that one pair of gratings on the
side-slopes or a single grating of dimensions 450mm X 450mm positioned on
the invert would be adequate for all the tests. It appears that these outlets are
slightly over designed but their extra capacity of the outlets may be put to use
if the maintenance of the channels is relaxed for some reason. The over
design of the outlets also reflects the adoption of a 'safe design' procedure by
engineers in view of the lack of design guidelines available until now.
The same analysis was carried out on the test results obtained at the A 487
Port Dinorwic Bypass. The fact that the sizes of the gratings adopted in this
scheme were, as at the Folkestone scheme, different from the sizes
considered in the Advice Note means that only an approximate comparison
can be made. The Froude numbers were calculated for all the tests from the
measurements of water depth and flow rate and are presented in Table 20.
It is important to note that the tests were carried out with the channels flowing
part-full whereas the Advice Note was developed to apply specifically to
channel-full conditions. In part-full flows the ratio of grating width, G, to water
depth can be significantly different from the ratio present in laboratory tests
which were carried out with channel-full conditions. This may affect the
present comparison, and an additional difference is that at Port Dinorwic the
gratings are positioned horizontally on the invert of the channel and are of a
bigger size than considered in the Advice Note (note that the Advice Note is
based on the minimum waterway areas of gratings currently recommended by
the British Standard). It can be seen in Table 20 that for outlets in the 1:19
slope the Advice Note would recommend a weir outlet in most cases if the
channel was flowing full. The fact that no bypass flow was observed is
probably due to the channel being only part-full, which allowed the gratings to
collect the flow more efficiently. Another factor is related to the uncertainty in
some values of flow (and therefore velocity) measured on site. The tests on
the lengths of channel at slopes of 1:16.5 and 1:204 slopes show a better
agreement with the recommendations of the Advice Note. It is interesting to
note in particular test no.7 where an efficiency of 97% was measured on site
due to some flow bypassing. The Advice Note shows that a similar value is
obtained with a grating of dimensions 450mm X 450mm. Overall it appears that
the outlets in the steeper channels at Port Dinorwic may be underdesigned for
the very high velocity flows that are generated in these locations.
C.5 CONCLUSIONS
(1) Although the field tests provided information for the preparation of the
Advice Note on Outfall Design, the range of conditions achievable on site
was not sufficiently wide to be used for the recommendations of suitable
designs. Therefore, the Advice Note was mainly based on the results of
the laboratory tests.
(2) The laboratory tests showed that grated outlets are not able to cope
efficiently with very high velocity flows such as those occurring in steep
roads (typically steeper than 1:50). In these situations it is recommended
to direct the water gently away from the carriageway onto the verge side
and then over a side weir into a lower collecting chamber.
PART D CONCLUSIONS AND RECOMMENDATIONS
(1) Extensive information on the use of surface water channels for road
drainage was obtained through questionnaires, meetings and site visits.
The adoption of this type of surface water drainage has rapidly spread in
the UK in recent years but most of the schemes identified are in the East
and South East of England, and in Wales.
(4) The current specification of 0-1Omm for the downward step between the
pavement surface and the edge of the concrete channel can be difficutt
to achieve and make consistent with the tolerances allowed for the
bituminous wearing course. These two different tolerances need to be
reviewed in parallel.
(5) Tolerances on level for surface water channels should not only apply to
the edge of the channel but also to the invert since it isthe difference of
the two levels that determines the capacity of the channel.
(7) The workability of the concrete mix should be primarily agreed between
the slipforming contractor and the concrete supplier within the
recommendations of BS 5931, 1980.
(1) An Advice Note on Outfall Design was prepared using the results
obtained from the laboratory and field tests, and from the information
gathered from the questionnaires and site visits carried out in the first
part of the study.
(2) The laboratory and field tests showed that grated outlets are not efficient
in collecting very high velocity flows which typically occur in roads steeper
than 1:50. A new design which directs the water away from the
carriageway over a side weir was developed from experimental data and
theoretical calculations.
(3) The work carried out to develop methods for the design of outfalls in
surface water channels has some implication on the existing Advice Note
HA 37/88 and on Amendment No 1 which deal with the hydraulic design
of surface water channels. These need to be revised so that consistency
is achieved with the newly prepared Advice Note on Outfall Design. The
topics that require development work are the following:
(b) The effect that flow bypassing intermediate outlets has on the
spacing of outlets;
The authors of this report are also thankful for the contributions provided by
Dr B J Chaddock, Mr B Robinson, Mr J Chandler and Mr M McDonald of TRL.
BS 497: Part 1: 1976. Specification for Manhole covers, road gully gratings
and frames for drainage purposes. Part 1. Cast iron and cast steel. British
Standards Institute.
BS 5931: 1980. British Standard Code of Practice for Machine laid in-situ edge
details for paved areas. British Standards Institute.
BS 6367: 1993. British Standard Code of practice for Drainage of roofs and
paved areas. British Standards Institute.
Road Note 35 (1 976). A guide for engineers to the design of storm sewer
systems. Department of the Environment. Transport and Road Research
Laboratory.
NOTATION: SCHEMES:
- ENGLAND -
C - Construction (1) LONDON:
D - Design (2) EASTERN:
M - Maintenance 2.1 - A47 Norwich Southern BP (Contract 1)
MP - Maintenance Period 2.2 - A47 Norwich Southern BP (Contract 2)
-
T Tender 2.3 - A47 Norwich Southern BP (Contract 3)
2.4 - A47 Norwich Southern BP (Contract 4)
R - Rural 2.5 - A1 1 Thetford BP
U - Urban 2.6 - A1 1 Red Lodge BP
2.7 - Al-M1 Link (Contract 8)
COMP - Composite 2.8 - M40 Widening
FLEX - Flexible 2.9 - A1 l Besthorpe - Wymondham Improvement
-
2.10 A5 Little Brickhill BP
-
FD Fin Drain (3) EAST MIDLANDS:
NFD - Narrow Filter Drain 3.1 - A16 Louth BP
3.2 - A16 Boston BP
F - Flat 3.3 - A6 Quorn-Mountsorrel BP
3.4 - A6 Market Haborough BP
EX - Extruded (4) NORTHERN:
IS - In Situ (5) NORTH WEST:
-
PC Precast 5.1 - A500 Nantwich BP
SF - Slip Form 5.2 - A523 Macclesfield Relief Road
-
5.3 A49 Weaverham Diversion
GC - Grating in Channel Invert (6) SOUTH EAST:
-
GV Grating Back in Verge -
6.1 A21 Pembury BP
6.2 - M20 J5-J8 Maidstone BP
CD - Carrier Drain 6.3 - A23 Muddleswood-Patcham
-
SO Soakaway 6.4 - A20 Folkestone-Court Wood (Contract 1)
TD - Toe Ditch 6.5 - A20 Court Wood-Dover (Contract 3)
WC - Water Course 6.6 - M3 Bar End-Compton
6.7 - A27 Westhampnett BP
NOTATION: SCHEMES:
0 - Other -
6.8 A3 Milford BP
(7) SOUTH WEST:
ND - Not Decided 7.1 - A36 Beckington BP
7.2 - A30 Okehampton-Launceston Improvement
CA - Carriageway (8) WEST MIDLANDS:
8.1 - A49 Dorrington BP
CR - Central Reserve (9) YORKSHIRE AND HUMBERSIDE:
9.1 - A15 Bonby Lodge BP
-
CH Channel 9.2 - A19 Easingwold BP
9.3- A1 Motorway Walshford to Dishford
- NORTHERN IRELAND -
10.1 - Strabane BP
- SCOTLAND -
11.l- A7 Moss Peeble to Bush
- WALES -
12.1 - A4042 Llantarnam BP
12.2 - A472 Maesycurmmer/Newbridge
-
12.3 M4 Renewal
12.4 - A494 Mold BP
12.5 - A487 Port Dinorwic BP
12.6 - A465 Neath-Abergavenny Trunk Road
Table I Summaryofresultsofquestionnaire
Overall description of scheme
Scheme Stage Carriageway Type of Length of Width of Longitudinal gradients Type of Drainage
cross-section Pavement Road (km) carriageway (m)
Max Min
(1) London CPD No schemes
(2) Eastern NMD
2.1 MP R-AP / A2 FLEX 5.2 7.3 +2X 1 1:29 F FD, T6, F19
2.2 MP R-AP / A2 FLEX 4.3 7.3 + 2 X l 1:25 F FD, T6
2.3 MP R-AP / A2 FLEX 7.1 7.3 + 2 X 1 1:25 F FD, T6
2.4 MP R-AP / A2 FLEX 5.8 7.3 + 2 X l 1:36 F FD, T6
2.5 M R-AP / A2 COMP 7.6 7.3 + 2 X 1 1:25 1:285 FD, T6 mod
2.6 MP & M R-D2 AP / A 2 COMP -
2.75 7.3 + 2 X 1 1:l
66 1:222 FD, T6
2.7 MP R-AP / A2 FLEX 6.2 7.3 + 2 X 1 1:50 1:3000 FD, T6
2.8 MP R-M / A1 FLEX 11.95 - 13.55 11 + 3.3 1:28 F NFD, T8
2.9 T R-AP / A2 -- 8.6 7.3 + 2 X 1 1:24 F
2.1 0 C R-AP / A2 FLEX 3.6 7.3 + 2 X l* 1:25 F NFD, T8
(3) East midlands CPD
3.1 M R-AP / A2 FLEX 6.0 7.3 to 10 + 2 x 1' 1:12.5 1: l 40 NFD, T9
$100 mm
3.2 M R-AP / A2 FLEX 9.1 7.3 + 2 X 1.65 1:175 1:2300 FD, T6
3.3 M R-AP / A2 FLEX 8.8 7.3 + 2 X 1 1:200 F NFD, T8
3.4 MP R-AP / A2 FLEX 8.4 (1.48 CH) 7.3 + 1 1:56 1:500 NFD, T8
Table I Continued
7.1 M R-AP lA2 FLEX 3.4 7.3 + 2 X 1' 1:25 1:284 NFD, T8
7.2 C R-AP lA2 FLEX 20.0 7.3 +2X 1 1:12 1:200 NFD, T8
11.l D R-WS I 2 FLEX 1.5 10.0 1:22 1:200 FD, T5, COMB
Table l Continued
8.1 ND ND ND ND ND ND
anlm papuaur
-- -- -- m- -- -- -- 9'Z L
S: L S: L 8L 006 -- P18 P L8 S'Z L
P: L L: L OS L SZL AS VEZ~
'Z 18 VEI '€8 P-zL
S: 1 L: L OS L SL8 AS Z L8 E'Z L
-- a3~s1a OS OS L 3d -- ~a z-zL
P: L P:L SL'OOL'SZL 009 '008 '001 3d 0 0 L'Z l
SalEM (ZL)
OE L 006 L
S: l S: L 8E L SLE L AS Z 18 0 1'11
PU9lWS ( l l )
1: L P: L OS L SEL AS Us0018 -- 1'01
PuElaJl UlallVoN (0 L)
9: L S: L S'L6 SL6 AS Z L8 E8 C6
9: l S: L OS 919 Z L8 E8 1'6
9: l L: L 001 009 3d E8 1'6
a d 3 ap!slaqunH pue a + ~ s y l o ~
(6)
(MM) (UN luauryuequq
sadols a p ! ~ rlldaa II~JW WP!M MOIA uB!saa U! s a 6 ~ a ~ 6u!lwa U! sa6.1a~
uo~pru~suo3
lauueqa p hlauroag 10 POlw"i ~!elaaa6p3 luaura~ad auraqas
Table 3 Summary of results of questionnaire
Surface channels in central reserve
(1 1) Scotland
m- -- -- -- -- m-
11.1
Table 3 Continued
Amended value
.. Stone filled trench over fin drain
Table 4 Summary of results of questionnaire
Description of channel outfalls
I I I
Scheme Total No of Outlets Type of Distance between Outlets Outlets Edition of HCD
Outlet discharge
Verge A Central Reserve Verge B Max (m) Min (m) into
(7) South West CPD
7.1 5 3 11 GC 350 80 CD 1987
7.2 118 49 136 GC 300 90 CD 1987
(8) West Midlands CPD
8.1 ND ND ND ND ND ND ND 1992
(9)Yorkshire and Humberside CPD
m- -a --
9.1 GC 90 30 CD 1987
-m
9.2 59 87 GC 50 50 CD 1987
9.3 >200 >l 00 >200 GC 100 10 CD 1991
(1 0) Northern Ireland
10.1 5 -- 6 GV 240 100 CD DOE (NI)
ROADS SERVICE
(11) Scotland
11.1 4 -- -- GC 500 20 WC, CD & 1991
CHANNEL
Table 4 Continued
Scheme Total No of Outlets Type of Outlet Distance between Outlets Outlets Edition of
discharge into HCD
Verge A Central Verge B Max (m) Min (m)
Reserve
(12) Wales
V - Verge
Asymmetrical channel with side slopes 1:1 and 1 :5
- Uncertain
Table 8 Results of field tests at A487 Port Dinorwic Bypass
Note: The values of velocity in brackets were obtained from estimated flows.
Doubtful data
2'69 29 10'0 9960'0 P6PO'O 8
8'96 9L0000'0 0900'0 PZOO'O L
(%) d
('-4 (s/p)
h '"d."'
0 4 0 Fa1
Table 10 Triangular channel
In-line outlet, intermediate
A) -
Channel full
Q Q h Slope
(rn3/s) (rn3k) (m)
1 pair of gratings
0.0597 0.02123 0.094 1 :60
0.0516 0.0133 0.096 1:lOO
0.0412 0.00476 0.094 1 :250
0.0288 0.00230 0.094 1500
0.0323 0.00197 0.100 1 :2000
2 pairs of gratings
0.0655 0.01122 0.094 1 :50
0.0592 0.00658 0.094 1 :60
0.0572 0.00257 0.098 1:lOO
0.0418 0.00376 0.093 1 :200
B) Surcharged
Q Q h Slope
(rn3/s) (rn'k) (m)
1 pair of gratings
0.0830 0.02598 0.116 1 :l00
0.0615 0.01034 0.103 1 :250
0.0515 0.00616 0.121 1 500
0.0489 0.00456 0.119 1 :2000
2 pairs of gratings
0.0902 0.02171 0.11 1 1 :50
0.0901 0.01643 0.112 1 :60
0.0831 0.00854 0.116 1:lOO
0.0722 0.00196 0.123 1 :200
Table I I Triangular channel
In-line outlet, terminal
A) -
Channel full
Q Q h Slope
(m3/s) (m3L) (m)
1 pair of gratings
0.0597 overtopping 0.093 1 :60
0.0528 overtopping 0.096 1 :l 00
0.0410 0 0.096 1 :250
0.0288 0 0.094 1 :500
0.0288 0 0.097 1 :2000
2 pairs of gratings
B) Surcharged
Q Q h Slope
(m3/s) (m3P,) (m)
1 pair of gratings
0.0830 overtopping 0.115 1:lOO
0.0650 overtopping 0.121 1 :250
0.0515 0 0.115 1 :500
0.0489 0 0.124 1 :2000
2 pairs of gratings
0.0902 overtopping 0.111 1 :50
Table 12 Effect of different bar patterns
Triangular channel
-
In-line intermediate outlet 1 pair of gratings
A) -
Channel full
Q Q h Slope
(m3/s) (m3L) (m)
1 grating
0.0538 0.02653 0.098 1 :80
0.0492 0.01941 0.097 1:lOO
0.0413 0.00682 0.106 1 :250
0.0357 0.00177 0.105 1 :500
2 gratings
0.0540 0.01584 0.097 1 :60
0.0500 0.01142 0.097 1 :70
0.0502 0.00982 0.098 1 :80
3 gratings
0.0627 0.00748 0.101 1 :50
0.0540 0.00443 0.097 1 :60
0.0560 0.00270 0.103 1 :70
0.0467 0 0.098 1 :l 00
0.0463 0 0.109 1:150
0.0352 0 0.11 1 1 :500
B) Surcharged
Q Q h Slope
(m3/s) (m3L) (m)
3 gratings
0.0873 0.02144 0.121 1 :50
0.0755 0.00541 0.126 1:lOO
0.0706 0.00152 0.134 1:150
0.0460 0 0.123 1:500
Table 14 Triangular channel
Off-line outlet, intermediate
Ramps between gratings
A) -
Channel full
Q Q h Slope
(m3/s) (m%) (m)
3 gratings and 2 ramps
0.0493 0.094 1 :l 00
0.0540 negligible 0.099 1 :80
0.0522 0.00082 0.098 1 :60
0.0585 0.00464 0.099 1 :50
2 gratings and 1 ramp
0.0492 0.00582 0.096 1:lOO
0.0525 0.00158 0.096 1 :70
0.0550 0.01346 0.096 1 :60
B) Surcharged
Q Q h Slope
(m3/s) (m") (m)
3 gratings and 2 ramps
0.0738 0.00170 0.118 1:lOO
0.0800 0.00636 0.121 1 :80
Table 15 Trapezoidal channel
In-line outlet, intermediate
Model values
A) Channel full -
Q Q h Slope
(m3/s) (m3b (m)
2 gratings
0.0515 0.0152 0.096 1 :250
0.0463 0.0096 0.093 1 :400
0.0423 0.0063 0.105 1 :667
3 gratings
0.0703 0.0231 0.097 1 :l00
0.0603 0.0129 0.099 1 :200
0.0510 0.0067 0.098 1 :250
0.0470 0.0024 0.094 1 :400
B) Surcharged
Q Q h Slope
(m3/s) (m3L) (m)
3 gratings
0.0740 0.0175 0.122 1 :300
0.0649 0.0127 0.120 1 :400
0.0598 0.011 1 0.120 1 :667
-
Table 16 Trapezoidal channel
In-line outlet, terminal
Model values
A) -
Channel full
Q Q h Slope
(m3/s) (m3P,) (m)
3 gratings
0.0649 0.0095 0.096 1 :l 00
0.0515 negligible 0.099 1 :250
0.0418 -- 0.104 1 :667
B) Surcharged
Q Q h Slope
(m3/s) (m3P,, (m)
3 gratings
0.0598 negligible 0.123 1 :667
Table 17 Trapezoidal channel
Off-line outlet, intermediate
Model values
A) -
Channel full
Q Q h Slope
(m3/s) (m3L) (m)
1 grating
0.0810 0.0491 0.103 1:150
0.0723 0.0393 0.103 1 :280
0.0652 0.0318 0.102 1 :300
0.0513 0.0158 0.107 1 :667
0.0524 0.0164 0.110 1 :711
2 gratings
0.1161 0.0615 0.113 1 :60
0.0849 0.0254 0.099 1:lOO
0.0797 0.0175 0.101 1:150
0.0747 0.0114 0.104 1 :200
0.0663 0.0062 0.103 1 :300
0.0568 0.0031 0.095 1 :400
0.0513 0.0017 0.10999 1 :667
3 gratings
0.1177 0.0248 0.11 1 1 :60
0.0884 0.0101 0.100 1:lOO
0.0731 0.0015 0.102 1 :200
0.0633 -- 0.099 1 :300
0.0584 -- 0.101 1 :400
Table 17 Continued
B) Surcharged
Q Q h Slope
(m3/s) (m3L) (m)
1 grating
0.0809 0.0372 0.136 1 :667
0.0821 0.0372 0.137 1 :711
2 gratings
0.1395 0.0651 0.132 1 :l00
0.1006 0.0287 0.128 1 :200
0.0947 0.0224 0.132 1 :300
0.0857 0.0152 0.127 1 :400
0.0782 0.0102 0.134 1 :667
3 gratings
0.1679 0.0455 0.134 1 :60
0.1444 0.0339 0.135 1:lOO
0.1046 0.0102 0.127 1 :200
0.0880 0.0025 0.129 1 :400
0.0903 0.0004 0.134 1 :667
OOE: C 98 1'0 alq!6!16au 8860'0
002: 1 981'0 OSOO'O OLLC'O
0OC:L 9E 1'0 9PZO'O P6P l'0
s6u!lm6
L991C 9€ 1'0 alq!6!16au LSLO'O
OOE: L SE 1'0 28 10'0 CZ60'0
OOZ: l 96 1'0 OOEOO
' 86 C 1'0
s6u!1a6 z
(4 (slcUJ)
adols '4
"d."'
0 0
OOZ: C C 11'0 alq!6!16au 18L0'0
00C:C C C 1'0 Z C 10'0 0860'0
s6u!ye.~6E
L99: C C C 1'0 -- OESO'O
OOE: C 60 1'0 C ZOO'O P690'0
OOZ: C 60 1'0 8E 10'0 €080'0
s6u!ya6 z
(UJ) (s/€UJ)
adols '4
(v) 0 0
Table 19 Weir outlet
Model values
Q h ya Slope yb Observations
(m3/s) (m) (m) (m)
-
A) Channel full, 1 grating
0.0645 0.104 0.0210 1 :250 --
0.0908 0.108 0.037 1:lOO
0.1160 0.110 0.042 1 :60 0.103
0.1267 0.111 0.042 1 :51 0.110
0.1200 0.108 0.046 1 :50 0.108
0.1330 0.110 0.052 1 :43 0.112 Capacity of outlet
exceeded
Section A-A
Dimensions in metres
-
Figure 12 Trapezoidal channel 1:4.5 Off-line outlet
Figure 14 Weir outlet
Trangular channel
In-line outlet
Surcharged channel 1 curves:
-
Figure 18 Design curves. Triangular channel Off-line outlet
Surcharged channel
Figure 20 Design curves. Trapezoidal channel with cross-falls of 1:4.5
In-line outlet. Surcharged channel
Trapezoidal channel with cross-falls of 1:4.5
Off-line outlet
Surcharged channel
slleM lauueqa jo uo!aaaljap 01 anp aneM anbilqo jo uo!leluloj a~n6!j
Appendix I
General Questionnaire
U a suolsuaula
(U) h e ~ a 6 ~ ! ~
40~4lP!M
83 ( W ) PeoJ10 416ual
auraq3s JOJ
( S ) U O S J ~l3aUO3
~
a a
auoqdalal s s a ~ p pue
p~ a u e ~
J
slleiino pue slauueya AaieM a a e ~ ~ n
uos aA!euuo!gsany)
D Insert information in appropriate box
J Tick appropriate box
* If channel has vertical side, enter side slope 1: 0
1 Central reserve
Pavement edge B6 B7 Other
detail J J D
(as defined by HCD)
E
Q)
L
C
Design flow width (mm) Overall depth (mm) Side-slopes
Geometryof
1 channel D D
1:
I I 1 I
Year of publication
Edition of HCD
0 referre to in
parts &and @
D
NOTES FOR COMPLETION OF QUESTIONNAIRE ON SURFACE WATER
CHANNELS AND OUTFALLS
1. This questionnaire concerns road schemes with surface water channels that
have already been built or are at any stage between design and construction.
2. Separate forms should be completed for each scheme (the two pages of the
questionnaire should be copied as many times as necessary). If an overall
scheme consists of sectior~swith different characteristics (eg, motorway, slip
road, link road), each section should be described separately.
3. In Part F, give separately the numbers of outlets in both verges and the central
reserve (if applicable). For example, verge A might be on the northbound
carriageway and verge B on the southbound carriageway.
5. After analysis of the data, a few representative schemes will be selected for
more detailed study. Please therefore identify in Part C of the questionnaire a
contact person for each scheme who would be able to assist if such a follow-up
is required.
Mr R W P May
HR Wallingford
Wallingford
Oxfordshire
OX10 8BA
A. HYDRAULIC DESIGN
A.l Channels
(c) (1) Does the pavement drainage connect to a carrier pipe serving the
surface drainage?
B. CONSTRUCTION
(b) Did the channels save money compared with alternative drainage
methods?
(c) How could the overall drainage system (surface channels and pavement
drainage) be improved?
(b) Did the channels save time compared with alternative drainage methods?
(c) Did the use of channels help or hinder the construction of the road
foundation and pavement?
(d) (1) Was it difficult to achieve the required tolerances on line, level and
shape of the channels?
(2) If yes, were the tolerances impractical or are they achievable with
experience?
(f) Were there difficulties with the construction of the pavement drainage
system?
(g) If the road were to r e q ~ ~ i an
r e overlay in the future, how best could the
surface channels be modified?
(b) (1) Was it difficult to achieve the required tolerances on line, level and
shape of the channels?
(d) If the road were to require an overlay in the future, how best could the
surface channels be modified?
C. SAFETY
D. MAINTENANCE
(f) Are there particular problems in cleaning the channels and outfalls?
(i) If the road were to require an overlay in the future, how best could the
surface channels be modified?
Appendix 111
FIGURES
Design curves
Trapezoidal channel with cross-falls of
114.5 - off-line outlet
Channel-full
Design curves
Trapezoidal channel with cross-falls of
1:4.5 - off-line outlet
Surcharged channel
Design curves
Trapezoidal channel with cross-falls of
1:5 - in-line outlet
Channel-full
Design curves
Trapezoidal channel with cross-falls of
1:5 - in-line outlet
Surcharged channel
Design curves
Trapezoidal channel with cross-falls of
1:5 - off-line outlet
Channel-full
Design curves
Trapezoidal channel with cross-falls of
1:5 - off-line outlet
Surcharged channel
4. TYPES OF OUTLET
The total length of the weir outlet L, is The new value of flow rate, Q',
formed by a straight stretch, L,, and a corresponding to the revised spacing is
stretch, L,at an angle 0 to the line of the then introduced in Chart A of Figure 31
channel. The value of L, is determined to give the total length of the weir, L.,
by: The value of the angle 0 (see Figure 25)
can then be read off Chart B of Figure
31. See last paragraph of Clause 6.2 for
L, = - B, further definition of the geometry of the
tan 8
weir outlet.
7.3 The plan shape of the chamber will be where E is the width of the rectangular
determined by the layout of the gratings channel (in m) and Q is the design rate
forming the outlet. The invert of the of flow (in m3/s).The width of the channel
outgoing pipe from the chamber should should not be less than E = 0.5m.
be set a minimum of 300mm above the
bottom of the chamber to retain an 7.7 It is recommended that the collecting
adequate volume of sediment. channel below a weir outlet should
discharge into a chamber with a
7.4 The invert level of the outgoing pipe removable cover in order to still the flow
should be chosen so that the water level and allow sediment to be collected. The
in the chamber does not rise high sizes of the chamber and the outgoing
enough to prevent flow discharging pipe should be determined in
freely from the surface water channel accordance with the general
into the outlet. For design, it is recommendations in Clauses 7.3 to 7.6.
recommended that the water level in the
chamber should be at least 150mm 8. SPACING OF OUTLETS WITH BY-
below the underside of the gratings PASSING
when the outlet is receiving flow from the
channel under surcharged conditions. When by-pass flow is allowed in the
The height Z (in m), of the water surface design of an intermediate outlet, ie when
in the chamber above the invert of the efficiencies lower than 100% are
outgoing pipe can be estimated from the adopted, the design of the channel
equation: downstream of the outlet is no longer
directly covered by Advice Note HA
37/88. In this case the spacing of the
outlets needs to be reduced in order to
allow for the additional flow by-passing
the upstream outlet. As an interim
where D is the diameter of the pipe (in measure, it is recommended that the
m) and Q is the flow rate (in m3/s) in the distance L between outlets, as
chamber corresponding to surcharged determined in HA 37/88, should be
conditions in the surface water channel. reduced to qL, where q is the adopted
The gradient and diameter of the design efficiency of the upstream outlet.
outgoing pipe should be determined
from standard flow tables or resistance
equation so that the pipe is just flowing 9. OVERALL DESIGN OF SURFACE
full under surcharged conditions. WATER CHANNEL SYSTEMS
7.5 Providedthe chamber below the outlet is In order to obtain the most cost-effective
designed to trap sediment, the outgoing solution for a drainage system using
pipe from the chamber may be surface water channels, the designer
connected directly to a collector pipe by should consider the total cost of the
means of a 45" Y junction without the channels and outlets together. In some
need for a manhole at the junction cases, a design based on the longest
position. possible spacings between outlets may
not be the optimum solution. Shorter
7.6 If a weir outlet is used (see Section 6), spacings will require more outlets but
the collecting channel into which flow these may be smaller and cheaper; also,
drops from the weir should be deep the shorter distance between outlets will
enough to allow the outlet to discharge allow use of smaller sizes of surface
water channel. The effect on the total Calculate also F, using Equation (5). It
cost of allowing different amounts of by- is first necessary to calculate B,. For a
passing at intermediate outlets should carriageway cross-fall of 1:40, 1m of
also be considered. For each option the surcharging corresponds to 0.025m of
relationship between channel size and water depth above the channel-full
required outlet spacing should be depth, ie a total depth of 0.145m.
determined from Advice Note HA 37/88 Therefore
(plus Amendment No l ) , and the effect
of allowing by-passing at intermediate
outlets should be estimated according to
Section 8.
Width of gratings
Length of gratings
rl Efficiency
12 REFERENCES
2. Amendment No 1 to HA 37/88,
Department of Transport, 1991.
No OF GRATINGS
TYPE OF OU1-LET 2 3
IIV-LINE OUTLET :
l
1 l :5 1:5
l
I Carriageway, hard-strip l I
or hard shoulder Terminal
L A
ramp
Section A-A
Dimensions in metres
I I I I I I l I I I I l I I I I I I l I I
Trangular channel
In-line outlet
Surcharged channel
100- 1 Pair of gratings
2 Pairs of gratings
---- 3 Pairs of gratings
90 - -
80
h
8
V
F"
70 - -
60 - -
\
\
\
50 I I I I I I l I I l I l l I I I l I I I I
-
Figure 14 Design curves. Triangular channel Off-line outlet
Surcharged channel
Figure 16 Design curves. Trapezoidal channel with cross-falls of 1:4.5
In-line outlet. Surcharged channel
Figure 18 Design curves. Trapezoidal channel with cross-falls of 1:4.5
Off-line outlet. Surcharged channel
Figure 20 Design curves. Trapezoidal channel with cross-falls of 1:5
In-line outlet. Surcharged channel
r - I I I I I
Trapezoidal channel with cross-falls of 1:5
Off-line outlet
Surcharged channel 1 Curves:
Figure 24 Example of triangular channel with weir outlet
Yes
.Trapezoidal channel
Calculate Q, and Q,
(Clauses 3.1 and 3.4)
,
IS Yes Yes
Weir outlet is
necessary
Determine geometry
of weir outlet from
Figs 25 and 29 and
Clauses 6.1 and 6.3
Determine geometry
Yes
N~ + of grated outlet from
Design curves in
Figs 19 to 22
and Figs 9 and 10
Yes Yes
y
Weir outlet is
necessary
r
- . f
Determine geometry Reduce design depth of
of grated outlet from water to 0.1 00m.
Table 3 and Re-calculate spacing
Figs 9 and 10 of outlets using
HA 37/88
L, of flow, Q'
Determine geometry
of weir outlet from
Figs 25 and 31 and
Clauses 6.1 and 6.4
Figure 30 Flow chart for design of weir outlet in trapezoidal channel 1:5
OZZ'O 002'0 08 1'0 09 1'0 Ob 1'0 OZ 1'0 00 1'0 080'0 090'0 1
APPENDIX A
Plan view