Claim Methodology PDF
Claim Methodology PDF
“Claim Methodology “
Page 1 of 2
2
CONTACTS
Tel +966-545026272
Mob +966-545026272
Email: [email protected]
[email protected]
NMDCE.
Masr Centre
AHM.RATEB Street,Cairo, 6Th October
Reference :
Page 2 of 2
Common Delay Analysis
Methodologies
The common delay analysis methods - which are categorized as per their
charcteristics - are depicted in Table 1 below.
Capabilities of considering the dynamic nature of the CP and actual work progress
are the fundamental strength of this method [2]. The procedure of the windows
analysis is depicted as follows;
Step 1: Compute the delays
and improvements for the First
Window
Step 1.1
Develop a baseline schedule. Divide the total period of a construction project into
digestible periods which is also named windows or snapshot [1], [3]. Windows size
can be selected according to schedule updates, milestones or major delay events [1].
Step 1.2
Obtain the first schedule update updated as of end date of the first window including
owner’s delays, contractor’s delays and delays resulting from acts of God. Update
data should include actual start, actual finish (for completed activities), % completion
and remaining duration. Please note that schedule update date should be 1 day 2023
© Copyright after Erachron. All Rights Reserv
the end date of the window.
Step 1.3
Detect the activities on Critical Path via first schedule update through 1st schedule
update.
Step 1.4
Detect and apportion the delays by comparing the activities on the Critical Path (CP)
detected in the first schedule update with the baseline schedule for the first window.
Obtain the second schedule update updated as of as of end date of the second
window.
Step 2.2
Detect the activities on Critical Path via 2nd schedule update.
Step 2.3
Detect and apportion the delays by comparing the activities on the Critical Path (CP)
in the first schedules window and second schedule update.
Step 3
Repeat step 2 for the other windows
Outcomes obtained from each window constitute overall project delays.
Delays and improvement are detected and apportioned by analyzing the activities on
CP through following sections
• Early and Late Commencement and Finish date of Activities → Non-Excusable Delay
• Duration Change → Non-Excusable Delay
• New Activities in the Schedule Update → Non-Excusable Delay or Excusable
Compensable Delay or Excusable Non-compensable Delay
Possible sources concerning delays and improvement are depicted in Table 1 below.