Madina Developments Ltd
Cost for Additional 5" Thickness Brick Work
Total area 100 Sft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 1st class Bricks 500.00 Nos 14.50 7,250.00 2 Cement 2.50 Bag 550.00 1,375.00 3 Local Sand 17.00 Cft 25.00 425.00
4 Labour Charge for making 100.00 Sft 20.00 2,000.00
5 others Cost (Curing ,Cleaning etc) 1.00 LS 500.00 500.00 Total= 11,550.00 6 25% Service Charge 25% 2,887.50 Total cost 14,437.50 Rate Per Sft 14437.5 100 144.38 Madina Developments Ltd Cost for Additional 10" Thickness Brick Work
Total Area 100 Cft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 1st class Bricks 1200 Nos 14.50 17,400.00 2 Cement 4 Bag 550.00 2,200.00 3 Local Sand 35 Cft 25.00 875.00 4 Labour Charge making 100 Cft 25.00 2,500.00 5 Others Cost 1 LS 500.00 500.00 Total 23,475.00 Rate Per Cft 234.75 6 25% Service Charge 25% 58.69 Rate Per Cft Cft 100 293.44 Madina Developments Ltd Cost for Additional 10" Thick Brick wall dismantling
Total Area 100 Cft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 1st class Bricks 1200 Nos 14.50 17,400.00 2 Cement 4 Bag 550.00 2,200.00 3 Local Sand 35 Cft 25.00 875.00 4 Labour Charge Making 100 Cft 25.00 2,500.00 Others cost 1 LS 500.00 500.00 Total 23,475.00 5 Labour Charge breaking and cleaning 100 Cft 25.00 2,500.00 6 Cleaning and Others 1.00 Nos 500.00 500.00 S. Total 26,475.00 7 Service Charge 25% 26,475.00 6,618.75 Total Cost 33,093.75 Rate Per Cft 33094 Cft 100 330.94 Madina Developments Ltd Cost for Additional 5" Thickness Brick wall dismantling
Total work = 100 Sft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 1st class Bricks 500 Nos 14.50 7,250.00 2 Cement 2.5 Bag 550.00 1,375.00 3 Local Sand 17 Cft 25.00 425.00 4 Making Labour Charge 100 Sft 20.00 2,000.00 5 others Cost 1 LS 500.00 500.00 6 Labour Charge Breaking 100 Sft 20.00 2,000.00 7 Cleaning and others 1 LS 500.00 500.00 Total= 14,050.00 8 25% Service Charge 25% 3,512.50 Total cost= 17,562.50 Rate Per Sft 100 175.63 Madina Developments Ltd Cost for 3" Thick R.C.C sunshed & drop wall/Lintel
Total work = 100 Sft 25 Cft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 3/4" Bricks chips 22.50 Cft 175.00 3,937.50 2 Cement 4.50 Bag 550.00 2,475.00 3 Local Sand 13.00 Cft 25.00 325.00 4 MS Rod 1% 55.50 Kg 95.00 5,272.50 - 5 Labour Charge - 6 Casting work 100.00 Sft 25.00 2,500.00 7 Shuttering Charge 113.50 Sft 25.00 2,837.50 8 Rent for shuttering 113.50 Sft 25.00 2,837.50 9 Ms Rod febrication 55.00 Kg 7.50 412.50 10 Others Cost 1.00 LS 500.00 500.00 Total= 21,097.50 Service Charge 25% 5,274.38 Total cost= 26,371.88 Rate Per Sft 26,371.88 Sft 100 263.72 For Lintel 26,371.88 Rft 100 263.72 Madina Developments Ltd 3" Thick R.C.C Slab,sunshed & drop wall Breaking Cost
Basis per Sft Total= 100 Sft 25 cft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 3/4" Bricks chips 22.50 Cft 175.00 3,937.50 2 Cement 4.50 Bag 550.00 2,475.00 3 Local Sand 13.00 Cft 25.00 325.00 4 MS Rod 1% 55.50 Kg 95.00 5,272.50 - 5 Labour Charge - 6 Casting work 100.00 Sft 25.00 2,500.00 7 Shuttering Charge 113.50 Sft 25.00 2,837.50 8 Rent for shuttering 113.50 Sft 25.00 2,837.50 9 Ms Rod febrication 55.00 Kg 7.50 412.50 10 Others Cost 1.00 LS 500.00 500.00 11 Labour Charge for Breaking 100.00 LS 130.00 13,000.00 34,097.50 Service Charge 25% 8,524.38 Total cost= 42,621.88 Rate Per Sft 42621.88 Sft 100 426.22 For Lintel (6"x5") 42621.88 Rft 100 426.22 Madina Developments Ltd 3/4"Thick Plastering work (1:4) Cost Basis per Sft Total= 100 Sft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 Cement 1.50 Bag 550.00 825.00 2 Local Sand 10.00 Cft 25.00 250.00 3 Labour Charge - 100.00 Nos 20.00 2,000.00 4 Others cost 1.00 LS 200.00 200.00 Total cost = 3,275.00 Service Charge 25% 818.75 4,093.75 Rate Per Sft 4093.75 100 40.94 Madina Developments Ltd 3/4"Thick Plaster breaking (1:4) Cost
Basis per Sft Total= 100 Sft
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks
1 Cement 1.50 Bag 550.00 825.00 2 Local Sand 10.00 Cft 25.00 250.00 3 Labour Charge for Making - 100.00 Nos 20.00 2,000.00 4 Labour Charge for breaking & Cleaning 100.00 Sft 20.00 2,000.00 Total 5,075.00 Service Charge 5,075.00 25% 1,268.75 Total Cost 6,343.75 Per Sft Cost 6,343.75 100 63.44 Madina Developments Ltd Cabinet Basin (3'-0"x2'-0")
Total Work 01 Nos
Date 10/7/2023
Sl no Particular of Materials Quantity Unit Rate in taka Amount Remarks