Chapter 8 Solutions Manual AST
Chapter 8 Solutions Manual AST
Cash 2,500,000.00
Accounts Receivable 2,500,000.00
To record collection
Cash 4,000,000.00
Accounts Receivable 4,000,000.00
To record collection
PROBLEM 8-2
June 30, 2019 Dec. 31, 2019 June 30, 2020 Dec. 31, 2020
Cost incurred to date 900,000.00 2,100,000.00 3,180,000.00 3,600,000.00
Total Estimated cost to complete 3,600,000.00 3,600,000.00 3,600,000.00 3,600,000.00
Percentage of completion 25% 58% 88% 100%
June 30, 2019 Dec. 31, 2019 June 30, 2020 Dec. 31, 2020
Constructions Revenue 1,125,000.00 2,625,000.00 3,975,000.00 4,500,000.00
Constructions Costs 900,000.00 2,100,000.00 3,180,000.00 3,600,000.00
Profit to date 225,000.00 525,000.00 795,000.00 900,000.00
Less: Recognized last period(s) - 225,000.00 525,000.00 795,000.00
Profit (loss) recognize this period 225,000.00 300,000.00 270,000.00 105,000.00
PROBLEM 8-3
2019 2020
Cost incurred to date 1,185,800.00 4,485,000.00
Total Estimated cost to complete 5,390,000.00 6,985,000.00
Percentage of completion 22% 64%
2019 2020
Constructions Revenue 1,386,000.00 4,045,168.22
Constructions Costs 1,185,800.00 4,485,000.00
Profit to date 200,200.00 - 439,831.78
Less: Recognized last period(s) - 200,200.00
Profit (loss) recognize this period 200,200.00 - 640,031.78
PROBLEM 8-4
1 a Cash 3,500,000.00
Advances from customer 3,500,000.00
Year-end adjustment
2 Under IFRS 15, CIP and PB are no longer use. Contract Asset / Contract Liability accounts will be used instead.
PROBLEM 8-5 (include billings of 800,000; 600,000; 600,000 for 2018, 2019, and 2020, respectively. Delete the estimated remaining costs in 2020)
2018 2019 2020
Cost incurred to date 720,000.00 1,600,000.00 1,740,000.00
Total Estimated cost to complete 2,400,000.00 2,100,000.00 1,740,000.00
Percentage of completion 30% 76% 100%
Cash 600,000.00
Accounts Receivable 600,000.00
To record collection
2019
Contract Asset 880,000.00
Various Accounts 880,000.00
To record cost incurred
Cash 600,000.00
Accounts Receivable 600,000.00
To record collection
2020
Contract Asset 140,000.00
Various Accounts 140,000.00
To record cost incurred
Cash 600,000.00
Accounts Receivable 600,000.00
To record collection
2019 2019
Constructions Revenue 11,760,000.00 Constructions Revenue 12,600,000.00
Constructions Costs 8,400,000.00 Constructions Costs 9,000,000.00
Profit to date 3,360,000.00 Profit to date 3,600,000.00
Less: Recognized last year - Less: Recognized last year -
Profit (loss) recognize this year 3,360,000.00 Profit (loss) recognize this year 3,600,000.00
4 D 2019 2020
Cost incurred to date 4,000,000.00 14,250,000.00
Total Estimated cost to complete 16,000,000.00 19,000,000.00
Percentage of completion 25% 75%
2019 2020
Constructions Revenue 5,000,000.00 15,750,000.00
Constructions Costs 4,000,000.00 14,250,000.00
Profit to date 1,000,000.00 1,500,000.00
Less: Recognized last year - 1,000,000.00
Profit (loss) recognize this year 1,000,000.00 500,000.00
**If customer is billed based on percentage of completion, then billing is always equal to revenue, therefore, no balance of Contract Asset at the end
6 2019 2020
Cost incurred to date 2,975,000.00 6,750,000.00
Total Estimated cost to complete 8,500,000.00 9,000,000.00
Percentage of completion 35% 75%
2019 2020
Constructions Revenue 3,500,000.00 7,500,000.00
Constructions Costs 2,975,000.00 6,750,000.00
Profit to date 525,000.00 750,000.00
Less: Recognized last year - 525,000.00
Profit (loss) recognize this year 525,000.00 225,000.00
2019
Constructions Revenue 3,500,000.00
Billings 3,000,000.00
Contract Asset 500,000.00
9 D Project X Project Y
Contract Price 4,200,000.00 3,000,000.00
Total Estimated cost to complete 3,600,000.00 3,500,000.00
Estimated gross profit (loss) 600,000.00 - 500,000.00
Percentage of completion 2/3 recognized 100% for expected loss in Project Y
Gross Profit (loss) recognize this year 400,000.00 - 500,000.00
Expenses - 200,000.00 - 100,000.00
Net profit (loss) 200,000.00 - 600,000.00
11 B 2019 2020
Cost incurred to date 3,900,000.00 6,300,000.00
Total Estimated cost to complete 7,800,000.00 8,100,000.00
Percentage of completion 50% 78%
2019 2020
Constructions Revenue 4,500,000.00 7,000,000.00
Constructions Costs 3,900,000.00 6,300,000.00
Profit to date 600,000.00 700,000.00
Less: Recognized last year - 600,000.00
Profit (loss) recognize this year 600,000.00 100,000.00
12 D 2019
Total Estimated costs 7,500,000.00
Percentage of completion 20%
Actual cost 1,500,000.00
2020
Total Estimated costs 8,000,000.00
Percentage of completion 80%
Actual cost to date 6,400,000.00
16 invalid question
18 D Prestige Greenville
Contract Price 50,000,000.00 20,000,000.00
Total Estimated cost to complete 42,000,000.00 21,000,000.00
Estimated gross profit (loss) 8,000,000.00 - 1,000,000.00
Percentage of completion 25% recognized 100% for expected loss in Project Greenville
Gross Profit (loss) recognize this year 2,000,000.00 - 1,000,000.00
19 C Y1
Cost incurred to date 16,800,000.00
Total Estimated cost to complete 48,000,000.00
Percentage of completion 35%
Y1
Constructions Revenue 21,000,000.00
Constructions Costs 16,800,000.00
Profit to date 4,200,000.00
Less: Recognized last year -
Profit (loss) recognize this year 4,200,000.00
22 C No profit is recognize since the outcome of the project cannot be estimated reliably in 2019. No revenue recognize is equal to the actual cost incurred, therefore, gross profit (loss) is ZERO
23 D Actual cost
Materials, labor, overhead 2,400,000.00
Materials with no alternative use 200,000.00
Sale of salvage materials - 40,000.00
2,560,000.00
Total billings
2019 1,400,000.00
2020 15,225,000.00
2021 4,200,000.00
20,825,000.00
Penalty (deducted from final billing) 35K x 5 175,000.00
Original contract price 21,000,000.00
based on estimate
ofit (loss) is ZERO