Chap 3
Chap 3
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
3.0 GENERAL
The entire project has two roads to be upgraded to two lane bituminous road from the
existing gravel road. The longer road Shire – Shiraro – Humera (SSH) road is 267 km
long, and the other road Humera – Lugdi (HL) road is 46 km long. SSH road passes
through flat, rolling, mountain, and escarpment terrains. HL road has a flat terrain and
primarily passes through farm land of Humera.
SSH road has a well formed section with 7 m wide gravel roadway where as the other
one, HL road is still under construction. The formation is no where defined, and the
final surface of HL road is yet to come up. Naturally no topographical survey could be
conducted for HL road, and as approved by ERA only primary control points using
GPS were fixed, in pairs, at every 2 km along the HL road alignment. The profile and
cross section data being used for the construction of the present upgradation work of
HL road were obtained from ERA, and the same has been used for finalizing the
highway design of upgradation to proposed 2 lane bituminous road.
For SSH road all the requisites of fixing primary GPS points at about every 5 km (in
pairs at each location), and bench marks at every 200 / 300 m for elevation control
were done. The detailed topographical survey including cross sections was
conducted as required by TOR.
Topographical Survey
3-1
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-2
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Survey Crew:
(1) GPS Group: Sri K V. Narayanan Sept. 2005 – Oct. 2005
Tewodros Tadesse
Gebreyesuse Worede
(2) Traverse and Topographic survey
Sri S P Singh Jan 3, 2006, Feb. 25, 2205
Gagan Puri
Shemeles Bekele
(3) Traverse and Topographic survey
Mr. Stefano Solingo Oct. 2005 - Feb. 25, 2006-03-30
Mr. Kunfu Paoulos and others
GPS control points are established as cement concrete pillars having a sharp mark in
the top centre on nail fixed in the centre of the pillar. The pillars are embedded in the
ground and properly grouted all around with cement and concrete so that they are
not easily disturbed. The location of the pillar is so selected that it has no obstacle
above 15 degrees altitude to receive satellite signal. These pillars are fixed about 5
km apart along the road side but safely away from the road so it is not accidentally
Topographical Survey
3-3
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
The co-ordinates of all these control points are observed using double frequency
GPS receivers in static mode. The twin pillars facilitate the checking of bearings and
used for the starting of independent survey in any 5 km stretch. The pillars will also
be used as permanent control stations for all the survey layout work at a later stage.
All these GPS pillars are suitably numbered and their description has been recorded
and photographed, to ensure easy identification and accessibility in future.
The first GPS observations were recorded at GPS 1 in static mode for about 6 hours
and coordinates computed in ‘Single Point Positioning’ mode to establish precise
coordinates of this point and being used as reference point for all other successive
points. Observations on all other points were recorded for a period of 15 minutes to
45 minutes depending upon the distance between two receivers and coordinates
were computed in ‘Base Line’ mode.
Accuracy of the GPS system is of the order of 10mm ± 2ppm and the accuracy
achieved of the complete network of planimetric control from Shire S. to Humera S. is
4ppm i.e. 4mm per kilometer.
The list of grid (X, Y and Z) coordinates of all the GPS Pillars fixed is given in Table
3.1, and list of Geodetic coordinates (Latitude, Longitude) in Table 3.2. The
schematic diagram of the complete GPS network is given in Figure 3.1.
Topographical Survey
3-4
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-5
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
1 6 0 7
390805.83 1498.48 0.9997467 0.9997465
67.060 GPS70A 3 1597733.507 3 20 LHS 7 0.99999976 4
387530.82 1304.42 0.9997557 0.9997555
71.540 GPS75 5 1596612.846 8 36 LHS 1 0.99999980 0
387366.88 1302.77 0.9997561 0.9997559
71.700 GPS75A 6 1596572.316 5 50 LHS 6 0.99999980 6
384355.79 1210.66 0.9997646 0.9997644
76.490 GPS80 3 1593255.319 5 18 LHS 2 0.99999981 3
384051.23 1194.74 0.9997654 0.9997653
76.780 GPS80A 3 1593201.124 0 41 RHS 9 0.99999981 0
380245.96 1111.17 0.9997765 0.9997763
81.000 GPS85 5 1592781.313 2 42 RHS 3 0.99999983 6
380054.91 1110.72 0.9997771 0.9997769
81.220 GPS85A 3 1592582.719 9 42 LHS 0 0.99999983 2
375423.83 1073.24 0.9997910 0.9997908
85.878 GPS90 7 1592830.578 6 19 LHS 4 0.99999983 7
375019.10 1070.06 0.9997922 0.9997921
86.282 GPS90A 9 1592873.510 9 15 RHS 8 0.99999983 1
370454.20 1043.89 0.9998065 0.9998064
91.150 GPS95 2 1592263.678 4 18 LHS 8 0.99999984 2
370180.61 1047.68 0.9998074 0.9998072
91.424 GPS95A 9 1592246.342 5 21 LHS 5 0.99999984 9
367040.56 1061.65 0.9998176 0.9998174
95.800 GPS100 8 1590283.482 1 33 LHS 1 0.99999983 5
366774.76 1059.70 0.9998184 0.9998183
96.100 GPS100A 3 1590175.685 0 51 LHS 8 0.99999983 2
363268.56 1091.65 0.9998301 0.9998299
101.825 GPS105 8 1586344.987 0 33 RHS 3 0.99999983 6
363176.79 1101.00 0.9998304 0.9998302
102.075 GPS105A 3 1586115.908 3 31 RHS 4 0.99999983 7
361586.75 1094.20 0.9998358 0.9998356
106.500 GPS110 9 1581993.242 8 41 LHS 3 0.99999983 6
361413.86 1096.46 0.9998364 0.9998362
106.900 GPS110A 2 1581623.494 5 40 RHS 2 0.99999983 5
358571.06 1089.48 0.9998462 0.9998460
111.675 GPS115 0 1578719.840 9 22 RHS 2 0.99999983 5
358132.15 1112.87 0.9998477 0.9998475
112.166 GPS115A 4 1578520.427 3 24 LHS 5 0.99999983 7
354799.24 1066.85 0.9998595 0.9998593
116.950 GPS120 7 1575780.264 8 26 LHS 3 0.99999983 6
354525.83 1066.85 0.9998605 0.9998603
117.230 GPS120A 3 1575707.595 8 23 RHS 1 0.99999983 4
350700.87 0.9998743 0.9998742
121.817 GPS125 6 1575249.321 953.346 20 RHS 8 0.99999985 3
350389.11 0.9998755 0.9998753
122.170 GPS125A 4 1575082.511 943.098 40 LHS 3 0.99999985 8
346430.21 0.9998903 0.9998901
127.488 GPS130 8 1571741.392 950.600 45 RHS 1 0.99999985 6
346388.58 0.9998904 0.9998903
127.765 GPS130A 4 1571451.754 946.046 23 LHS 6 0.99999985 2
345207.18 0.9998949 0.9998948
132.310 GPS135 5 1567475.798 906.070 22 LHS 5 0.99999986 1
345135.72 0.9998952 0.9998950
132.430 GPS135A 4 1567369.506 908.238 32 RHS 2 0.99999986 8
343008.30 0.9999033 0.9999032
136.650 GPS140 6 1564004.160 864.828 28 LHS 9 0.99999986 5
342833.68 0.9999040 0.9999039
136.838 GPS140A 0 1563894.218 864.066 43 RHS 6 0.99999986 3
340200.82 0.9999143 0.9999142
141.100 GPS145 8 1561866.842 771.999 31 LHS 4 0.99999988 1
340155.63 0.9999145 0.9999143
141.450 GPS145A 7 1562233.264 801.239 17 LHS 1 0.99999987 9
338027.51 1044.73 0.9999229 0.9999227
146.030 GPS150 5 1560042.088 3 22 RHS 4 0.99999984 8
Topographical Survey
3-6
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-7
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
2 1 9
269491.59 1.0002540 1.0002539
235.000 GPS235 2 1565869.617 721.314 15 RHS 6 0.99999989 5
269288.00 1.0002552 1.0002551
235.200 GPS235A 7 1565916.929 720.812 20 RHS 2 0.99999989 0
265138.40 1.0002790 1.0002788
239.800 GPS240 3 1567656.285 699.152 20 LHS 0 0.99999989 9
264963.10 1.0002800 1.0002799
240.030 GPS240A 5 1567794.793 698.509 20 RHS 1 0.99999989 0
260959.11 1.0003033 1.0003032
244.465 GPS245 4 1569729.785 682.359 20 RHS 8 0.99999989 7
260560.88 1.0003057 1.0003056
244.910 GPS245A 0 1569920.932 680.385 30 RHS 2 0.99999989 2
255956.60 1.0003331 1.0003330
249.984 GPS250 4 1572057.147 661.116 25 LHS 3 0.99999990 2
255708.84 1.0003346 1.0003345
250.285 GPS250A 6 1572237.726 660.111 17 RHS 2 0.99999990 1
251888.98 1.0003577 1.0003576
254.500 GPS255 3 1574008.761 646.984 20 RHS 7 0.99999990 7
251653.64 1.0003592 1.0003591
254.750 GPS255A 5 1574107.681 646.175 30 LHS 1 0.99999990 1
247898.05 1.0003823 1.0003822
259.015 GPS260 8 1576124.358 632.069 25 LHS 4 0.99999990 4
247651.44 1.0003838 1.0003837
259.300 GPS260A 0 1576258.636 631.326 20 LHS 7 0.99999990 8
243985.10 1.0004068 1.0004067
263.545 GPS265 1 1578394.664 619.583 24 LHS 2 0.99999990 2
243887.75 1.0004074 1.0004073
263.700 GPS265A 7 1578516.630 619.270 30 LHS 3 0.99999990 3
242245.22 1.0004178 1.0004177
266.100 GPS267 2 1580282.979 614.151 20 LHS 2 0.99999990 2
Center of
242035.80 round about
266.435 GPS267A 1580537.714 607.139
2 at Humera 1.0004191 1.0004190
town 5 0.99999990 5
Topographical Survey
3-8
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-9
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-10
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Figure 3.1
Topographical Survey
3-11
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
The upgradation work for Humera – Lugdi road to a 7 m wide gravel road is under
implementation stage. Almost half the road length, from Gondar junction to Maikdara
town is at different stage of embankment construction. There is no final level of the
finished road available which could be surveyed. Therefore, as per approval of ERA,
only GPS control points at every 2 km have been fixed. The details are in Table 3.3
(a) and (b). The schematic GPS net work is illustrated in Figure 3.2.
HUMERA-LUGDI
Topographical Survey
3-12
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
1 1 3 9
228666.64 1.0005102 0.9999115 1.0004217
7.910 GPSL36A 8 1547418.469 655.682 35 LHS 1 6 3
226672.94 1.0005236 0.9999074 1.0004310
5.800 GPSL39 3 1547220.292 681.909 30 LHS 5 3 3
226206.60 LHS 1.0005268 0.9999064 1.0004331
5.342 GPSL39A 5 1547175.021 688.376 27 0 1 6
224099.20 LHS 1.0005411 0.9999072 1.0004483
3.165 GPSL42 8 1547743.335 683.228 48 3 2 0
223848.02 LHS 1.0005428 0.9999070 1.0004498
2.900 GPSL42A 1 1547822.533 684.037 40 5 9 9
221323.48 RHS 1.0005601 0.9999092 1.0004693
0.095 GPSL46 2 1548476.640 670.449 50 7 2 4
221291.25 RHS 1.0005603 0.9999093 1.0004696
0.020 GPSL46A 9 1548538.571 669.902 40 9 3 7
Topographical Survey
3-13
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-14
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Figure 3.2
Topographical Survey
3-15
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
The relevant photographs showing the location of GPS points are presented at the
end. However, the details monographs have been submitted separately in
Topographical survey Report.
The traverse observations completed by Total station in the stretch of 0 km (at Shire)
to 185 km, were recorded in the form of Horizontal angles, vertical angles and sloped
distances. The appropriate calculations were carried out using standard formula and
proper adjustments were carried out to get final coordinates of all the secondary
traverse control pillars.
However, in the last 77 km (from km185 to km 267), GPS was used in static mode to
carry out secondary traverse fixation to expedite the survey process.
All the secondary traverse control points are fixed along the road side with suitable
offset from the centre line of the existing road. The monuments are in the form of
cement concrete pillars, caste- in-situ with an 8mm iron rod in the centre, painted and
uniquely numbered.
Adjustment accuracy of secondary traverse control points fixed by Total Station was
better than 1:10,000 however the accuracy achieved by GPS traverse was of the
order of 1:100,000.
The co-ordinate details: Easting, Northing, and Elevation, of all the secondary
traverse control points, designated also as Bench marks, may be referred in
Annexure 3.1.
Topographical Survey
3-16
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
been carried out in order to collect co-ordinate data (x, y, z) of all the topographical
features as required for the preparation of plan and Digital terrain Model. In general,
these include:
Road centre line
Pavement edges
Outer shoulder edges
Toe lines of fills and cuts
Longitudinal and transverse drains / ditches
All man-made and natural topographical features have been surveyed, including:
Water sources
Structures
Buildings
Utilities etc. as visible, falling inside the corridor
Surveys have been extended to a minimum of 25m beyond each side of the centre
line of the existing carriageway, or to the ROW boundary, whichever is more.
Accordingly, a corridor of about 50m (25m on either side of the existing centre line)
has been surveyed. Surveys are carried out to pick up sufficient level points in the
corridor to create accurate digital terrain model.
Topographical Survey
3-17
Consultancy Services for Feasibility Study, Environmental and
Social Impact Assessment and Detailed Engineering Design for Engineering Report
Shire-Shiraro-Humera -Lugdi Road Upgrading Project, Ethiopia
Topographical Survey
3-18