0% found this document useful (0 votes)
33 views12 pages

DPWH-RIZAL-BoQ

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views12 pages

DPWH-RIZAL-BoQ

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

PROJECT REFERENCE : 23OI0008

PROJECT NAME : Construction/Improvement of Access Roads leading to Declared Tourism Destinations


PROJECT LOCATION : Tanay-Pililla Road leading to Windmills, Rizal

ITEM DESCRIPTION QTY


FACILITIES FOR THE ENGINEERS
Provision of Field Office for the Engineer 6.60
OTHER GENERAL REQUIREMENT
Project Billboard/Signboard 2.00
Occupational Safety and Health Program 1.00
Traffic Management 1.00
Mobilization/Demolition 1.00
EARTHWORKS
Individual Removal of Trees (301mm-500mm dia) 38.00
Removal of Actual Structures and Obstructions, 0.23mm thick PCCP (unreinforced) 2,604.70
Surplus Common Excavation 1,284.32
Structure Excavation - Common Soil 475.56
Pipe Culvert and Drain Excavation - Common Soil 719.40
Embankment from Borrow, Common Soil 265.29
Subgrade Preparation Common Material 585.60
SUBBASE AND BASE COURSES
Aggregates Subbase Course 842.03
SURFACE COURSES
Portland Cement Concrete Pavement (Unreinforced), 0.23m thick - 14 days 3,190.30
BRIDGE CONSTRUCTION
Reinforcing Steel - Grade 40 24.94
Structural Concrete - 20.68MPa - Class A 14 days 1.55
DRAINAGE AND SLOPE PROTECTION STRUCTURE
Pipe Culverts - 910mm dia, Class II 644.00
Pipe Culverts - 910mm dia, Class IV 10.00
Manholes - 910mm dia CHB 77.00
Concrete Covers 910mm dia 154.00
MISCELLANEOUS STRUCTURES
Curb and Gutter - Precast 777.00
Sidewalk (100mm) 965.69
Hazard Markers, 450mm x 600mm, Chevron Signs 40.00
Internally Illuminated (Solar) Pavement 362.00
Reflectorized Thermoplastic Pavement Markings White 1,468.10
Reflectorized Thermoplastic Pavement Markings Yellow 129.90
TOTAL AMOUNT
estinations

UNIT MATERIAL COST LABOR COST TOTAL UNIT COST TOTAL AMOUNT

mos

each
ls
ls
ls

each
sqm
cum
cum
cum
cum
sqm

cum

sqm

kg
cum

lm
lm
each
each

pc
sqm
each
each
sqm
sqm
-
PROJECT REFERENCE : 23OI0009
PROJECT NAME : Road Widening - Tertiary Roads
PROJECT LOCATION : Tanay and Pililla, Rizal 2nd LD

ITEM DESCRIPTION QTY


FACILITIES FOR THE ENGINEERS
Provision of Field Office for the Engineer 7.40
OTHER GENERAL REQUIREMENT
Project Billboard/Signboard 2.00
Occupational Safety and Health Program 1.00
Traffic Management 1.00
Mobilization/Demobilization 1.00
EARTHWORKS
Individual Removal of Trees (501mm-750mm dia, small) 137.00
Removal of Structures and Obstructions 1.00
Removal of Actual Structures and Obstructions, 0.23mm thick PCCP (unreinforced) 3,450.80
Structure Excavation - Common Soil 281.57
Pipe Culvert and Drain Excavation - Common Soil 3,439.55
Embankment from Roadway Excavation - Common Soil 5,790.92
SUBBASE AND BASE COURSES
Aggregates Subbase Course 2,814.73
SURFACE COURSES
Crushed Aggregate Surface Course 521.22
Portland Cement Concrete Pavement (Unreinforced), 0.23m thick - 14 days 509.20
Portland Cement Concrete Pavement (Unreinforced), 0.28m thick - 14 days 5,366.17
BRIDGE CONSTRUCTION
Reinforcing Steel - Grade 40 4,983.30
Structural Concrete - 20.68MPa - Class A 14 days 46.56
DRAINAGE AND SLOPE PROTECTION STRUCTURE
Pipe Culverts - 910mm dia, Class II 1,060.00
Pipe Culverts - 610mm dia, Class IV 18.00
Pipe Culverts - 910mm dia, Class IV 92.00
Manholes - 910mm dia CHB 132.00
Concrete Covers 910mm dia 264.00
Cleaning Culvert Pipe in Place - 610mm dia, Half Silted 12.00
Stone Masonry 1,737.99
Bed Course Granular Material 286.74
MISCELLANEOUS STRUCTURES
Curb and Gutter - Precast 1,228.00
Sidewalk (100mm) 2,164.48
Reflectorized Thermoplastic Pavement Markings White 264.81
TOTAL AMOUNT
UNIT MATERIAL COST LABOR COST TOTAL UNIT COST TOTAL AMOUNT

mos

each
ls
ls
ls

each
ls
sqm
cum
cum
cum

cum

sqm
sqm
sqm

kgs
cum

lm
lm
lm
each
each
lm
cum
cum

pc
sqm
sqm
-
PROJECT REFERENCE : 23OI00022
PROJECT NAME : Road Widening - Tertiary Roads
PROJECT LOCATION : Tanay - Sampaloc Rd Rizal 2nd LD

ITEM DESCRIPTION QTY


FACILITIES FOR THE ENGINEERS
Provision of Field Office for the Engineer 4.90
OTHER GENERAL REQUIREMENT
Project Billboard/Signboard 2.00
Occupational Safety and Health Program 1.00
Traffic Management 1.00
Mobilization/Demobilization 1.00
EARTHWORKS
Individual Removal of Trees (501mm-750mm dia, small) 21.00
Removal of Structures and Obstructions 1.00
Removal of Actual Structures and Obstructions, 0.23mm thick PCCP (unreinforced) 799.30
Removal of Actual Structures and Obstructions, 0.10mm thick ACP 533.70
Surplus Common Excavation 3,947.30
Structure Excavation - Common Soil 1,269.40
Embankment from Roadway Excavation - Common Soil 143.00
Subgrade Preparation Common Material
SUBBASE AND BASE COURSES
Aggregates Subbase Course 1,561.50
SURFACE COURSES
Crushed Aggregate Surface Course 380.10
Portland Cement Concrete Pavement (Unreinforced), 0.28m thick - 14 days 3,205.60
BRIDGE CONSTRUCTION
Reinforcing Steel - Grade 40 66,996.80
Structural Concrete - 20.68MPa - Class A 14 days 600.00
DRAINAGE AND SLOPE PROTECTION STRUCTURE
Concrete Covers 910mm dia 104.00
Grouted Riprap, Class A 318.40
Bed Course Granular Material Concrete 114.00
MISCELLANEOUS STRUCTURES
Concrete Gutter, Precast 912.00
Warning Signs, 600mm x 600mm W6-2B 2.00
Regulatory Signs, 450mm x R6-8A Pedestrian Crossing 4.00
Hazard Markers, 450mm x 600mm, Chevron Signs 10.00
Reflectorized Thermoplastic Pavement Markings White 620.70
0
UNIT MATERIAL COST LABOR COST TOTAL UNIT COST TOTAL AMOUNT

mos 10,120.95 4,048.38 14,169.33 69,429.72

each 3,982.23 1,592.89 5,575.12 11,150.24


ls 519,323.70 207,729.48 727,053.18 727,053.18
ls 66,622.50 26,649.00 93,271.50 93,271.50
ls 571,922.40 228,768.96 800,691.36 800,691.36

each 8,869.18 3,547.67 12,416.85 260,753.95


ls 152,250.00 60,900.00 213,150.00 213,150.00
sqm 128.33 51.33 179.66 143,604.96
sqm 102.50 41.00 143.50 76,586.70
cum 179.64 71.86 251.50 992,755.03
cum 339.21 135.69 474.90 602,835.78
cum 255.27 102.11 357.37 51,104.15

cum 923.97 369.59 1,293.56 2,019,887.54

cum 1,235.85 494.34 1,730.19 657,645.22


sqm 2,330.42 932.17 3,262.59 10,458,563.31

kgs 55.88 22.35 78.23 5,241,387.45


cum 6,729.00 2,691.60 9,420.60 5,652,358.74

each 146,002.50 58,401.00 204,403.50 21,257,964.00


cum 5,554.96 2,221.98 7,776.95 2,476,179.86
cum 4,725.00 1,890.00 6,615.00 754,110.00

pc 2,625.00 1,050.00 3,675.00 3,351,600.00


each 9,964.38 3,985.75 13,950.14 27,900.28
each 12,610.38 5,044.15 17,654.54 70,618.15
ech 772.32 308.93 1,081.24 10,812.44
sqm 927.07 370.83 1,297.89 805,601.81
56,827,015.37