Project Management Gantt Chart type 2

New toy production Project Management Gantt Chart type 2

Uploaded by

champa.hapangama
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

Project Management Gantt Chart type 2

New toy production Project Management Gantt Chart type 2

Uploaded by

champa.hapangama
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

New Toy Introduction Project Project start: Tue, 12/3/2024

Display week: 1

September October November December January February March

3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
TASK START END
Duration (Days) T

Project Initiation 18 Days

Define project objectives and scope 6 Days 12/3/24 12/9/24

Identify Stakeholders 4 Days 12/10/24 12/14/24

Prepare project charter 4 Days 12/15/24 12/19/24

Develop project management plan 4 Days 12/20/24 12/24/24

Conduct market research 44 Days

Design market research strategy 7 Days 12/25/24 12/31/24

Collect and analysze data 30 Days 1/1/25 1/31/25

Prepare market research report 7 Days 2/1/25 2/8/25

Product Design 74 Days

Create initial design concepts 30 Days 12/25/24 1/24/25

Finalize design 30 Days 1/25/25 2/23/25

Document design specifications 14 Days 2/24/25 3/10/25

Prototype Development 45 Days

Build Prototype 30 Days 2/9/25 3/10/25

Prototype testing preparatio 15 Days 3/11/25 3/26/25

Protype testing in lab environment 28 Days

Perform safety and durability test 13 Days 3/28/25 4/10/25

Document and evaluate results 15 Days 4/11/25 4/26/25

Market Acceptance testing 25 Days

Select target audience for market testing 6 Days 4/27/25 5/3/25

Distribute prototype for user testing 6 Days 5/4/25 5/10/25

Collect feedback and analyze results 13 Days 5/11/25 5/24/25


September October November December January February March

3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
TASK START END
Duration (Days) T

Bulk Production for the launch 6 Days

Secure production materials 3 Days 5/25/25 5/28/25

Begin mass production 3 Days 5/28/25 5/31/25

Launch and monitor the Toy 2 Days

Launch product in the market 1 Day 6/1/25 6/1/25

Monitor customer feedback and sales 1 Day 6/2/25 6/2/25