Pre existing case laws
Pre existing case laws
OC's Claim:
o The OC deals in poultry feed and claims the CD placed orders
for these feeds.
o Invoices for Rs. 1,66,40,224.18 were raised for these supplies
(invoices attached in application).
o An additional interest of Rs. 26,57,734 is claimed for delayed
payment (from Oct 2021 to June 2022).
o A demand notice for the total amount (Rs. 1,92,97,958.18)
was sent to the CD's registered and corporate address on June
17th, 2022.
CD's Contentions:
o They argue that the OC did not comply with mandatory
requirements before filing the application under Section 9 of
the IBC.
o They claim the demand notice wasn't served at their
registered address (postal records show it was returned) and
the email address used was incorrect.
o They deny the invoices' validity and allege the OC fabricated
them.
o They claim a pre-existing dispute regarding the quality of the
goods (email dated July 19th, 2021).
o The amount claimed falls below the minimum threshold for
filing such an application (Rs. 1 crore as per notification dated
March 24th, 2020).
Existence of Debt:
o The invoices and statements of account submitted by the OC
are considered as evidence of debt.
o However, the Tribunal finds the OC lacked convincing
evidence (delivery challans, weight bridge slips, etc.) to
prove the actual supply of goods.
Dispute:
Ruling:
-----------------------------------------------------------------------------------------------
--------
2. NATIONAL COMPANY LAW APPELLATE TRIBUNAL- NEW DELHI
Parties:
Key Evidence:
Ruling:
The pre-existing dispute defence was not upheld due to the later
acknowledgment of the debt.
Parties:
Time-barred Claims: The invoices from which the debt arises are
allegedly time-barred (beyond the legal limit to claim them).
Respondent's Arguments:
Court's Decision:
30. The contention of the Learned Counsel for the Appellant that
there
were transactions between one Mr. Puneet Shiv Kumar Agarwal and
the Operational Creditor through various group of Companies
cannot fall within the definition of dispute relevant to the subject
matter of the instant case, in the absence of any communication
filed evidencing any ‘Pre-Existing Dispute’, prior to the filing of the
Section 9 Application. It is pertinent to mention that in their Reply to
the Application, filed before the Learned Adjudicating Authority, the
Appellant apart from raising a bald denial has not filed any
substantive material in support of their contentions. We are of the
considered view that ratio laid down by the Hon’ble Supreme Court
in ‘Mobilox Innovations Private Limited’ V/s. ‘Kirusa
Software Private Limited’, (2018) 1 SCC 353 is squarely
applicable to the facts of this case.
At this juncture, we find it relevant to reproduce the specific
paragraphs is
detailed as hereunder;
“40. It is clear, therefore, that once the operational
creditor has filed an application, which is otherwise
complete, the adjudicating authority must reject the
application under Section 9(5)(2)(d) if notice of dispute
has been received by the operational creditor or there
is a record of dispute in the information utility. It is
clear that such notice must bring to the notice of the
operational creditor the “existence” of a dispute or the
fact that a suit or arbitration proceeding relating to a
dispute is pending between the parties. Therefore, all
that the adjudicating authority is to see at this stage
is whether there is a plausible contention which
requires further investigation and that the “dispute” is
not a patently feeble legal argument or an assertion of
fact unsupported by evidence. It is important to
separate the grain from the chaff and to reject a
spurious defence which is mere bluster. However, in
doing so, the Court does not need to be satisfied that
the defence is likely to succeed. The Court does not at
this stage examine the merits of the dispute except to
the extent indicated above. So long as a dispute truly
exists in fact and is not spurious, hypothetical or
illusory, the adjudicating authority has to reject the
application.”
Key Points:
Background:
Appellant's Contentions:
15. For deciding the dispute no. (iii) we have gone through the
mandate agreement dated 9.3.2016 which is an admitted
document and the terms and conditions of services rendered
by the Appellant is explicitly written. In this agreement in
clause 4 breakup of services and the scope of services
provided by the Appellant is mentioned in detail.
Clause 4 (f) provides that obtaining appropriate sanction from
bank/NBFC. In this agreement it is nowhere mentioned that
the Appellant will organise funding from Nationalised or
scheduled bank at low rate of interest. Thus, the dispute is not
supported by any document. Therefore, we find no basis for
such dispute.
Grounds:
Parties:
o Appellants Contention:
1. No pre-existing dispute at any point of time
2. Existence of amount debt, due and payable (by way of
issuance of cheque and it being dishonoured)
3. Reliance of emails for pre-existing disputes can be
nullified by subsequent payment and certificate of
actual work done by OC.
o Respondents’ contention:
1. Pre-existing dispute: Case of suppression of facts
wherein reply to demand and emails not brought to the
notice of the AA
o Tribunal's Findings:
1. Routine correspondence in commercial relationship
cannot automatically be considered as dispute.
2. Operational Creditor has to justify its claim by adducing
sufficient documentary evidence has all issues are
resolved and payment is still due.
3. Application u/s 9 without delivery of notice of demand
u/s 8 of IBC, 2016 on the Corporate Debtor is liable to be
rejected at the very outset. Likewise, without a notice of
dispute within 10 days of notice by the Corporate Debtor
is liable to be admitted and CD is not allowed to raise
the issue of pre-existing dispute later on.
The application is admitted.
Parties:
o Respondents Contentions
1. Executed MOU dated 25.07.2018 and paid Rs. 1Lakh
towards full and final settlement and the balance on the
said date is NIL
2. Debit notes of Rs. 91 Lakh towards defective goods
acknowledged by OC and balance paid & cleared on receipt
of demand notice.
3. Ledger accounts filed by OC are forged and fabricated along
with email dated 30.11.2017 and pleaded the tribunal to
examine its authenticity. That all documents are without
stamp as against section 25 of the Indian stamps Act.
4. Claim is time barred
o Appellant’s Contentions
1. The alleged MOU is fabricated and an afterthought that only
Rs. 1 Lakh was payable.
2. Debit notes dated 25.07.2018 with fictitious stamp and no
“receiver “stamp. Denial of any signature on MOU.
3. Claim not barred by limitation, having received part
payment on 25.07.2018
o Tribunal’s findings
1. Admission by Corporate Debtor vide email dated
30.11.2017
2. No correspondence in writing for raising any disputes
w.r.t quantity and quality. Accordingly, issuance of debit
notes also puts this claim in flimsy ground wherein all
debit notes were issued on a single day relating to
goods sold even four years ago
3. The tribunal tallied the signatures of the OC under
power vested sunder section 73 of the Indian Evidence
Act and doubted the execution of the said MoU.
4. The Petition is not barred by limitation as Rs. 1 Lakh
was paid by CD to OC on 25.07.2018
5. Whether documents are forged or not cannot be
determined by NCLT or NCLAT (Ref. Shelendra kumar
Sharma Vs DSC Ltd.)
Petition admitted.
Dispute:
Whether the debt is genuine or disputed.
Admissibility of disputed documents and emails as evidence.
Applicability of limitation period.
Authority of the Adjudicating Authority to determine forgery.
the outcome of the appeal is that the National Company Law Tribunal
(NCLT) judgement admitting the application for Corporate Insolvency
Resolution Process (CIRP) is set aside. The application is found to be
barred by limitation.
The judgement concludes that the Respondent's claim is time-barred
based on the following reasons:
The alleged default occurred on 25.07.2011 as per the Respondent.
The Limitation Act prescribes a three-year period for filing such
applications (Article 137).
The Respondent did not provide any evidence of acknowledgement
from the company before the limitation period expired (24.07.2014).
The Respondent relied on later communications (dated 29.01.2015)
to establish the claim, but these fell outside the limitation period.
In essence, the Respondent waited too long to file the application after the
alleged default, exceeding the limitation period set by law.
Key take away paras:
PRE-EXISTING DISPUTES:
Issue: 9. The Learned Counsel for the Appellant submits that the
pendency of the 'Protest Petition' involving determination of 'Forgery' and
'Fraud' would constitute a pending
legal dispute, under the tenets of the I&B Code, 2016 and, therefore, the
'Application'
filed by the 1st Respondent/Operational Creditor warrants dismissal, in
respect of a
'Disputed Debt'