lecturenote_994404249Cha 1 con
lecturenote_994404249Cha 1 con
2
A project cycle is a sequence of events, which a project follows.
These events, stages or phases can be divided into several equally valid ways,
depending on the executing agency or parties involved.
Some of these stages may overlap. There are various models that deal with the
project cycle.
3
2. UNIDO PROJECT CYCLE
A. The Pre-Investment Phase: (Opportunity Study; Pre feasibility Study;
Feasibility Study; Appraisal)
B. Investment Phase: (Negotiation and Contracting; Engineering Design;
Construction; Pre production marketing; Recruitment and Training; etc.)
C. Operational/Normalization Phase: (Expansion and Innovation; Replacement
and Rehabilitation; Commissioning and Start-up)
5
Negotiation and Contracting: It includes definition of
The legal obligations in respect to project financing,
Acquisition of technology,
Construction of building and services, and
Supply of machinery and equipment for the operation phase
6
Construction: It includes actual construction of building,
installation of machinery and manpower.
It involves site preparation, construction of building and other
civil works together with the erection and installation of
equipment in accordance with proper programming and
scheduling.
Recruitment and Training of Workers: It includes local and
abroad recruitment and training of workers for the smooth
running of operation.
It should proceed simultaneously with the construction stage
and it may prove relevant to the rapid growth of productivity
and efficiency. 7
Commissioning and Start up: It requires handover of the building to project
sponsor or promoter.
Start up (delivery stage) is brief but technically critical span in project
development.
Its success indicates the effectiveness of the planning and execution of the
project.
C. OPERATION PHASE: The operation phase includes project activities such as
expansion and innovation, replacement and rehabilitation, and commissioning and
start-up.
The issues in the operational phase need to be considered both from long and short-
term viewpoints.
i. The short-term view point relates to:
Application of production
Operation of Equipment 8
ii. The long-term view point relates to :
Production cost
Pre-investment
Investment and
Operation
Each of these three phases may be divided into stages. The guideline
has divided the cycle into 6 stages. 9
Each of these three phases may be divided into stages. The guideline has divided the cycle into 6
stages.
Identification
Preparation pre-investment phase
Appraisal/decision
Implementation investment phase
10
Baum’s model of project cycle
Initiated by W. Baum in 1970, was improved in 1978 and has
been adopted by the World Bank ever since, initially recognized
four main stages. Evaluation was added in a later version in
1978, namely:
Five phases:
1. Identification (finding the project)
2. Preparation/analysis (Pre-feasibility and feasibility studies) (Does
it have merit?)
3. Appraisal (critical review, independent)
4. Implementation (getting it started)
5. Evaluation (success or failure) 11
Capital expenditure decision is a complex decision process,
which may be divided into six broad phases:
A. Identification
B. Pre-feasibility Study
C. Feasibility (technical, financial, economic)
D. Selection and project design - Appraisal
E. Implementation
F. Ex-post evaluation
12
13
I. Identification
Need - a need assessment survey may show the need for intervention
Market demand - domestic or overseas
Resource availability - opportunity to make available resources more profitable
Technology - to make use of available technology
Natural calamity - intervention against natural calamity such as flood or
drought
Political considerations 16
II. Project preparation and analysis phase
Once project ideas have been identified the process of project
preparation and analysis starts.
Project preparation must cover the full range of Market analysis,
Technical analysis, institutional, financial analysis, Socio-
economic analysis, Environmental analysis, Organization and
management analysis.
Critical element of project preparation is identifying and comparing
technical and institutional alternatives for achieving the project’s
objectives.
Resource endowment (labor or capital) would have to be
considered in the preparation of projects. 17
Preparation thus require feasibility studies that identify and
prepare preliminary designs of technical and institutional
alternatives, compare their costs and benefits.
Pre-feasibility studies
Feasibility studies
18
A. Pre-feasibility Study
The identification process will give the background information
for defining the basic concept of the project, which leads to the
feasibility study stage.
B. Feasibility Study
The major difference between the pre-feasibility and feasibility
studies is the amount of work required in order to determine
whether a project is likely to be viable or not.
If the preliminary screening suggests that the project is prima facie
worthwhile, a detailed analysis of the marketing, technical,
financial, economic, and ecological aspects will is undertaken.
21
The focus of this phase of capital budgeting is on gathering,
preparing, and summarizing relevant information about various
project proposals, which are being considered for inclusion in the
capital investment.
Based on the information developed in this analysis, the stream of
costs and benefits associated with the project can be defined.
At this stage a team of specialists (Scientists, engineers,
economists, sociologists) will need to work together.
At this stage more accurate data need to be obtained and if the
project is viable it should proceed to the project design stage.
22
The final product of this stage is a feasibility report. The
feasibility report should contain the following elements:
Market analysis
Technical analysis
Organizational analysis
Financial analysis
Economic analysis
Social analysis, and
Environmental analysis
23
The feasibility study would enable the project analyst to select the most likely
project out of several alternative projects. Selection follows, and often overlaps,
analysis.
This stage involves a systematic review of all aspects of the project in order that
decision can be made as to whether to proceed. The following aspects should be
covered in the appraisal process:
25
It is considered as an independent stage of the pre-investment
phase, marked by the final investment and financing decisions
taken by the project promoters, where various parties will handle
their own appraisal of the investment project in accordance with
their individual objectives and evaluation of expected risks, costs,
and gain.
It addresses the question - is the project worthwhile? Wide ranges
of appraisal criteria have been developed to judge the worthwhile of
a project.
They are divided into two broad categories, viz.,
Non-discounting criteria and
Discounting criteria.
26
To apply the various appraisal criteria suitable cut off values (hurdle
rate(minimum acceptable rate of return), target rate, and cost of capital)
have to be specified. The level of risk pursued influences these.
Despite a wide range of tools and techniques for risk analysis (sensitivity
analysis, scenario analysis, Monte carol simulation, decision tree
analysis, portfolio theory, capital asset pricing model, and so on).
27
Implementation
After the project design is prepared negotiations with the funding
organization starts and once source of finance is secured
implementation follows.
The better and more realistic the project plan is the more likely it is
that the plan can be carried out and the expected benefits realized.
The investment phase, where the major investments are made. This may extend
from three to five years.
Development phase, which may also extend from three to five years
The project life
32
End!
33
34
35