1. Machines used in track

Machines details

Uploaded by

Md Arifullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Various Machines used for Track Maintenance

Minimum Stipulated Block Period Maximum Stipulated


Type of
S. Purpose of Setting & Output/Eff
Track Deliverables To & fro Working Minimum Ty. Speed
No Deployment winding up Total ectivehour
Machines time (in*) time Restriction, if any.
time (in*) (new m/c)
It corrects track geometry i.e.
alignment, twist, cross level,
Nil, except in summer
Plain Track longitudinal level and pack
1 09-3X 15 10 3:35 4:00 1.6Km with 50 kmph, if not
Tamping ballast under sleepers. This
followed by DTS
machine can pack three
sleepers at a time.

Plain Track DO. But can pack two sleepers


2 CSM 15 10 3:35 4:00 1.2 Km do
Tamping at a time.

DO. Generally deployed at work


Plain Track
3 UNO site. But can pack one sleeper 15 10 3:35 4:00 0.5km do
Tamping
at a time.

Plain Track
4 DUO (0) DO. Generally deployed at work 15 10 3:35 4:00 0.8km do
Tamping
site. But can pack two sleepers
Plain Track
5 WST at a time 15 10 3:35 4:00 0.8 km do
Tamping
20kmph or 40kmph if
Ballast It screens track ballast by
30 as 3 DTS+ TTM deployed
screening of removing muck, thus, improve
6 BCM m/c go in 40 2:50 4:00 0.2km behind it & stipulated
Plain & Turnout drainage & elasticity of track for
block safety instructions
Track safe & comfortable running
followed.

It is used to carry out cleaning of


shoulder ballast by removing Nil, ecxept in summer
Shoulder Ballast
7 FRM muck, drainage of track and 30 30 3:00 4:00 0.4km with 50 kmph if not
Cleaning
elasticity improving of ballast followed by DTS
bed.

It corrects turnout track


geometry i.e. alignment, twist,
8 UNI Turnout packing cross level, 1ongitudinal level 15 10 3:35 4:00 1 T/Out Nil
and pack ballast under sleepers

It build up lateral resistance &


Consolidation of
consolidation of track faster and
9 DGS newly tamped 15 10 3:35 4:00 1 km Nil
helps to relax speed restriction
track
early
30kmph or 40 kmph if
DGS deployed and
It is a fully mechanized system
10 TRT Laying of Track 40 50 2:30 4:00 O.36km ballasting, rail joints
of complete Track Renewal
are done as per
IRPWM
It is a semi mechanised system
of track renewal wherein pre
11 PQRS Laying of Track fabricated rail panels are laid 25 20 3:15 4:00 0.24km 20kmph
and existing panels removed
with minimum labour
Turnout It is a fully mechanised system
1Turnout
12 T-28 Replacement of complete turnout with 10 10 2:40 4:00 20 Kmph
per 4 hour
Machine minimum manual labour
It is a mechanized system of
50 rails per
transporting heavy material like
13 UIV Utility Vehicle 15 10 2:45 4:00 hour in one Nil
rail, sleepers, etc, from one
BFR
station to another in traffic block.
Ballast It is a mechanized system of
14 BRM Regulating track ballast equalization, 20 20 3:20 4:00 2km Nil
Machine regulatation and profiling,
*As per Board’s Joint Ciruclar.