Case study Transit System
Case study Transit System
Three years after the Rapibus was commissioned, the Board of Directors of the Société de
transport de l’Outaouais (STO) mandated Strategia Conseil to conduct an independent
review of the Bus Rapid Transit (BRT) project built in 2013.
• Identify the strengths and weaknesses of project management and governance; and
Various studies have identified the integration of a dedicated bus lane within the existing
rail corridor as the best technological choice. Essentially, the Rapibus project is a Bus Rapid
Transit on a 15 km bidirectional track.
Five months later, in November 2009, the MTQ granted a final authorization and
announced its financial contribution to the Rapibus project: up to 75%, through its
government assistance program for public transit. The City of Gatineau would be
responsible for the remaining 25%.
Over the years, several adaptations were made to the scope of the project. These
adaptations led, among others, to an overrun of
the initial schedule and an increase in expected costs.
Summary of costs and delays
The table below summarizes the cost and time overruns for the project.
40 65 + 25
Schedule + 62.5%
months months months
The initial schedule was established when the project scope was not defined enough to
clearly establish its duration. This schedule should have been qualified as “provisional”,
with a certain margin of error, rather than a fixed duration. Rather, the 40-month duration
was interpreted erroneously as being “a realistic timeframe” for the project’s target
schedule.
The schedule for the final design stage, produced after detailed information on the project
was made available, shows that the timeframes for design activities were significantly
underestimated.
Better planning could have avoided a significant underestimation of the time required for
design activities.
The schedule should have allowed for contingency for delay risks. While it’s impossible to
predict all unforeseen events, it would have been wise to perform a risk analysis at the
preliminary project stage. Doing so would have exposed the risks and quantified the
likelihood of not meeting the 40-month target.
1. Cost escalation
The primary cause of cost overruns was the cost escalation factor. For work to be
completed in 2016–2017, the $27.7 million budget (in 2010 dollars) must be indexed by
$5.5 million, bringing the total amount to $33.2 million.
Despite its importance, this rate is rarely taken into account in the project’s financial
documents; the reference year of the dollar value is almost never mentioned. However, cost
escalation has a very significant impact on the costs of a project, as it provides a measure of
the true value of the work over time.
In addition to cost escalation, the budget overrun was largely due to additional direct costs
resulting from changes in the scope of the initial work. Underestimated indirect costs in
areas such as the following were also a factor:
– Professional services
– Site overhead costs
– Project management and funding
The increase in indirect costs is certainly linked to budgetary underestimation, but also to a
much-too-optimistic timetable (see above).