An Introduction to Slope Stability and Protection R1
An Introduction to Slope Stability and Protection R1
2020
CONTENTS
1.1 GENERAL. Retaining walls must be designed so that foundation pressures do not
exceed allowable bearing pressures, wall settlements are tolerable, safety factors
against sliding and overturning are adequate, and the wall possesses adequate
structural strength. Methods for evaluating earth pressures on retaining walls and
design procedures are summarized herein for cohesionless backfill materials, which
should be used whenever practicable.
2. EARTH PRESSURES.
2.1 EARTH PRESSURE AT REST. For cohesionless soils, with a horizontal surface,
determine the coefficient of earth pressure at rest, K0, from the following:
K0 = 1 - sin Φ (eq 1)
2.2 ACTIVE EARTH PRESSURE. Formulas for calculating the coefficient of active
earth pressure for a cohesionless soil with planar boundaries are presented in figure 2.
2.6 SURCHARGE LOADS. Equations for concentrated point and line load are
presented in figure 5. For uniform or non-uniform surcharge pressure acting on an
irregular area, use influence charts based on the Boussinesq equations for horizontal
loads and double the horizontal pressures obtained.
2.7 DYNAMIC LOADS. The effects of dynamic loading on earth pressures are
beyond the scope of this publication. Refer to geotechnical engineering textbooks
dealing with the subject.
Figure 1
Load diagrams for retaining walls
Figure 2
Active pressure of sand with planar boundaries
Figure 3
Passive pressure of sand with planar boundaries
The equivalent fluid method should be used for estimating active earth
pressures on retaining structures up to 20 feet high, with the addition to earth
pressures resulting from backfill compaction (fig 8).
For walls higher than 20 feet, charts, equations, or graphical solutions should
be used for computing lateral earth pressures, with the addition of earth
pressures resulting from backfill compaction.
Use at-rest pressures for rigid retaining structures resting on rock or batter
piles. Design cantilever walls founded on rock or restrained from lateral
movement for at-rest pressures near the base of the wall, active pressures
along the upper portions of the wall, and compaction-induced earth pressures
from the top to the depth at which they no longer increase lateral earth
pressures (fig 8/14-8). Generally, a linear variation in earth pressure coefficients
with depth may be assumed between the sections of wall.
Consider passive pressures in the design if applied loads force the structure to
move against the soil. Passive pressures in front of retaining walls are partially
effective in resisting horizontal sliding.
4.2 OVERTURNING. Calculate the factor of safety, FS, against overturning, defined
as the ratio of resisting moments to the overturning moments. Calculate the resultant
force using load diagrams shown in figure 1, as well as other loadings that may be
applicable. Use only half of the ultimate passive resistance in calculating the safety
factor. The resultant of all forces acting on the retaining wall should fall within the
middle third to provide a safety factor with respect to overturning equal to or greater
than 1.5.
aFigure 4
Active and passive earth pressure coefficients according to Coulomb theory
4.3 SLIDING.
The factor of safety against sliding, calculated as the ratio of forces resisting
movement to the horizontal component of earth plus water pressure on the
back wall, should be not less than 2.0. If soil in front of the toe is disturbed or
loses its strength because of possible excavation, ponding, or freezing and
thawing, passive resistance at the toe, Pp, should be neglected and the
minimum factor of safety lowered to 1.5; but if the potential maximum passive
resistance is small, the safety factor should remain at 2.0 or higher.
For high walls, determine the shearing resistance between the base of wall and
soil from laboratory direct shear tests in which the adhesion between the
concrete and the undisturbed soil is measured. In the absence of tests, the
coefficient of friction between concrete and soil may be taken as 0.55 for
coarse-grained soils without silt, 0.45 for coarse-grained soils with silt, and 0.35
for silt. The soil in a layer beneath the base may be weaker, and the shearing
resistance between the base of wall and soil should never be assumed to
exceed the soil strength. Consider maximum uplift pressures that may develop
beneath the base.
Figure 5
Horizontal pressures on walls due to surcharge
Figure 6
Design loads for low retaining walls, straight slope backfill
4.4 BEARING CAPACITY. Calculate from the bearing capacity analysis. Consider
local
building codes or experience where applicable.
4.6 DEEP-SEATED FAILURE. Check the overall stability of the retaining wall against
a deep-seated foundation failure using accepted methods of analysis in the technical
literature. Forces considered include weight of retaining wall, weight of soil,
unbalanced water pressure, equipment, and future construction. The minimum safety
factor is 1.5.
4.7 USE OF PILES. When stability against bearing capacity failure cannot be satisfied
or settlement is excessive, consider a pile foundation. Use batter piles if the horizontal
thrust of the lateral earth pressure is high.
Figure 7
Design loads for low retaining walls, broken slope backfill
Figure 8
Estimate of increased pressure induced by compaction
Figure 9
Design criteria for crib and bin walls
slopes are commonly supported by a cantilever wall (only for shallow excavations), a
braced wall, or a tieback wall (fig 10). In some cases, it may be economical to mix
systems, such as a free slope and a tieback wall or a tieback wall and a braced wall.
Table 1 summarizes the wall types with their typical properties and advantages and
disadvantages. Table 2 lists factors for selecting wall support systems for a deep
excavation (>20 feet). Table 3 gives design parameters, such as factors of safety,
heave problems, and supplemental references.
Figure 10
Types of support systems for excavations
7. STRUTTED EXCAVATIONS.
N = γH/su (eq 2)
where γ, H, and su, are defined in figure 11. If N exceeds about 4, m < 1.0.
7.2 FOR STIFF-FISSURED CLAYS, diagram (c) of figure 11 applies for any value of
N. If soft clays, diagram (b) applies except when the computed maximum pressure
falls below the value of the maximum pressure in diagram (c). In these cases,
generally for N < 5 or 6, diagram (c) is used as a lower limit. There are no design rules
for stiff intact clays and for soils characterized by both c and f such as sandy clays,
clayey sands, or
cohesive silts.
7.3 THE UPPER TIER OF BRACING should always be installed near the top of the
cut, although computations may indicate that it could be installed at a greater depth.
Its location should not exceed 2su below the top of the wall.
to the surcharge load are computed as indicated in previous discussions and added to
the earth and water pressures.
7.5 EACH STRUT is assumed to support an area extending halfway to the adjacent
strut (fig 11). The strut load is obtained by summing the pressure over the
corresponding tributary area. Temperature effects, such as temperature increase or
freezing of the retained material, may significantly increase strut loads.
7.6 SUPPORT is carried to the sheeting between the struts by horizontal structural
members (wales). The wale members should be designed to support a uniformly
distributed load equal to the maximum pressure determined from figure 11 times the
spacing between the wales. The wales may be assumed to be simply supported
(pinned) at the struts.
Table 1
Types of walls
Table 2
Factors involved in choice of a support system for a deep excavation
1. Earth loads For struts, select from the semiempirical diagrams (fig. 14-10); for walls and wales
use lower loads - reduce by 25 percent from strut loading. Tiebacks may be
designed for lower loads than struts unless preloaded to higher values to reduce
movements
2. Water loads Often greater than earth load on impervious wall. Should consider possible lower
water pressures as a result of seepage through or under wall. Dewatering can be
used to reduce water loads
3. Stability Consider possible instability in any berm or exposed slope. Sliding potential beneath
the wall or behind tiebacks should be evaluated. Deep seated bearing failure under
weight of supported soil to be checked in soft cohesive soils (fig. 12)
4. Piping Loss of ground caused by high groundwater tables and silty soils. Difficulties occur
due to flow beneath wall, through bad joints in wall, or through unsealed sheetpile
handling holes. Dewatering may be required.
5. Movements Movements can be minimized through use of stiff impervious wall supported by
preloaded tieback or braced system. Preloads should be at the level of load
diagrams (fig. 11) for minimizing movements
6. Dewatering – Dewatering reduces loads on wall systems and minimizes possible loss of ground
recharge due to piping. May cause settlements and will then need to recharge outside of
support system. Not applicable in clayey soils
7. Surcharge Storage of construction materials usually carried out near wall systems. Allowance
should always be made for surcharge, especially in upper members
8. Preloading Useful to remove slack from system and minimize soil movements. Preload up to the
load diagram loads (fig. 14-10) to minimize movements
9. Construction Sequence used to build wall important in loads and movements of system.
sequence Moments in walls should be checked at every major construction stage for maximum
condition. Upper struts should be installed early
10. Temperature Struts subject to load fluctuation due to temperature loads; may be important for long
struts
11. Frost In very cold climates, frost penetration can cause significant loading on wall system.
penetration Design of upper portion of system should be conservative. Anchors may have to be
heated
12. Earthquakes Seismic loads may be induced during earthquake. Local codes often govern.
13. Codes For shallow excavations, codes completely specify support system. Varies from
locality to locality. Consult OSHA requirements
14. Factors of Item Minimum design factor of safety
safety Earth berms 2.0
Critical slopes 1.5
Non-critical slopes 1.2
Basal heaves 1.5
General stability 1.5
Table 3
Design considerations for braced and tieback walls
8.1 PIPING IN SAND. The base of an excavation in sand is usually stable unless an
unbalanced hydrostatic head creates a "quick" condition. Among the methods to
eliminate instability are dewatering, application of a surcharge load at the bottom of the
excavation, and deeper penetration of the piling.
8.2 HEAVING IN CLAYS. The stability against heave of the bottom of an excavation in
soft clay may be evaluated from figure 12. If the factor of safety is less than 1.5, the
piling should be extended below the base of the excavation. Heave may also occur
because of unrelieved hydrostatic pressures in a permeable layer located below the
clay.
8.3 CARE OF SEEPAGE. Small amounts of seepage into the excavation can be
controlled by pumping from sumps. Such seepage can be expected if the excavation
extends below the water table into permeable soils. If the soils consist of fine sands
and silts, the sumps should be routinely monitored for evidence of fines being washed
from the soil by seepage. If large quantities of fine-grained materials are found in the
sumps, precautionary steps should be taken to make the lagging or sheeting
watertight to avoid excessive settlements adjacent to the excavation.
Figure 11
Pressure distribution – complete excavation
Figure 12
Stability of bottom of excavation in clay
Figure 13
Typical tieback details
Figure 14
Methods of calculating anchor capacities in soil
9. ANCHORED WALLS.
9.1 TIEBACKS have supplanted both strut and raker systems in many instances to
support wide excavations. The tieback (fig 13) connects the wall to an anchorage
located in a zone where significant soil movements do not occur. The anchorage may
be in soil or rock; soft clays probably present the only condition where an anchorage in
soil cannot be obtained reliably. In figure 13, the distance Lub should extend beyond
the "Rankine" zone some distance. This distance is necessary, in part, to obtain
sufficient elongation in anchored length of rod La during jacking so that soil creep
leaves sufficient elongation that the design load is retained in the tendon. After jacking,
if the soil is corrosive and the excavation is open for a long time, the zone Lub may be
grouted. Alternatively, the length of tendon Lub is painted or wrapped with a grease
impregnated wrapper (prior to placing in position).
9.2 THE TIEBACK TENDON may be either a single high-strength bar or several high-
strength cables (fy on the order of 200 to 270 kips per square inch) bunched. It is
usually inclined so as to reach better bearing material, to avoid hole collapse during
drilling, and to pass under utilities. Since only the horizontal component of the tendon
force holds the wall, the tendon should be inclined a minimum.
9.3 TIEBACK ANCHORAGES may be drilled using continuous flight earth augers
(commonly 4 to 7 inches in diameter) and may require casing to hold the hole until
grout is placed in the zone La of figure 13, at which time the casing is withdrawn. Grout
is commonly used under a pressure ranging from 5 to 150 pounds per square inch.
Under-reaming may be used to increase the anchor capacity in cohesive soil. Belling
is not possible in cohesionless soils because of hole caving. Typical formulas that can
be used to compute the capacity of tieback anchorages are given in figure 14.
9.4 EXACT KNOWLEDGE OF THE ANCHOR CAPACITY IS NOT NEEDED as all the
anchors are effectively "proof-tested" (about 120 to 150 percent of design load) when
the tendons are tensioned for the design load. One or more anchors may be loaded to
failure; however, as the cost of replacing a failed anchor is often two to three times the
cost of an initial insertion, care should be taken not to fail a large number of anchors in
any-test program. If the tieback extends into the property of others, permission, and
possibly a fee, will be required. The tieback tendons and anchorages should normally
be left in situ after construction is completed. See table 3 for additional design
considerations.