RATE ANALYSIS 1 1.5 3 - Copy
RATE ANALYSIS 1 1.5 3 - Copy
Total 1236.92
C)
Add cost of carriage of stone aggregate as per consumption required for one cum of concrete. ( As per
table:T-2), Barasat
Upto 5km 124.00
Above 5-10km (per Km) 10.9
5 54.50
Above 10 Km up to 20 Km 10.1 10 101.00
Above 20 km up to 50 km
(per km 9.5 15 142.50
TOTAL 422.00
D)
Add cost for loading and unloading of stone aggregate (As Per Table:3)
0.86 CUM 58.00 49.88
Final Rate of Item = [Rs. A +Rs.B + Rs.C + Rs.D] = Rs.
A 4651.00
B 1236.92
ADD 5% ON B 61.85
ADD 10% ON B 123.69
C) 362.92
D) 49.88
Final Rate 6486.26