RATE ANALYSIS 1 1.5 3 - Copy

Uploaded by

atanuroy.eng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
738 views1 page

RATE ANALYSIS 1 1.5 3 - Copy

Uploaded by

atanuroy.eng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ANNEXURE-II, Page No.

307, Schedule of Rates for Building Works


FORMAT-A
FORMAT OF RATE ANALYSIS OF CONCRETE
Cement Concrete 1:1.5:3
A)
PAGE 26 , 10(A) / Ordinary Cement concrete (mix 1:1.5:3) with graded stone 4651.00
(3rd Corrigenda P- 13, SL-33) chips (20 mm nominal size) excluding shuttering and
reinforcement if any, in ground floor
as per relevant IS codes
B)
Add cost of stone aggregate of different grading as per consumption required for one cum of concrete.
( As per table:T-1 Page:- 308) From Bangao
20 mm Grade Aggregade 1482.00
10 mm Grade Aggregade 1351.00

Cost of 20 mm grade nominal 0.573 CUM 1482.00 849.19


Size aggregade As per (P-B-
60)
Cost of 10 mm grades Nominal 0.287 CUM 387.7
size aggregates (P-B-60) 1351.00

Total 1236.92

C)
Add cost of carriage of stone aggregate as per consumption required for one cum of concrete. ( As per
table:T-2), Barasat
Upto 5km 124.00
Above 5-10km (per Km) 10.9
5 54.50
Above 10 Km up to 20 Km 10.1 10 101.00
Above 20 km up to 50 km
(per km 9.5 15 142.50
TOTAL 422.00

Cost of 20 mm grades 0.86 CUM 422.00 362.92


aggregates (P-B-60)

D)
Add cost for loading and unloading of stone aggregate (As Per Table:3)
0.86 CUM 58.00 49.88
Final Rate of Item = [Rs. A +Rs.B + Rs.C + Rs.D] = Rs.
A 4651.00
B 1236.92
ADD 5% ON B 61.85
ADD 10% ON B 123.69
C) 362.92
D) 49.88
Final Rate 6486.26