PR-NET-CAB-008 - Earthing systems basis of design - design standard
PR-NET-CAB-008 - Earthing systems basis of design - design standard
Name Title
Author John R. Baker Senior Technical Authority
Checked by Elina Bezusko Asset Policy Engineer
Approved by Shirley Robertson Head of Strategic Policy and Sustainability
CONTENTS
1 Introduction ...................................................................................................................................... 4
2 References ...................................................................................................................................... 4
3 Acronyms ......................................................................................................................................... 5
4 Definitions ........................................................................................................................................ 6
5 Deviations from this Standard ......................................................................................................... 9
6 Function of an Earthing System ...................................................................................................... 9
7 Statutory Requirements ................................................................................................................... 9
8 Provision of an LV Earth Terminal................................................................................................. 10
9 Separate Neutral and Earth (SNE) Networks ................................................................................ 10
10 Protective Multiple Earthing and Combined Neutral and Earth (CNE) Networks ......................... 11
11 PME Enabled Networks ................................................................................................................ 13
12 Hybrid Networks ............................................................................................................................ 14
13 Protective Neutral Bonding (PNB) ................................................................................................. 14
14 Where it is Unsafe for Us to Provide an Earth or the Customer Cannot Use Our Earth............... 15
15 Earth Fault Loop Impedance ......................................................................................................... 15
16 Why it is Important not to Exceed the Maximum Value of Earth Fault Loop Impedance .............. 17
17 Consideration of Fault Currents on Networks Operating Above LV.............................................. 17
18 Ratings of Earthwires, Bonding Leads and Earth Electrodes ....................................................... 19
19 Surface Current Density of Earth Electrode .................................................................................. 22
20 Standardised Earthing Resistances and Conductors ................................................................... 23
21 Standardised Earthing and Bonding Layouts, Design and Installation Methods for Substations . 25
22 Earth Potential Rise ....................................................................................................................... 25
23 Hot Sites – Primary and Grid Substations ..................................................................................... 29
24 Hot Sites – Secondary Substations ............................................................................................... 30
25 Neutral Earthing............................................................................................................................. 31
26 Retention of Abandoned PILC Type Cables for Network Earthing ............................................... 32
27 Soil Resistivity Measurement ........................................................................................................ 32
28 Soil Resistivity Values ................................................................................................................... 33
Page 2 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 3 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
1 Introduction
1.1 This mandatory document is intended to be used by:
1.2 This procedure covers the basis of design for fixed earthing systems at voltages used by
SSEN Distribution. It covers background areas which are not included in specific design
standards whilst setting the ground rules for these standards. However, this Document does
not require to be read in conjunction with other Design Standards which can be used in
isolation.
1.2.1 There may be times, for the sake of clarity, that sections included in this document are
repeated verbatim in other Design Standards or even expanded upon.
1.3 This document is evolving and will be supplemented as other Design Standards are
completed.
1.4 Where the term “shall” or “must” is used in this document it means the requirement is
mandatory. The term “should” is used to express a recommendation. The term “may” is
used to express permission.
1.5 TG-NET-SST-004, Bonding and Earthing - Design Standard is a publicly accessible
document covering bonding and earthing not detailed in other Design Standards. This
document will eventually be removed when all the information it contains is contained within
other publicly assessable Design Standards.
2 References
The documents detailed in Table 2.1 - Scottish and Southern Electricity Networks Documents, Table
2.2 - British and International Standards Documents, Table 2.3 - Energy Networks Association
Documents, and Table 2.4 - Miscellaneous Documents, shall be used in conjunction with this
document.
Reference Title
Voltage Supplies to Local Earthed Mobile Phone Base Stations on Steel Towers at
PR-NET-CAB-001
132 kV and Above-Design Standard
Voltage Supplies to Insulated Base Mobile Phone Base Stations on Steel Towers at
PR-NET-CAB-002
132 kV and Above-Design Standard
PR-NET-CAB-006 Electric Vehicle Charging Points-Supply Arrangements-Design Standard
Fuse and Earth Fault Loop Impedance Requirements for Secondary Plant, Networks
PR-NET-ENG-032
and Low Voltage Cut-outs – Design Standard
TEM-NET-CAB-004 11 kV Cable Rating and Earthing Calculation Sheet
TEM-NET-CAB-005 Earthing Calculator for Primary Distribution Substations
TEM-NET-CAB-007 11 kV and 6.6 kV Fault Level and Earthing Data Calculator
TEM-NET-CAB-008 33 kV and 22 kV Cable Rating and Cross Bonding Earthing Calculation Sheet
TG-NET-CAB-005 Alterations to Separate Neutral Earth Services and Mains
TG-NET-CAB-014 Underground Service Connections to Unmetered Street Furniture - Design Standard
TG-NET-CAB-026 Connections of Earthing and Bonding Conductors – Installation Instruction
TG-NET-CAB-029 Grid and Primary Substation Earthing Data (SEPD) - Data Sheet
TG-NET-CAB-030 Primary Substation Earthing Data (SHEPD) - Data Sheet
TG-NET-CAB-427 Cable Sheath Bonding Methods of 33kV Cable Systems
Page 4 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Reference Title
TG-NET-ENG-022 Principles for Cost Benefit Analysis in Supporting ALARP Decisions
TG-NET-SST-004 Bonding and Earthing - Design Standard
TG-NET-SST-005 Secondary Distribution Substations Common Clauses - Design and Installation
Standard
TG-NET-SST-006 Replacement of Copper Earthing Conductor with Aluminium
TG-NET-SST-013 Locations with High Earth Potential Rise (Hot Sites)- Design Standard
TG-NET-SST-032 Primary Distribution Substations- Earthing Requirements-Design Standard
Identification and Rectification of High Earth Fault Loop Impedances – Separate
WI-NET-CAB-140
Neutral and Earth Networks
WI-NET-CAB-150 Earthing of Secondary Substation Ground Mounted Plant – Installation Instruction
WI-NET-CAB-154 11 kV Cables – Theft of Copper Earthing - Remediation Works
Reference Title
BS 6651 Protection of Structures against Lightning
BS 7430 Code of Practice for Earthing.
BS 7671 Requirements for Electrical Installation (the IEE Wiring Regulations)
BS EN 50522 Earthing of power installations exceeding 1 kV a.c
IEC 60479 The Effects of current on human beings and livestock.
Reference Title
Requirements for the Application of Protective Multiple Earthing to Low Voltage
G12
Networks
S34 A guide for assessing the rise of earth potential at electrical installations
Identification and recording of 'hot' sites - joint procedure for Electricity Industry and
S36
Communications Network Providers
Guidelines for the design, installation, testing and maintenance of main earthing
TS 41-24
systems in substations
Title
Electricity, Safety, Quality and Continuity Regulations 2002 (as amended)
3 Acronyms
The acronyms shown in table 3.1 are used in this document.
Acronym Definition
ABC Aerial Bundled conductor
ABSD Air Break Switch Disconnector
ALARP As low as reasonably practicable
ASL Automatic Sectionalising Links
BLL Belagt Luftledning (Covered Overhead Line)
BLX Belagt Linesystem XLPE (Covered Line system XLPE)
CEW Continuous Earthwire
CNE Combined Neutral and Earth
Page 5 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Acronym Definition
DOEF Drop out expulsion fuse
EFC Earth Fault Current
EFLI Earth Fault Loop Impedance
ENA Energy Networks Associations
EPR Earth Potential Rise (was Rise of Earth Potential, ROEP)
ESQCR Electricity Safety, Quality and Continuity Regulations
EV Electric Vehicle
GES Global Earthing System
GRC Ground Return Current
IDNO Independent Distribution Network Operator
ITU International Telecommunication Union
LER Liquid Earthing Resistor
LPS Lightning Protection System
LV Low Voltage
LVAC Low Voltage Alternating Current
m metres
MES Main Earthing System
NCD Neutral Current Division
NER Neutral Earthing Resistor
PILC Paper Insulated Lead Covered
PILCSTA Paper Insulated Lead Covered, Steel Tape Armoured
PILCSWA Paper Insulated Lead Covered Steel Wire Armoured
PME Protective Multiple Earthing
PMR Pole Mounted Reclosers
PNB Protective Neutral Bonding
RMS Root – Mean – Square
ROEP See EPR
SEN Single Earthed Networks
SEPD Southern Electric Power Distribution
SHEPD Scottish Hydro Electric Power Distribution
SNE Separate Neutral and Earth
SSEN Scottish and Southern Electricity Networks
TN-C-S Terre – Neutral – Combined - Separate
TNP Telecommunications Network Provider
TN-S Terre – Neutral – Separate
TT Terre - Terra
4 Definitions
The following definition apply to terms used in this document
Term Definition
Additional Earth See Supplementary Earth. This is not the same as the additional earth required
under the Operational Safety Rules.
Assembly Instruction A mandatory document, produced by SSEN, covering the specific requirements
for putting together SSEN assets. They typically take the form of work
instructions.
Page 6 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Term Definition
Auxiliary Electrode See Supplementary Electrode.
Backup Protection Protection set to operate following failure or slow operation of primary protection.
For design purposes, the backup protection clearance time may be taken as a
fixed clearance time.
Bonding An abbreviated version of Equipotential Bonding.
A protective conductor providing equipotential bonding. This conductor may not
Bonding Conductor
necessarily be connected to earth.
A mandatory document, produced by SSEN, covering the specific requirements
Design Standard
for SSEN designed assets.
The conductive mass of earth whose electric potential at any point is
Earth
conventionally taken as zero.
A conductor or rod, or, set of conductors and rods providing an electrical contact
Earth Electrode
with Earth.
Earth Electrode Potential The difference in potential between the Earth Electrode and a remote Earth.
Earth Electrode The resistance of an Earth Electrode with respect to Earth.
Resistance
That area of ground over which the resistance of an Earth Electrode effectively
Earth Electrode
exists. It is the same area of ground over which the Earth Electrode Potential
Resistance Area
exists.
A fault causing current to flow in one or more earth-return paths. Typically, a
Earth Fault single phase to earth fault, but this term may also be used to describe two-phase
and three-phase faults involving earth.
The RMS value of current which flows in the earthing system resulting from a
Earth Fault Current phase to earth short circuit. Note, this can be modified in some situations where
it is realistic to include fault resistance.
An earth electrode formed by overlapping groups of buried horizontal electrodes
Earth Grid
usually laid at right angles and connected at each intersection.
An electrode consisting of bare conductor or mesh laid in, or on, the ground to
Earth Mat equalise the potential across an area where a person can stand. An earth mat
does not form part of an earth electrode.
Earth Nest An earth electrode consisting of a set of conductors and rods.
The difference in potential which may exist between a point on the ground and a
Earth Potential Rise remote Earth. May also be known as Rise of Earth Potential (ROEP) or Ground
Potential Rise (GPR).
Earthed Connected to Earth.
A protective conductor connecting a main earth terminal of an installation to an
Earthing Conductor or
Earth Electrode or to other means of earthing, or a conductor connecting
Earthing Connection
equipment to a main earth terminal of an installation.
The current entering the ground through the substation’s electrode system under
earth fault conditions. For design purposes, the electrode current may be taken
Electrode Current as the maximum current flowing into a substation’s electrode system under
foreseeable fault conditions including, where relevant, the loss of metallic return
paths and/or cross-country faults.
Equipotential A line of equal voltage.
An electrical connection between exposed metallic (conductive) parts installed to
Equipotential Bonding
equalise the potential (voltage) not necessarily connected to earth.
The ohmic resistance of a fault. This can vary during the fault but where
Fault Resistance
reasonable a value can be assumed when working out the fault current.
An earthing system of sufficiently dense interconnection such that all items are
Global Earthing System bonded together and rise in potential together under fault conditions. No true
earth reference exists and therefore safety voltages are limited
An electrode installed to reduce a touch potential hazard on equipment. Can be
Grading Ring
installed as part of the Main Earthing System or in addition to it.
Page 7 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Term Definition
The proportion of the earth fault current flowing into ground. The earth fault
Ground Return Current current can be split between the ground, cable sheaths and overhead earth
wires. The ground return current results in the earth potential rise.
A Hot site is defined as one which exceeds ITU limits for EPR. These thresholds
Hot Site
are 650 V (for reliable fault clearance time <= 0.2 seconds), or 430 V otherwise.
A mandatory document, produced by SSEN, covering the specific requirements
Installation Standard for the installation of SSEN assets. It is a higher-level document than an
assembly instruction.
An electric line which multiple consumer’s installation as one intake position to a
Intake Line distributing main. An example is the cable connected into a heavy duty cut-out in
a multi-occupancy building.
The Main Earthing System comprises the interconnected arrangement of the
Main Earthing System Earth Electrodes and Earthing Conductors in a substation. Other terms are
Substation Earthing System or Main Earth Grid.
Clearance of a fault under normal (usual) circumstances. The protection
clearance time will include relay operating time and mechanical circuit breaker
Main Protection delays for all foreseeable faults and may be calculated for design purposes.
Alternatively, standard time may be used for the main protection clearance time
for earthing design purposes.
A low voltage electric line which connects a source of voltage to one or more
Mains Distributor
service or intake lines. Other terms are Distributing Main.
Normal Protection See main protection
An earthing arrangement, found in TN-C-S systems, in which the supply neutral
Protective multiple conductor is used to connect the Earthing conductor of an installation with earth,
earthing (PME) in accordance with the Electricity Safety, Quality and Continuity Regulations
2002.
PNB refers to the situation where there is only one point in a network at which
consumers’ installations are connected to a single source of voltage. In such a
Protective neutral bonding
case, the supply neutral conductor connection to earth may be made at that
(PNB)
point or at another point nearer to the source of voltage. This type of earthing is
not permitted for new installations.
Safety Voltage Permissible touch, step or transfer potential.
An electric line which either connects a street electrical fixture, or a single
Service line
consumer’s installation to a distributing main.
Voltage between two points on the ground surface that are 1 m distant from
Step Potential
each other, which is considered to be the stride length of a person.
Voltage difference between two segregated earthing systems, which may appear
Stress Voltage
across insulators/bushings etc. or cable insulation.
An electrode that improves the performance of an earthing system, and may
Supplementary Earth
increase resilience, but is not critical to the safety of the system.
The value of earth resistance which is to be achieved on site following
Target Earth Resistance
installation of the earthing system as per the design.
A system having one or more points of the source of energy directly earthed, the
TN system exposed conductive parts of the installation being connected to that point by
protective conductors. Not normally used in the UK.
A system in which neutral and protective functions are combined in a single
TN-C system
conductor throughout the system. Not normally used in the UK.
A system in which neutral and protective functions are combined in a single
TN-C-S system conductor in part of the system. Another term is Combined Neutral and Earth
(CNE).
A system having separate neutral and protective conductors throughout the
TN-S system
system. Another term is Separate Neutral and Earth (SNE).
Touch Potential Voltage between conductive parts when touched simultaneously.
Voltage transmitted along a conductive path to an area of lower potential, such
Transfer Potential
as a metallic screen wires of a PVC sheathed cable.
Page 8 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Term Definition
A system having one point of the source of energy directly earthed, the exposed-
TT system conductive-parts of the installation being connected to earth electrodes
electrically independent of the earth electrodes of the source.
7 Statutory Requirements
7.1 The ESQCR incorporates the requirements for providing earthing.
7.2 This, and other, Design Standards provide the specific requirements needed for SSEN to be
compliant with the ESQCR.
Page 9 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 10 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
9.2 TN-S is the international description for SNE. T is for Terre comes from the French for earth,
N is for Neutral and S for separate.
9.3 Where there is a need to alter a SNE Mains and Services these alterations shall be carried
out using SNE cables. In exceptional circumstances this may not be possible and CNE
cables have to be used. Where this is the case refer to TG-NET-CAB-005.
Page 11 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
terminal. For PME to work needs to be numerous additional earth electrodes installed
around the network and specially there must be one at every pot end on a PME circuit.
10.2 Combined Neutral and Earth, CNE or TN-C-S cables or overhead line networks provide the
connection suitable for a PME earthing terminal. Here the neutral and earth are provided in
the same conductor.
10.2.1 Customers must have separate neutral and earth networks within their properties.
10.2.2 Public street lighting and other street furniture can have PME earthing subject to specific
requirements.
10.3 Typical overhead and underground systems are shown in figure 10.1 and 10.2.
10.4 TN-C-S is the international description for CNE. T is for Terre and comes from the French
for earth, N is for Neutral, C is for Combined and S for separate. Part of this system (that
owned by SSEN) has a combined neutral and earth (C) conductor and part of the system
(the network owned by the customer) has separate neutral and earth conductors (S).
Page 12 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
10.5 At the service termination within the customer's premises a label as shown in figure 10.3.
Page 13 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
11.3 Services shall have the same type of earthing as the mains distributor to avoid any issues
with conflicts of earthing.
11.3.1 Converting a SNE service to PME by connecting the Neutral and Earth together at the cut-
out is forbidden.
11.4 The conversion or provision of a PME service from an SNE main purely by connecting the
neutral to the earth in the service joint without ensuring the remainder of the network is PME
enabled is forbidden.
11.4.1 Appendix C gives examples of where a CNE service can be connected to an SNE main
distributor and more importantly where it cannot. Neutral to earth bonding connections are
not shown on our records however it can be concluded that these have been made in the
transition joints between CNE and SNE cable.
11.4.2 It however cannot be assumed that the end of a radial SNE cable has the neutral and earth
bonded and as such any services installed in this section must be SNE.
12 Hybrid Networks
Hybrid networks are those where CNE cable and services have been introduced into SNE networks
but compliance with the requirements of section 11 is only partial or not at all.
Page 14 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 15 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Figure 15.1 – Example of Earth Fault Loop Impedance on SNE Underground Network
15.3 High earth loop impedances cannot be reduced by adding more earth rods. Either the
network has to be repaired or redesigned. Details of identification and rectification of high
earth fault loop impedances are given in WI-NET-CAB-140.
Figure 15.2 - Example of Earth Fault Loop Impedance on CNE Underground Network
Page 16 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
16.2 SSEN are also designing networks so that a substation fuse will operate in 100 seconds for
a fault up to the cut-out.
16.3 For legacy networks which have lead-sheathed cables the provision in 16.1 and 16.2 may
not be able to be met, however there is still a need to minimise the maximum values of
EFLI.
16.4 Refer to PR-NET-ENG-032 for details of EFLI values and fuse sizes.
Page 17 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
17.6 Phase to phase fault via the earthing system (Cross-country fault)
17.6.1 The cross-country fault can occur within substations and between substations connected by
cable. AIS switchgear is more susceptible to cross-country faults than GIS plant and
therefore sites where AIS equipment is installed shall take into account the value of the
cross-country fault. In the absence of any supporting calculations the cross-country
fault current shall be taken as equivalent to 87% of the three-phase fault current.
17.6.2 It is worthy of note that cross-country faults are not limited by any neutral earthing resistors.
Page 18 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 19 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
18.4.1 As a general guide, shear-off connections shall not be used in Primary and Grid
Substations. Compression connections shall not be used underground in Primary and Grid
Substations.
Page 20 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 21 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Connection Type
Single Bolt Lug Double Bolt Lug
with Transition with Transition Welded, brazed,
Material Washer or Washer or plumbed or
single shear- multiple shear- compressed
bolt connector bolt connector o
C
o o
C C
Copper 250 405 405
Aluminium 250 325 325
Steel 250 405 405
BLX or BLL Covered Aluminium Alloy 190 190 Not applicable
PVC Covered Copper 175 175 Not applicable
Lead Note 1 Note 1 200
Note 1. Bolted connections are not the permitted on Lead as it can extrude under pressure
weakening the connection. Either a mechanical clamp (refer to jointing instructions) or
plumbing can be used.
Table 18.8 gives details of the parameters to be used in the non-adiabatic formula for
calculation of the ratings of earthing conductors.
Page 22 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
19.3 The surface area of a bar is calculated by multiplying its length, width and thickness.
19.4 For a round or stranded conductor the surface area is calculated by multiplying its length by
the circumference of the circumscribing circle. Common surface areas for round or circular
conductors are given in table 19.1.
19.5 Table 25.1 gives the maximum current density for soil types (resistivities). By calculating J
and altering the formula in 19.2, the limiting value of resistivity for the design can be
calculated and checked against the soil type. This allows a basic design to be undertaken
prior to undertaking site measurements if required.
19.6 For Primary and Grid design, the earth electrode to be considered shall be that of the
peripheral ring and its rods. Spur connections shall be ignored.
19.6.1 Where, when calculated as 19.6, the current density is excessive then the mesh
interconnection conductors can be included.
Page 23 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Minimum size of
Minimum size Aluminium Maximum
of Copper Earthing or Earth
Plant/Equipment Location
Earthing or Bonding Lead Resistance
Bonding Lead (only to be used Ohms
above ground)
Grid Distribution Substations
Including cable and overhead line terminations in substations. Refer enquiry to [email protected]
Primary Distribution Substations
Including cable and overhead line terminations in substations. Refer enquiry to [email protected]
Ground Mounted Secondary Distribution Substations
HV Metalwork supporting or Substation
enclosing electrical 70 mm² bare 120 mm² Aluflex 50
equipment
LV Neutral Earth Substation 32 mm² PVC Not used 40
Cables not inside substations
Metalwork supporting or Cable
enclosing electrical Termination
equipment support 32 mm² PVC 50 mm² PVC 50
steelwork on
pole.
Bonding Metallic
sheaths/screens to Substation 70 mm² bare 100 mm² n/a
metalwork
Surge Arresters 11 kV Cable
32 mm² PVC 50 mm² PVC 10
Terminations
33 kV Cable
70 mm² PVC 100 mm² PVC 10
Terminations
Cross-bonding joints - main
33 kV 70 mm² PVC Not used 10
earth connections
Cross-bonding joints - link
33 kV Refer to TG-NET-CAB-427
box connections
Overhead Lines not inside substations
Steel Towers operating at Steel Tower Leg 70 mm² or
Not used 10
33 kV and above 35 x 4 mm tape
Steelwork supporting or Structures
enclosing electrical required to be
32 mm² PVC 50 mm² PVC 50
equipment earthed, trussing
tackle
Steelwork Bonding Wire Crossarms and
32 mm² PVC 50 mm² PVC n/a
other metalwork
Surge Arresters at cable 11 kV Cable
32 mm² PVC 50 mm² PVC 10
terminations Terminations
33 kV Cable
70 mm² PVC 100 mm² PVC 10
Terminations
Autoreclosers or other HV Earth 32mm² PVC 50 mm² PVC 50
Switchgear controlled at
ground level using control Earth Mat 32 mm² PVC 50 mm² PVC n/a
boxes Control box 32 mm² PVC 50 mm² PVC n/a
Stays Pole top make-
Kingwire n/a
offs
Handle Operated Air Break HV Earth 32 mm² PVC 50 mm² PVC 50
Switch Disconnector Earth Mat 32 mm² bare Not used n/a
Hook Stick Air Break Switch Bonding 32 mm² bare or
50 mm² bare or PVC n/a
Disconnector PVC
Page 24 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Minimum size of
Minimum size Aluminium Maximum
of Copper Earthing or Earth
Plant/Equipment Location
Earthing or Bonding Lead Resistance
Bonding Lead (only to be used Ohms
above ground)
Pole Mounted Transformer HV Steelwork
32 mm² PVC 50 mm² PVC 50
fitted with arcing horns Earth
Pole Mounted Transformer HV Steelwork
32 mm² PVC 50 mm² PVC 10
fitted with surge arresters Earth
Pole Mounted Transformer LV Neutral Earth
at transformer or 32 mm² PVC 50 mm² PVC 40
first pole away
Continuous Earth Wire SNE Lines and 16 mm2 bare or 50 mm² PVC or
n/a
Services PVC XLPE Covered
General
LV Neutral to Earth CNE main earth 32 mm² PVC 50 mm² PVC 20
PNB main earth 32 mm² PVC 50 mm² PVC 40
SNE main earth 32 mm² PVC 50 mm² PVC 40
Other connections to earth Additional/
supplementary 16 mm² PVC 25 mm² PVC 100
earths
Link boxes and
16 mm² PVC n/a 100
street pillars
Page 25 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
22.5 Ground return current must not get confused with earth fault current as for cable networks a
proportion of the EFC follows in the cable sheath.
Page 26 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 27 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
22.8.4 For example, on 150 mm chippings, for a 1 second fault Vt = 298 V and Vs = 24083 V.
Page 28 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
soil. There are no safety limits prescribed for animals, but technical report IEC/TR 60479-3
provides some limited experimental data. Interpretation of this data suggests that potential
gradients (such as around remote electrodes or structures placed in fields) not exceeding 25
V/m will generally not result in animal fatality.
22.11 Injury or shock to persons and animals outside of substations and earth
grids.
22.11.1 Shock risk outside an installation can be introduced by metallic transfer (fence, pipe, cable)
or via the soil. Where a hazardous transferred potential can occur due to a continuously
metallically conductive construction, the transfer potential shall be blocked by the
introduction of insulation or other protective measures (examples include insulated sections
introduced into external metal fences). Where metal fences are bonded to the substation
MES, the touch and step potentials external to them shall be controlled by the design, such
that they are within the acceptable limits. Where HV and LV earthing systems are combined,
the EPR is transferred from the installation into domestic, commercial or industrial properties
and shall not exceed 430 V.
22.11.2 In many situations, risk to individuals may be beyond the control of SSEN, for example if a
building is erected close to an existing substation. In such circumstances, a risk assessment
shall be carried out to establish the level of risk, and the justifiable spend to mitigate against
that risk. Acceptable voltage thresholds will be influenced by activity (such as wet/dry),
location (such as beach-side) and the presence of animals.
Page 29 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
• 1700 V
23.4.1 In addition to the voltage contours in 23.4 in petroleum filling stations the 250 V contour is
also required as this is the maximum voltage which can be tolerated on the fuel pump
forecourt TT earth grid.
23.4.2 Where SSEN does not have sufficient information to detail the extent of a hot zone it will
assume that this is 100 m. The associated sites will be termed in the hot site register as
‘presumed Hot’.
23.4.3 SSEN will not be providing maps showing these voltage contours.
23.5 In designing sites at all voltages SSEN shall strive to ensure where it is reasonable,
practicable and economic that sites are not hot, or where hot, the EPR is reduced where
achievable.
23.6 The hot site register will be incorporated into the Grid and Primary Substation Earthing Data
Sheets.
23.7 The responsibility for costs associated with mitigation required for a hot site comes is on the
second comer up to an EPR zone of 100 m. Where the EPR zone is greater than 100 m the
costs will be agreed between SSEN and the TNP.
23.7.1 Either party may have to take steps to reduce the level and spread of EPR however the
funding required shall still be as per 23.7.
23.8 Refer to TG-NET-SST-013 for the required mitigation at hot sites.
Page 30 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
25 Neutral Earthing
25.1 Method of Neutral Earthing
25.1.1 The method of neutral (or star point) earthing strongly influences the fault current level. The
earthing system shall be designed appropriate to any normal or alternative neutral earthing
arrangements, in a similar way that it will be necessary to consider alternative running
arrangements that may affect fault levels or protection clearance times.
25.3 Primary and Grid Transformer with Star Connected Secondary Windings
25.3.1 Neutral earthing resistors will be installed directly connected to the neutral point of the
secondary winding unless both of the following can be achieved without:
• The earth fault current is less than 625 A per transformer
• The EPR is limit is less than 3 kV
25.3.2 With the advent of the solid resistor NER, which requires minimal maintenance NERs shall
be installed when installing new or replacement transformers. The earth fault current shall
be limited to 625 A per transformer.
Page 31 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
27.5 The apparent soil resistivity is calculated from the formula shown below,
𝜌 =2 × 𝜋×𝑅 ×𝐴
Where p = resistivity in Ωm.
R = resistance measured on meter in Ω.
A = Wenner spacing in m.
Page 32 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Resistivity Maximum
Soil Type Current Density
Ωm x 10 -5 A/mm2
Clay 40 69
Farming soil 100 44
Silt 150 36
Sand 200 31
Chalk 400 22
Sandstone/limestone 500 20
Shale/gravel 600 18
Peat/loam 700 17
Stone/rock 1000 14
Granite 5000 6
Page 33 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 34 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
31.4 The formula shown below is used to calculate the segregation value, SV.
𝑅3
𝑆𝑉 =
(𝑅1 + 𝑅2)
If SV is 0.9 or greater then satisfactory earth separation exists.
If SV it is less than 0.9 then work must be undertaken to obtain the rectify the separation.
31.5 Segregation tests are not required on pole mounted transformer installations where the
neutral earth is one pole away from the transformer, providing the pole is at least 15 m
away.
31.6 This method of test can be used wherever earth electrodes are required to be segregated.
32 Fences
32.1 Secondary Distribution Substations
32.1.1 Where SSEN own all the equipment within the substation the fence shall not be earthed.
32.1.2 Where SSEN own the majority of the equipment (except say the RMU) within the substation
the fence shall not be earthed unless the other party requires it as part of their standard
design. Where this is the case, the SSEN HV earth installed within the substation shall be
connected to the fence in opposite corners of the substation. A grading ring of
70 mm2 copper shall be installed external to the fence, 0.5 m away and 0.5 m deep (unless
the other party requests differently) and bonded to the fence on each side of the fence.
32.1.3 Where SSEN is the minority user then the fence earthing will be to the majority owner’s
design standards.
Page 35 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 36 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
35 Cross-Bonded Systems
35.1 Long lengths of single core cable can experience high screen circulating currents. To reduce
this effect the cables shall be laid in tight trefoil.
35.2 Where design calculations show that the screenwires to earth voltage shall exceed 65 V
under full load conditions cross-bonding shall be installed.
35.3 To mitigate the effects of extreme voltage rise under fault condition sheath voltage limiters
shall be installed where required.
35.4 Refer to TG-NET-CAB-427 for systems up to and including 33 kV.
36 Overhead Lines
36.1 Plant Poles
36.1.1 Poles fitted with transformers, autoreclosers, surge arresters, air break switch disconnector,
fusegear and cable terminations must have the steelwork bonded and earthed.
Page 37 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
36.2 Stays
36.2.1 The pole top make-offs of all stays will be bonded to the line support steelwork. Stay wires
entering the ground within 2 m of a metallic secondary distribution substation fence, will be
bonded to the fence.
36.2.2 Wind stays are normally fitted well below the crossarm steelwork. Where, however, the pole
top make-off will be in contact with the pole steelwork, will be within 1.5m of the steelwork,
or, the pole is earthed then it must be bonded to the steelwork either by installing a bonding
conductor or connecting the king wire to the HV steelwork as appropriate. Otherwise the
wind stay does not need bonding.
36.2.3 Stay insulators must be positioned so that no part of the stay insulator is less than 3 m
above ground level (or climbable obstruction). This applies under both the normal and
broken conditions.
36.3 Steelwork
36.3.1 All supporting steelwork attached to, or, forming part of a wood pole will be bonded together.
This will also apply where there are multiple crossarms on the pole, such as a tee-off pole.
36.3.2 Cross bracing (trussing tackle) will not be earthed unless the lowest member is less than 3
m above ground level or earthed equipment is installed on the same pole. Bonding is not
required between the cross bracing and the pole top steelwork. On earthed poles the cross
bracing shall be bonded to the earth conductor.
36.3.3 When a pole is required to be earthed and is situated within 2 m of the perimeter fence of a
secondary distribution substation then the steelwork earth will be bonded to the main
substation earthing system. This may be inherent by virtue of a cable being installed
between the terminal pole and the substation in which case no additional earthing is
required. If a separate earthwire has to be laid then it shall be either PVC covered or
installed in duct for a distance of 0.5m inside of the secondary distribution substation fence
to the pole.
Page 38 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
36.5.2 A connection must be made between the earthing points on the plant or cable to be
protected and the surge arrester bracket or earthwire. This can be achieved by either
running an earthwire from the plant to the surge arrester bracket, or, by connecting the plant
earthwire to the surge arrester earth using angle taps (‘L’ taps).
Page 39 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
• Where there are two outgoing circuits from the transformer then either a single neutral
earth installed at the transformer, or a neutral earth installed on the first pole out on
each circuit
• Where an LV cable is attached on the transformer pole the neutral earth will always
be installed on the transformer pole
• Where there are services attached on the transformer pole the neutral earth will
always be installed on the transformer pole
36.14.6 The neutral earth electrode will consist of a minimum of 2 x 1200 mm rods coupled together
connected to the LV neutral using PVC covered conductor. The resistance of the LV neutral
earth shall comply with table 18.1. Where a single electrode does not produce the desired
resistance then addition electrodes consisting of 2 x 1200 mm rods, spaced 4 m apart,
connected together using 32mm² bare copper, shall be installed until the correct value of
resistance has been obtained.
Note: on CNE systems the overall LV network earth value is required to be lower than the
LV transformer neutral earth. Where the network consists of a few isolated poles it is
beneficial for the transformer neutral earth resistance to be close to that of the CNE neutral
to earth value. This is because a small number of, close, additional earths may not reduce
the overall neutral earth resistance sufficiently.
36.14.7 A third type of installation is the PNB connection which is applied to a single customer fed
from a PMT.
36.15 Pole Mounted Reclosers with control boxes within 3 metres of ground level
36.15.1 PMR with control boxes within 3 m of ground level must have the following.
36.15.2 Surge Arresters installed on the source side and a surge arrester earth conductor run
directly from the surge arresters to the earth electrode. The earth electrode shall be installed
a minimum of 500 mm from the pole.
36.15.3 The PMR and supporting steelwork earthed to the surge arrester earth.
36.15.4 The HV steelwork shall be bonded to the surge arrester earth.
36.15.5 The control box bonded to the surge arrester earth by installing a separate PVC insulated
earth lead from the surge arrester earth to the control box.
36.15.6 An earth mat loop will be installed in a position where a person will stand to operate the unit
(using the control box). Both ends of the loop of the earth mat will be connected to the
control box.
Page 40 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 41 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
the customer.
37.2.2 Where the site is Hot the customer will need to segregate their HV steelwork and LV neutral
earth for EPRs up to and including 2 kV. Above 2 kV the customer must take other
mitigating action.
Page 42 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
38.4.2 Table 38.1 gives details of the parameters used to obtain the protective length. Where
different values of Ures are used the formula in 38.4.3 shall be used to calculate the
protective length.
Steel
Towers
Wood Poles
or Substations (Primary Voltage)
(Note 2)
Wood
Poles
11kV 33kV 132 kV 11 kV 33 kV 66 kV 132 kV
LIVW of
equipment kV LIVW 95 200 650 75 170 325 550
(Note 1)
safety factor Ks 1.05 1.15 1.2 1.15 1.15 1.2 1.2
Residual
Voltage of kV Ures 39.1 77.6 440 39.1 77.6 189 280
arrester Ures
Wave
kV/μs S 1000 1000 1000 1000 1000 1500 1500
steepness
Wave
m/μs Vw 300 300 300 300 300 300 300
velocity
Maximum
Protective m Lp 7.71 14.45 15.25 3.92 10.53 8.18 17.83
length
Protective
Length used
m 7.00 14.00 15.00 3.00 10.00 8.00 17.00
in
documents
Note 1 -LIVW is the Lightning Impulse Withstand Value also known as BIL (Basic Impulse
Level).
Page 43 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Note 2 – the protective length for some wood pole installations cannot be achieved due to
the height of the pole. However, in most cases a lightning strike to the line will dissipate
through corona discharge and so the voltage reaching the item to be protected is a lot lower
than for a direct strike on the item. It should also be noted that some equipment has a lower
LIVW that that of the overhead line.
38.4.3 The protective length of an arrester is calculated using the formula below.
Vw LIVW
Lp = x( − Ures )
(2 x S) Ks
Page 44 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
42.3 PF, the probability of an earth fault on the network shall be obtained from historical records.
Note the earth faults can be due to network failure and some degree of sense needs to be
applied. Such as the EPR at a primary substation can be due to faults on the secondary
network, but all faults on the secondary networks are not earth faults.
42.4 PE is the probability of exposure or contact of the individual, either a member of staff or
member of the public. Care must be taken to establish what the individual is doing, where
they are in relation to earth grid, mats and extraneous metalwork etc. and how they would
be affected by a dangerous voltage rise. For instance, a member of the public is unlikely to
be holding the hand of an ABSD within a Primary Substation at the time of fault whereas a
member of staff could be. PE is therefore an estimate of the likely time a person could be
subject to the hazard.
42.5 PFB is the likelihood that, if a person were exposed to the earth potential rise, heart
fibrillation would occur. In undertaking this study, the human body resistance needs to be
taken into account.
42.5.1 Providing that the touch voltage is less than the total human resistance multiplied by the
current shown in Table 42.1 appropriate to the fault clearance time then the value of PFB is
0.05.
42.6 For hand to foot contact (touch) (the most likely effect), this is made up of a number of
factors:
• The actual human body resistance
• Resistance of footwear
Page 45 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
• Resistance of hand coverings (not normally included even where PPE is worn)
• Resistance of the ground
42.7 The following standard values will be used for the risk assessment process:
• Human body resistance of 431 Ω (covers 95% of the population)
• Resistance of footwear shall be taken as 8000 Ω per shoe
• Resistance of hand coverings 0 Ω
• Resistance of ground per foot shall be 3 x soil resistivity (as per ENA TS 41-24) or
300 Ω if the soil resistivity is unknown
42.8 Table 42.1 gives details of the data relating body current to duration of current flow. For the
principles of earthing adopted by SSEN this data reflects the curve relating to the lower end
of AC-4.1 (IEC 60479); this table is shown graphically in Appendix A. Effectively if the body
current is less than 30 mA then mitigation is not required. Typical fault clearance times are
shown in red.
Page 46 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
44 Design Considerations
The following items need to be addressed when considering the earthing design:
• The magnitude and type of earth fault and ground return currents
• Cross-country faults
• Faults outside of a substation on the lower voltage network creating an EPR
• Faults on the higher voltage side of the substation creating and EPR and transfer
potential to the lower voltage side
• Specific safety criteria which limit the EPR
• Transfer potential to metallic objects
• The target earth resistance required
• The need for grading rings and earth mats
• Size and configuration of earth electrodes and their constituent parts
• Rebar and concrete piles
• Earth mesh within switchrooms (indoor GIS at 66 kV and above)
• Lightning protection
• Shared sites
• Metallic Fences
• Hot Sites
• Third-party infrastructure
46 Theft of Earthing
46.1 Earthing shall be protected as detailed in the Design Standards; protection can include:
Page 47 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 48 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
50.2 CNE cable into a substation solely designed for SNE cables.
50.2.1 The neutral earth of the CNE cable shall be connected to the neutral/earth bar of the SNE
substation.
50.2.2 As the neutral and earth are connected at the substation there is no requirement to provide
an extra bond at the substation.
50.2.3 The remote end of the CNE cable shall be fitted with a supplementary earth.
50.3 CNE cable into a substation designed for both SNE and CNE cables.
50.3.1 The neutral earth of the CNE cable shall be connected to the earth bar of the SNE/CNE
substation.
50.4 SNE cable into a substation solely designed for SNE cables.
50.4.1 The neutral of the SNE cable shall be connected to the neutral bar with the earth wire being
connected to the earth bar of the SNE substation.
50.5 A supplementary earth shall be installed at the remote end of the SNE cable connected only
to the earth.
50.6 SNE cable into a substation solely designed for CNE cables.
50.6.1 Both the neutral and earth of the SNE cable shall be connected to the neutral/earth bar of
the CNE substation.
Page 49 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
50.7 A supplementary earth shall be installed at the remote end of the SNE cable connected only
to the earth.
50.8 SNE cable into a substation designed for both SNE and CNE cables.
50.8.1 The neutral of the SNE cable shall be connected to the neutral bar of the SNE/CNE
substation.
50.8.2 The earth wire of the SNE cable shall be connected to the earth bar of the SNE/CNE
substation.
50.9 A supplementary earth shall be installed at the remote end of the SNE cable connected only
to the earth.
51 Earthing Study
51.1 Earthing studies are not mandatory unless stated in the documents. Where this is required,
the following information will need to be provided to the Earthing Study Specialist:
• An overall plan showing the route from the source substation to the new substation
• A plan of the new substation showing the location of the plant, other electrical
equipment and the interconnection to other non-electrical metallic objects (rebar,
piles, etc.). A radius of 50 m centred on the new substation site should be considered
when collecting this information
• The earth resistance at the source substation. Where the earth resistance at the
source substation is not known then a value of 0.1 can be assumed
• EPR at the source substation where the EPR is greater than 430V
• The predicted earth fault current at the new secondary substation and protection
clearance time, at the source, at the predicted value for the new secondary
substation. Where the current is not known at the secondary substation then that at
the source substation can be used, although this will give a overestimated EPR value
• The surface type of the new substation and its thickness
• The types, sizes and lengths of cables and overhead lines supplying the new
secondary substation from the source including any overhead earth wires.
• The soil resistivity at the new secondary substation. Where this is unknown the
Earthing Study Specialist can be requested to provide this information
• Any restrictions on installing earth rods within the substation
51.2 The Earthing Study Specialist shall compile a report detailing the following:
• The EPR at the proposed site
• Touch and step potentials
• The spread of EPR detailing the 430 V contour (250 V contour if the substation is
going within the confines of a petrol filling station). This shall be shown on an overall
plan of the site
• Any mitigation required at the site
Page 50 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
52 Survey
The survey data below is required to undertake a design:
• Proposed layout drawing
• Layout drawing showing any existing earthing (if applicable)
• Details of incoming and outgoing circuits; cables or overhead lines
• Source earth fault current and EPR at the voltage levels of the source
• Soil Resistivity
• Substation resistance
• Contribution of any un-insulated cables connected into the substation within a 1 km
radius
• Protection operating time for main and backup protection
• Extent of the 430 V or 650 V contour (from the fence line) as applicable to the
protection operating time
• Extent of the 1150 V or 1700 V contour (from the fence line) as applicable to the
protection operating time
53 Pre-Construction Documents
53.1 A documented Earthing Survey shall be provided by the third party for approval by SSEN for
all Primary Substations with an operating voltage of 6.6 kV and above and all Grid
substations. SSEN Designers will also need to provide an earthing survey. This document
shall include and consider the following:
53.2 A system diagram showing the position of all electrode systems.
53.3 Earth potential rise.
53.4 Touch potentials and where appropriate step potentials.
53.5 An Earthing schedule detailing:
• Measured value of soil resistivity at each location
• Type of earth electrode system
• Specification for each earth electrode system
• Maximum design value of resistance to earth of each electrode system
53.6 An earthing survey will also be required for secondary distribution substations where there
will be a single HV/LV earth electrode, or the site requires a special design such as a petrol
filling station.
54 Final Records
54.1 Drawings detailing how earthing has been installed is required. The drawing(s) shall give
details of the installation, such as number of rods and sizes of conductors, including the
dimensions from permanent fixed objects to the location of the earth rods and conductors.
Page 51 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
54.2 The installed earth resistance values measured at each electrode system shall be recorded
on an Earthing Schedule which shall be included with the handover documents.
Page 52 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
metallic plant that is not bonded to the local ‘global’ earthing system. Such arrangements
can cause ‘islands’ of higher potential inside a ‘GES’, and thus the benefits of a GES do not
apply. Within a GES the neutral earth/HV steelwork earth link shall remain closed.
55.7 Care must be taken when reviewing the reports of Earthing Consultants to ensure that their
proposals do not introduce any ‘islands’ within a GES. Such an island would be produced if
the recommendation is to have the neutral earth/HV steelwork earth open; it is essential
within a GES that the link remains closed to increase the effectiveness of the earthing.
55.8 If we use the example of 40 secondary substations and assume that each are connected by
plastic sleeved cables, then the only earthing is provided by the secondary substation earth
resistance. If we assume a maximum of 50 ohms for the HV earth and 40 ohms for the LV
and that they are combined, then each substation has a contribution of 22.2 ohms. With 40
substations the contribution is 0.56 ohms. These act in parallel with the primary substation
soil resistance. It is important that only substations connected directly back the primary
substation can be included in the count. Those, where the route back, is via an overhead
line cannot be included.
55.9 The main mitigation achieved by using a GES model is that transfer potential is distributed
and reduced. This is useful where the primary 22/33 kV transfer potential is creating a hot
site rather than an 11 or 6.6 kV network fault. As the feeder substations to these primaries
are normally fitted with NERs, whilst there is a slight increase in earth fault current, the use
of the GES will in many cases reduce the transfer potential to below that of the hot site value
but will control the touch and step potential in all cases.
Page 53 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
• Street lighting and other street furniture with either fixed or fortuitous earthing
• Steel tower lines, where running through urban areas.
Where there is any doubt as to the application of the GES or the site falls outside of the
rules please send your enquiry is internal to SSEN. Email [email protected]
56 Revision History
No Overview of Amendments Previous Document Revision Authorisation
01 New Document None 1.00 Matt Thomas
Page 54 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Page 55 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Curve AC-4.1
Appendix A, Figure 1
Page 56 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Example 1
The EPR on the substation fence is 1200 V. The fault clearance time is 0.2 seconds, and
from Table 42.1 the maximum body current is 350 mA.
Thus the maximum voltage which can be present on the fence is 4956 x 0.35 = 1735 V. This
is above the fence EPR of 1200 V and so is acceptable.
However, what is the potential risk to the 5% of the public who could be affected. For this we
need to work out the probability.
Appendix B, Table 1
PF
A Number of faults per annum on type of network at voltage level 180
B Number of automatically isolated sections (circuit breaker or fuse protected) 12000
on type of network at voltage level
C = A/B Probability of occurrence per annum on any one automatically isolated section 0.015
Appendix B, Table 2
PFB
D Probability of heart fibrillation (5 % affected) 0.05
Appendix B, Table 3
PE
E Length of time stood by fence 20 minutes 3.80 x 10 -5 per
annum
F Number of days stood by fence per 200
annum
G Probability of touch fence out of 100 10
Page 57 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
As this figure is less than 1 x 10-06 the risk is acceptable with no further mitigation.
Example 2
In this example we use most of the parameters from the previous example but change the
EPR on the fence.
The EPR on the substation fence is 2400 V. The fault clearance time is 0.2 seconds, and
from Table 42.1 the maximum body current is 350 mA.
Thus the maximum voltage which can be present on the fence is 4956 x 0.35 = 1735 V. This
is above the fence EPR of 2400 V and so is unacceptable.
In this case it has to be assumed that 100% of the public are affected as SSEN will not be
using figures for other percentages of human body resistance.
Appendix B, Table 4
PF
A Number of faults per annum on type of network at voltage level 180
B Number of automatically isolated sections (circuit breaker or fuse protected) 12000
on type of network at voltage level
C = A/B Probability of occurrence per annum on any one automatically isolated section 0.015
Appendix B, Table 5
PFB
D Probability of heart fibrillation (100 % affected) 1
Appendix B, Table 6
PE
E Length of time stood by fence 20 minutes 3.80 x 10 -5 per
annum
Page 58 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Appendix C, Figure 1
Page 59 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
Figure Appendix C. 1
The following descriptions give details of the individual sketches shown in Figure Appendix C.1.
Sketch 1 - extension of an existing SNE cable with a new CNE cable.
At the joint between the SNE cable and CNE cable the neutral and earth conductors of the SNE cable
shall be joined together and an earth rod installed. At the end of the CNE cable an earth rod shall be
connected to the CNE NEUTRAL conductor.
PME customers can be joined on the SNE cable although it is preferrable to install SNE services onto
the SNE cable.
Sketch 3 - extension of an existing SNE cable with a new CNE cable and connecting via a link box.
Where a CNE cable is to be laid from a new substation and connects onto an SNE cable fed via a link
box, the neutral and earth conductors of the SNE cable shall be joined together and an earth rod
installed.
PME customers can be joined on the SNE cable although it is preferrable to install SNE services onto
the SNE cable.
Sketch 6 extension of an existing CNE cable (already connected to an SNE cable) with a new SNE
cable
The neutral and earth conductors of the new SNE cable shall be joined together and an earth rod
installed. At the end of the SNE cable an earth rod shall be fitted to the SNE EARTH conductor.
PME customers cannot be joined onto the new SNE cable.
Page 60 of 61
Uncontrolled if Printed
Applies to
Earthing Systems, Basis of Design – Distribution Transmission
PR-NET-CAB-008
Design Standard
✓
Revision: 2.00 Classification: Internal Issue Date: December 2022 Review Date: December 2027
This connection is done using a link box. The neutral and earth conductors of the SNE cable shall be
joined together and an earth rod installed. At the end of the SNE cable an earth rod shall be fitted to
the SNE EARTH conductor.
PME customers cannot be joined on the SNE cable.
Where a particular application is not detailed in the examples a Design Deviation shall be submitted to
[email protected].
Page 61 of 61
Uncontrolled if Printed