abe inter 2 pdf-1
abe inter 2 pdf-1
UNIVERSITY
INSTITUTE TECHNOLOGY
Internship report
DECLARATION
I declare this report is an original work of my own and written based on the experience I have
gained from four months of internship practice. I assure you that the report contains the actual
events and facts that, I have observed and performed during the period of the internship program.
This is to certify that the internship report entitled Lega Arba Water Supply Project was prepared
by Abel Tadele under my guidance based on the regular reports that he had submitted.
I recommend this report to the faculty of Hydraulic and water resource engineering for
evaluation.
ACKNOWLEDGMENT
Firstly; I would like to thank all workers of the West Hararghe Zone Water Development and
Energy office. who involved me for four months in the internship period. Especially, I would like
to express my deepest gratitude to site engineer Mr. Dino (B, sc) for his sacrifice and great
support in sharing his knowledge relating the theoretical concept to practical real life.
Finally, I would like to give special thanks to my family and friends for their priceless advice and
different kinds of support.
Internship report
EXECUTIVE SUMMARY
This internship program was conducted on the Lega Arba Water Supply Project from July to
November 2023 G.C. Lega Arba Water Supply Project is found in Oromia Regional State West
Hararghe Zone Water Development and Energy office in Gubba Qoricha Woreda Lega Arba
Kebele. The overall objective of this project is to design and implement a sustainable water
supply system for the community of Lega Arba Kebele to improve the quantity, quality, and
level of service. The lack of potable and clean water within a short distance is the main problem
for the construction of the Water supply project in this Kebele, so the construction of this project
increases the consumption rate of pure water for drinking and other purposes. This internship
program was carried out by an integrated approach like interviewing, observation on site, focus
group discussion, and participating in activities with co-workers on physical work.
The Lega Arba water supply project has different components like the construction of
Reservoirs, Waterpoint construction, Trench excavation, and Pipeline installation. So, it
familiarizes the students with fieldwork and compares what they are learning theoretically with
practical activities.
This internship program gave me great benefits by enabling me to observe and participate in
practical activities and communicate with the organization, co-workers, and community.
Internship report
Table content
DECLARATION...............................................................................................................................................i
ADVISOR APPROVAL PAGE...........................................................................................................................i
ACKNOWLEDGMENT...................................................................................................................................ii
EXECUTIVE SUMMARY................................................................................................................................iii
Table content..............................................................................................................................................iv
List of figures...............................................................................................................................................1
Chapter 1 ; INTRODUCTION.........................................................................................................................2
1.1 Background of the Hosting Company................................................................................................2
1.2 Objective of the Company.................................................................................................................3
1.3 Its Main Product and Service.............................................................................................................3
1.4 The End Users and Customers of the Company’s Products and Services...........................................3
1.5 Overall organization workflow...........................................................................................................4
1.6 Project description.............................................................................................................................5
1.6.1 Background of the Project..........................................................................................................5
1.6.2 Location and Climate Condition of the project area....................................................................5
1.6.3 Statement of the problem............................................................................................................6
1.6.4 Objective of The Project.............................................................................................................6
1.6.5 Scope of the project....................................................................................................................6
Chapter 2 ; overall internship experience....................................................................................................7
2.1 How I get in to the company..............................................................................................................7
2.2 Section of the company I have been working....................................................................................7
2.3 The Work Flow In The Section...........................................................................................................7
2.4 The work task or work piece I have been executing..........................................................................8
2.4.1 Site clearance..............................................................................................................................9
2.4.2 Excavation..................................................................................................................................9
2.4.3 Filling and compacting.............................................................................................................10
2.4.4 Hard rock placing.....................................................................................................................10
2.4.5 Lean concrete............................................................................................................................11
2.4.6 Reinforcement bars placing......................................................................................................12
2.4.7 Casting of the base slab............................................................................................................13
Internship report
List of figures
1
Internship report
Chapter 1 ; INTRODUCTION
Clean drinking water is one of the basic needs of human beings. But millions, especially in
developing countries like Ethiopia, have low access to clean drinking water and sanitation,
leaving citizens exposed to water and water-related diseases. so the Lega Arba water supply
project is constructed by considering the problems of potable water in Gubba Qoricha Woreda,
lega Arba Kebele.
The project area is one of the rural Kebele with a shortage of fresh water for domestic use. In the
project area, safe water usage and sanitation facilities coverage are currently weak. According to
the Woreda health office, the major problems related to water and related diseases that frequently
occur in the study area are diarrheal disease, intestinal disease, typhoid fever, and trachoma
disease, which are directly related to the existing situation of lack of clean and adequate supply
of water.
The office is a public institution that performs the professional task of implementing the Oromia
regional government’s development endeavors in water resource utilization.
Vision: In the next 40 years, the office aims to provide a safe water supply to all the local
districts and eliminate waterborne diseases. The office seeks to become a competitive country
both in Africa and internationally by promoting quality-based practices and new technologies in
construction.
2
Internship report
for users. It wants to satisfy all sections of society in rural and urban areas by providing safe and
healthy water in an easily accessible place and by providing water in sufficient quantity and
quality.
Generally, the objectives of the Office are: to ensure continuity of the water supply for
consumers, to raise public awareness of the effective use of water resources with reliable
information, to carry out standardized studies, design and supervision activities of drinking water
to make the regional people beneficiary of potable to supply clean and safe water for drinking, to
reduce the burden on a woman in collecting water which involves traveling long distances and to
improve social well-being, enhance national economic performance, and ensure equitable
provision of adequate water and sanitation services to all users at affordable cost and on a
sustainable basis
1.4 The End Users and Customers of the Company’s Products and Services
The following are the main customers of this company
3
Internship report
Planning, Energy
Community Water supply and Water resource
monitoring and development
Participation sector sanitation sector magement sector
evaluation sector sector
Administration of
Water Quality and
Laboratories
Administration of
Machinery
4
Internship report
Source - from West Hararghe Zonal Water, Mineral & Energy Office project on Lega Arba water
supply project on 2023
6
Internship report
I have chosen the company because it has many years of experience in water supply service
construction and maintenance.
Then After I received the request paper from the HWRE engineering department. I sent it to the
project manager and he led me to the team leader of the construction work After the team leader
discussed it with the engineers in the company, he attached me to one of the site engineers
Finally, I started.
7
Internship report
Office engineer : the main responsibility of this staff is the preparation of weekly and monthly
reports of the activities on the project and reporting to the project manager and to head office.
Some of the things that should be included in the weekly and monthly reports are the expense of
the project, income gained on that week or month, profit gained. Some of the responsibilities of
the engineering service staff are:
Site Engineer:
Prepares daily labour output report.
Organizes the monthly reports to be sent to the Head office.
Schedules weekly or monthly work implementation.
Checks and reviews any sub-contract payments.
Quantifies any materials on request etc.
Forman: there are three kinds of Forman according to their job specification. They are
Construction Forman
Labourers Forman
The tasks of construction Forman are Checking the whole work process, quantifying
some materials making requests, and reporting any challenges of work procedures and their
execution, etc. The task of laborer Forman is to control laborers in the project.
During this time there are many tasks in which I participate in the site work with my advisor Mr.
Dino. Those are: By participating in work with the site engineer, Forman, and others by asking
questions and answering the questions which are not clear during site work. During the site visit
the following activities are done;
8
Internship report
Site cleaning
Excavation
Hard rock properly placing,
placement of reinforcement bar,
Casting of base slab
Pipe alignment
Trench excavation and pipe fitting.
The goal of site clearing is to create a construction site conducive to the project
In our project, according to the direction of the engineer, about 20 cm deep site clearing work
has been done
During site clearance, we removed The topsoil of the surface because it contains plants that can
damage the foundation and are not strong enough to support the building. Also, We Did not use
plant roots and soil uprooted from topsoil to fill holes created during site clearing because
thesoil will settle into the holes at different levels and cause extensive cracks in the concrete
above the site..
2.4.2 Excavation
Excavation for setting foundation or slabs is done to remove weak materials with less bearing
capacity and reach sustainable strata if any or to make space for the insertion of selected (better)
materials. The excavation includes an area for working space.
In our project, we encountered loose soil and highly weathered materials, so it was completely
removed by using backhoes and hand tools such as shovels. As instructed by the Engineer
the excavated depth is 1 m on the lower level and 1.7 m on the higher level
9
Internship report
Excavation procedures
Before commencing an excavation the following stage was conducted.
A survey was conducted to determine the depth and general area of the excavation
Obtained permission from the local authority
In our project, the depth of fill used was 35cm. an experienced mason has done the placing. The
hard core is well-rolled consolidated and blinded with gravel.
10
Internship report
In our project, we cast 50 mm thick Lean concrete over hard-core with Grade C-15 concrete with
a minimum cement 150kg/m3 mix ratio (1:3:6)
11
Internship report
When all of the reinforcement bars have been cut as per the required length and all of the bars
are tied with wire. Therefore, the remaining operation was placing the reinforcement bar
properly on the floor of lean concrete.
In our project the Bottom surface is reinforced with a 10mm bar at 15 c/c cm in both ways, the
top base surface is reinforced with a 10mm bar at 20cm c/c and the distance between the top and
bottom Reinforcement is 20cm
12
Internship report
A. Concrete mixing
The process of mixing cement, water, fine aggregate, and coarse aggregate in suitable proportion
is known as the mixing of concrete. This process should ensure uniform color, consistency, and
homogeneity of the concrete. Segregation should not take place during the process of mixing. On
our site, the mixing process is done by concrete mixer machine
B. Concrete filling
Concrete filling refers to the proper distribution of concrete in the structure. on our project
Casting 25 cm thick Base slab in Grade C-25 reinforced concrete with minimum cement
360kg/m3 and a 1:11/2:3 mix ratio
C. Concrete compaction
The objective of compaction is to achieve maximum density by removing air voids from the
concrete. We compact the concrete using a machine-like vibrator.
D. Leveling of concrete
After the concrete is placed and compacted concrete is leveled by using strait edge timber
E. Curing of concrete
Curing is a controlled process of keeping the newly laid concrete just enough to dry out without
shrinking and cracking or is the process through which the concrete becomes hard and strong.
13
Internship report
14
Internship report
15
Internship report
2.5 Procedures I have been using while performing the work tasks
From the suggestion of the host company supervisor, I work on the site visiting for a week. My
supervisor was the project execution team leader. So he attached me to one of the project site
engineers to experience on-site work with the engineer
I followed the following Procedures As a starting point for performing certain tasks
16
Internship report
17
Internship report
Internship plays an important role in applying practically what we have known about theoretical
knowledge. It helps also to develop practical experience and know-how in all water supply and
other Important project works and also acquire lots of skills
mixing of concrete,
placing of reinforcement,
site operation, solving problems, and so on.
orally theoretical knowledge can be obtained by asking and having discussions with workers of
the project. Such as
Site engineers
Skilled & unskilled Forman’s
Daily workers
avoiding judging and criticizing others rather have a reasonable discussion with
them
one should listen to his colleague's thoughts and express his ideas positively show
a willingness to listen to others during discussion
before communicating with others one must understand the willingness of the
others
avoid imposing others to accept your ideas because it leads to conflict
While communicating with others one must be open & honest in expressing ideas
19
Internship report
Understand and listen to the ideas of workers by openly discussing with them.
Making workers responsible for every operation, they do.
Punctuality
Confidence
Respect for work
Responsibility
Honesty
Integrity
Accountability
Impartiality
Transparency
Safety
20
Internship report
5.1. Conclusions
This internship program provides a bridge between theoretical and Practical life. During the past
months, I have been able to see different theoretical and practical aspects of water supply
projects. Different materials are used for both construction and water distribution system
Excavation of the proposed project is undertaken to build the foundation of the service reservoir
with the size of footing 1mx1m and backfill of the excavated surface is taken by compacting by
hand role to level the excavated ground surface.
The service reservoir is circular and has, a floor slab, wall, top flat slab, and structural
components, like an outlet, inlet, washout, air vessel valves, etc. Different types of pipe materials
are used for distribution systems and different materials are used for construction purposes.
21
Internship report
5.2. Recommendation
Based on the four-month stay in the company for the internship program, I would like to forward
the following recommendations:
During the time of excavation of the trench and foundation of the reservoir does not have
a soil test since it must experiment with soil tests.
Some local people disagree with site managers on their farmland. I advise; that the
company creates awareness among local people about the use of or the importance of the
project..
If there is a shortage of transportation services, I recommend; that the company increase
the number of services or change the
The society around the project area will need special advice to protect springs, reservoirs,
pipes, and others from damage.
22
Internship report
REFERENCE
23
Internship report
24