(Slickline) MPLT-logging Work Execution Plan
(Slickline) MPLT-logging Work Execution Plan
PLAN
FOR
INTRODUCTION................................................................................................................... 3
EXECUTION SUMMARY........................................................................................................ 4
Project Management..................................................................................................... 7
MPLT- LOGGING.............................................................................................................. 9
PRE-JOB PREPARATIONS................................................................................................... 14
PROJECT SCHEDULE.......................................................................................................... 15
CHANGE MANAGEMENT.................................................................................................... 15
Bell WellScience Wireline Logging Services caters to a diverse clientele within the
Oil and Gas industry, encompassing a wide range of critical operations such as
perforation, packer setting, pipe retrieval, back-off procedures, severing operations,
and an array of logging services including but not limited to Production Logging Tool
(PLT), Well Integrity Evaluation, Cement Bond Log, Gamma Ray (GR), Density
measurements, water flow assessments, depth determination utilizing the
Conductivity-Contrast Log (CCL), Elemental Electroscope, Neutron Logging,
Magnetic Resonance Logging, and Carbon Oxygen/Saturation Logging
as well as formation pressure
determination with high-resolution evaluation and interpretation. Our services
are instrumental in supporting Oil Mining Licensing (OML) platforms, both offshore,
in swamp regions, and on land, serving the oil and gas sector in Nigeria and beyond.
In this context, we have meticulously organized our services to align with the specific
requirements of NEPL for wireline logging and data interpretation pertaining to
the Well1 Intervention. Our Wireline Logging services adhere to the prescribed
scope of work as outlined in the Request to Bid (RTB). This comprehensive offering
includes our robust Quality Assurance and Quality Control (QA-QC) procedures,
which not only ensure the precision of our services but also bring significant
advantages in terms of data reliability and accuracy. Furthermore, we provide
insight into our meticulous work execution plan and well-defined work procedures,
demonstrating our commitment to delivering exceptional results.
• Project Management
• Provision of wireline unit (Slickline) and ancillary equipment.
• Provision of MPLT logging Tools.
• Mobilization and demobilization of equipment to and from the well site.
• Operation and maintenance of equipment.
• Data acquisition and interpretation.
• Reporting and documentation.
• Provision of experienced personnel’s (wireline operators, logging engineers
etc.).
• Health, Safety, Security, and Environmental Management Coordination
In the execution of this project, Bell WellScience will employ a global project delivery
strategy with a proven track record of effective project control, on-time delivery, smooth
start-up, and ongoing support. Our strategy revolves around meeting project objectives
and ensuring client satisfaction.
We adhere to a consistent methodology that forms the foundation for project success. To
implement this methodology, our team carefully selects and integrates suitable Bell
WellScience technologies to enhance productivity, streamline engineering tasks, and mitigate
common project risks. This approach ensures that we deliver outstanding results while
upholding the highest industry standards.
EXECUTION SUMMARY
The intention of this section is to provide Customer with a basic understanding of the
planned Project Execution Strategy and some of the processes and procedures BELL
WELLSCIENCE plans to follow. As the scope and requirements dictate, BELL
WELLSCIENCE may provide a more detailed insight to this Project Execution Plan
document after the Kick-off meeting.
1) Meet the objectives of the Wireline (Slickline), MPLT logging project while
minimizing execution risk.
2) Ensure on time delivery, predictability, and cost control, and
3) Timely wireline logging operation.
4) Safety & Environmental excellence.
5) Continuous performance improvement.
6) Optimizing productive time; and
7) Quality data.
The key strengths of BELL WELLSCIENCE Nigeria Execution Plan are summarized below:
1. The use of methods which are suitably validated, fit-for-purpose and based on
internationally recognized methods.
2. The use of a Quality Management System that strives to provide customer
satisfaction by ensuring, through its documented policies and procedures, that all
quality-related activity is clearly demonstrated, assessable and followed. We will
achieve this by:
3. Being innovative and providing added value to our product and/or service. Giving a
committed team effort.
4. Standardizing our processes.
5. Employing a detailed quality audit program that ensures corresponding quality feedback.
6. Utilizing a continuous improvement system.
7. The clever and extensive use of quality control and quality assurance to ensure
delivery that exceeds the industry benchmark.
8. Providing appropriate Safety Training to mitigate risks.
9. Review our Quality System to assist NEPL to achieve its principal objectives in
performance of the work.
Bell WellScience team are appropriately empowered to ensure these requirements
are met. All employees and contractors are familiar with the requirements of the
Quality Management System, the above objectives and process outcomes.
Project Management
BELL WELLSCIENCE will assign a dedicated Project Manager – Mr Annson Musa,
who will be responsible for ensuring the successful delivery of the Project. He will be
the single-point interface for any field project issues that may arise.
Shortly after award of the contract, the Project Manager will initiate a kick-off
meeting to review the total project scope, verify the project schedule and identify
any key issues that need to be addressed. Other key members from the BELL
WELLSCIENCE team will attend this meeting.
The Core Team personnel will be based at BELL WELLSCIENCE Nigeria Offices. This
team will produce (in conjunction with your engineering team) the functional design
data to be used for project execution. This team will also control the overall design
implementation to ensure consistency, and will modify, amend and add to the
design as needed.
Well control describes well pressure control on the surface and discusses how to
safely gain access to the wellbore. BELL WELLSCIENCE describes relevant well
divisions and stresses the importance of downhole data. It reviews common
applications of surface pressure control equipment and offers recommendations on
the selection and application of surface pressure control equipment. It concludes
with a discussion of the mitigation of surface fire and explosions hazards and offers
recommendations for downhole pressure control selection.
MPLT LOGGING
1 M/U the MPLT tool string on surface and function test/calibrate same on the weather deck.
2 Slide the tool string into the lubricator. Pick up the lubricator + tool string and M/U same
to the rest of the PCE stack. Pressure test the Q-test sub to 300psi/5min and
3,000psi/10min
3 RIH the MPLT tool string to xxm/RT and slow down the RIH speed to 10m/min.
4 Continue to RIH tool string at 10m/min while recording down pass from xxm/RT to xxm/RT
or 1m above the last recorded top of sediment. Label this down pass “Temperature
Log” and mark the Slickline wire.
5 Pick up the tool string at 10m/min and record shut in up pass from xxm/RT (or 1m above
the top sediment) to xxm/RT. The mark on the Slickline wire could be used determine
when the tool string is 1m above TOS.
6 Run back in hole with the tool string at 10m/min to xxm/RT or the mark on the cable and
record the shut-in down pass.
7 Repeat steps 5 and 6 to record shut-in passes at 20m/min, 30m/min and 40m/min
8 With the tool string at xxm/RT (or 1m above the top sediment), station for 10min to
record the static pressure.
9 Pick up the tool string from xxm/RT to xxm/RT, stopping at the various stations for the
recommended time duration till all the static pressure stations have been completed as per
table 2 below:
PRE-JOB PREPARATIONS
BELL WELLSCIENCE needs accurate and complete information prior to the start of
the job to perform their jobs safely and efficiently. Our Wireline (Slickline) field
engineers will collect specific data from customers at the time of the job request to
make appropriate equipment selections and provide the right tools and
equipment information pertinent to a safe work environment.
PROJECT SCHEDULE
The project team will produce a detailed project schedule for the kick-off meeting for your
review and agreement.
The BELL WELLSCIENCE Project Manager is the primary focal point for all formal
communications with the other parties outside of the BELL WELLSCIENCE project
team. Formal communication provides information that is considered as input or
direction required for or impacting performance of project work activities involving
scope and/or execution.
CHANGE MANAGEMENT
As part of the BELL WELLSCIENCE project management system, we identify and
record changes to the project. When changes are identified as scope changes,
BELL WELLSCIENCE and
Customer will approve the change before acting on the request. This ensures that
resources will not be used inappropriately. The change management tool assists
BELL WELLSCIENCE and Customer in the management of change, as it monitors the
approval process and documents all change details.
The BELL WELLSCIENCE project team will manage change based on the provisions
defined in the contract and this BELL WELLSCIENCE Project Execution Plan. The
objective is to ensure strict control of potential changes to project specifications,
standards, procedures, controlled design documents, materials, equipment,
execution plans, and commercial contracts.
The BELL WELLSCIENCE project team is committed to ensuring that all deliverables
are designed, procured, inspected, tested, and turned over to high and consistent
standards and comply with all relevant codes, standards, specifications, procedures
and regulations.
Quality Management Program
The objectives of the BELL WELLSCIENCE Quality Management Program (QMP) are
to ensure that work processes are well defined and documented and are carried out
efficiently and cost effectively.