3.2_Labour Productivity_Revised
3.2_Labour Productivity_Revised
Introduction
Labour productivity is an important concept in the construction industry that refers to the
amount of output or work that can be achieved by a worker or a group of workers in a given
amount of time. It is a crucial factor that determines the efficiency and profitability of
construction projects. Labour productivity can be affected by various factors such as the skills
and experience of the workers, the availability and quality of equipment and tools, the level of
organization and planning of the work, and the working conditions on the construction site. In
this introduction, we will explore the concept of labour productivity in construction in more
detail, examining its significance and how it can be improved to optimize construction projects.
How many hours per week did an average machine spend in each category?
Solution
Proportions of time determined as number of observations in each category divided by 500
Time in each category determined by multiplying proportion by total hours (40 hr.)
Category Proportion Hours per category
1) Being set up 75/500 = 0.15 0.15 x 40 = 6
2) Running 300/500 = 0.60 0.60 x 40 = 24
production
3) Machine idle 125/500 = 0.25 0.25 x 40 = 10
1.00 40
Example 2
A construction site manager conducted a work sampling study for a period of 50-hour
workweek and observed the activities of workers involved in formwork, reinforcement, and
concreting. The manager recorded the following observations:
Activities
Formwork Number of Reinforcement Number of Concreting Number of
observations observations observations
Plywood 188 Tying of 204 Setting up 54
transportation reinforcement concrete
pump
Formwork erection 288 Iron fabrication 304 Concrete 182
compaction
Giving or receiving 18 Iron material 24 Concrete 72
order transportation curing
Crane Operator 88 Giving or 94 Concrete 105
(Lifting of receiving order transportation
materials)
Shoring and 54 Crane operator 74 Giving or 45
Bracing receiving
order
Private Time 20 Cleaning 25 Crane 65
operator
Delay due to 40 Minor Cont. 65 Checking the 25
weather Work batch sheet
Delay due to crane 25 Walking bare 25 Performing 35
handed slump test
Waiting for 35 Attending 54 Pep talk to 65
material phone call labours
Walking bare hand 30 Waiting for 47 Walking bare 25
material or handed
Order
Waiting for next 35 Waiting for the 35 Waiting for 35
job next job RMC
Sitting, drinking, 25 Private time 20 Delay due to 30
and Smoking weather
Formwork Total 486 Delay due to 25 Concreting 738
weather Total
Delay due to 35
crane
Activities
Formwork Number of Reinforcement Number of Concreting Number of
observations observations observations
Sitting, 45
drinking, and
Smoking
Reinforcement 1076
Total
A) What is the percentage of non-productive activities for each task at the job site?
B) Calculate the labour utilization ratio (LUR) for each task and critically comment on the
labour-crew productivity for the job.
Assume that the number of activities observed is representative of the entire workweek and
that non-productive activities have the same duration as productive activities.
Solution
Step 1: Categorizing the activity type for Formwork, Reinforcement and Concreting task:
Activities
Formwork Category Reinforcement Category Concreting Category
Plywood Essential Tying of Effective/ Setting up Essential
transportation contributory reinforcement Productive concrete pump contributory
(188)
Formwork Effective/ Iron Essential Concrete Effective/
erection(288) Productive fabrication contributory compaction Productive
Giving or Essential Iron material Essential Concrete curing Essential
receiving contributory transportation contributory contributory
order(18)
Crane Essential Giving or Essential Concrete Essential
Operator contributory receiving contributory transportation contributory
(Lifting of order
materials)(88)
Shoring and Essential Crane operator Essential Giving or Essential
Bracing(54) contributory contributory receiving order contributory
Private Non- Cleaning Essential Crane operator Essential
Time(20) Productive/ contributory contributory
Idle
Delay due to Non- Minor Cont. Essential Checking the Essential
weather(40) Productive/ Work contributory batch sheet contributory
Idle
Delay due to Non- Walking bare Non- Performing Essential
crane(25) Productive/ handed Productive/ slump test contributory
Idle Idle
Waiting for Non- Attending Non- Pep talk to Essential
material(35) Productive/ phone call Productive/ labours contributory
Idle Idle
Walking bare Non- Waiting for Non- Walking bare Non-
hand(30) Productive/ material or Productive/ handed Productive/
Idle Order Idle Idle
Activities
Formwork Category Reinforcement Category Concreting Category
Waiting for Non- Waiting for Non- Waiting for RMC Non-
next job(35) Productive/ the next job Productive/ Productive/
Idle Idle Idle
Sitting, Non- Private time Non- Delay due to Non-
drinking, and Productive/ Productive/ weather Productive/
Smoking(25) Idle Idle Idle
Delay due to Non-
weather Productive/
Idle
Delay due to Non-
crane Productive/
Idle
Sitting, Non-
drinking, and Productive/
Smoking Idle
Step 2: Work Sampling Analysis (adding the observations category wise and finding
proportion and calculating LUR)
1
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 + 4 𝑒𝑠𝑠𝑒𝑛𝑡𝑖𝑎𝑙 𝑐𝑜𝑛𝑡𝑟𝑖𝑏𝑢𝑡𝑜𝑟𝑦
𝐿𝑈𝑅 (%) =
𝑡𝑜𝑡𝑎𝑙 𝑜𝑏𝑠𝑒𝑟𝑣𝑎𝑡𝑖𝑜𝑛𝑠
Activities Category Sum of observations Proportion LUR (%)
(%)
Overall, at construction project, there is a need to improve the labour productivity. To improve
the productivity, a detailed analysis of the work activities should be done to identify the reasons
for the low utilization rate. Possible reasons could be ineffective work practices, inadequate
training, or inefficient work processes. Once the causes are identified, appropriate measures
can be taken to address them, such as providing additional training to the workers,
implementing better work processes, or improving the availability of resources.
Visualizing activity productivity and production
performance
The matrix above illustrates the relationship between productivity and production with respect
to cost and time. It consists of four quadrants, with productivity represented on the X-axis and
production on the Y-axis. At the center, we have the planned productivity and planned
production. When actual productivity exceeds the planned productivity, we move towards the
positive X-axis; similarly, if actual production surpasses planned production, we move towards
the positive Y-axis. For any activity, measuring productivity and production can place it in any
of the four quadrants, at the origin, or along the boundaries of the matrix.
Problem: Based on the given project requirement analyse the effect of productivity and
production on cost and time
Project requirement = 1000 electricity poles to be installed in 50 days
Estimated productivity = 2 poles/crew-day
Cost of labour = 2500/crew-day
1) What is planned/required productivity and production per day?
2) What is total crew-day required to complete the task?
3) What is the total labour cost (Rs) required as per estimated productivity?
4) Calculate actual productivity based on the scenario mentioned below
Scenario A: Actual No. of poles installed at site = 20; No. of crew =10
Scenario B: Actual No. of poles installed at site = 22; No. of crew =10
Scenario C: Actual No. of poles installed at site = 25; No. of crew =15
Also calculate total days, total crew-days and labour cost required for all the given
scenario. Based on the above calculations mention which quadrant does the scenario
productivity and production belongs to?
Solution:
Scenario A: Origin (Exactly matches with the requirement of planned productivity and
production of a project)
Scenario B: Quadrant I
Scenario C: Quadrant II
Work Study
Whilst the study and measurement of work has been considered by many, it was Fredrick
Winslow Taylor who is considered the founder of the subject. He broke work activities into
discrete elements, timing them with a stopwatch many times to achieve a statistical average.
He was the first person to apply a scientific approach to the subject. Frank Gilbreth approached
the problem from a different angle by asking the question: ‘Is there a better way?’ He studied
the movements of bricklayers to arrive at what is considered the forerunner of method study.
The application of work study on construction projects is more difficult due to uncertainties
such as the weather, labour turnover and unpredictable problems associated with ground works.
Further, as more work has been sub-contracted, much of the onus for carrying out work study
falls on these organisations which may not be large enough to sustain the added overhead on
what for them is a short-term contract. The main contractor is more likely to use method study
to improve productivity especially where many trades have to be co-ordinated.
The object of work study is to assist management in obtaining the optimum use of human, plant
and material resources that are available to an organisation for the accomplishment of the work.
It has three aspects:
3. To evaluate the time and effort required to carry out specific tasks.
Work study is divided into two distinct sections: method study and work measurement.
However, they are interrelated, as illustrated in Figure 1, which elaborates on the main
elements of carrying out either a method study or conducting a work measurement exercise.
The systematic recording and critical examination of the factors and resources involved in
existing and proposed ways of doing work, as a means of developing and applying easier and
more effective methods, and reducing costs.
The application of techniques designed to establish the time for a qualified worker to carry out
a specified job at a defined level of performance.
A worker who has acquired the skill, knowledge, and other attributes to carry out the work at
hand to satisfactory standards of safety.
The engineer as per his experience has to assess the rate at which the operative(s) are working
against a standard norm. This is referred to as rating R
The observed times (OT) required to complete the task need to be recorded. These OT must be
normalized as if the activities recorded and timed were carried out at the standard rating of 100.
This is referred to as the basic time (BT)
In this case the standard rating is the norm of 100. So an observed time of 0.87 minutes given
an observed rating of 95 gives a basic time of 0.83 minutes. In other words, if an operative is
working below par, the basic time will be lower and if working harder than the norm, the basic
time will be higher.
In case of single operator the observed time is as recorded, whereas in the cumulatively timed
study, observed time is calculated based on the number of operatives working on any activity.
For example, the four operatives A, B, C and D commence fetching their tools, etc. at 08.49.5
and complete at 08.51, a total of 1.5 minutes, but since there are four of them, the total observed
time for that activity is 6 minutes and with an observed rating of 90, the total basic time is 5.4
minutes.
Relaxation factors and relaxation times
It is unrealistic to expect operatives to work without a break and equally to ignore the effort
and posture required to carry out the task and the energy expended. Relaxation factors and
times are applied from various categories such as energy output, posture, motions, personal
needs, and thermal and atmospheric conditions. Some of these can be considerable and wide
ranging. For example, energy output can be as little as less than 5 percent for sedentary work
to 50 per cent for very heavy work; posture can vary between 0 and 10 per cent; motions up to
15 per cent when working in very confined conditions, extremes of temperature and very dusty
conditions (up to 20 per cent). Personal needs such as going to the toilet, having a cup of tea,
etc. is added to every activity, as it is not practical to isolate this to a specific element. This is
8 per cent for a man and 10 per cent for a woman. In construction, the total of these can be in
excess of 50 per cent.
Activity sampling
Activity Sampling is concerned with establishing the frequency at which operatives are
working. It does not measure the effectiveness or efficiency of the work being carried out. It is
ideal for the manager to obtain a feel for what is happening in the workplace, thereby giving
an indication of the overall health of the operation. The method can also be used for establishing
the usage of rooms and plant.
The process is relatively simple. The observer travels the whole area of the workplace and
records activity, or the lack of it, ensuring that the same person is not recorded twice. This is
known as the field count. It is important to travel the workplace several times, at random and
in different directions. The frequency and randomness determine the accuracy of the work. For
example, if sampling room use, looking at the use of classrooms only at the time between
lessons would clearly give a false reading about their usage. When taking an activity sample
of operatives, whilst it is not expected to count and observe everybody working on the site, it
is usual to have seen at least 75 per cent of those who should be in place, otherwise the
reliability of the study becomes suspect.
The observer counts the number of operatives that are active and those classed as non-active.
Active Operatives:
Physically engaged in carrying out their trade or activity that is related to it.
Assisting others doing work such as holding the end of a timber whilst another joiner
is cutting it.
Driving or operating of a vehicle or machine, or assisting in it such as acting as a
banksman to a crane or excavator.
Carrying materials from one place to another or moving a load.
Giving or receiving instructions.
Watching over or standing by equipment or machines for safety or control reasons. The
plant may be wholly or part automatic but the operative has to be there in case human
intervention is required.
As can be seen from these descriptions it takes no account whether the work being carried out
is the most effective or efficient way of carrying out the task.
Inactive Operatives:
Waiting for others to complete an operation
Waiting for materials to arrive
Waiting for instructions to be given
Standing or travelling with for no apparent productive reason
Riding on vehicles when not required.
The count is conducted using two counters, one for the total number observed and the other for
those classed as active. Active percentage is expressed as a percentage of those observed as
active as against the total number observed. During the sampling process, it may be observed
that the number of people present increases as individuals arrive late to the site. For example,
the number present may be higher after lunch break.
Calculate:
1. Average percentage of active workers throughout the day
2. Plot the graph of activity during the working day (with time along the X-axis and %
active along the Y-axis). Comment on the trend of the graph.
3. Discuss potential reasons for the variations in worker activity percentages throughout
the day
4. Identify the time period with the highest percentage of active worker
5. Propose two strategies to improve worker productivity based on the observed data
Problem 2: Solution
Trend analysis: For most people at work gradually build up self-motivation as morning
progresses, but as lunch-time approaches begin to turn their mind to the break. After lunch
there is a rapid increase to one’s peak followed by a gradual decline to the end of working day.
Time Study
Time study is a technique used to measure the time it takes for a worker to complete a
specific task or activity. The goal is to identify the most efficient way to perform the task
while minimizing wasted time and effort.
Fig. Before and After implementing Time Study for brickwork task
Calculating Labour Productivity
The simplest way for calculating labour productivity is to divide the output by the input.
The output is the job done by the labour, such as shuttering; rebar cutting-bending
work, concrete pouring work, etc. The following image shows the labour productivity
equation –
Excavation Work
The output of the excavation works is the soil excavation and its disposal. The unit of work
is cubic meters (cum). The following image shows the labour productivity equation for
excavation work.
Excavation Work Labour Productivity Calculation
02. Labour Productivity for Reinforcement Works
Reinforcement Works
The reinforcement works include several activities such as-
Rebar selection and transportation from store yard to the steelyard
Rebar straightening
Marking & cutting
Bending in the desired shape
Transporting to the worksite
Placing & fixing in the member (footing, beam, column, slab, etc.)
A fitter (bar binder), helper and unskilled complete the rebar job. The labour productivity
is calculated as per the rebar fixing, as it is the last activity for the rebar work. The rebar
work productivity is in kg per man-day. The following image shows the labour
productivity equation for rebar work.
Rebar Work Labour Productivity Calculation
For, large construction projects where a separate team cuts and bends the bar and a
different team fixes the bar, the rebar work productivity for cutting-bending and fixing is
calculated.
However, the diameter of the rebar plays an important role in defining labour productivity.
The higher diameter bars (>20mm dia.) yield more labour productivity than the lower
diameter bars (<20 mm dia.).
03. Labour Productivity for Shuttering Works
Shuttering Work
The shuttering work is a collection of multiple activities like-
Board making and re-making
Transporting the shuttering material at the work site
Staging for the superstructure shuttering jobs
Fixing of shuttering in place
Applying the supports and props to the shuttering fixed
The following image shows the labour productivity equation for shuttering work.
Concreting Work
A team of masons, helpers and unskilled labours complete the concreting work. The
activities performed for the entire work are-
The concrete mixing in batching plant and transportation by transit mixer significantly
improves labour productivity. On the other hand, the Capex requirement is also higher.
According to the research paper “A Study on Construction Labour
productivity Parameters in India” developed by ‘K Dasari, and Rao Rameshwara C B’,
The standard labour attributes and their constants for 1, cum of RCC in building
construction up to plinth level as per IS7272, Telangana State Building Data (TS), and
CPWD are as follows –
Standard Labour Attributes & Their Constants
How to improve labour productivity in construction?
Planning and ensuring the availability of the right tools for the work, particularly in this digital
era.
Facilitation of work with construction equipment like the crane, bar cutting machine, bar
bending machine, and wheelbarrow for concrete transportation.
Ensure the drawings are clear before handing them to the site workers. Discuss the working
methodology with the carpenters, fitters and masons to reinforce the correct procedure. The
methodology discussion reduces rework.
Develop a safety culture at the site. The labours should have information on occupational
hazards. The safety culture motivates the labour to focus on the work.
Supervisors should behave impartially with the workers. The implementation of fair working
culture should prevail.
Time and motion study is a tool to identify the unnecessary movements by workers. It helps in
reducing fatigue and timely completion of the job.
Enhance the work site facility. General and job-specific lighting at night, rain protection, etc.
should be kept handy.
Recognize the good performers and make them role models for other workers. Also, encourage
the workers to take ownership of their work.
Reward the timely completion of work. It enhances labour productivity. Similarly, punish the
non-performer at the right time.
No of labour days required = No of hours / Working hours/ day = 5000/8 = 625 labour days
Amount payable = No of labour days * wage/day =625*800= Rs 5,00,000
Now let us assume there are five 10 hours days a week i.e. overtime of 2 working hours/day
No of labour days required by 1 labour to complete the whole work without any loss in
productivity
= No of hours / working hours per day = 5000/10 = 500 labour days
However, there will be impact on their efficiency.
Below mentioned table shares the sensitivity analysis with increased overtime and number of
week of extended overtime (OT).