Schematic (Submission of Work Programme)

Uploaded by

Toh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views1 page

Schematic (Submission of Work Programme)

Uploaded by

Toh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start

December 2020 Finish Predecessors January 2021 February 2021


Mode 20/12 27/12 3/1 10/1 17/1 24/1 31/1 7/2 14/2 21
0 Contract Administration 35 days Mon 4/1/21 Sun 7/2/21
1 Construction Planning Stage 35 days Mon 4/1/21 Sun 7/2/21
2 Work Programme Submission 14 days Mon 4/1/21 Sun 17/1/21
3 Receipt of LoA by Contractor 0 days Mon 4/1/21 Mon 4/1/21 4/1
4 Preparation of Work Programme by Contractor 14 days Mon 4/1/21 Sun 17/1/21 3
5 Preparation of Construction Methods by Contractor 14 days Mon 4/1/21 Sun 17/1/21 3
6 Submission to PD 0 days Sun 17/1/21 Sun 17/1/21 4,5 17/1
7 Work Programme Processing by PD 21 days Mon 18/1/21 Sun 7/2/21
8 Process and Approve 21 days Mon 18/1/21 Sun 7/2/21 6
9 Process and Reject 21 days Mon 18/1/21 Sun 7/2/21 6
10 Process and Request Further Info 21 days Mon 18/1/21 Sun 7/2/21 6
11 Approval from PD 0 days Sun 7/2/21 Sun 7/2/21 8,9,10 7/2

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: Contract Administration Split External Tasks Inactive Summary Manual Summary Progress
Date: Mon 14/12/20
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only