CEDg12271-Settlement Pile Groups
CEDg12271-Settlement Pile Groups
A DISSERTATION
Submitted In partial fulfilment of the
requirements for the award of the degree
of
MASTER OF TECHNOLOGY
in
CIVIL ENGINEERING
(With Specialization in Gsotechnical Engineering)
By
VENKATA RAMI REDDY CHALLA
/~ear►i ari
se
Alt Z.Giavi
an.2~~-~2•vs
! ~
I hereby declare that the work presented in this dissertation report entitled
"ESTIMATION OF SETTLEMENT OF PILE GROUPS" submitted in the partial
fulfillment of the requirement for award of the degree of Master of Technology in Civil
Engineering with the specialization in Geotechnical Engineering of the Indian Institute
of Technology Roorkee, Roorkee, is an authentic record of my own work carried out
under the supervision of Dr. G. Ramasamy, Professor, Department of Civil
Engineering, Indian Institute of Technology Roorkee, Roorkee.
I have not submitted the matter embodied in this dissertation for award of any
other degree or diploma.
CERTIFICATE
This is to certify that the above statement made by the candidate is correct to the
best of my knowledge and belief.
Dr. G. Ramasamy
Professor,
Department of Civil Engineering,
Indian Institute of Technology Roorkee,
Roorkee — 247667, India.
i
ACKNOWLEDGEMENT
Words fail to express my deep sense of gratitude to my parents for their blessing
and support during my studies.
I also thank all my friends for their direct or indirect support in completing my
dissertation.
Place: Roorkee
Dated: 30th June 2005
cLa
(Venkata Rami Re dy Challa)
ii
ABSTRACT
equivalent raft method, which is empirical in kind. On the other hand, the literature
provides a few sophisticated methods which involve inputting too many soil parameters
which cannot be reliably estimated. Therefore, an attempt has been made to develop a
simple but a rational method of estimating settlement of pile groups based on load
transfer approach as adopted by Hazarika & Ramasamy (2000) for single piles and
equivalent pier method given by Randolph (1994). The method takes into account layered
soil system and makes use of input parameters obtained from usually conducted field
tests such as standard penetration test (SPT) and static cone penetration test (SCPT) in
The method has been computerized and a user friendly program has been
developed using C++. Using the program, settlement of pile groups has been estimated
for a number of cases and parametric studies have been carried out to bring out the effect
of type of soil and number of piles in a group. Further a few reported case histories have
been compiled and a comparison of predicted and observed settlements has been made.
iii
CONTENTS
CADIDATE'S DECLARATION i
ACKNOWLEDGEMENT ii
ABSTRACT iii
CONTENTS iv
LIST OF TABLES vi
1. INTRODUCTION 1
1.0 General 1
1.1 Present work 2
1.3 Organization of dissertation 2
2. LITERATURE REVIEW 3
2.0 Introduction 3
2.1 Single pile 3
2.1.1 Elastic continuum method 3
2.1.2 Finite element Analysis 4
2.1.3 Load transfer method 4
2.2 Pile Groups 5
2.2.1 Equivalent raft method 5
2.2.2 Empirical methods 13
2.2.3 Theoretical methods 14
2.2.4 Load test on pile groups 18
2.2.5 Equivalent pier method 18
3.ESTIMATION OF SETTLEMENT OF PILE GROUPS 21
PROPOSED METHOD
3.0 Introduction 21
3.1 Details of the method 21
3.1.1 Development of Q — z curve 21
3.1.2 Development off— z curve 22
3.2 Procedure 24
VA
4. RESULTS AND DISCUSSIONS 26
4.0 General 26
4.1 Example problem 26
4.2 Case studies 30
4.3 Parametric study 36
4.3.1 Pile group in cohesive soil 36
4.3.2 Pile group in cohesionless soil 39
5. CONCLUSIONS 42
REFERENCES 43
FIGURES 47
V
LIST OF TABLES
No. Description Page No.
vi
CHAPTER 1
INTRODUCTION
1.0 General
There exist many procedures for estimating the settlement behavior of pile
groups, ranging from simple closed form solutions to sophisticated nonlinear finite
element analyses. The mechanism of load transfer in pile groups involves a complex
system interaction of piles, pile cap, and surrounding soil. The process is affected by
many factors such as soil properties, pile group geometry, pile — soil interaction and
interaction between different elements in the group. Due to the difficulty in quantifying
these factors, no method is capable of accounting their effects on the pile group
settlements,
Traditionally, the settlement of a pile group has been estimated by considering an
"equivalent raft". Equivalent raft is considered at two-third depth in the case of friction
piles or at the end of pile group if the piles are end bearing piles.
In most of the available empirical methods, the pile group settlement is related to
the settlement of a single pile, similar to one of those in the group.
Equivalent pier method has been developed as an alternative to the equivalent raft
approach considering the region of soil in which the piles are embedded as an equivalent
continuum, effectively replacing the pile group. The representation of a pile group by an
equivalent pier provides a useful, practical tool for estimating the settlement behavior of
pile groups. The load — settlement response of the equivalent pier can be calculated as for
a single pile. Naturally, the equivalent pier approach gives an estimation of only the
average settlement of the pile group.
The load — settlement behavior of pile group for a pile — soil system can be
obtained from a field load test on pile group, but it is very expensive, time consuming and
that data is useful only for that soil conditions. Because of this, field load tests on group
of piles are not generally carried out except in major projects. Alternatively, one among
the several empirical methods or analytical methods available in the literature are used
for the estimation of load — settlement relationship of the pile groups.
The design load on an axially loaded pile group depends on settlement criteria
rather than bearing capacity criteria. Therefore, estimation of a load — settlement curve
for a given pile — soil system is very important to design pile foundations.
2
CHAPTER 2
LITERATURE REVIEW
2.0 Introduction
Generally, field pile load tests are conducted to get the load — settlement response
of single piles under axial loads, and these results are extrapolated to estimate the
settlement of pile groups. However load tests are expensive, time consuming , difficult to
conduct, and also the results pertain to only the particular pile — soil system as it exist at
the time of test. The settlement calculated from the pile load test is immediate settlement
only, but in case of cohesive soils the settlements are primarily from consolidation of
soils which takes place over a long period of time. So, pile load tests do not consider the
effect of consolidation in the case of cohesive soils. Because of this, generally any one of
the available analytical methods are used for the estimation of load — settlement curves
for the pile groups under axial loading.
This chapter briefly discusses some of the available methods on the estimation of
load — settlement behavior of piles and pile groups.
4
from instrumented pile load tests (Coyle and Reese, 1966; Coyle and Sulaiman, 1967). It
is also possible to generate them theoretically, based on geotechnical properties of soil
deposit (Vijayvergiya, 1977; Kraft et al., 1981; Hazarika and Ramasamy, 2000;) solution
requires the pre — determination of load transfer curves for a particular pile — soil system,
after which an iterative procedure is followed to obtain pile response for a particular
load applied at the pile head.
Recently, this method has gained more popularity because of its adaptability to a
wide variety of pile — soil situations which are normally encountered in practice and also
it requires input of geotechnical parameters which can be reliably obtained from routine
in — situ and laboratory tests.
Limitations
In using the load transfer curves, it is inherently assumed that the movement of
the pile at any point is related only to shear stress at that point and is independent of the
stresses elsewhere on the pile. Thus, no proper account is taken of the continuity of the
soil mass. Because of the disregard to the continuity of the soil mass, this method is
limited to the settlement analysis of single pile.
5
A) Pile group settlement in cohesive soils
According to Skempton and Bjerrum (1957), the total settlement (S) of a pile
group in cohesive soil is the sum of initial elastic settlement and consolidation
settlement. Hence the total settlement is given by following equation
S = S; + S, + Ss (2.1)
Where, S = Total settlement of a pile group
Si = Initial settlement of pile group
S, = Primary consolidation settlement
S, = Secondary consolidation settlement
Case 1: For flexible pile groups
A) Estimation of Elastic Settlement (Si):
Initial elastic settlement takes place immediately after load application and it
varies linearly with the magnitude of load applied.
Initial elastic settlement can be estimated by using the method proposed by
Steinbrenner (1934). According to Steinbrenner (1934), initial settlement for flexible pile
group at the centre of loaded area is obtained by the following expression
(Si) surface = ~p 2B
Si = µd (Si) surface
M Ip (2.2)
(2.3)
0
Table: 2.1 Steinbrenner's influence factor (I.S:8009 part I)
Flexible foundation (J r,)
Shape of foundation Rigid foundations (Ii,)
Centre Comer Average
Circle 1.00 0.64 0.85 0.86
Square 1.12 0.56 0.95 0.82
Rectangle
L/B = 1.5 1.36 0.68 1.20 1.06
L/B = 2 1.52 0.76 1.30 1.20
L/B = 5 2.10 1.05 1.83 1.70
L/B = 10 2.52 1.26 2.25 2.10
L/B = 100 3.38 1.69 2.96 3.40
Table: 2.2 Empirical relationship between undrained deformation modulus (E„) and
undrained shear strength (S„) of soils given by Skempton and Bjerrum (1957)
S.No Type of clay Empirical relationship
I.
Under and Normally consolidated soils E„ = 500 S
2.
Firm to Stiff clays (O.C.R. <2) E„ = 1000 S~
3.
Very stiff clays (O.C.R. > 8) E = 1500 S
my = (2.4)
}
Saed = µd my OP AH (2.5)
(Sc)field = Jig Seed (2.6)
Where, el = void ratio corresponding to effective overburden pressure p,
7
e2 = void ratio corresponding to effective overburden pressure plus pressure
increment due to net foundation pressure ( i.e. corresponding to pressure
(pr - Ap))
m„ = Coefficient of volume change
Sced = odeometer settlement for each soil layer at the centre of loaded area
4p = Average effective vertical stress at the centre of loaded area on the soil layer
due to net foundation pressure (q„) at the base of equivalent raft. This can be
obtained by assuming spread of load at 2V: 1 H below base of equivalent raft
level.
AH = Thickness of each layer
(S,)reld = Field value of primary consolidation settlement
µg = Geological factor, which can be taken from the curve derived by skempton
C` g, /
= (f togiolt) _ Ae, (2.12)
)
login ( 1
l ~l
tp = Time required for the completion of primary consolidation
t, = Service life of proposed structure or any other desired period (measured after
application of structural load)
9
Aes =eS2 —eg,
Here both void ratios es i and e,2 are taken after completion of primary consolidation.
Where the pile group is surmounted by a rigid pile cap or if the pile group
supports a rigid superstructure, the pile group can be regarded as being equivalent to a
rigid block foundation having a uniform settlement. In this case the settlement is obtained
by following expression
Under identical conditions, generally the value of rigidity factor is taken as 0.80.
However the rigidity factor is not considered for secondary consolidation settlement.
S= C i xC 2 xApx Z f= x AZ (2.14)
o Ed
c2 =1+0.2xlog,o ` (2.16)
o. t
where, t = time in years
Ctid = Static cone resistance
B = Width of loaded area
10
ci = Depth correction factor
c2 = Creep factor (secondary time effect factor)
Ed = Deformation modulus
AZ = Thickness of soil layer
1, = Schmertmann's vertical strain influence factor (Fig: 2.3)
M = A coefficient suggested by Schmertmann (1970). The values of M are shown
in Table: 2.4
Table: 2.4 Value of coefficient 'M' for obtaining deformation modulus proposed by
Schmertmann (1970)
S.No Description of soil Value of M
'Cable: 2.5 Approximate relationship between static cone resistance (q3 and standard
penetration value (N) given by Peck et al. (1974)
Hence, Pd
C = 1.5 k (2.18)
0
values are assigned to different layers, and then computation is done for each layer. The
sum of settlement for all these layers will be the estimated value of settlement for pile
group.
The settlement predicted by De — Beer and Marten's are regarded as somewhat on
higher side. Meyerhof (1965) recommended that the allowable bearing pressures
computed from De — Beer and Marten's method should be increased by 50% for the same
computed settlement this proposal corresponds to assuming that
C = 1.9 Pkd
0
(2.19)
12
D) Pile group settlement in/on rock
Pile group settlement may be important in this case of piles are heavily loaded. If
piles are well seated in rock mass then the total settlement is obtained by following
expression.
S = SJ-+ Si (2.20)
Here,
+2 L
AP (2.21)
n
Limitations
Equivalent raft method, gives higher values of settlements of the pile groups than
actual field observed values. Load — settlement behavior of pile groups predicted by this
method are linear, where as actual behavior is non — linear.
Most of the empirical methods involve estimating the settlement of a single pile
and extrapolating this for calculation of the group settlement. Among the empirical
methods, those given by Skempton (1953) and Meyerhof (1959) are more popular among
all. These empirical methods are applicable to cohesionless soils only.
13
A) Skempton's method
, _ (SA
I
(222)
S B,
According to I.S.8009 part 11, this formula is applicable to friction piles in cohesionless
soils only.
B) Meyerhof's method
Meyerhof (1959) expressed the settlement ratio for square pile groups driven in sand as
S, _
( z (2.23)
S. Il+~~
l r 1}
Limitations
These methods are not applicable to cohesive soils. Empirical methods are not
Analytical methods based on the elastic theory have been employed for settlement
analysis of pile groups with some success. These analyses are extensions of the methods
14
for single piles. Basic approach in most of these methods is to estimate the group
settlement ratio of the pile group — soil system defined as
Other popular approach based on elastic theory is to estimate the influence factors
for all piles in the group and superimposing these factors to get the settlement of pile
group settlement. The interaction factor (a) between two piles i and j in the pile group is
defined as
Some of the methods for estimating pile group settlement based on elastic
continuum approach are briefly described in the following section.
15
The general methodology followed in methods based on interaction factor
approach is as follows.
1.Interaction factor (a) between piles i and j are calculated using either design charts or
analytical solutions.
2. For a group of piles, the interaction factors may be superposed to develop e a
relationship as given by Eq (2.24) for settlement of any pile I (w;), in the group.
w,i = w1 (2.24)
Where,
w, = settlement of single pile under unit head load
Pj = load at head on pile j
= interaction factor between pile I and pile j
(for i j, a = 1.0)
n = total number of piles in the group
3. For equilibrium,
Equations may be written for all piles in the group giving n displacement equations.
The (n+l) equations thus obtained from Eq.2.24 and Eq.2.25 may be solved for two
simple conditions
• Equal load on all piles, corresponding to a loading over a flexible pile cap
• Equal settlement of all piles, corresponding to a perfectly rigid cap on the piles
16
ratio (l /R,,) and number of piles (np) when plotted to logarithmic scale was found to be a
straight line for a particular slenderness ratio (1/ro). Here p is the inhomogeneity factor, I
is length of pile and ro is the radius of pile. The rigid pile group settlement ratio for a pile
group having any number of piles can be estimated from the slope of this straight line,
which is obtained from the formula developed for group settlement ratio of 2x2 rigid
square pile groups(RS,4) using load transfer curve method. The pile group settlement ratio
for 2x2 symmetric rigid pile groups can be expressed as
2zrpl + 4
(2.26)
ro { 1-v:
Rs,4 =
2npl + 4
rocI (1-vs)C,
1= length of pile
v5 = soil Poisson's ratio
? i = t; + 2 In (qn/s) + In (rn,/ 2s) (2.29)
17
2.2.4 Load Tests on Pile Groups
Load testing of a pile group is considered the most reliable and acceptable method
of obtaining load — settlement relationship of a pile group because it is the in — situ test.
These involve applying a series of loads on the pile cap and noting the corresponding
settlements. Loads are usually applied by some reaction mechanism, and settlements are
measured by dial gauges.
Limitations
Load testing is very difficult to conduct, highly expensive and time consuming.
Further the load — settlement behavior obtained from a particular load test is applicable
only for the pile — soil conditions that exist at the time of test. Hence load testing is rarely
used (only in major projects) for estimating the load — settlement relationship of pile
groups.
18
the pile shaft and at the base. Load transfer functions for shaft and base are expressed as
below
w() (2.32)
K,, f.
w(z)
9= 1 w(z) (2.33)
Kb, qn
2 AR
Dey (2.34)
Jr
19
For a square group of n piles with diameter D, at spacing s, and an embedded
length 1, the validity of the equivalent pier methods depends on a parameter defined by
Randolph and Clancy (1993), the overall aspect ratio R, given by
(in-1+D
R= (2.36)
Randolph and Clancy (1993) showed that the equivalent pier approach was
suitable for R less than 4 and certainly for value less than 2.
Limitations
This method may not be applicable if the overall aspect ratio is greater than 4 and
the spacing of piles in a group is not uniform. Settlement of pile group depends on the
properties of subsoil strata on which it is bearing, but in this method the soil properties up
to pile tip only are considered.
20
CHAPTER 3
ESTIMATION OF SETTLEMENT OF PILE GROUPS -
PROPOSED METHOD
3.0 Introduction
A new method is proposed here based on Hazarika and Ramasamy (2000) method
and equivalent pier method. Some modifications have been made to these two methods
and adopted here, In this method, pile group is converted into an equivalent pier and then
the analysis of pile group is carried out adopting Hazarika and Ramasamy (2000)
method. However, developments of q — z curve and f— z relationships are different from
the Hazarika and Ramasamy (2000) method.
21
3.1.2 Development of f — z curve
The f — z curve is assumed to be same as that of single pile given in Hazarika and
Ramasamy method (2000). The normalized f-z curve given by Vijayvergiya (1977) is
shown in Fig: 3.2. The unit shaft resistance `f' mobilized at any shaft movement `z' is
expressed as a function of `fmax ', the maximum shaft resistance by the following non-
linear relationship:
.1= .. 2 2. (3.1)
Z.
Where z, = critical movement of the pile segment at which fm.is mobilized, and z:Szs
For sands the load transfer function is assumed to remain constant for shaft
movements larger than z,. For clays reduction in f to fmax to a residual value of f, may be
allowed at larger values of z say z,, after which it remains more or less constant.
In the case of the equivalent pier, the shear resistance, along the pier surface is
between the soil enclosed within the pier and soil outside the pier. Further, the shear
displacement along the periphery of the pier may not be uniform. It is likely to be
maximum at the location of the pile and reduces away from the pile. These deviations
from a single pile situation are taken into account as described below.
Estimation of fm„,:
(a) For cohesionless soils:
fma,, = K, 6• tanb (3.2)
Where, K, = Lateral earth pressure coefficient,
cU = Angle of wall friction. i.e. shearing resistance is between soil and
soil.
= Vertical effective pressure at the pile location under consideration
The value of Ks has to be chosen. The value of Ks suggested in the case of single
pile is given in Table: 3.1 to 3.2.
22
Table: 3.1 Values of KS
Installation method KS/Ko
Driven piles, Large displacement 1.00-2.00
Driven piles, Small displacement 0..75-1.25
Bored and cast insitu 0.70-1.00
Jetted piles 0.50-0.70
23
3.2 Procedure
The following procedure is adopted in the analysis of pile group.
1. Pile group is converted into an equivalent pier by using the relation given below
Dy = 2 AR (3.4)
24
RI = area reduction factor
8. Assuming a linear variation of load distribution in a segment,
(3.8)
9. Now the elastic deformation in the bottom half of the segment is calculated as
C —
(3.9)
sy .4E ey x
Here A, Leg are cross sectional area and elastic modulus of pier material respectively
L, = length of the segment considered.
10.New mid point movement is computed for the bottom segment, as:
Yn = 8Y + Yr (3.10)
11.Using the computed new mid point movement, the shaft load of the segment is
calculated using step 7.
12.Shaft load now calculated and previously calculated are compared. If the
difference is not within the specified limit, steps 7 to 12 are to be repeated, until
convergence reached.
13.The steps 6 to 12 are to be repeated for the next segment above the bottom
segment and worked upwards to compute the load (Q) and the settlement (y) at
the pier head.
14.The procedure is to be repeated for different tip movement values and a set of
load - settlement values are to be obtained. The same are to be plotted to give the
load - settlement curve.
A computer program is developed for the above computational procedure. The
program is made in C++.
25
CHAPTER 4
RESULTS AND DISCUSSION
4.0 General
The proposed method of analysis has been computerized. This program requires
the user to input various parameters of a pile - soil system under consideration which
include details of subsoil strata such as number of soil layers, depth of water table,
thickness and properties of soil in each layer etc., details of pile group such as number of
piles, length and diameter of piles, spacing of piles, method of pile installation and type
of pile material.
P
Table: 4.1 comparison of manually computed and program computed results
Load on pile group (kN) Settlement (mm)
27
3.5 m
X
3.5 m
O 0 e
3d Input data
dia =0.5
O 0 ± 6
ZS = 6.5 mm
Pile Group
Pile
L= 15m
Medium stiff clay, a = 0.7
-y= 18kN/m3,eo=0.7S
7m C~=70kN/m2,C,=0.25
0
Q-z curve
Load, kN
0 500 1000 1500 2000 2500
2
E
E 4
6
E
CD
~ 8
U) 10
12
14
• pile group
Load, kN
2000 4000 6000 8000 10000 12000
0
E
E
U)
10
12
29
4.2 Case studies
To assess the validity of the proposed method, some case studies taken from
literature are analyzed. The predicted and observed settlements are compared.
This case history concerns the load test reported by Briaud et al. (1989). A pile
group consisting of five piles was loaded to failure in a medium dense sand. A control
single pile was also loaded to failure as a reference. The piles were closed —end steel
piles driven to a depth of 9.15 m below the ground surface. Arrangement of piles in the
group and soil profile are shown in Fig: 4.4 and 4.5
Given data:
Length of pile below ground Ievel, L = 9.15 m
Outside diameter of pile = 273 mm
Wall thickness = 9.3 mm
Area of pile group, Ag = 2.0535 m2
Total cross sectional area of piles in group, Al = 0.293 m2
Youngs Modulus of soil, E, = 21840 kN/ m2 (Es = 3.5 x Ckd)
Youngs Modulus of pile, Ep = 2.1 x 108 kN/ m2
The above case study is analyzed for different values of reduction factor (Rf) and results
are shown in Fig: 4.6. It is observed that for Rf = 0.7, the load — settlement results agrees
with the observed results.
The load — settlement for the above case is also obtained using equivalent raft at
2/3 L from the top. This estimated load — settlement curve is also shown in Fig: 4.6. It is
found that the equivalent raft method considerably over estimates the settlement.
Case B: piles in overconsolidated clay (O'Neill et al. 1982)
A load test on a group of piles is reported by O'Neill et al. (1982).A pile group
consisting of 9 closed ended steel pipe piles in stiff overconsolidated clays as shown in
Fig: 4.7 was load tested. Load tests were also conducted on single piles for reference.
The pile — soil situation is as shown in Fig: 4.8
Input data:
Length of pile below ground level, L = 13.1 m
Outside diameter of pile = 273 mm
Wall thickness = 9.3 mm
Area of pile group, Ag =3.65 m2
Total cross sectional area of piles in group, A,p = 0.527 m2
Youngs Modulus of soil, E, = 157445 kN/ m 2
Youngs Modulus of pile Ep = 2.1 x 106 kN/ m2
The above case study is analyzed for different values of reduction factor (Rf) and the
results are shown in Fig: 4.9.It is observed that for Rf = 0.6, the results are agree well
with the observed results.
The load — settlement for the above case is also obtained using equivalent raft at
213 L from the top. This estimated load — settlement curve is also shown in Fig: 4.9. It is
found that the equivalent raft method considerably over estimates the settlement.
31
Fig: 4.4 Arrangement of piles in group (Case
A) Briaud et al. 1989
525 m
nI
Sandy gravel (fill) 7=21 kN/m3
1.5 m
Gap
Clean sand, y = 19.25 kN/m3
.9m K I,pp = 35.24°
32
Case A
Load, kN
1000 2000
0
5
10
15 +measured jl
E20 —•— Equivalent raft
II
3 25 ~—•—Rf=1
E 30
a, 35 t
40
45
50
33
Fig: 43 General test condition (O'Neill et al. 1982)
Pile Cap
V
vt i Very stiffclay,
2.6m
2.3m y 20kN/ml,
I
Cu _ 150 kN/ m''
34
Case B
Load, RN
2000 4000 6000 8000 10000
10
20
Equivalent Raft
E 30
«:
u— measured iI
E 40 0.4
—Rf=0.6 j
50 —Rf=1
60~
70
Fig: 4.9 comparison of predicted (for Zs =0.015 m) and observed behavior of pile
group.
35
4.3 Parametric study
Behavior of pile group with varying width is studied for size of group varying
from 2 x 2 to 9 x 9 piles. Pile groups in cohesive and cohesionless soils are considered.
Spacing of piles in the group is kept constant as 3 times the diameter of pile. Plots of
variation of group ratio with width of pile group are made. Group ratio is defined as
settlement of pile group for a given load per pile to the settlement of single pile for the
same load on the single pile. Pile group settlement is calculated by the present proposed
method and single pile settlement is calculated by Hazarika and Ramasamy (2000)
method,
4.3.1 Pile group in cohesive soil
To study the effect of width on pile group, a typical soil system shown in Fig:
4.10 is taken and load - settlement behavior of pile groups of size varying from 2 x 2 to
9 x 9 piles is estimated using the proposed method of analysis. In this case spacing of
piles is taken as 3D and kept same for all pile groups. The load on each pile in a group is
taken as 500 kN. Soil strata and details of piles are shown in Fig: 4.10. Variation of
group ratio with B is shown in Fig: 4.11 and values are given in Table: 4.2
Table: 4.2 values of Group ratio (Sg/Si) with varying B in cohesive soil
Pile Spacing = 3D, D = Diameter of Single Pile (0.5 m)
Surface area per lm
Total Load
length of Equivalent
Pile group on the pile Sg (mm) Si (mm) Sg/S;
Pier (m2)
group (kN)
36
Area of pile group = 3.5 x 3.5 mZ
C/C spacing = 3D
rap
Pile C D = din of single pile = 0.5 rn
Soft clay,
4m y= l 7 kN-/m3,
I CU = 45 kN/m2
T Soft clay,
2M y = 17 kN/m3, C„ = 45 kN/m 2
L= 15m
37
Group ratio Vs Width
140 1
120
100
°_ 80
2 60
a
40
20
0
0 2 4 6 8 10 12 14
Width, m
Fig: 4.11 Variation of group ratio with width (B) in cohesive soil
38
4.3.2 Pile group in cohesionless soils
As explained in 4.3.1, the same procedure is adopted in the case of a pile group in
cohesionless soils also. Soil profile and pile characteristics are given in Fig: 4.12. The
variation of group ratio with width is shown in Fig; 4.13 and values are given in Table:
4.3.
Table: 4.3 values of Group ratio (S g/Si) with varying B in cohesionless soil
Pile Spacing = 3D, D = Diameter of Single Pile (0.5 m)
Surface area per lm
Total Load on
length of Equivalent
Pile group 2 the pile group SB (mm) Si (mm)
Pier (m)
(kN)
It is seen from Fig: 4.11 and 4.13, the group ratio increases with increasing
number of piles in the group. It may be noted that the surface area of the equivalent pier
increases by five to six times and total load increases by 20 times, when the group size is
increased from 2 x 2 to 9 x 9.(Table: 4.2). This implies, in a large group, maximum load
is transferred to the base of the pile group. Further, with increasing width of the
foundation in the case of large groups, the compressible strata also increases. These
factors result in substantial increase in settlement at the base with increasing the size of
the group. This is the reason for increase in group ratio with the increase in pile group
size.
39
Q Area of pile group = 3.5 x 3.5 m2
C/C spacing = 3D
Pile Cap D = dia of single pile = 0.5 m
L = 20m 5 =0.7,cp=30
7.5m K
40
Group ratio Vs Width
18
16
14
12
0
10
Q 8
c7
6
4
2
0
0 2 4 6 8 10 12 14
Width, in
Fig: 4.13 variation of group ratio with width (B) in cohesionless soil
CHAPTER 5
SUMMARY AND CONCLUSIONS
Based on the work reported in this dissertation, the following conclusions are drawn.
1. The available methods of settlement computation for pile groups are either empirical
nature or too involved requiring many pile — soil parameters which cannot be easily
obtained.
2. A rational and simple method to estimate load — settlement behavior of pile groups is
developed based on equivalent pier approach suggested by Randolph (1994) and load
— transfer approach suggested by Hazarika and Ramasamy (2000) for single pile.
3. The method developed takes into account layered soil system and requires input of
soil properties which can be readily estimated from usually conducted field and
laboratory tests
5. A few numerical problems and few case histories have been analyzed using the
program. The results of these investigations show that:
i) The proposed method is capable of providing reliable estimate of load
— settlement behavior of pile groups.
ii) The equivalent raft method widely adopted in practice may
significantly over estimate the settlement.
42
REFERENCES
1. Briaud, J. L., Tucker, L. M. and Ng, E (1989): "Axially Loaded 5 Pile Group and
Single Pile in Sand", Proceedings of the 12`h International Conference on Soil
Mechanics and Foundation Engineering, Rio de Janeiro, Vol.2, pp. 1121 — 1124.
2. Butterfield, R. and Benerjee, P. K. (1971a): "The Elastic Analysis of
Compressible Piles and Pile Groups", Geotechnique, Vol. 21, No.1, pp. 43 — 60.
3. Butterfield, R. and Benerjee, P. K. (1971b): "The Problem of Pile Group and Pile
Cap Interaction", Geotechnique, Vol.21, No.2, pp. 135— 142.
4. Castelli, F, and Michele, M. (2002): "Simplified Nonlinear Analysis for
Settlement Prediction of Pile Groups", Journal of geotechnical and
Geoenvironmental Engineering, ASCE, Vol.128, No.1, pp 76— 84.
5. Castelli, F. and Motta, E. (2003): "Settlement Prevision of Piles under Vertical
Load", Proceedings of the Institution of Civil Engineers, Geotechnical
Engineering, Vol.156, No. GE4, pp, 183— 191.
6. Cooke, R. W. and Price, G. (1973): "Strains and Displacements around Friction
Piles", Proceedings of the 8th International Conference on Soil Mechanics and
Foundation Engineering, Moscow, Vol. 2, Part I, pp. 53 —60.
7. Coyle, H. M. and Reese, L. C. (1966): "Load Transfer for Axially Loaded Piles
43
11. Hazarika, P.J. and Ramasamy, G. (2000): "Response of Pile under Vertical
Loading", Indian Geotechnical Journal, Vol.30, No.2, pp 23 — 27.
12. I.S: 8009 (part II) (1980): "Code of Practice for Calculation of Settlement of
Foundations, Deep Foundations Subjected to Symmetrical Static Vertical
Loading", BIS, New Delhi.
13. I.S: 8009 (part II) (1980): "Code of Practice for Calculation of Settlement of
Foundations, Shallow Foundations Subjected to Symmetrical Static Vertical
Loading", BIS, New Delhi.
14. Juan, M. P., Christopher, E. H. and Jonathan, D. B. (2002): "Soil Deformation
and Excess Pore Pressure Field around a Closed Ended Pile", Journal of
Geotechnical and Geoenvironmental Engineering, ASCE, Vol.128, No.1, pp. I -
12.
15. Kraft, M. L., Ray, P. R. and Takkaki, K. (1981): "Theoretical t — z Curves",
Journal of Geotechnical Engineering Division, ASCE, Vol.107, No.GT11, pp.
1543 — 1561.
16. Lee, C. Y. (1993): "Settlement of Pile Groups — Practical Approach", Journal of
Geotechnical Engineering Division, ASCE, Vol.1 19, No.9, pp.1449 — 1461.
17. McCarty, D. F. (1988): "Essentials of Soil Mechanics and Foundations", 3rd
Edition, Prentice Hall.
18. Meyerhof, G. G. (1959): "Compaction of Sands and Bearing Capacity of Piles",
Journal of Soil Mechanics and Foundation Engineering Division, ASCE, Vol.85,
No. SM 1, pp. 1 — 29.
19. Meyerhof, G. G. (1965): "Shallow Foundations", Journal of Soil Mechanics and
Foundation Engineering Division, ASCE, Vol.91, No.SM2, pp. 21 —31.
20. O'Neill, M.W., Hawkins, R. A. and Mahar, L.J. '2): "Load Transfer
Mechanism in Piles and Pile Groups", Journal of Geotechnica Engineering,
ASCE, Vol.108, No.12, pp. 1605 — 1623.
21. Peck, R. B., Hanson, W. E. and Thornburn, T. H. (1974): "Foundation
Engineering", 2 Edition, John Wiley, New York.
22. Poulos, H. G. (1968): "Analysis of the Settlement of Pile Groups", Geotechnique,
Vol. 18, No. 4, pp. 449-471.
23. Poulos, H. G. and Davis, E. H. (1968): "The Settlement Behavior of Single
Axially Loaded Incompressible Piles and Piers", Geotechnique, Vol.18, No.3, pp.
351 —371.
24. Poulos, H. G. and Davis, E. H. (1969): "The Behavior of Axially Loaded End
Bearing Piles", Geotechnique, Vol.19, No.2, pp. 285 — 300.
25. Poulos, H. G. and Mattes, N. S. (1971): "Settlement and Load Distribution
Analysis of Pile Groups", Australian Geotechnical Journal, G 1, pp. 18 — 28.
26. Poulos. H. G. and Davis, E. H. (1980): "Pile Foundation Analysis and Design",
John Wiley and Sons, New York.
27. Randolph, M. F. (1994): "Design Methods for Pile Groups and Piled Rafts",
Proceedings of the XIII International Conference on Soil Mechanics and
Foundation Engineering, New Delhi, India, Vol.1, pp. 61 — 82.
28. Randolph, M. F. and Clancy, P. (1993): "Efficient design of Piled Rafts",
Proceedings of the Second International Geotechnical Seminar on Deep
Foundations on Bored and Auger Piles, Ghent, Vol.1, pp. 119— 130.
29. Randolph, M. F. and Wroth, C. P. (1978): "Analysis of Deformation of Vertically
Loaded Piles", Journal of Geotechnical Engineering Division, ASCE, Vol.104,
No.0T12, pp. 1465 - 1488.
30. Ranjan, G and A.S.R (2000): "Basic and Applied Soil Mechanics", 2"d Edition,
New Age International, New Delhi.
31. Schmertmann, J. H. (1970): "Static Cone to Compute Static Settlement Over
Sand", Journal of Soil Mechanics and Foundations Division, ASCE, Vol.96,
No.SM3, pp. 1011 — 1043.
32. Shen, W. Y., Chow, Y.K. and Yong, K. Y. (2000): "Practical Method for
Settlement Analysis of Pile Groups", Journal of Geotechnical and
Geoenvironmental Engineering, ASCE, Vol.126, No.10, pp. 890-897.
33. Skempton, A. W. (1953): "Discussions on Piles and Pile Foundations, Settlement
of Pile Foundations", Proceedings of 3"d International Conference on Soil
Mechanics and Foundation Engineering, Zurich, Vol.9, pp. 172.
34. Skempton, A. W. and Bjerrum, L. (1957): "A Contribution to the Settlement
Analysis of Foundations on Clay", Geotechnique, Vol. 7, No. 4, pp. 168 — 178.
45
35. Terzaghi, K. and Peck, R. B. (1974): "Soil Mechanics in Engineering Practice",
2nd Edition, John Wiley, New York.
36. Tomlinson, M. J. (1977): "Pile Design and Construction Practice", Viewpoint
Publications, London.
37. Vijayvergiya, V. N. (1977): " Load Movement Characteristics of piles",
Proceedings of 4`h Symposium of Waterway, Port, Coastal and Ocean Division,
ASCE, Long Beach, Calofomia, Vol.2, pp.269 — 284.
38. White, D. J and Bolton, M. D. (2004): "Displacement and Strain Paths during
Plane — Strain Model Pile Installation in Sand", Geotechnique, Vol. 54, No. 6, pp.
375-397.
To
P 0
04
D yi
Sc
Fig: 2. l (a) Load — transfer to soil from pile group (I.S:8009 part II)
47
11 Q
1
V1IIiiIII
M
riiiiia
OK2fl7l7C7tC7t7
t
h
0A
SI
U
Fig: 2.1 (b) Load — transfer to soil from pile group (Tomlinson, 1977)
DEPTH FACTOR
0.5 0.6 0.7 0.8 0-9 1.0
____rae
I. a
____ VA______
■■■f 111/■■■■■
■■■////■■■■■
. ME//i■■■■■■
• =~/I/I■■■■■■
RZ
[-
2B • 0.6 curve
Fig: 2.3 Vertical strain factor
Cap
,A,.L $.5J.LZ2_7
r
502 05 1
I1
Ile Cap
Cohesive soil
j 2
1
2 L
1
Cohesionless soil
51
t•0- f; 1
CURVE FOR Z ZS
0.5 b -C _ PROBABLE f- r CURVE FUR SAND (Z7Zs)
b_d_e tPROSABIE f = CURVE FOR CLAY(Z>Zs)
Z=Zr
0•S t•0
2/h
Fig: 3.2 f— z curve (Vijayvergiya, 1977)
52
Q = Applied load
Pier
Pier
segments y
~ Q1 LE, L2. ....L = Segment lengths
Y1, Y2......Y,= Segment movements
Qi, Q2.....Qn = Axial forces on
L21IY
W
S2 --1
1Yi
segments
4
Yi = Tip movement
_I,Y3
LnI Sn
Yn
53
Column
1 1
• *~f
1 1
Dcq
O 0 0
0 O 0
x Pile Group
Equivalent Pier
z
Shear displacement
Section x — x
54