ESTIMATE
ESTIMATE
No: 780/2A1A1A1A Part, Plot No: 37 West Side Part," RAINBOW GARDEN " Layout at Kottur
Town Panchayat,Anaimalai Taluk,Coimbatore District. ( D.T.C.P.App.No: 21/2009)
Sl. Length Breath Depth Amount
Description of work No Quantity Rate Per
No. ( in ft ) ( in ft ) ( in ft ) ( in RS )
1 Earth work excavation in all
soils for foundation upto a
depth of 3'-9" below the
ground level
Main walls alround the
building 1 86.00 3.00 3.75 967.50
967.50 15.00 Cft 14513
2 Plain cement concrete 1:5:10
using 40mm HBGS metal for
foundation.
Main walls alround the
building 1 86.00 3.00 0.75 193.50
193.50 120.00 Cft 23220
3 R.C.C.Footing
Main walls alround the
building 1 8.00 2.50 1.50 30.00
1 8.00 2.00 1.50 24.00
1 10.00 1.50 1.50 22.50
76.50 150.00 Cft 11475
4 Filling the basement in layers
of 6" tk consolidation with
excavated earth rammed well
etc., complete.
rooms 1 0.75 22.00 1.50 24.75
24.75 120.00 Cft 2970
5 Flooring concrete in C.C.
1:4:8 using 40mm HBGS
metals with 4 1/2" tk.
rooms 1 0.75 22.00 0.33 5.45
156.00 150.00 Cft 23400
6 Brick work in C.M. 1:6 for
walls using good quality bricks
including scaffolding charges
etc., complete.
G. Floor
Main walls alround the
building 1 10.00 0.75 10.00 75.00
Deduction for opening :
W-Window 1 4.00 0.75 4.50 -13.50
D-Door 3 3.50 0.75 7.00 -55.13
162.00 180.00 Cft 29160
7 Wall plastering in C.M. 1:5
including scaffolding charges
etc. complete
a. Inside
Room 1 126.00 - 10.00 1260.00
Deduction for opening :
W-Window 9 4.00 - 4.50 -162.00
D-Door 7 3.25 7.00 -159.25
938.75 35.00 Sft 32856
b. Outside
Walls alround the building 1 142.00 - 15.00 2130.00
2130.00 45.00 Sft 95850
8 Floor finish with cement
mortar 1:4 mix including
curing charges etc., complete.
Inside:-
Walls 1 850.00 Sft - 850.00
850.00 22.00 Sft 18700
Sft
Outside:-
Walls 1 560.00 Sft - 560.00
560.00 24.00 Sft 13440
Sft
12 Provision of Septic Tank *** *** *** 46525