0% found this document useful (0 votes)
33 views

SOW General Overhaul DG#1

Uploaded by

Soto Gobyoss
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views

SOW General Overhaul DG#1

Uploaded by

Soto Gobyoss
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

Scope Of Work General Overhaul

DG#1
LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

CHANGE LOG:
Revision Date Author Changes

0.0 September Hanis Muhantoyo Original draft


2024

Scope Of Work General Overhaul DG#1 Page 2 of 9


LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

BACKGROUND

This LDC East Indonesia site located on a very remote location in Kariangau Village, Balikpapan on
the Island of Kalimantan, Indonesia is a crude palm oil refinery. Road access to the plant is very
limited. Access to the plant for personnel as well as raw material and finished goods is via barge /
vessel only. The plant receives crude palm oil (CPO) and refines it into refined, bleached, de-
odorized palm oil (RBDPO) which is then further split into both Olein and Stearin via a fractionation
plant.

It has a designed capacity of 1500 ton per day, upgraded up to 1700 ton per day and is producing
refined bleached deodorized palm oil (95%) with the rest comprising of pure fatty acid distillate
(PFAD, 4.5%) and free fatty acid (0.5%). About half of the refined oil product is then sent to the
fractionation plant which has a similar design capacity with the refinery, to produce 80% olein
(cooking oil) and 20% of stearin. The other half from the refinery is used as the final product. Raw
material is obtained from local palm oil plants and is transported to the site using barge vessel and
is pumped to several storage tanks. There are 31-unit main storage total Cap. 130,100MT,

For support production facilities, we have diesel generator for support power producing in plant
operations.

We planned general overhaul in Diesel Generator #1.

Scope Of Work General Overhaul DG#1 Page 3 of 9


LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

SCOPE OF WORK
A. General Overhaul & Parts Overhaul

With Detail

No Description Quantity
1 General Overhaul Engine Generator - Cummins
Cummins VTA-28-G6 1
KTA19
2 General Overhaul Parts
Gasket Upper 1
Gasket Lower 1
Ring Piston 6
Valve Inlet 12
Valve Exhaust 12
Cylinder Liner 1
Conrod Bearing 1
Main Bearing 1
Valve Seating 12
Guide Valve 24
Consumable 1
Labour Cost 1

And

1. Perform a General Overhaul on the engine in accordance with engine manual rules and engine
conditions

2. Perform service and calibration on the injection pump

3. Replace the bearings on the generator and clean the generator winding.

Scope Of Work General Overhaul DG#1 Page 4 of 9


LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

B. Parts Calibration

With Detail

No Description Quantity
3 Parts Calibration
Set, fuel pump gasket 1
hub, jaw coupling 1
shaft, fuel pump drive 1
shaft, tachnometer 1
bearing ball 1
cover 1
a.gov, plunger 1
idlir plunger 1
check valve 1
cup injector 6
screen injector filter 6
seal, injector o ring 18
kit tappet HYD 3
kit STC tappet repair 6
retainer spring 1
barrel plunger 6
actuator 1
kit seal 2
torque spring 1
gear pump 1
spring 1
shutoff selenoid assy 1
plug, injector orifice 6
pin, injector roll 24
ball check 12
seal, injector o ring 12
cup tappet top stop 6
spring compression 6
spring compression 6
retainer injector spring 6
screen PT pump 2

Scope Of Work General Overhaul DG#1 Page 5 of 9


LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

C. Labor Calibration

With details:

No Description Quantity
4 Labour PT pump 1
5 Labour Injector KSTC 1

D. Transportations, meals, and accommodation

With details:

No Description Quantity
1 MOB DEMOB 1
2 Speedboat 30
3 Meals 30
4 Accomodation 1
5 Transport 30

E. Safety, Health, and Environment


1. Vendors / Contractors are required to provide SHE coordinator of General K3 Experts and
submit certificates to PT.LDC.
2. It is mandatory to use standard PPE (safety helmet, safety goggles, safety shoes), additional
PPE needed for hot work, working at high places.
3. Must comply with SHE regulations (safety, health, environment) and regulations for making
documents: Risk Assessment, Occupational Hazard Analysis Process, PERMIT, and Safe
Work Procedures (SWP).
4. Obligation to carry out inspections The equipment used is in good condition. Suppose the
extension cord is not peeled off, the webbing sling is not deformed, etc.
5. It is mandatory to use a Flash back restore on a welding torch (LPG Tubes & Oxygen
Cylinders).
6. It is mandatory to wear a life jacket during sea transportation and entering the PT. LDC.

Scope Of Work General Overhaul DG#1 Page 6 of 9


LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

F. Administration and document project

Statement results of analysis normal or not normal source.

1. Contractor submits detail timeline for project until commissioning.


2. Contractor creates daily report for progression project.
3. Contractor creates method for work.
4. Contractor creates “final report project” 2 EA hardcopy and file softcopy.

Scope Of Work General Overhaul DG#1 Page 7 of 9


LOUIS DREYFUS COMPANY
SCOPE OF WORK GENERAL OVERHAUL DG#1 Last update: September 2024

1.

ASSET & RELIABILITY SECTION

MAINTENANCE DEPARTMENT

PT. LDC EAST INDONESIA

Scope Of Work General Overhaul DG#1 Page 8 of 9