Hilton Hotel
Hilton Hotel
Note: 'Contractor shall ensure submission of detailed GA drawings (Plan & Section), P &
I diagram, schematic diagram for the mentioned component in SOQ and additional
component if so required for the complete working of the STP and got it approved by
the Owner’s Architect / Project Manager / Consultants.
A MECHANICAL EQUIPMENT
1 Supply, installation, testing & commissioning of Stainless Steel Coarse Screen with suitable lifting No. 2 12500
arrangement (size shall be as per actual drawings). Spacing between bars to be 16 mm for
coarse screens and 10 mm for fine screens.
Make : Uttam
Supply of MS hot dip galvanized puddle flanges in accordance to BS:10 table D as required to 11500
be provided (in the structural slab and wall) of various diameters. Puddle flanges shall be
provided for all the structural component of the STP. The installation of the puddle flanges
2 shall be carried out by the Civil contractor in accordance to the Civil GA drawing (to be Lot 1
prepared by the STP contractor) at the required levels & position; under the supervision
of the STP contractor.
Make : Uttam
3 Supply, installation, testing & commissioning of float type level switches for automatic Lot 1 55000
operation of the system with high/low level alarm complete with auxillary NO/NC contacts
for (To be provided for all the tanks and plant room
sump)
Cost shall be inclusive of PVC flexible Hose pipe ( for piping submreged in effluent) with
PVC piping (for piping non-submerged in effluent)
5.1 Submersible Sewage Pumps (non cutter type) for transfer of Raw Sewage in Set 1 85000
EQT (1 working & 1 standby) :-
Flow rate (each) = 5.5 m3/hr
Head = 10-12 m
Make: Kirloskar, KSB, Willo
5.2 Submersible Sewage Pumps (cutter type) for transfer of STP plant room sump Set 1 162000
tanks ( 1 working + 1 standby )
Head = 15 m
6.1 Air Blower for Equilisation, MBBR Tanks and sludge tank : Air blowers of suitable HP Suitable Set 1 295000
for 415 ± 10% volts, 3 phase, 50 cycles A/C supply. Numbers & capacity as per
requirement with standby to be specified by
vendor.Capacity: 150 m3/hr , @ 0.4 kg/cm2 Qty (1W+1S) Make: Akash, Uttam
Non clog, Self Cleaning type air dispersion system capable of handling 3-5 cfm of air with 55000
oxygen transfer efficiency of 3-4% per / meter water depth. Air dispersion grid shall be
assembled in modular form so that they can be replaced
6.2 / repaired easily from plat form at the top. (Coarse Disc Type Diffusers for EQT & Lot 1
SHT)
Non clog, Self Cleaning type air dispersion system capable of handling 3-5 cfm of air with 135000
oxygen transfer efficiency of 3-4% per / meter water depth. Air dispersion grid shall be
6.3 assembled in modular form so that they can be replaced Lot 1
/ repaired easily from plat form at the top. (Fine Bubble Tube Type Diffusers for
Aeration Tank)
Make: PP Aqua
9 Providing and fixing all piping (as described below) and isolation control valves for making the
system complete.
Supply, installation, testing and commissioning of Filters constructed of M.S material Epoxy
Coating / Composite FRP. The inner distribution system and the under bed draw off system shall
be of Hub & Lateral type / Riser tube with top & bottom strainers of vessel shall be supplied
with first fill media with supporting media like silex, gravel etc. The Filter shall be complete with
12 pressure gauge at inlet & outlet, sample cock, MS / UPVC interconnected piping, manual
valve, overflow & drain, outlet fitting and all associated pipe work with manual Butterfly Valves/
MPV.
Make: E-dose
Supplying, installing, testing & commissioning of ultravoilet dis-infection unit. The unit shall
have over 99.9 % bacterial reduction from inlet to outlet. The dis- infection chamber shall be
constructed of SS 316L on all welted parts. The UV lamp shall be of low pressure mercury vapour
17 type with hard glass enclosure, the sockets shall be water tight & vibration resistant. The lamp life
shall be rated for 6000 hours. The unit shall be complete with temperature safety control and lamp
out alert circuit.
The UV unit shall have with reactor, cabinet housing, cabinet cooling, treatment chamber,
electrical panel, temperature safety control, lampout alert. The UV Dosage should be >
60,000 uW – Sec / sq.cm. The lamps should be selected
based upon the flow requirement of respective unit
19.1.1 Oulet of Raw Sewage Transfer Pumps - 5.5 m3/hr Make Zest, Astral No. 1 66000
19.2 Supply, installation, testing and commissioning of BMS compatible Digital Turbine Type
flow meter with online sensor, standard cable and fitting for flow measurement.
a. Vertical, In-Line, Multisage, centrifugal pumps with SS-304 casing and impeller and SS shaft,
CI base & head TEFC motor (with mechanical seal)
(Vendor to submit performance curves and technical catalog of the proposed model for
review & information) Pumps shall be factory assembled and factory tested with 1 VFD
common.
The pump shall be selected for performance at best efficiency point. However, the pump
selection shall be suitable for performance with set point @ + 20% of the rated head.
b. External Pump mounted or wall mounted microprocessor PID controller and frequency
inverter integrated in a single body or as separate components with pressure sensor
transmitter minimum two lined LCD display, diodes to indicate pump ready, pump running
and fault and capable to communicate with other controllers following MODBUS-RTU or
BACNET Class-2 protocall through RS485 port. System should be capable to
compensate for frictional losses at lower flows. All alarms should be displayed in the
controller. System should be equiped with dry running protection
d. Precharged diaphram pressure vessel with food grade membrane, charging connection,
connected to outlet header with necessary flanges, gaskets, isolating valves, nuts/bolts etc
complete.
f. Accessories like pressure gauge, MS base frame (Synthetic enamel painted over a coat
of primer)
g. GI suction and delivery header with flanges for inlet connection, common outlet header
with flanges for outlet connections as required, and inter connecting piping with
flexible connections, eccentric type reducers etc. all necessary indigenous accessories as
required to complete the installation.
b. 0-100 amps 96 x 96 mm square electronic ammeter with selector switch and 100./5 amps 10
VA CL:1 CTs. 1 Set
Bus Bar
Outgoing
200 amps TPN (15 KA) copper bus bar with heat shrinkable insulation sleeves.
a. Required Nos of required capacity TPN MCB for direct on line starter/star delta starters and
out going feeders to all the pumps/blowers etc. (including standbies). Each
compartment shall contain auto / manual selector switch and indicating lamp with MCB’s for
‘ON/OFF/TRIP’ status of motor
b.Necessary cable alleys, internal / cabling, wiring, cabling from MCC to various pumps /
equipment and interlocking, earthing for all equipment shall also included.
c.All MCCBs/MCBs shall be of 15 KA breaking capacity and suitable for motor duty
application.
d.All motor starters shall be provided with Automatic level controller
e.DOL starters shall be used for mototrs below 7.5 HP and Star-Delta Starters for other motors
above 7.5 HP .
f.Provision shall be made for providing potential free contacts to all pumps starters
g. Energy Meter to be provided with Panel
MCC for all STP equipments/pumps as described above Set 425000
23 Providing and fixing electrical cables, cable trays, control cabling, earthing etc with in the STP Lot 155000
from electrical panel to the equipments complete in all respect as per direction of Engineer in
charge .
Amount
25000
11500
55000
28000
85000
162000
295000
55000
135000
145000
62000
250000
92000
92000
78000
162000
210000
550000
1475000
125000
25000
155000
Not required
Not required
285000
66000
22000
Not required
22000
25000
25000
25000
25000
725000
525000
Not Required
525000
150000
425000
155000
7272500